This document contains a quality control plan section from construction specifications and details for a federal construction contract opportunity. The quality control plan outlines requirements for construction quality control organization and personnel, submittals, inspections, documentation and reporting. It specifies preparatory, initial and follow-up quality control phases. The federal contract opportunity is a multiple award task order contract for sensitive compartmented information facility construction projects in Europe. Task orders will address new construction and renovation, including excavation, plumbing, demolition, electrical, structural, mechanical and concrete work. Offerors must have or be able to obtain a facility security clearance. Proposals were due by July 17, 2019. The estimated contract value is not to exceed $49.9 million over three years.

SECTION 01 45 00 QUALITY CONTROL (NAU) FEB 2019

View the file

Other files for this federal contract opportunity

Other files attached to FY19 SCIF MATOC, newest first.
File Type Posted
B.08.03_19R0027_Am-0001_SF30_FINAL.pdf PDF
B.08.03_A2_Contractor_Past_Experience_Information_Sheet_Am-0001.docx DOCX document
B.08.03_Responses_to_RFIs_Am-0001_FINAL.pdf PDF
B.08.03_Pre-proposal_conference_slides_FINAL_Am-0001.pdf PDF
B.08.03_Pre-proposal_conference_sign_in_sheet_Am-0001.pdf PDF
B.08.03_A7_BidBond_Form_SF24.pdf PDF
01_32_16.pdf PDF
Construction_Signs_(DE).pdf PDF
01_45_10.pdf PDF
A6_ProjNet_Instructions.pdf PDF
00_74_00.pdf PDF
ICS_705_Technical-Specifications-SCIF-Construction.pdf PDF
01_78_00.pdf PDF
00_74_02.pdf PDF
01_32_01.pdf PDF
Construction_Signs_(EN).pdf PDF
A5SAMPLE_LETTER_OF_COMMITMENT.pdf PDF
W912GB19R0027_FINAL.pdf PDF
01_30_05.pdf PDF
01_35_26.pdf PDF
01_78_23.pdf PDF
00_74_10.pdf PDF
FCL_Orientation_Handbook_10OCT18.pdf PDF
00_74_18.pdf PDF
A3USACEPastPerformanceQuestionnaire.docx DOCX document
A2Contractor_Past_Experience_Information_Sheet_Final.docx DOCX document
01_33_00.pdf PDF
ICS-705-1.pdf PDF
A4AE_Experience_FINAL.docx DOCX document
01_33_16.pdf PDF
01_30_00.pdf PDF
01_45_05.pdf PDF
ABPRICING_SCHEDULE.XLSX XLSX spreadsheet
01_45_01.pdf PDF
00_74_19.pdf PDF
A1Contractor_Past_Experience_Overview_Sheet_Final.docx DOCX document
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 45 00

QUALITY CONTROL (NAU)

02/19

PART 1 GENERAL

1.1 PURPOSE

1.2 REFERENCES

1.3 SUBMITTALS

1.4 QUALITY CONTROL ORGANIZATION

1.5 CONSTRUCTION QUALITY CONTROL (CQC) PERSONNEL

1.5.1 Personnel

1.5.2 Training

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.1.1 Quality Control System Requirements

3.1.2 Content of Quality Control Plan

3.2 CONSTRUCTION QUALITY CONTROL (CQC) PLAN

3.2.1 Acceptance of Plan

3.2.2 Notification of Changes

3.3 COORDINATION MEETING

3.4 SUBMITTALS AND DELIVERABLES

3.5 CONTROL

3.5.1 Preparatory Phase

3.5.2 Initial Phase

3.5.3 Follow-up Phase

3.5.4 Additional Preparatory and Initial Phases

3.6 TESTS

3.6.1 Testing Procedure

3.6.2 Testing Laboratories

3.6.2.1 Capability Check

3.6.3 Onsite Laboratory

3.7 COMPLETION INSPECTION

3.7.1 Punch-Out Inspection

3.7.2 Pre-Final Inspection

3.7.3 Final Acceptance Inspection

3.8 DOCUMENTATION

3.8.1 Quality Control Activities

3.8.2 QC Report Preparation and Submission Requirements

3.8.2.1 Projects Using Section 01 45 05

3.8.2.2 Projects Using Section 01 45 06

3.9 NOTIFICATION OF NONCOMPLIANCE

-- End of Section Table of Contents --

SECTION 01 45 00 Page 1

SECTION 01 45 00

QUALITY CONTROL (NAU)

02/19

PART 1 GENERAL

1.1 PURPOSE

This section establishes the Quality Control requirements for construction projects and for the construction activities under a Design-Build contract. Section 01 45 10 Design Quality Control establishes additional Quality Control requirements for the design activities on a Design-Build contract.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D3740 (2012a) Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction

ASTM E329 (2014a) Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Construction Quality Control (CQC) Plan; G

SD-07 Certificates

Testing Laboratory Certification

1.4 QUALITY CONTROL ORGANIZATION

Maintain the QC staff at full strength at all times. When it is necessary to make changes to Quality Control staff, revise the QC Plan to reflect the changes and submit the changes to the Contracting Officer for acceptance.

SECTION 01 45 00 Page 2

QC staff shall have complete authority and responsibility to take any action necessary to ensure Contract compliance.

All personnel are subject to acceptance by the Contracting Officer.

Provide adequate office space, filing systems and other resources as necessary to maintain an effective and fully functional QC organization.

Promptly complete and furnish all letters, material submittals, shop drawing submittals, schedules and all other project documentation to the QC organization. The QC organization is responsible to maintain these documents and records.

1.5 CONSTRUCTION QUALITY CONTROL (CQC) PERSONNEL

1.5.1 Personnel

The contractor shall provide CQC Personnel in accordance with Section 01 45 05 CONTRACTOR SITE PERSONNEL REQUIREMENTS or Section 01 45 06 JOB ORDER CONTRACT (JOC) CONTRACTOR SITE PERSONNEL REQUIREMENTS (NAU). Refer to the contract documents for the section applicable to this contract.

1.5.2 Training

The CQC System Manager, Alternate CQC System Manager, and CQC Designees are required to have completed the Construction Quality Management (CQM) for Contractors course. This course is periodically offered by the the Army Corps of Engineers. Contact the Contracting Officer for information on the next scheduled class.

The Construction Quality Management Training certificate expires after 5 years. No one may be appointed or continue to serve in a position requiring this training if their certificate has expired. Retaking the course is required to obtain a new certificate.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.1.1 Quality Control System Requirements

Establish and maintain an effective QC system. QC consist of plans, procedures, and organization necessary to produce an end product which complies with the Contract requirements. The QC system covers all operations, both onsite and offsite, and is keyed to the proposed sequence of operations necessary to perform all works required by the contract.

3.1.2 Content of Quality Control Plan

Include, as a minimum, the following to cover all activities, both onsite and offsite, including work by subcontractors fabricators, suppliers and purchasing agents:

a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff will implement the three phase control system for all aspects of the work

SECTION 01 45 00 Page 3 specified.

b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a QC function.

c. A copy of the letter to the CQC SM signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC SM, including authority to stop work which is not in compliance with the Contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will be issued by the CQC System Manager.

d. Procedures for scheduling, reviewing, certifying, and managing submittals. These procedures must be in accordance with Section

01 33 00 SUBMITTAL PROCEDURES.

e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test.

f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.

g. Procedures for tracking deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.

h. Reporting procedures, including proposed reporting formats.

i. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and is identified by different trades or disciplines, or it is work by the same trade in a different environment. Although each section of the specifications can generally be considered as a definable feature of work, there are frequently more than one definable features under a particular section. This list will be agreed upon during the coordination meeting.

3.2 CONSTRUCTION QUALITY CONTROL (CQC) PLAN

Submit no later than 45 calendar days prior to mobilization and at least 14 calendar days prior to the coordination meeting discussed in paragraph COORDINATION MEETING, the Construction Quality Control (CQC) Plan.

Construction will be permitted to begin only after acceptance of an CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional work.

3.2.1 Acceptance of Plan

Acceptance of the CQC Plan plan is required prior to the start of construction. Acceptance is conditional and will be predicated on satisfactory performance.

SECTION 01 45 00 Page 4

The Government reserves the right to require the Contractor to make changes in the CQC Plan and operations including removal of personnel, as necessary, to obtain the quality specified.

3.2.2 Notification of Changes

After acceptance of the CQC Plan, notify the Contracting Officer in writing of any proposed change via a revised submittal of the applicable plan.

Proposed changes are subject to acceptance by the Contracting Officer.

3.3 COORDINATION MEETING

Prior to acceptance by the Government of the CQC Plan, meet with the Contracting Officer and discuss the Contractor's quality control system.

During the meeting, a mutual understanding of the system details must be developed, including the forms for recording the CQC operations, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting will be prepared by the Government, signed by both the Contractor and the Contracting Officer and will become a part of the contract file. There can be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings or address deficiencies in the CQC system or procedures which can require corrective action by the Contractor.

3.4 SUBMITTALS AND DELIVERABLES

Submittals, if needed, shall comply with the requirements in Section 01 33 00 SUBMITTAL PROCEDURES. The CQC organization is responsible for certifying that all submittals and deliverables are in compliance with the contract requirements.

3.5 CONTROL

CQC is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. At least three phases of control are required to be conducted by the CQC System Manager for each definable feature of the construction work as follows:

3.5.1 Preparatory Phase

This phase is performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase includes:

a. A review of each paragraph of applicable specifications, reference codes, and standards. Make available during the preparatory inspection a copy of those sections of referenced codes and standards applicable to that portion of the work to be accomplished in the field. Maintain and make available in the field for use by Government personnel until final acceptance of the work.

b. Review of the Contract drawings.

c. Check to assure that all materials and equipment have been tested, submitted, and approved.

d. Review of provisions that have been made to provide required control

SECTION 01 45 00 Page 5 inspection and testing.

e. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the Contract.

f. Examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawings or submitted data, and are properly stored.

g. Review of the appropriate activity hazard analysis to assure safety requirements are met.

h. Discussion of procedures for controlling quality of the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that feature of work.

i. Check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer.

j. Discussion of the initial control phase.

k. The Government needs to be notified at least 48 hours in advance of beginning the preparatory control phase. Include a meeting conducted by the CQC System Manager and attended by the superintendent, other CQC personnel (as applicable), and the foreman responsible for the definable feature. Document the results of the preparatory phase actions by separate minutes prepared by the CQC System Manager and attach to the daily CQC report. Instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.

3.5.2 Initial Phase

This phase is accomplished at the beginning of a definable feature of work. Accomplish the following:

a. Check work to ensure that it is in full compliance with contract requirements. Review minutes of the preparatory meeting.

b. Verify adequacy of controls to ensure full contract compliance. Verify required control inspection and testing are in compliance with the contract.

c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required sample panels as appropriate.

d. Resolve all differences.

e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.

f. The Government needs to be notified at least 48 hours in advance of beginning the initial phase for definable feature of work. Prepare separate minutes of this phase by the CQC System Manager and attach to the daily CQC report. Indicate the exact location of initial phase for definable feature of work for future reference and comparison with follow-up phases.

SECTION 01 45 00 Page 6

g. The initial phase for each definable feature of work is repeated for each new crew to work onsite, or any time acceptable specified quality standards are not being met.

3.5.3 Follow-up Phase

Perform daily checks to assure control activities, including control testing, are providing continued compliance with contract requirements, until completion of the particular feature of work. Record the checks in the CQC documentation. Conduct final follow-up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the deficient work. Do not build upon nor conceal non-conforming work.

3.5.4 Additional Preparatory and Initial Phases

Conduct additional preparatory and initial phases on the same definable features of work if: the quality of on-going work is unacceptable; if there are changes in the applicable CQC staff, onsite production supervision or work crew; if work on a definable feature is resumed after a substantial period of inactivity; or if other problems develop.

3.6 TESTS

3.6.1 Testing Procedure

Perform specified or required tests as required by the contract documents to verify that control measures are adequate to provide a product which conforms to contract requirements. to include compliance with any host nation testing requirements. Upon request, furnish to the Government duplicate samples of test specimens for possible testing by the Government. Testing includes operation and acceptance tests when specified. Perform the following activities and record and provide the following data:

a. Verify that testing procedures comply with contract requirements.

b. Verify that facilities and testing equipment are available and comply with testing standards.

c. Check test instrument calibration data against certified standards.

d. Verify that recording forms and test identification control number system, including all of the test documentation requirements, have been prepared.

e. Record results of all tests taken, both passing and failing on the CQC report for the date taken. Specification paragraph reference, location where tests were taken, and the sequential control number identifying the test. If approved by the Contracting Officer, actual test reports are submitted later with a reference to the test number and date taken. Provide an information copy of tests performed by an offsite or commercial test facility directly to the Contracting Officer. Failure to submit timely test reports as stated results in nonpayment for related work performed and disapproval of the test facility for this Contract.

SECTION 01 45 00 Page 7

3.6.2 Testing Laboratories

All testing laboratories must be validated by the USACE Material Testing Center (MTC) for the tests to be performed in accordance with contract specified US Standards.

Tests required to show compliance with Host Nation standards or requirements shall be performed in accordance with certification standards required by that standard. The contractor shall provide Testing Laboratory Certification substantiating the laboratory is licensed or otherwise authorized by Host Nation authorities to perform the identified test.

3.6.2.1 Capability Check

The Government reserves the right to check laboratory equipment in the proposed laboratory for compliance with the standards set forth in the contract specifications and to check the laboratory technician's testing procedures and techniques. Laboratories utilized for testing soils, concrete, asphalt, and steel are required to meet criteria detailed in ASTM D3740 and ASTM E329 or the Host Nation equivalent.

3.6.3 Onsite Laboratory

Should the contractor establish an onsite laboratory, the Government reserves the right to utilize the Contractor's control testing laboratory and equipment to make assurance tests, and to check the Contractor's testing procedures, techniques, and test results at no additional cost to the Government.

3.7 COMPLETION INSPECTION

3.7.1 Punch-Out Inspection

Conduct an inspection of the work by the CQC System Manager near the end of the work, or any increment of the work established by a time stated in the contract clause, "Commencement, Prosecution, and Completion of Work", or by the specifications. Prepare and include in the CQC documentation a punch list of items which do not conform to the approved drawings and specifications, as required by paragraph DOCUMENTATION. Include within the list of deficiencies the estimated date by which the deficiencies will be corrected. Make a second inspection the CQC System Manager or staff to ascertain that all deficiencies have been corrected. Once this is accomplished, notify the Government that the facility is ready for the Government Pre-Final inspection.

3.7.2 Pre-Final Inspection

The Government will perform the pre-final inspection to verify that the facility is complete and ready to be occupied. A Government Pre-Final Punch List may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government, so that a Final inspection with the customer can be scheduled. Correct any items noted on the Pre-Final inspection in a timely manner. These inspections and any deficiency corrections required by this paragraph need to be accomplished within the time slated for completion of the entire work or any particular increment of the work if the project is divided into increments by separate completion dates.

SECTION 01 45 00 Page 8

3.7.3 Final Acceptance Inspection

The Contractor's Quality Control Inspection personnel, plus the superintendent or other primary management person, and the Contracting Officer's Representative is required to be in attendance at the final acceptance inspection. Additional Government personnel including, but not limited to, those from Base/Post Civil Facility Engineer user groups, and major commands can also be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the Pre-Final inspection. Notify the Contracting Officer at least 14 days prior to the final acceptance inspection and include the Contractor's assurance that all specific items previously identified to the Contractor as being unacceptable, along with all remaining work performed under the Contract, will be complete and acceptable by the date scheduled for the final acceptance inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with the Contract clause titled "Inspection of Construction".

3.8 DOCUMENTATION

3.8.1 Quality Control Activities

The contractor shall use the Resident Management System - Contractor Mode as required by Section 01 45 01 to maintain current records providing factual evidence that required quality control activities and tests have been performed. Include in these records the work of subcontractors and suppliers that includes, as a minimum, the following information:

- Weather conditions encountered.

- The number of personnel working and number of hours worked.

- Operating plant/equipment with hours worked, idle, or down for repair.

- Work performed each day, giving location, description, and by whom. When Network Analysis (NAS) is used, identify each phase of work performed each day by NAS activity number.

- Test and control activities performed with results and references to specifications/drawings requirements. Identify the control phase (Preparatory, Initial, Follow-up). List of deficiencies noted, along with corrective action.

- Quantity of materials received at the site with statement as to acceptability, storage, and reference to specifications/drawings requirements.

- Submittals and deliverables reviewed, with Contract reference, by whom, and action taken.

- Offsite surveillance activities, including actions taken.

- Job safety evaluations stating what was checked, results, and instructions or corrective actions.

- Instructions given/received and conflicts in plans and specifications.

SECTION 01 45 00 Page 9

3.8.2 QC Report Preparation and Submission Requirements

3.8.2.1 Projects Using Section 01 45 05

When Section 01 45 05 CONTRACTOR SITE PERSONNEL REQUIREMENTS (NAU) is part of this contract, the contractor shall prepare a report documenting the above items for each day construction work occurs on site. When no construction work occurs, a report is not required provided the period of no work is less than 7 calendar days. The first report after the period of no work shall indicate the non-work period.

For all non-work periods of 7 days or longer, and during the Design phase of a Design-Build project where no construction is ongoing, the report shall be prepared at least weekly.

The report shall be prepared in RMS-CM and submitted through that system.

Hard copy documents are not required.

3.8.2.2 Projects Using Section 01 45 06

When Section 01 45 06 JOB ORDER CONTRACT (JOC) CONTRACTOR SITE PERSONNEL REQUIREMENTS (NAU) is part of this contract, the contractor shall prepare a report documenting the above items at least once per week for any week where any design or construction work occurs.

The report shall be prepared in RMS-CM and submitted through that system.

Hard copy documents are not required.

3.9 NOTIFICATION OF NONCOMPLIANCE

The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. Take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, will be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer can issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for extension of time or for excess costs or damages by the Contractor.

-- End of Section --