About this file

This document provides supplemental conditions for federal construction projects in Germany. It outlines requirements for referenced standards, submittals, access control procedures, and permits. Contractors must follow all technical standards described and obtain any required special permits for U.S. construction projects. The document also details additional responsibilities for design-build projects, such as ensuring design compliance with host nation requirements. It concludes with instructions for final inspections to be completed jointly with German and U.S. government representatives prior to project closeout.

The related federal contract opportunity is a solicitation for an Indefinite Delivery Indefinite Quantity Multiple Award Task Order Contract for Sensitive Compartmented Information Facility construction projects in Europe. Task orders will primarily include new construction or renovation of buildings for SCIFs in Germany, Belgium, Poland, Romania, or Estonia. Offerors must have or be able to obtain a Facility Clearance. Evaluation criteria include past performance, management approach, team qualifications, and a sample project narrative with price. Proposals are due by July 17, 2019. With an estimated value of $49.9 million over three years, the MATOC will be awarded to at least two responsible offerors deemed to provide the best value to the government.

SECTION 00 74 10 SUPPLEMENTAL CONDITIONS FOR PROJECTS IN GERMANY (NAU) MAR 2019

View the file

Other files for this federal contract opportunity

Other files attached to FY19 SCIF MATOC, newest first.
File Type Posted
B.08.03_19R0027_Am-0001_SF30_FINAL.pdf PDF
B.08.03_A2_Contractor_Past_Experience_Information_Sheet_Am-0001.docx DOCX document
B.08.03_Pre-proposal_conference_sign_in_sheet_Am-0001.pdf PDF
B.08.03_A7_BidBond_Form_SF24.pdf PDF
B.08.03_Responses_to_RFIs_Am-0001_FINAL.pdf PDF
B.08.03_Pre-proposal_conference_slides_FINAL_Am-0001.pdf PDF
01_78_00.pdf PDF
00_74_02.pdf PDF
01_32_01.pdf PDF
01_32_16.pdf PDF
Construction_Signs_(DE).pdf PDF
01_45_10.pdf PDF
A6_ProjNet_Instructions.pdf PDF
00_74_00.pdf PDF
ICS_705_Technical-Specifications-SCIF-Construction.pdf PDF
A3USACEPastPerformanceQuestionnaire.docx DOCX document
A2Contractor_Past_Experience_Information_Sheet_Final.docx DOCX document
01_33_00.pdf PDF
ICS-705-1.pdf PDF
A4AE_Experience_FINAL.docx DOCX document
01_33_16.pdf PDF
01_30_00.pdf PDF
01_45_05.pdf PDF
01_45_00.pdf PDF
ABPRICING_SCHEDULE.XLSX XLSX spreadsheet
01_45_01.pdf PDF
00_74_19.pdf PDF
A1Contractor_Past_Experience_Overview_Sheet_Final.docx DOCX document
Construction_Signs_(EN).pdf PDF
A5SAMPLE_LETTER_OF_COMMITMENT.pdf PDF
W912GB19R0027_FINAL.pdf PDF
01_30_05.pdf PDF
01_35_26.pdf PDF
01_78_23.pdf PDF
FCL_Orientation_Handbook_10OCT18.pdf PDF
00_74_18.pdf PDF
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 74 10

SUPPLEMENTAL CONDITIONS FOR PROJECTS IN GERMANY (NAU)

03/19

PART 1 GENERAL

1.1 REFERENCED STANDARDS

1.2 SUBMITTALS

1.3 ACCESS CONTROL PROCEDURES

1.4 PERMITS

1.4.1 Special Permits for U.S. Construction

1.4.2 Additional Requirements for Design-Build Projects

1.4.3 Final Inspection

-- End of Section Table of Contents --

DOCUMENT 00 74 10 Page 1

SECTION 00 74 10

SUPPLEMENTAL CONDITIONS FOR PROJECTS IN GERMANY (NAU)

03/19

PART 1 GENERAL

1.1 REFERENCED STANDARDS

Any DINs referenced in these specifications are incorporated only to the extent that they describe a technical standard to which the contractor must perform the work described in the specifications.

Any language that does not describe a technical standard, such as, for example, payment procedures, how specifications are to be drafted, or references to parts of the Vergabe- und Vertragsordnung für Bauleistungen (VOB), are not included in this contract, and are explictly not to be interpreted as establishing any requirement which would establish a right for additional payment beyond that specified in the contract documents.

Neither the VOB A nor B are included in this contract either explicitly or by reference with the exception of references to the VOB in contract clauses. All work required to complete this project is included in the contract price. No distinction will be made between associated tasks and special tasks. The contractor is solely responsible to determine quantities and work needed based on the contract documents.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Art. 30 ABG 75 Permits; G

SD-11 Closeout Submittals

ABG 7B Documentation

1.3 ACCESS CONTROL PROCEDURES

Application for and use of badges will be as directed. Obtain access to the installation by participating in the Garrison Access Control System, or by obtaining passes each day from the Base Pass and Identification Office.

Costs for obtaining passes through the Garrison are the responsibility of the Contractor. One-day passes, issued through the Base Pass and Identification Office, will be furnished without charge. Furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for all personnel requesting badges. This form is available at http://www.uscis.gov/portal/site/uscis by searching or selecting Employment Verification (Form I-9). Immediately report instances of lost or stolen badges to the Contracting Officer.

DOCUMENT 00 74 10 Page 2

a. The Garrison Program is a voluntary program in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to one year, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit. The Government performs background screening and credentialing. Throughout the year the Contractor employee must continue to meet background screening standards.

Periodic background screenings are conducted to verify continued participation and installation access privileges. Under the program, no commercial vehicle inspection is required, other than for Random Anti-Terrorism Measures (RAM) or in the case of an elevation of Force Protection Conditions (FPCON). Any time invested, or price(s) paid, for obtaining credentials will not be compensated under this contract.

b. One-Day Passes: Participation in the Garrison procedure is not mandatory, and if the Contractor chooses to not participate, the Contractor's personnel will have to obtain daily passes, be subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government will not be responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the Garrison procedure.

1.4 PERMITS

1.4.1 Special Permits for U.S. Construction

As part of this project, the US Government will coordinate with the applicable German authorities for Federal Building (Bundesbauaufgaben) to identify any special permissions or notifications required to be obtained by the U. S. Government. These permissions or notifications are separate and distinct from those required to comply with the remainder of the contract. The contractor shall coordinate their work with these requirements.

Where the U.S. Government is required to obtain permits in accordance with Art. 30 of the ABG 1975, the Government will notify the contractor and the contractor shall prepare all necessary documentation and submit this information under a submittal titled Art. 30 ABG 75 Permits. This includes providing documentation to show compliance with permit requirements.

As part of this coordination, the contractor shall prepare all necessary documentation and ensure the US Government receives it timely to prevent delays in the execution of the contractors work. Changes, revisions, or adjustments to the documentation may be required after coordination with Host Nation Construction and Permitting Authorities, and the contractor shall be responsible for making any changes as part of their responsibility under this section.

Information required to be provided by the contractor includes, but is not limited to:

a. Documentation required by the Honorarordnung für Architekten und Ingenieure (HOAI) Leistungsphasen (LP) 4 Genehmigungsplanung and 8 Objektüberwachung - Bauüberwachung und Dokumentation

b. Documentation required by the German state where the construction

DOCUMENT 00 74 10 Page 3 work is performed (Landesbauordnung), to include certificates and registrations of personnel performing work for the contractor.

c. Compliance with permit requirements and applicable standards (to include inspections by third parties) and provide required documentation.

d. Forms for the permitting process for all relevant trades involved in the project

1.4.2 Additional Requirements for Design-Build Projects

This paragraph applies only to design-build projects: nothing in this paragraph shall be construed to require the contractor to prepare a design unless this contract is specifically identified as a design-build contract.

The special permits for U. S. Construction described above may depend upon, or be impacted by, the contractors design. As part of the contractors design responsibility under this contract, the contractor shall coordinate their design with these requirements and shall be responsible for ensuring their design and the resulting construction complies with any conditions, provisions, or restrictions identified by the German Government as part of this process.

1.4.3 Final Inspection

Prior to acceptance of the project by the Government, a final inspection with representatives of the German and US Governments will be conducted.

This inspection shall be performed in accordance with the procedures established in the Auftragsbautengrundsätze for US Forces (ABG 1975) and documented using the ABG7B form. Additional information regarding the ABG 1975 is available (in German) at the following website:

http://www.abg-plus.de.

As part of this final inspection requirement, the Contractor shall coordinate with the German Government, in conjunction with the U.S.

Government, the requirements for proper final inspection in accordance with these procedures and submit any information required in accordance with the Richtlinien für die Durchführung von Bauaufgaben des Bundes (RBBau) Article K14 (Bauakte). the submittal will be provided by the contractor under a submittal titled ABG 7B Documentation.