This document is a request for proposal for an indefinite delivery indefinite quantity multiple award task order contract to provide sensitive compartmented information facility construction services. The contract will have a total maximum value of $49.9 million over a three-year base period and will be awarded to at least two offerors. Services will include design-build and design-bid-build construction projects in Germany, Belgium, Poland, Romania, and Estonia for new sensitive compartmented information facilities as well as building renovations and associated environmental work. Offerors must have a facility security clearance or the ability to obtain one. Proposals are due by July 17, 2019. Evaluation will be based on past performance, management approach, architect-engineering team qualifications, a seed project narrative, and a seed project price schedule.
Responses for Requests for Information (RFIs)_Am-0001
View the file
Other files for this federal contract opportunity
Show all 36
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED\\FOR OFFICIAL USE ONLY
Bid Inquiry Contractor Report All Inquiries
Project: FY19 SCIF MATOC Review: W912GB19R0027 (00001) (sorted by CommentID ) Displaying 37 inquiries.
Id Discipline Sheet Detail Spec
8064530 Contracting Section 00 21 16, Section II, Paragraph C
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Factor 2: Management Approach (Section 00 21 16, Section II, Paragraph C). Please confirm that page count for Factor 2, excluding identified exemptions, is thirty (30) single spaced typed pages.
On: Jun 24 2019.
Government Response. . Yes, 30 page limitation. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8064532 Contracting Section 00 21 16, Section II, Paragraph C
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Factor 2: Management Approach (Section 00 21 16, Section II, Paragraph C). Can we use a font smaller than 12 point for graphics and tables?
On: Jun 24 2019.
Government Response. . Yes, provided the tables and graphics are legible. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8067026 General Section 01 00 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Summary of Work, 1. General Information, 1.e. Bonding - Will Bank Letter of Assurance or Guarantee be considered or accepted?
On: Jun 25 2019.
Government Response. . No, since a US firm must be the Prime, only Performance and Payment Bonds are accepted. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8068049 Contracting Section 00 21 16 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Section 00 21 16, Instructions to Proposers, Section II, Proposal Submission Requirements and Instructions-Phase I, paragraph p states "Offeror shall submit a signed Offer, Standard Form (SF) 1442 for both Phases I and II.";
however, the SF 1442 is not listed under Proposal Format for Phase I Proposal: Factors 1, 2 or 3. Should the SF1442 be submitted as an attachment to the proposal cover letter?
On: Jun 25 2019.
Government Response. . The SF1442 does not belong under any Factor and should be submitted with the proposal for both Phases I and II as stated. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8068056 Contracting Section 01 00 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Page 1 of 10ProjNet: Logged In User
7/11/2019https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAl...
Section 01 00 00, Summary of Work, Paragraph 2, states "The offeror will be required to have a valid FCL or have the ability to obtain FCL". In addition, the end of paragraph 2 states "Potential Offerors must have already completed the telephonic survey and be prepared to complete document upload to NISS in order to be considered for award."
Should potential offerors state their FCL status in the cover letter for Phase I or should this be addressed in the Phase II proposal for contractors selected for Phase II?
On: Jun 25 2019.
Government Response. . Indicating current FCL status on the cover is acceptable. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8068062 Contracting Section 00 21 16 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Section 00 21 16, Instructions to Proposers, Section II, Proposal Submission Requirements and Instructions – Phase I, paragraph 3t. Please confirm the Reps and Certs and remaining documents in paragraph "t" are required for Phase II proposal submission only. Also, please confirm the items in paragraph "t" are to be submitted in Volume II under Price/Administrative Proposal.
On: Jun 25 2019.
Government Response. . Confirmed. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8070364 General Section II Page 26 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Proposal Submission Requirements and Instructions – Phase I. Can you confirm the table of contents, cover, cover letter, tile page per FAR 52.215-1, completed SF1442, and list of acronyms are excluded from page count?
On: Jun 26 2019.
Government Response. . Confirmed. The page limitation applies only to Factor 2: Management Approach. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8070367 General Attachment 2 Page 1 and
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Can the government please confirm item #5 and letter c are missing in the project information form? Is there additional information to be provided for #5 or letter c?
On: Jun 26 2019.
Government Response. . Confirmed. 4c and 5 were missing and corrected via Amendment 0001. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8070545 General Section II Page 30 Proposal Format – Phase I, Factor 2 :
Management Approach
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Factor 2 Management Plan; Evaluation Criteria #3.Can the offeror assume that personnel letters of commitment are not applicable for submission in the proposal if all proposed personnel are currently employed with the Prime or Team Subcontractors?
On: Jun 26 2019.
Government Response. . Letters of commitment are required if the individual is not currently hired by the Offeror. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
Page 2 of 10ProjNet: Logged In User
8073704 General Proposal Due Date Extension Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Respectfully, would the Government please grant a 30 day proposal due date extension to allow bidders sufficient time to prepare the most competitive pricing possible.
On: Jun 28 2019.
Government Response. . Pricing is not required at this time. Only the Offerors that pass from Phase I to Phase II will be requested to submit pricing with Phase II proposals. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8075737 General RFP TOC page 3 of
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The TOC included with the RFP (page 3 of 230) is inconsistent with the section numbers/titles of the contents. For example, Sections 00 22 00 "Supplementary Instructions", 00 72 00 "General Conditions", and 01 11 00 "Summary of Work" are identified in the TOC, but could not be located in the RFP. However, RFP appears to contain other sections, not listed in the TOC (00 60 00 "Project Forms", 00 62 00 "Certificates and Other Forms", 00 62 00 "Certificates and Other Forms", and 01 00 00 General Requirements). In addition, Section 01 30 00 "Administrative Requirements", can only be located in the Specifications, but under different title SECTION 01 30 00 GENERAL REQUIREMENTS (NAU) APR 2019. Please confirm applicability of sections listed in TOC but not provided, or those provided but not listed in the TOC, and provide updated TOC and applicable RFP sections.
On: Jul 01 2019.
Government Response. . Revised via Amendment 0001. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8076324 Contracting 00 10 00, CLIN 0001 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
"Ref: CLIN OOO1 ""Indefinite Delivery Indefinite Quantity (IDIQ) Multiple Award Task Order Contract (MATOC) to provide SCIF construction, real property repair and maintenance, associated environmental work..."" Section I, Para B (Section 00 21 16) in multiple sentences "The purpose of this NAU Indefinite Delivery Indefinite Quantity (IDIQ) MATOC is to provide SCIF construction, real property repair and maintenance, associated environmental work..."" Amplification: The RFP document does not define the scope of environmental work efforts. This type of work can have broad implications requiring specialized skills set depending on site assessment/remediation activities, laboratory work with the appropriate licensing. Depending on the scope it may cause offerors to alter teaming approach and insurance requirements.
Question:
1. Would the Government please provide amplification of the range of environmental work?"
On: Jul 01 2019.
Government Response. . Environmental work may include asbestos abatement necessary for demolition/renovation and proper disposal of contaminated materials (soil). On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8076366 Contracting Section 00 10 00, CLIN 0001 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Ref: CLIN OOO1 "Indefinite Delivery Indefinite Quantity (IDIQ) Multiple Award Task Order Contract (MATOC) to provide SCIF construction, real property repair and maintenance, associated environmental work, and force protection work in Germany, Belgium, Poland, Romania, or Estonia. ..."
Section I, Para B (Section 00 21 16) in multiple sentences "The purpose of this NAU Indefinite Delivery Indefinite Quantity (IDIQ) MATOC is to provide SCIF construction, real property repair and maintenance, associated environmental work and force protection work in Germany, Belgium, Poland, Romania, or Estonia. ..."
Amplification: The RFP document does not define the scope of force protection efforts. The phrase may imply offerors would be in security systems to providing personnel security. Depending on the scope it may cause offerors to alter teaming approach and insurance requirements.
Page 3 of 10ProjNet: Logged In User
Question:
Would the Government please provide the scope of "force protection" requirements?
On: Jul 01 2019.
Government Response. . Force protection requirements may include such things as cameras, sensors, fencing, barriers, and other physical measures to prevent or restrict access. It is anticipated that most of the work performed on this contract will be conducted on already established military bases and posts. There shall be no requirement for armed guards under this contract. Actual requirements will be defined at the task order level. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8076372 Contracting Section 00 70 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
"Ref: FAR 52.228-5 (a) The Contractor shall, at its own expense, provide and maintain during the entire performance of this contract, at least the kinds and minimum amounts of insurance required in the Schedule or elsewhere in the contract.
Amplification: We were unable to locate any minimum insurance amounts in the RFP Question:
Would the Government please provide minimum insurance amounts in the areas of General Liability, Personnel, vehicle etc?"
On: Jul 01 2019.
Government Response. . Minimum insurance amounts will be determined at the task order level. In addition, proof of DBA insurance will be required for each task order. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8076376 Contracting Administrative Requirements Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Paragraph 3.10 Asbestos Plan
1. Can you describe any asbestos remediation efforts as part of the anticipated Task Orders?
2. If Asbestos Abatement is required during the course of work, will the Government be the Generator?
On: Jul 01 2019.
Government Response. . Any asbestos remediation or abatement (if required) will be determined at the task order level. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8076378 Contracting Administrative Requirements Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Paragraph 3.10 Asbestos Plan Ref: "When required by the task order, the Contractor shall submit an Asbestos Plan that demonstrates the Contractor's ability to perform asbestos abatement in accordance with AHERA and EPA requirements and Section 00106 Asbestos Abatement. "
Would the Government please provide a copy of Section 00106 Asbestos Abatement?
On: Jul 01 2019.
Government Response. . This will be provided at the Task Order level (if required). On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8076446 General Section 00 21 16 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Ref: Section 00 21 16, paragraph C, pg 14 "A Top Secret Facility Site Clearance IS NOT required for this MATOC however individual projects may require Statements of Affiliation (SOAs) for all companies."
Page 4 of 10ProjNet: Logged In User
FAR 52-222-54 indicates employment eligibility is not required using E-Verify for any employee "(2) Who has been granted and holds an active U.S. Government security clearance for access to confidential, secret, or top secret information in accordance with the National Industrial Security Program Operating Manual; or Section 00 74 18 "Level VI security vetting - top secret facility security clearance; 180 calendar days shall be allowed for the vetting process" Amplification: The scope of work indicates that the Government intends to use this contract for Sensitive Compartmented Information Facility (SCIF) construction. Given the RFP requirements do not require a Top Secret Facility Security Clearance, then a company without a FCL could win one of the MATOC.
Section "Activities which are the responsibility of any Host Nation or foreign (non-US) Government agency at any level, including, but not limited to: reviews, permit approvals, and clearances must have a Host Nation Responsibility Code assigned."
Amplication: Throughout the RFP there are references to Clearance Levels, security clearance requirements etc.
Given the work may require personnel with a SECRET or TOP SECRET Clearance to construction SCIFs it appears Facility Clearance Level is required during execution but not stated.
Question:
1. Would the Government please amplify the RFP with the expected Task Order security clearance levels expected?
2. Would the Government indicate whether they will support sponsorship for a Facility Clearance Level for companies or subcontractors who do not have not have a FCL after MATOC Award?
On: Jul 01 2019.
Government Response. . 1. A FCL is not required to receive an award on the MATOC, but it may be required at the Task Order level.
2. Yes, the Government will sponsor companies at the Task Order level (if required). On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8076458 Contracting Section 00 21 16 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Proposal Submission Instructions Paragraph 3.s, page 27 of 230 Ref: Offerors are reminded that in accordance with FAR 52.228-15 the successful offerors will be required to submit 100% Performance and Payment Bonds for each Task Order award.
Questions:
1. What is the projected average size of Task Orders?
2. What is the maximum size of Task Orders required and are offerors required to provide a bonding capability letter supporting that maximum with the Phase I submission?
On: Jul 01 2019.
Government Response. . 1. See Section 01 00 00 - General Requirements/Summary of Work for the Task Order limitations.
2. No. A bid bond is only required with submission of Phase II. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8076463 Security Section 00 74 18; 1.2.1 "Alteration of Procedures"
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Background: SOW states: "Base access and security requirements may be altered by the Romanian authorities at any time. The contractor shall have no recourse as to costs or time extensions for any delays resulting in changes to access and/or security requirements."
Question: Please confirm that projects may be on foreign bases and that USACE will not give time or cost modifications due to unknown or changing Access Control procedures at these bases. This appears to be an unfair statement in the SOW for a potentially unknown condition at bid.
On: Jul 01 2019.
Government Response. . Task order work may be performed on installations where the Host Nation (HN) controls installation access. The Army Corps of Engineers (USACE) will provide access procedures and will facilitate coordination with the HN, however, USACE does not warranty the process, duration, or actions of another sovereign nation. In situations where project delays occur as a result of sovereign acts, or other acts outside of the control of USACE, these delays will not be compensable. With that said, the construction contractor may be entitled to a non-compensable time extension to the contract and relief from liquidated damages if they can demonstrate that the cause of delays were beyond their control. In all situations, Page 5 of 10ProjNet: Logged In User construction contractors will have a duty to understand and follow installation access and other HN requirements. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8076471 General General Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will a local A/E be required to certify Local Building Codes and submit designs for Construction Permits? Or will USACE self-permit the designs?
On: Jul 01 2019.
Government Response. . USACE does not self-permit designs. If the task order is design-bid-build (contractors are provided 100% designs with the RFP) then USACE and the A/E will coordinate with the HN for the issuance of HN construction authorizations/permits. Construction contractors may still be responsible for generating additional information/documentation and obtaining some additional authorizations/permits.
These requirements should be provided on a task order by task order basis.
If the task order is design-build and the MATOC contractor is responsible for completing the design, then the MATOC contractor will have the responsibility to ensure the design is capable of obtaining HN authorization and permits. The process for actually obtaining HN authorization/permit varies by country and additional information will be provided with each task order. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8076516 Contracting General Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Background: SOW states "Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed."
Will each Contract holder be required to attend pre-bid site visits for each Task Order? If yes, will a stipend be granted for these site visits?
On: Jul 01 2019.
Government Response. . 1. Yes, it is anticipated that a site visit will be held for each Task Order.
2. No, the Government does not pay any costs associated with a site visit. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8076518 Contracting 00-21-16 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Background: SOW states "this acquisition will be based on competition among all United States firms or US Joint Ventures responding to the solicitation, which will be issued to qualified firms that meet or have the ability to obtain Facility Clearance (FCL) IAW the requirement as set forth by the Defense Security Service."
Will this be a Classified Contract? Will safeguarding and processing of classified data be required?
On: Jul 01 2019.
Government Response. . The MATOC is unclassified. Task Orders may be classified. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8076522 Contracting 00 21 16 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Background: A Top Secret Facility Site Clearance IS NOT required for this MATOC however individual projects may require Statements of Affiliation (SOAs) for all companies. All contractors must have personnel that meet the U.S.
citizenship requirements identified in the task order Scope of Work as some task orders will require only U.S. citizens to perform on those task orders.
Questions:
Page 6 of 10ProjNet: Logged In User
1. If a TS Facility Clearance is not required, but a Facility Clearance is required, does that mean a minimum of having or the ability to have a Secret Level Facility Clearance is a requirement?
2. Will there be Task Orders that require Classified Processing, and if so what is the highest level of processing that may be required?
3. If some Task Orders are Classified, how are permits to be obtained in each country?
4. Will redacted drawings and Specs be submitted to local authorities for Permitting Applications? 5. Will local A/E firms be able to review, sign, translate, etc the design documents?
On: Jul 01 2019.
Government Response. . 1. Yes.
2. Possibly.
3. This will be determined at the task order level.
4. Possibly.
5. Possibly.
These will be answered at the Task Order level. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8076528 General 01 33 16, paragraph 1.4.1 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Background: SOW states "The DOR must be legally licensed to perform design work in the jurisdiction the construction is performed."
Question: Due to the sensitivities of the Task Orders, the specialty SCIF design requirements, the potential classified nature of them, the requirements to meet UCF and IBC requirements, and the requirements for U.S. design firms to perform the work, is it acceptable to have a local A/E design firm, licensed in the country where the project is to be performed, be a consultant to the U.S. Designer of Record to ensure local codes are met and permits are filed properly?
On: Jul 01 2019.
Government Response. . Possibly. Certain Task Orders may require only U.S. personnel and subcontractors to perform the work. This will be determined at the Task Order level. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8076601 Contracting Specs Specs Comment Classification: UNCLASSIFIED (U)
Is there a minimum or maximum for project ROM in price to be considered relevant for the subject solicitation?
On: Jul 02 2019.
Government Response. . See Section 01 00 00 - General Requirements/Summary of Work for the Task Order limitations. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8083519 General ICS 705 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Does USACE expect to achieve ICD 705 certification on all or the majority of task orders and which agency is the certifying agency for ICD 705 accreditation?
On: Jul 08 2019.
Government Response. . 1. Yes.
2. Accrediting Official will vary depending on the Task Order. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8084429 Construction Management page 30 of 230
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Page 7 of 10ProjNet: Logged In User
Factor 2 Management support there appears to be a typo, please confirm that the management approach section can have a total of 30 complete pages. The paragraph states that "if more than 20 pages submitted, only the first 30 pages will be reviewed and evaluated.
On: Jul 09 2019.
Government Response. . Corrected via Amendment 0001. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8084432 Construction Management Page 31 of 230
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
There is no page limited listed for Factor 3 A/E Team, is there a page limit?
On: Jul 09 2019.
Government Response. . No page limit for Factor 3. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8084442 Construction Management Page 31 of 230
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please confirm that the three design projects requested under A/E team can be totally new projects not included in the first five projects requested in Factor 1, Past Performance of Construction Projects
On: Jul 09 2019.
Government Response. . Correct. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8084545 Construction Management
SF 1442 Cover page Section 13
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Due to national holiday would it be possible to delay the submission of Phase I submission until July 24th, 2019?
On: Jul 09 2019.
Government Response. . No. Proposal due date remains. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8084994 Contracting Specs Specs Specs Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
As the July 4th holiday was during the week, my partners and affiliates have scheduled summer holidays either last week or this coming week- we are respectfully requesting a one week extension for the delivery of phase one...
On: Jul 09 2019.
Government Response. . No. Proposal due date remains. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8085343 General SF 1442 Page 30 of 230 SF1442 Page31 and33 of 230 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Are Letters of Commitments and Resumes required in Management Approach Phase I or in Technical Approach Phase II Narrative?
It seems appropriate that the Key personal resumes, qualifications and letter of commitment should be included in Phase II submission. The page 31 paragraph 2, includes that the organization structure should be explained in Phase I submission including roles and responsibilities for Key personnel.
Page 8 of 10ProjNet: Logged In User
Page 30 Factor 2: Management Approach submissions states, The organization chart, resumes (if provided), and letters of commitment are not considered part of the 30 page limitation. NOTE: Pages that exceed the required page limitations will not be evaluated. Additional pages over the maximum allowed will not be evaluated by the Government.
In this sentence the owner accepts that resumes may not be provided in Phase I submission.
The Phase II Technical Approach Narrative Key Personnel requirements requires names and qualifications, and letters of commitment.
Please confirm resumes and letters of commitment are not required in Phase I Management Approach submission.
On: Jul 09 2019.
Government Response. . Letters of Commitment are required if the Offeror is using the Experience/Past Performance of another firm. Letters of Commitment could be submitted in both Phases for different Factors. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8085362 Other N/A N/A Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will the Contracting Officer be releasing the presentations from the pre-proposal conference? When can we expect to see these documents?
On: Jul 09 2019.
Government Response. . Issued via Amendment 0001. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8085367 Other N/A N/A Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Page 28 of 230 paragraph 5 Teaming arrangements states that the proposal include an agreement that has been executed between/among all team members. Please confirm that this refers to TAs between the prime and individual key subcontractors only since there is no teaming relationship between key subcontractors.
On: Jul 09 2019.
Government Response. . Correct. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8085379 Other N/A N/A Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Federal holidays and summer vacations are impacting our team's availability to submit a compliant proposal. We respectfully request a 30-day extension to the Phase 1 due date.
On: Jul 09 2019.
Government Response. . Proposal due date remains. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8086022 Contracting Page 26 d Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please confirm that the font for tables, charts, and graphics can be 8 point.
On: Jul 10 2019.
Government Response. . Smaller font is acceptable for anything other than the narrative text provided it is easy to read otherwise it may not be considered. On: Jul 11 2019 Current Request Status: Request Closed
Page 9 of 10ProjNet: Logged In User
Information for this report is procurement sensitive.
8086024 Contracting Attachment B Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please verify that submission of the Pricing Schedule is not required. The instructions regarding Attachment B:
Pricing Schedule #1 do not give any direction regarding the submission of Pricing Schedule 1 in Phase 1, Factors 1, 2, or 3, nor is it identified in the evaluation criteria.
On: Jul 10 2019.
Government Response. . Correct. Pricing is NOT required in Phase I. On: Jul 11 2019 Current Request Status: Request Closed
Information for this report is procurement sensitive.
Report Complete
UNCLASSIFIED\\FOR OFFICIAL USE ONLY
Patent 11/892,984 ProjNet property of ERDC since 2004.
Page 10 of 10ProjNet: Logged In User