US Army Corps of Engineers ®
Technical Specifications
ERI: Improve Support Infrastructure
03/22/2017
AECOM International, Inc.
Siemensstraβe 10 Neu‐Isenburg, 63263
Technical Specifications
ERI: Improve Support Infrastructure
03/22/2017
AECOM International, Inc.
Siemensstraβe 10
Neu‐Isenburg, 63263
PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 73 15.01 GOVERNMENT FIELD OFFICE
00 73 15.15 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
00 73 15.50 GENERAL CONDITIONS FOR CONSTRUCTION PROJECTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 26.10 ADDITIONAL SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS FOR
PROJECTS IN THE EUROPEAN UNION
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 01.10 USACE QUALITY CONTROL SYSTEM (QCS)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 COMPLETION PROCEDURES
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE
03 42 13.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE
CONSTRUCTION
DIVISION 13 - SPECIAL CONSTRUCTION
13 10 00 NAVAIDS
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 13.00 40 MEDIUM-VOLTAGE CABLES
26 56 20.00 10 AIRFIELD AND HELIPORT LIGHTING AND VISUAL NAVIGATION AIDS
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 01 26.71 GROOVING FOR AIRFIELD PAVEMENTS
32 11 10 DRAINAGE LAYER
32 11 16 SUBBASES FOR RIGID AND FLEXIBLE PAVING
32 11 23 AGGREGATE BASE COURSE
32 12 10 BITUMINOUS TACK AND PRIME COATS
32 12 15.13 HOT-MIX ASPHALT AIRFIELD PAVING
32 13 11 CONCRETE PAVEMENT FOR AIRFIELDS
32 17 23 PAVEMENT MARKINGS
32 31 13 CHAIN LINK FENCES AND GATES
32 92 19 SEEDING
PROJECT TABLE OF CONTENTS Page 2
DIVISION 33 - UTILITIES
33 40 00 STORM DRAINAGE UTILITIES
33 46 16 SUBDRAINAGE SYSTEM
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
-- End of Project Table of Contents --
SECTION 00 07 15.01 Page 1
SECTION 00 73 15.01
GOVERNMENT FIELD OFFICE (04/17)
PART 1 GENERAL
1.1 General
The work covered by this section consists of furnishing all labor, materials, equipment, and services and performing all work required for or incidental to the items herein specified. No separate payment will be made for the construction and services required by this section, and all costs in connection therewith shall be included in the overall cost of the work unless specifically stated otherwise.
This specification does not establish the requirements for the contractors site facilities; the contractor is responsible for providing adequate site facilities for the use of their personnel in accordance with other contract terms and conditions.
1.2 Government Field Office
The contractor shall be responsible for providing an office for the sole use of government personnel, in a structure physically separated from the contractor’s site offices, and shall be maintained in good condition by the Contractor until completion of all work under this contract.
Facility shall be furnished at a location designated by the Contracting Officer, approved by the Contracting Officer, and available for use concurrent with availability of Contractor's site office or within 15 calendar days of Notice to Proceed, whichever occurs first.
1.2.1 Office
The Contractor shall provide the Government with an office with a minimum of 40 square meters in floor area, with windows and a door with lockset individually keyed with two keys, and one battery operated smoke detector in each room (contractor shall provide and replace batteries in each smoke detector at least twice yearly).
The walls and ceiling of the office shall be insulated. All windows shall be screened. The windows shall be openable and be securely fastened from the inside. Glass panels in windows shall be protected by bars or heavy mesh screens to prevent easy access to the building through these panels.
The office shall contain a minimum of eight (8) standard electrical outlets meeting local requirements and additionally provide for delivery of a minimum 3000 Watts.
The office shall contain an integral toilet facility with western-type (with a push-type flush button) toilet fixture (bowl) which shall hold water in it at all times and a wash basin. The toilet facility shall be supplied with liquid soap, toilet paper, and paper towels for daily use.
SECTION 00 07 15.01 Page 2
Adequate quantity of these supplies shall be maintained on site and replaced as needed.
The office facility shall contain a kitchenette type facility with a counter top/work area with a minimum surface area of 55cm (W) by 150 cm (L). A minimum of two electrical outlets (local current) shall be located adjacent to the counter top.
Hot water for all faucets shall be provided.
The office facility, including all furniture, equipment, and connections, will remain the property of the Contractor and, upon completion of work under this contract, shall be removed from the site by the Contractor and the site returned as nearly as practical to the original conditions.
1.2.2 Furniture and Supplies
The contractor shall furnish the office with the following equipment. All furnishing shall be new and manufactured by a recognized supplier of office equipment. All items shall be assembled, installed, and maintained by the contractor.
• Two desks (minimum 80 cm x 150 cm) double pedestal with lockable drawers
• One Desk chair for each desk with arms, swivel tilt, hydraulic height- adjustable, medium back, fabric covered seat cushion, castored
• One conference table (minimum 120 cm x 250 cm), not less than six new arm-chairs, castored
• Three file cabinets, capable of holding US letter-size documents, with a minimum five drawers each
• Two bookcases with a minimum of five shelves each. Minimum dimensions are 120 cm (W) x 200 cm (H) x 30 cm (D).
• A clock, wall hung, quartz, minimum 12” dial, battery powered.
• Plan racks capable of holding two full-size set of contract plans.
• Provide a dry-erase board with a minimum dimension of 1.5 m by 1.0 m.
Dry erase markers (minimum four different colors) shall be provided and replaced as depleted.
• Microwave (minimum 0.028 cubic meter )
• Refrigerator (minimum 0.70 cubic meter)
The contractor shall not be responsible for providing office supplies, including computers, copiers, or paper except as specifically identified in other specifications or the scope of work.
1.2.3 Lighting Requirements
The office facility shall include suitable electric lighting to meet the minimum lighting requirements (luminance) of Administrative areas as indicated in EM385-1-1
1.2.4 Heating/Cooling Requirements
The contractor shall be responsible for providing heating and cooling capable of maintaining an interior temperature of between 16° Celsius and 25° Celsius in all seasons.
SECTION 00 07 15.01 Page 3
Refrigerant (if applicable) shall be one of the fluorocarbon gases that has an Ozone Depletion Potential (ODP) of less than or equal to 0.05.
1.3 Utilities
The contractor shall provide connections to all utilities, including water, sewer, and electric mains. Exterior utilities shall be permanently installed and connected with existing utilities or generator. Exposed utilities shall be insulated to prevent freezing. Contractor shall ensure an adequate hot water supply is available such as through the use of water heaters. All utility connections shall be connected and disconnected in accordance with local codes and to the satisfaction of the Contracting Officer.
If electrical service is not available in the immediate vicinity the contractor may request, subject to approval of the Contracting Officer, the use of generator(s) to provide electrical service. If approved, the contractor shall be responsible for providing all fuel, maintenance, and other services necessary to maintain electrical service during all hours the contractor is on site.
1.3.1 Drinking Water
The contractor shall provide potable drinking water for the facility that meets or exceeds US Drinking Water standards.
http://water.epa.gov/drink/index.cfm
1.3.2 Telephone
The contractor shall provide telephone installation and connection to telephone service, including telephone equipment (phones), unless no telephone service is available within 10 km of the project site and installation of telephone utilities is not included in the scope of work of this contract.
The contractor shall be responsible for all connection and installation fees. Costs for telephone service, including basic or “monthly” service, and additional services, such as DSL, shall be the responsibility of the Government.
1.3.3 Data Connection
The contractor shall provide DSL connectivity at a minimum of 10 Mbps with a fixed static IP address. All network cables designated for Corps offices will be ran back to the ADSL origination point.
1.4 Maintenance
The contractor shall provide all maintenance and janitorial services, to include emptying of trash at least twice a week and cleaning of the office, including the toilet facilities, weekly.
1.5 Security Requirements
The physical security of the Government personnel, their property, and their office shall be the responsibility of the Contractor throughout the
SECTION 00 07 15.01 Page 4 duration of the contract.
If the project site is outside of the controlled area of an existing military installation, the field office compounds for Government employees shall have 30 meters standoff from a fence enclosing the office and all parking or roads. Additional fencing, earth berms, concrete barriers, controlled access points and the like should be provided to limit access to the site and provide additional building standoff or security.
1.6 RELOCATION
The Contractor shall locate the facility such that it will not require relocation to accommodate the sequence of construction.
-- End of Section --
SECTION 00 73 15.15 Page 1
SECTION 00 73 15.15
TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (01/09)
1. This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
2.
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
c. The delay must occur during the contractual performance period. Weather delays occurring after the required completion date, prior to Notice to Proceed, or during other non-working days are not excusable under the Defaults clause.
3. The following schedule of monthly anticipated adverse weather delays will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER
DELAY WORK DAYS BASED ON (5) DAY WORK
WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
All Other Countries and Locations
8 6 7 6 5 5 5 4 4 6 7 8
Monthly anticipated adverse weather delays shall be adjusted proportionately should the actual work week be based on more or less than 5 work days (i.e. if a 6 day work week, the anticipated adverse weather delay work days for a month would be adjusted by multiplying the number shown above by 6/5).
4. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract performance period, the contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Impacted activities shall be identified by name and activity id on the CQC report.
Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day.
The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual
SECTION 00 73 15.15 Page 2 adverse weather delay days exceeds the number of days anticipated in paragraph 2, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "Default (Fixed Price Construction)".
5. When the contract performance period, or any extension thereof, has passed, no extensions for unusually severe weather will be granted.
SECTION 00 73 15.50 Page 1
SECTION 00 73 15.50
GENERAL CONDITIONS FOR CONSTRUCTION PROJECTS (04/17)
PART 1: GENERAL
1.1 ORGANIZATION AND LAYOUT
1.2 DEFINITIONS
1.3 PAYMENT
1.4 SUBCONTRACTOR COMPLIANCE
1.5 PERMITS AND RESPONSIBILITIES
1.6 CONTRACTOR LIASON AND COMMUNICATION WITH HOST GOVERNMENT AND OTHER
GOVERNMENT OFFICIALS
1.7 IMMUNITY FROM LEGAL PROCESS
1.8 APPLICABLE LAW FOR BREACH OF CONTRACT
1.9 SUBMITTALS
1.10 PUBLIC RELEASE OF INFORMATION
1.10.1 Prohibition
1.10.2 Subcontracts and Purchase Orders
1.11 REFERENCED STANDARDS
1.12 PROHIBITED ITEMS
1.13 PROPRIETARY NAMES
1.14 KEY PERSONNEL, SUBCONTRACTORS AND OUTSIDE ASSOCIATES OR CONSULTANTS.
1.15 ENGLISH SPEAKING REPRESENTATIVE
1.16 NO WAIVER BY GOVERNMENT
1.17 CONTRACTOR LIAISON WITH HOST GOVERNMENT
1.18 GENERAL SECURITY REQUIREMENTS
1.18.1 Access Guidelines
1.18.2 Responsibility for Physical Security
1.18.3 Access to Operational Areas
1.18.4 Employment
1.18.5 Project-Specific Security Requirements
1.19 EXPERIENCE AND QUALIFICATIONS OF PERSONNEL
1.20 COMMERCIAL POWER INTERRUPTIONS
1.21 EQUIPMENT GUARANTEES
1.22 AS-BUILT DRAWINGS
1.22.1 General
1.22.2 Working As-Built Drawings
1.22.3 Final As-Built Drawings
1.22.4 Execution and Review
1.23 CORRESPONDENCE AND LANGUAGE
1.23.1 Correspondence in the English Language
PART 2: PRODUCTS
PART 3: EXECUTION
3.1 CONTRACTOR RESPONSIBILITY
3.1.1 Protective Measures
3.1.2 Contractor’s Supervision
3.2 PERMISSION TO EXCAVATE
3.3 UTILITY SERVICE INTERRUPTIONS
3.4 CONTRACTOR SITE FACILITIES
3.4.1 Availability and Use of Utility Services
3.4.2 Storage Areas
3.4.3 Trash Disposal
3.4.4 Additional Requirements
3.5 ENVIRONMENTAL PROTECTION
3.5.1 General
3.5.2 Protection of Land Resources
1.23.2 Required Acknowledgement
1.24 COMPLIANCE WITH LOCAL LABOR LAWS
1.25 SUBMITTALS OF PROOF OF QUALIFICATIONS AND EXPIERENCE
SECTION 00 73 15.50 Page 2
3.5.3 Protection of Water Resources
3.7 ROAD MAINTENANCE AND TRAFFIC CONTROL
3.9 USE OF EXPLOSIVE MATERIALS
3.10 PROJECT SIGNS
3.11 WARRANTY
3.12 CONTRACTOR SAFETY PROGRAM
3.13 CONTRACTOR QUALITY CONTROL PROGRAM
3.13.1 General Requirements
3.13.2 Personnel Requirements
3.13.3 Control
3.13.4 Documentation
3.14 PROJECT SCHEDULE
3.14.1 General Requirements
3.14.2 Basis for Payment
3.15 SUBMITTAL PROCEDURES
3.15.1 Transmittal Form
3.15.2 Scheduling
3.15.3 Variations / Substitution Requests
3.15.4 Disapproved Or Rejected Submittals
3.15.5 Approved/Accepted Submittals
3.15.6 Withholding Of Payment
3.6 DISPOSAL OF MATERIAL
3.6.1 Turn-In Salvage Material
3.6.2 Title to Materials
3.8 DUST CONTROL
SECTION 00 73 15.50 Page 3
PART 1: GENERAL
1.1 ORGANIZATION AND LAYOUT
The headings in this document and in other documents of this contract are for convenience of reading only and should not be utilized to interpret the contents of the documents.
Any place in the documents of this contract where singular is used, it can also mean plural and vice versa.
1.2 DEFINITIONS
Unless stated otherwise, the term “Contracting Officer” in these documents refers to the Contracting Officer or Administrative Contracting Officer (ACO) (For the purposes of these specifications, the term “ACO” is understood to mean “Ordering Officer” or OO on Job Order Contracts (JOC); ACO’s have no contractual authority on JOC contracts.
The term “Contracting Officer’s Representative” (COR) refers to the Contracting Officer, Administrative Contracting Officer, or other specifically designated representative. Designation of an ACO or COR will be made in writing by the Contracting Officer and a copy of the designation provided by the ACO or COR to the Contractor, who shall keep a copy with their files.
As used in this specification, the term “local authorities” refers to all civil and military agencies of the host nation, be they national or local, having jurisdiction over any respective part of the project. “Host Nation” as used herein refers to the country where the work is performed and shall include all local, federal, national, and any other governmental entity of the host nation.
1.3 PAYMENT
Separate payment will not be made for compliance with this specification. All costs associated therewith shall be included in the applicable unit prices or lump-sum prices contained in the Bidding Schedule.
1.4 SUBCONTRACTOR COMPLIANCE
Compliance with this specification by subcontractors shall be the responsibility of the Contractor.
1.5 PERMITS AND RESPONSIBILITIES
The contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any applicable laws, codes, and regulations in connection with the prosecution of the work. It shall be similarly responsible for all damages to persons or property that occurs as a result of the contractors fault or negligence. It shall take proper safety and health precautions to protect the work, the workers, the public, and the property of others. It shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire construction work, except for any completed unit of construction thereof which
SECTION 00 73 15.50 Page 4 theretofore may have been accepted.
1.6 CONTRACTOR LIASON AND COMMUNICATION WITH HOST GOVERNMENT AND
OTHER GOVERNMENT OFFICIALS
All communication by the Contractor with all officials, representatives and/or offices of the Host Government in all matters pertaining to the design or construction of this contract, shall be through and in full liaison with the Contracting Officer. This does not relinquish Contractor responsibility for obtaining routine items to conduct day-to-day business, such as visas, permits, and custom clearances.
The contractor is further reminded that only the Contracting Officer or their authorized representative may give the contractor direction in regards to contract interpretation. ONLY a Contracting Officer or Administrative Contracting Officer may modify the contract terms or conditions.
1.7 IMMUNITY FROM LEGAL PROCESS
The contractor agrees to indemnify and save harmless the United States Government against all claims and suits of whatsoever nature arising under or incidental to performance of this contract by any subcontractor against the United States Government. The Contractor further agrees to waive his rights to bring suit or other legal against the United States Government, except as provided in the “Disputes” clause of this contract and in the United States Federal Statutes.
1.8 APPLICABLE LAW FOR BREACH OF CONTRACT
United States law will apply to resolve any claim of breach of this contract.
1.9 SUBMITTALS
A list of submittals has been provided in the attached submittal register. Additional submittals may be required when deemed necessary to adequately describe the work covered in the respective sections.
Each submittal is to be complete and in sufficient detail to allow determination of compliance with contract requirements. Contractor's Quality Control (CQC) System Manager and the Designer of Record, if applicable, shall check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified.
Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited
to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals(including parts list); certifications;
warranties; and other such required submittals.
1.10 PUBLIC RELEASE OF INFORMATION
1.10.1 Prohibition
SECTION 00 73 15.50 Page 5
There shall be no public release of information or photographs concerning any aspect of the materials or services relating to this solicitation, contract, purchase order, or other documents resulting therefrom without the prior written approval of the Contracting Officer.
1.10.2 Subcontracts and Purchase Orders
The Contractor agrees to insert the substance of above paragraph "Prohibition" in each subcontract and purchase order generated for this contract.
1.11 REFERENCED STANDARDS
Unless specifically called out in the specifications, Host Nation Standards shall be used for this contract. Where reference is made in the contract to Host Nation Standards, including, but not limited to those issued by the Deutsches Institut für Normung e.V. (DIN; in English, the German Institute for Standardization) and The European Committee for Standardization or Comité Européen de Normalisation (CEN) (EN Standards), including where such standards are incorporated into the contract in full text or by reference, the reference /incorporation applies only to establish a technical standard or level of performance or quality and does not create substantive rights under the contract.
All costs required to comply with these standards shall be included in the bid price, including the performance of any additional work, such as “associated” and “special” tasks. Notwithstanding any language in any standard, the requirement to provide any necessary material, item of equipment or work, rests with the contractor unless another contract provision clearly states that such will be government furnished.
When standards referenced in a specification are in conflict with each other (such as when a US Standard conflicts with a European or Host Nation standard within the same specification section), Host Nation Standard shall govern unless otherwise specified within the contract documents. A conflict does not exist when standards require separate methods or performance and both are achievable. In these situations, the contractor shall comply with both standards. This does not apply to documents with a different Order of Precedence (for example, a standard referenced in a Contract clause would have a higher order of precedence than one referenced in a specification).
The Contractor shall make available in his site office any standard referenced in the contract specifications or used in the project design and construction.
1.12 PROHIBITED ITEMS
The following is prohibited in this construction project:
a. Use of aluminum for electrical conductors.
b. Embedding aluminum conduit in concrete.
c. Use of fluorescent light ballasts and other products containing
PCB's.
d. Use of urea-formaldehyde foam insulation products.
e. Use of any paint/coatings having a lead content of over 0.06 percent by weight of non-volatile content.
f. Use of any ozone depleting chemicals
SECTION 00 73 15.50 Page 6
g. Use of zinc-chromate
h. Use of materials containing asbestos
The Contractor shall submit only materials, equipment, or systems for approval that have been in service/manufacture for at least two (2) years.
1.13 PROPRIETARY NAMES
Unless specifically identified in the contract as a Sole Source Item, manufacturer's proprietary names indicated for colors, textures and patterns of materials are for the purpose of color, texture and pattern selection only. Other materials are acceptable provided they closely approximate colors, textures and patterns indicated. Any substitutions must conform to all other requirements and must be approved by the Contracting Officer.
1.14 KEY PERSONNEL, SUBCONTRACTORS AND OUTSIDE ASSOCIATES OR CONSULTANTS
In connection with the services covered by this contract, any in-house personnel, subcontractors, and outside associates or consultants identified in the Contractor’s proposal shall be limited to individuals or firms that were specifically identified in the proposal. The Contractor shall obtain the Contracting Officer's written consent before making any substitution for any designated in-house personnel, subcontractors, associates, or consultants.
1.15 ENGLISH SPEAKING REPRESENTATIVE
At all times during the performance of work on this contract, the Contractor shall have a representative, on site, capable of explaining the work operations and receiving instructions in the English language.
The Contracting Officer shall have the right to determine, without appeal of such decision, whether the proposed representative has sufficient technical and linguistic capabilities, and the Contractor shall immediately replace any individual not acceptable to the Contracting Officer.
Notwithstanding any other contractual requirements, the Site Safety and Health Officer, all Quality Control Personnel, the Site Superintendent, and Project Manager shall be able to communicate to site workers and other subordinates in their native language(s) and take direction from the Contracting Officer or Contracting Officers Representative through the designated English Language Speaking Representative.
1.16 NO WAIVER BY GOVERNMENT
The failure of the Government, in any one or more instances, to insist upon the strict performance of any of the terms of this contract or to exercise any option herein conferred shall not be construed as a waiver or relinquishment to any extent of the right to assert or rely upon such terms or option on any future occasion.
1.17 CONTRACTOR LIAISON WITH HOST GOVERNMENT
All communication by the Contractor with all officials, representatives and/or offices of the Host Government in all matters pertaining to the design or construction of this contract, shall be through and in full liaison with the Contracting Officer. This does not relinquish Contractor responsibility for obtaining routine items to conduct day-to-day business, such as visas, permits, and custom clearances.
1.18 GENERAL SECURITY REQUIREMENTS
1.18.1 Access Guidelines
The Contractor shall be responsible for adhering to all guidelines established by local authorities for access to the project/work site(s) and will be responsible for the daily access of their personnel and subcontractor workers. The Contractor is solely responsible for obtaining any required access for both its employees and any subcontractor employees, and ensuring they remain qualified for base access throughout contract performance.
Delays due to difficulty in access will not be justification for time or monetary compensation from the Government.
The Contractor is cautioned to review any Additional Security Guidelines specified elsewhere in this contract for more stringent requirements or specific access conditions.
The Contractor shall be responsible for obtaining installation access for both its employees and any subcontractor employees, and ensuring they remain qualified for base access. The Contractor must maintain access throughout contract performance.
1.18.2 Responsibility for Physical Security
The contract price shall include an amount sufficient to cover all security measures based on local conditions and as required by the Government and as directed by the Contracting Officer throughout the duration of the contract.
a. The Contractor shall be responsible for physical security of all construction materials, supplies, and equipment of every description (including property which may be Government furnished or owned) provided and/or utilized in the execution of this contract.
b. Adequate outside security lighting shall be provided at the Contractor’s temporary facilities.
c. Contractor’s personnel shall assure that all equipment is de-energized and stored in designated storage areas together with supplies upon completion of work. When buildings are unoccupied, lights, water outlets and blowers shall be turned off and windows closed and locked on a floor-to-floor basis as work progresses, followed by locking of all exterior doors upon completion of work. Keys to buildings shall be deposited with the pertinent installation or building duty officer. The Contractor shall be responsible for any losses or damages arising from their failure to secure buildings during and after working hours.
SECTION 00 73 15.50 Page 7
SECTION 00 73 15.50 Page 8
d. The Contractor shall be responsible in the event of theft by their personnel of Government property or personal property of Governmentpersonnel, civilian or military. All lost or misplaced articles found by their employees shall be turned in to the COR.
1.18.3 Access to Operational Areas
Contractor personnel are expressly prohibited and shall be restricted from entering operational buildings or areas without the specific authorization of the COR. To perform work, where "security escorts" are required for access to a facility, the Contractor shall coordinate with the Contracting Officer for access to such facilities.
1.18.4 Employment
Should the continued employment of any person in connection with this contract, or any subcontract hereunder, be deemed by the Contracting Officer to be prejudicial to the interests of the Government, that person shall immediately be removed from the work. In this connection the Contractor agrees that:
a. Cases which may involve disciplinary action against such persons, or the necessity of reassignment or termination of their services, shall be investigated, processed, reported and disposed of, as directed by the Contracting Officer.
b. Employment contracts of all persons employed in connection with this contract, or any subcontract hereunder shall include clauses containing the substance of this clause.
c. Compliance with the foregoing provisions of this clause by subcontractors shall be the responsibility of the Contractor.
1.18.5 Project-Specific Security Requirements
a. Project Fence. The project site shall be full enclosed by a 1.5 meter high construction fence. The fence shall be in accordance with Section 01 50 00 Paragraph 3.8 and EM-385 Section 4 Temporary Facilities. A proposed fence layout is shown on Sheet G-105. The contractor is free to propose alternate fencing layouts, however they are subject to the approval of the Government and Base. The contractor is responsible for maintaining Base access through normally closed gates.
b. Security Guards. Anytime the Contractor needs to open a normally unmanned/closed gate in the Lask Airbase perimeter fence the Contractor shall provide a minimum of two guards and one guard house at the gate to be opened. The guards main obligation will be guarding the entrance/exit gate to the airport area, including verification of entrance permit both personal and for the vehicles. The Executor is obligated to prepare the “security service manual” along with the User that will be obeyed by all the security guards.
c. Security Guard Qualifications. Every security guard on duty must have all documents and equipment mentioned below:
a. License qualifying the guard for physical protection
b. Polish license to carry fire arms
c. 1 PM or KBK
SECTION 00 73 15.50 Page 9
e. Radio – used for communication with the security/emergency services of the complex
f. Flashlight
g. Personal first aid kit
1.19 EXPERIENCE AND QUALIFICATIONS OF PERSONNEL
When qualifications of key personnel referenced in other sections require experience or “related experience”, the experience must be on projects of the same type and nature as the work identified in the project scope of work, and be on contracts with the government of the United States of America, either with the US Army Corps of Engineers or Department of Defense agencies. References and experience must be sufficiently detailed to allow for verification of experience. The Contracting Officer shall have final authority on determining the relevance of any experience submitted. Any individual found to not be in compliance with this paragraph shall be subject to removal by the Contracting Officer.
1.20 COMMERCIAL POWER INTERRUPTIONS
Commercial power interruptions are anticipated during the construction period. In the event of commercial power interruptions, the Contractor shall provide back-up power if they deem necessary, at no additional cost to the U.S. Government. No time extension, however, will be allowed because of commercial power interruptions.
1.21 EQUIPMENT GUARANTEES
When a completed facility is transferred to the User and the facility has equipment installed which is covered by a guarantee, the Contractor shall furnish to the COR the following information:
a. Contract number and a list of all items of equipment, properly identified, that are covered by a guarantee period under the terms and conditions of the contract, including make and model numbers.
b. A copy of all manufacturer's or vendor's guarantee documents.
c. The dates during which the Contractor's guarantee is in effect under the identified individual section and paragraph of the contract specifications for each item of equipment on the list (indicating for each item the date of acceptance for the beginning of the guarantee period, either for beneficial use or final acceptance, whichever is earlier, and the expiration date of the guarantee period).
d. Name of an authorized representative of the Contractor with complete address and telephone number; and the names, addresses and telephone numbers of all subcontractors and/or equipment suppliers or manufacturers specifically designated in writing by the Contractor for direct contact by the COR for implementing the guarantee after transfer of the equipment.
The performance security will not be returned until all implementing equipment guarantees are delivered.
d. Authorization to access to FOR OFFICIAL USE ONLY (FOUO) Information.
SECTION 00 73 15.50 Page 10
1.22 AS-BUILT DRAWINGS
1.22.1 General
The Contractor shall receive the final solicitation drawings in electronic format. These drawings shall be the basis for the working as-built drawings.
The final as-built drawing submittal shall be in Polish and English Languages and shall consist of the following:
a. Four (4) complete copies of the CADD drawing files including all reference files on separate compact or DVD discs.
b. Four (4) sets of final as-built full-size prints.
c. Four (4) sets of final as-built half-size prints.
1.22.2 Working As-Built Drawings
The working as-built drawings shall be print sets taken from the contract drawings. They are kept at the construction site for mark-up by the Contractor to record all as-built conditions, and shall be revised and updated continuously to show the as-built conditions during the progression of the project.
a. Where contract drawings or specifications allow options, only the option selected for construction shall be shown on the as-built drawings.
b. Shop drawings containing as-built information shall be incorporated into the working as-built drawings. This additional information may be added to an existing working as-built drawing or may require the addition of a new drawing to the working as-built drawing set.
The working as-built drawings will be jointly reviewed for accuracy and completeness by the Contracting Officer and the Contractor prior to submission of each pay estimate. Deductions to the pay request shall be made if the As-built drawings are not up to date.
1.22.3 Final As-Built Drawings
The final as-built drawings shall be the final record of construction as installed and completed by the Contractor and as indicated on the working as-built drawings. All changes, variations and/or required additions to the contract drawings shall be included. In the event the Contractor accomplishes additional work which changes the as-built conditions of the facility after submission of the final as-built drawings, the Contractor shall furnish revised and/or additional drawings as required to depict as- built conditions. The requirements for these additional drawings will be the same as for the as-built drawings included in the original submission.
1.22.4 Execution and Review
The Contractor shall mark up two (2) set of paper prints by the red-line process to show the as-built conditions. The as-built marked prints shall be kept current on a weekly basis and available on the jobsite at all times.
SECTION 00 73 15.50 Page 11
Upon completion of the project and within 10 days of the final inspection, the Contractor shall revise the final drawings to reflect the as-built changes to match the approved working as-built drawings.
1.23 CORRESPONDENCE AND LANGUAGE
1.23.1 Correspondence in the English Language
In additional to FAR 52.214-34, it shall be the responsibility of the Contractor to prepare proposals and all documents related to this contract, to include, change orders, shop drawings and submittals, quality control reports, computations, and all correspondence, in the English language. In the event of disputes or litigation arising out of performance of this contract, the contractor will provide English language translations of any documents that are provided to the Government in support of the contractor's position or any documents pertinent to the dispute that are requested by the Government. For the purposes of this paragraph, pertinent means any documents that would normally be considered to be within the scope of discovery in an ASBCA or court proceeding concerning the dispute.
The term 'documents' includes electronic documents including but not limited to email and includes documents generated by subcontractors or suppliers.
In the event a dispute results in litigation, including actions at the ASBCA or actions in U.S. courts, the contractor will be responsible for providing translations of any documents that are within the scope of a discovery request filed by the U.S. Government and for providing certified translations upon request by the U.S. Government.
1.23.2 Required Acknowledgement
The contractor shall acknowledge receipt of any correspondence, to include letters and e-mails, as requested by the government. This may consist of either signing copies of documents or replying to e-mails. Specific instructions shall be provided by the Contracting Officer’s Representative.
1.24 COMPLIANCE WITH LOCAL LABOR LAWS
The Contractor shall comply with all:
(1) Local laws, regulations, and labor union agreements governing work hours; and
(2) Labor regulations including collective bargaining agreements, workers' compensation, working conditions, fringe benefits, and labor standards or labor contract matters.
The Contractor indemnifies and holds harmless the United States Government from all claims arising out of the requirements of this paragraph. This indemnity includes the Contractor's obligation to handle and settle, without cost to the United States Government, any claims or litigation concerning allegations that the Contractor or the United States Government, or both, have not fully complied with local labor laws or regulations relating to the performance of work required by this contract.
Notwithstanding the above, consistent with paragraphs 31.205-15(a) and 31.205-47(d) of the Federal Acquisition Regulation, the Contractor will be reimbursed for the costs of all fines, penalties, and reasonable litigation expenses incurred as a result of compliance with specific contract terms and conditions or written instructions from the Contracting officer.
PART 2: PRODUCTS
Not Used
PART 3: EXECUTION
3.1 CONTRACTOR RESPONSIBILITY
3.1.1 Protective Measures
The Contractor shall be responsible for protective measures during construction and shall provide barricades and protective signs in both the English and host nation languages for the safety of building inhabitants and passers-by. For inside work, the Contractor shall protect floors, furniture, and furnishings, appliances, other objects and structural parts against soiling or damage, by using drop cloths or other suitable coverings.
If specifically stated elsewhere in this contract, the Contractor shall be responsible for removal of furnishings (including furniture, carpets and drapes) and equipment (such as machines which are in addition to equipment which forms part of integral building systems requiring work under the contract) as required for preparation of work areas, and the reinstallation thereof. The Contractor shall replace furnishings and equipment at their original locations upon completion of the work. If not
Where qualifications or experience requirements are set forth in the specifications with respect to equipment and equipment installers, written proof of such qualifications or experience must be provided within thirty
(30) calendar days after contract award, and before placing any order for equipment or before dispatching equipment installers to the project site.
1.25 SUBMITTAL OF PROFF OF QUALIFICATIONS AND EXPIERENCE
SECTION 00 73 15.50 Page 12 specifically stated elsewhere in this contract to be the Contractor’s responsibility, furnishings and equipment as described above required to be removed for preparation of work areas, and the reinstallation thereof, shall be the responsibility of Government forces.
Repair of damages to personal property, buildings, vehicles, ground or other Government property caused directly or indirectly by their personnel shall be the Contractor's responsibility and shall be repaired or replaced at the Contractor’s expense.
3.1.2 Contractor’s Supervision
The Contractor shall provide adequate supervision of all employees to ensure complete and satisfactory performance of all work required in accordance with the specifications and terms of the contract. The Contractor shall be at the site of the work whenever services are being performed to receive instructions from the Contracting Officer.
SECTION 00 73 15.50 Page 13
3.2 PERMISSION TO EXCAVATE
Before excavation begins, the Contractor shall obtain all necessary permits in addition to written permission to excavate from the appropriate local authorities having jurisdiction.
The contractor remains responsible for identifying and confirming the location of all utilities prior to performing any excavation and shall be responsible for repairing any damages to utilities caused by their construction activities at no additional cost to the government.
Additional requirements are specified elsewhere in the contract, including but not limited to the contract clauses and in EM 385-1-1.
3.3 UTILITY SERVICE INTERRUPTIONS
The Contractor shall be responsible for coordination with appropriate utility companies and installation representatives to obtain all necessary permits and approvals for utility service interruptions in writing. If, as a condition of approval, outages are required to be limited to weekends, holidays, or non-standard work hours, the Contractor shall perform the work during the time designated.
Additionally, the Contractor shall submit written notification to the Contracting Officer not less than 15 calendar days in advance of each interruption for each utility and or communication service to or within existing buildings and facilities being used. As a minimum, the request should include the location of the outage, utilities being affected, duration of outage and any necessary sketches. No single outage will exceed hours unless approved in writing by the Contracting Officer.
3.4 CONTRACTOR SITE FACILITIES
The Contractor shall provide, at its own expense, all facilities as may be necessary for the purposes of construction work. The location, construction, maintenance, operation and removal of the Contractor’s buildings, shops, storage areas and other facilities at the project site shall be subject to the approval of the Contracting Officer. The Contractor shall maintain a temporary on-site office which will provide project files and drawings, telephone service and space for the Contracting Officer to conduct on-site meetings with the Contractor.
Adequate break
3.2 MOBILIZATION PLAN
The Contractor shall submit a mobilization plan within two weeks of contract award. This mobilization plan must describe:
-Fencing, gates and doors -Storage and working areas -Material and tool storage structures and locations -Sanitary and personnel containers -Connected loads in kW -Site lighting plan -Parking spaces for employees and USACE (inside the construction fence if possible) -Other, specific installations and systems
SECTION 00 73 15.50 Page 14 room and a portable toilet facility shall be furnished by the Contractor for use by contract personnel, and will be the Contractor’s responsibility to maintain in a sanitary condition.
The Contractor will be permitted to use the designated area within the contract limits for operation of their construction equipment and plants, shops, warehouses, and offices. The Contractor is responsible for obtaining any required additional mobilization above that designated. The Contractor will conduct delivery and storage of materials in an area approved by the Contracting Officer in writing. If a road must be blocked, or any additional area is required during construction, this must be coordinated with the Contracting Officer at least ten calendar days in advance. On completion of the contract, all facilities shall be removed from the mobilization area by the Contractor and shall be disposed of in accordance with the applicable host nation laws and regulations. The site shall be cleared of construction debris and other materials and the area restored to its final grade.
The Contractor shall provide, at its own expense, such temporary heating or cooling as may be necessary for their office and personnel, or for the purposes of construction work. Any temporary type of heating or cooling provided shall conform to all applicable safety requirements and will be subject to the approval of the Contracting Officer.
Contractor shall insure that grounds within the contract boundaries are maintained according to the installation standards and that grass is regularly mowed to the satisfaction of the Contracting Officer.
3.4.1 Availability and Use of Utility Services
The contractor is responsible for making all necessary evaluations prior to bid as to the availability of utility services.
Connection to the sources of water and electricity and bringing them to the work location shall be done by the contractor at his own expense. The government is not responsible for water or electrical stoppage and the contractor has the responsibility to make prior proper arrangements, at their own expense for independent supply (water storage, generators, etc.).
3.4.2 Storage Areas
All materials, equipment, and supplies shall be stored in accordance with manufacturer’s regulations, EM385-1-1, and host nation codes. In the event of conflicts between regulations, the Host Nation regulations shall govern. Materials which are stored out-of-doors shall be adequately protected. Unless specifically authorized by the government, no materials may be stored in open areas exposed to the elements.
The Contracting Officer may direct the removal of any items which are stored improperly. If the government allows for payment of stored materials, no payment shall be allowed for materials, equipment, or supplies which are improperly stored. Additionally, the government may withhold sufficient funds from pay requests to provide for the repair or replacement of materials, equipment, or supplies which have been improperly stored and installed.
3.4.3 Trash Disposal
SECTION 00 73 15.50 Page 15
All waste material, including excess soil materials, shall be the property and responsibility of the Contractor. The Contractor shall be responsible for collection and disposal of trash from the work areas and from the mobilization area in a manner complying with all local laws. It is prohibited to allow dig material and litter to pile up in the area of the construction site.
3.4.4 Additional Requirements.
The Contractor shall be responsible for coordinating use of existing roads as haul routes with the host nation Government and local authorities. Construction, and routing of new haul routes, and/or upgrading of existing roads to carry anticipated construction traffic shall be coordinated with the host Government and local authorities and is the sole responsibility of the Contractor. It shall be the Contractor's responsibility to obtain such local authorizations, permits, and licenses necessary to establish quarry operations, batching operations, and haul routes.
3.5 ENVIRONMENTAL PROTECTION
3.5.1 General
The Contractor shall be responsible for the prevention of environmental pollution during and as the result of construction operations under this contract, and shall comply with all host nation environmental laws and regulations. During the Preconstruction Conference, the Contractor will meet with the Contracting Officer to develop an understanding of the environmental pollution control program. The environmental protection plan shall include, but shall not be limited to, the following:
a. A list of host nation and local laws, regulations, and permits concerning environmental protection, pollution control and abatement that are applicable to the Contractor’s proposed operations and the requirements imposed by those laws, regulations and permits.
b. Methods for protection of features to be preserved within authori ed work areas like trees, shrubs, vines, grasses and ground cover, landscape features, air and water uality, fish and wildlife, soil, historical, archeological,…