Attachment A - Statement of Work
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Army Corps of Engineers Europe District
APO AE 09049
Statement of Work Project Number: PAYZ15002A
Improve Support Infrastructure, Łask Air Base, Poland
Prepared by:
Special Projects Section
Construction Branch 03/22/2017
01010 Statement of Work Improve Support Infrastructure, Łask Air Base, Poland
22 March 2017 Page 2 of 9
SECTION 01010
STATEMENT OF WORK
1.0 PROJECT INFORMATION
Contract: Stand Alone Contract for Design Bid Build Construction Contract No.: W912GB-17-R-0036 Project Title: Improve Support Infrastructure Project Sponsor: US Air Force Location: Łask Air Base, Poland
2.0 GOVERNMENT ENGINEER
US ARMY CORPS OF ENGINEERS
Rachael Raposa DSN: 314-570-2600 Chief of Contracting +49 (0)611-9744-2600 e-mail: Rachael.Raposa@usace.army.mil
John R. Galloway, PE DSN: 314-570-2099 Resident Engineer, Special Projects Office +49 (0)611-9744-2099 e-mail: John.R.Galloway@usace.army.mil
Ben Schreiber DSN: 314-570-2044 Project Engineer, Special Projects Office +49 (0)611-9744-2044 e-mail: Benjamin.j.schreiber@usace.army.mil
Cynthia Perez DSN: 314-570-2559 Project Manager, Project Management Branch +49 (0)611-9744-2559 e-mail: Cynthia.B.Perez@usace.army.mil
3.0 PRELIMINARY UNDERSTANDING
The “Scope of Work” shall be accomplished in its entirety for the negotiated price. The Contractor's Proposal must include everything in the “Scope of Work” upon submission to the Government. The Contractor must be prepared to do the specified work for the negotiated value.
3.1. MODIFICATIONS: Modifications will only be issued in compliance with the contract clauses.
3.2. CONTRACT DIRECTIVES: Only the Contracting Officer or designated Contracting Officer
Representative (COR) can direct the Contractor.
3.3. USER REQUEST CHANGES: Any additional work requirements to the task order award must be submitted through the Facility’s POC and incorporated into the contract by a contract modification (SF 30).
22 March 2017 Page 3 of 9
3.4. Contractor shall be responsible for ensuring that all work is accomplished in compliance with the proper building codes, regulations, local authorities and in accordance with contract.
4.0 GENERAL
4.1 PROJECT DESCRIPTION: The Request for Proposal (RFP) provides parameters for a design-bid-build project for the extension of the concrete runway and construction of a safety berm for the arm/disarm pad at Lask Air Base, Poland. Purpose of the runway expansion is to allow aircraft operation during inclement weather. The arm/disarm pad berm will provide necessary containment for aircraft arming and disarming on the apron. This project also includes installation upgrades or modifications of existing exterior facilities, utilities, relocation of navigational aids, and drainage features as required to allow for the planned extension of the runway and construction of the berm.
4.2 GENERAL REQUIREMENTS: The Contractor shall constructed and deliver a fully function turnkey type facility in accordance with design and submittal provided in these documents. The work includes but is not limited to incidental design, demolition, fabrication, delivery, installation, construction, and site work.
The facility and the installed equipment shall be permanent construction. The facility in this project shall be complete and usable to meet codes and technical and functional requirements per this SOW and associated specification documents and plan set. All design, calculations, approvals, certificates, fees, labor, material, equipment, direct overhead, indirect overhead, G&A and general conditions to complete this project as described in the SOW shall be included in the proposal price. See plan set and specifications for additional information.
4.3 PERMITS: The contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any applicable laws, codes, and regulations in connection with the prosecution of the work. It shall be similarly responsible for all damages to persons or property that occurs as a result of the contractors fault or negligence. It shall take proper safety and health precautions to protect the work, the workers, the public, and the property of others. It shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire construction work, except for any completed unit of construction thereof which theretofore may have been accepted. See specifications for additional information.
Prior notice of at least 15 days shall be given to the COR before commencing work on the following work operations:
Backfilling over installation utility lines Video inspection of utility lines Work on test strip Starting of concrete paving.
Prior notice of at least 2 days shall be given to the COR before commencing work on the following work operations:
Tests and inspections of layers to be covered by pavement or the next grade layer.
4.4 SUBCONTRACTOR COMPLIANCE: Compliance with the provisions of the drawing and specifications by subcontractors shall be the responsibility of the Contractor.
4.5 MATERIALS AND EQUIPMENT: Materials and products used, shall be durable, heavy duty industry standard. The equipment shall be the manufacturer’s standard quality and shall be compatible with all other equipment and materials within the system or assembly. Equipment and materials shall include all
22 March 2017 Page 4 of 9 connections and accessories necessary to ensure operability and correct installation according to manufacturer’s requirements.
Any material installed that does not meet the requirements of this RFP shall be promptly removed and replaced with materials that meet RFP requirements at the Contractor’s expense.
Each major piece of equipment shall have the manufacturer’s name, address, contact information, type or style, model or serial number, and catalog number, stamped or engraved on a c o r r o s i o n r e s i s t a n t m e t a l plate secured to the piece of equipment. The definition of a “major piece of equipment” shall be at the discretion of the COR. At minimum, two (each) of all Operation and Maintenance manuals shall be provided for each piece of equipment. These shall be clearly labeled, bound and delivered at one time 30 days prior to and required training. All manuals shall be approved and be available on site prior to the final inspection. Provide two (2) each of any unique tools required to operate or maintain each piece of equipment.
All equipment delivered and placed in storage shall be stored with protection from the weather and temperature variation, dirt and dust, and other contaminants. The contractor shall be responsible for the materials safety and condition while in storage. The government shall not be responsible for damaged or missing equipment or material.
4.6 DESIGN DIMENSIONS: The design was developed using the metric system. All submittals and incidental design work shall be done in the metric system.
4.7 GENERAL DESIGN INSTRUCTIONS: The Contractor's construction process shall comply with technical requirements contained herein. The Contractor shall provide incidental design work and construction of the subject project using the best blend of cost, construction efficiency, system durability, ease of maintenance and environmental compatibility to complete the incidental design. See plan set and specifications for additional information.
4.8 DESIGN CRITERIA: This project is Design Bid Build. The plans and specifications for the project have been provided separately. Incidental design may still be required as part of the project. Site facilities, utility systems and material standards shall be in accordance with the included specifications and plans set, Host Nation, US and NATO building & construction codes.
Incidental designs are to meet US and Host Nation codes and requirements. It is the designer's responsibility to demonstrate that the Host Nation standard is equal to the US cited standard or specifications being supplanted. The more restrictive standards shall apply when the conflicts arise between the requirements of this RFP and any referenced or other applicable codes, standards or regulations. If equivalency cannot be met, the more stringent requirement shall be used and both codes shall be quoted verbatim in the Contractor’s correspondence to the COR. Where specific standards are not indicated, the contractor shall determine the required material and execution standards. Provide electronic copy of any local host nation standards and building codes in both English and its original language as related to facility construction.
4.9 SUBMITTALS: The contractor shall submit all documents in electronic format (.pdf for text and calculations, .pdf and .dwg (AutoCAD, latest version) for drawings). See Specification 01 33 00 SUBMITTAL PROCEDURES for additional information.
4.10 LIFE-SPAN: Construction must have an expected life span of 25 years.
22 March 2017 Page 5 of 9
4.11 MAINTAINABILITY: Low maintenance materials and systems must be employed and shall be appropriate for the project climate and location.
4.12 OPERABILITY: Systems including but identical to those currently installed to the extent possible.
4.13 STANDARDIZATION: The Contractor shall use standardized materials, products, equipment, and systems, already on base to minimize the requirements for replacement parts, storage facilities, and service requirements.
5.0 SYNOPSIS
The following tasks (Base and Options) are part of this project:
(1) Construction of a concrete runway extension with asphalt shoulders, runway overrun and a hammerhead turnaround pad.
(2) Berm for Arm/Disarm pad with lighting
(3) Installation of arresting gear system
(4) Relocation and re-installation of Navigational Aids
(5) Airfield lighting
(6) Runway marking
(7) Construction of drainage features
(8) Site grading
5.1 OPTION ITEMS: See Price Schedule for optional items.
All work shall be coordinated with USACE construction personnel. In carrying out each work assignment issued under the contract, the Contractor shall furnish the personnel, services, equipment, materials, facilities, and other requirements necessary for, or incidental to, the performance of work set forth herein.
Contractor shall provide a 4-foot by 8-foot project sign denoting that this is a USACE Europe project. The sign is inclusive and applicable for all projects. See specifications for additional information.
6.0 SITE INFORMATION
The location of the job site mobilization, and construction material storage areas are shown on the attached plans. Any deviation from these plans must be approved by the Facility Manager and USACE Project Engineer, in writing.
7.0 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK
The Contractor acknowledges that he has taken all steps reasonably necessary to ascertain the nature and location of the work, and that he has investigated and satisfied himself as to the general and local conditions which can affect the work or its cost. Any failure of the Contractor to take the action described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the governmental agency involved.
8.0 PROJECT REQUIREMENTS
Contractor shall provide all material, equipment, plant and manpower to execute construction and deliver
22 March 2017 Page 6 of 9 the fully functional facilities as described in this the attached plan set and specifications.
8.1 SITE LAYOUT: The full site design is included in the attached specifications and drawings. These drawings and specifications show the location of the planned elements in their proposed dimensions. The Contractor is responsible for the validation of all aspects of the work whether they are shown on the plans or not. The Contractor also may propose alternatives however these are subject to the approval of the COR and the Customer. The Contractor shall lay out the facility on the designated site taking into consideration the location of existing facilities and structures and shall include site elements that are to be upgraded, adjusted and/or added by the requirements of this SOW.
8.2 SITE SURVEY: The Contractor is required to survey the site and the features that will be affected by construction as part of the contract work effort, and furnish a final topographic survey of the existing conditions. The survey shall include all documentation in compliance with applicable standards.
The survey shall provide all data needed to conduct incidental design and construct the project. The survey shall include location and elevation of all features within the project site limits, as well as all features and utilities outside of the site that will be tied into or included in the project scope of work. The survey shall also include sufficient documentation and analysis of the existing drainage to allow for a new proper drainage design, including areas which will be affected by new drainage patterns and surfaces which new construction will abut or adjoin. Surveys performed during the design of the project do not alleviate the construction contractor from performing sufficient investigations to ensure that the construction is appropriate for the onsite conditions.
Upon completion of construction, the original survey shall be updated with an as-built survey of the site as constructed. The as-built survey shall be submitted to the COR for approval.
8.3 GEOTECHNICAL INVESTIGATION: The Contractor shall investigate, as needed, subsoil conditions at the proposed locations of the pavements or any other planned facilities requiring subsoil information for proper layout and construction. The Contractor shall perform the necessary penetration tests as well as borings or test pits to collect soil samples at depths suitable for the anticipated loads. The Contractor shall obtain soil samples and perform all laboratory testing necessary for computation of the geotechnical parameters required for proper layout and construction of the new or upgraded facilities in compliance with the applicable standards and the requirements of this SOW.
The Contractor shall perform pavement borings. The pavement material, thickness, strength, contamination, and sub base soil properties shall be investigated and provided in the geotechnical report prior to beginning the design.
The Contractor shall assess groundwater conditions as base of design for pavement constructions, drainage facilities etc. The Contractor shall perform percolation test as base of design for drainage facilities etc.
Investigation performed during the design of the project do not alleviate the construction contractor from performing sufficient investigations to ensure that the construction is appropriate for the onsite conditions.
8.4 HAZARDOUS MATERIALS AND CONTAMINATION: There is no prior knowledge of any hazardous materials at the site. However, it is possible that hazardous materials maybe found from previous use of the site, or that materials to be removed contain hazardous materials.
If hazardous materials are found to exist, the Contractor shall immediately notify the COR, cease work in the area and secure the site. The Contractor shall take precautions to protect the site from surface run-off
22 March 2017 Page 7 of 9 and precipitation, and prevent leaching of any hazardous material in the surrounding area.
8.5 UXO CLEARANCE: The possibility of (unexploded) ordnance at the site cannot be eliminated. Prior to construction begin, a ‘surface sweep’ may have been performed by the Base Authority to find and dispose of ordnance, however during construction, surface or subsurface ordnance might still be found. Inert practice ordnance may also be encountered. If any ordnance material is discovered, the Contractor will immediately cease work in the area and notify the COR. The Contractor shall cordon the area with any means available, such as tape or a red banner. If possible, provide GPS coordinates of the found object and appoint supervision until the arrival of the Base Authority. Once notified of ordnance material, the COR will notify the Base Authority. The Base Authority will then engage an Explosive Ordnance Disposal (EOD) team. The Contractor will allow an EOD team provided by the host nation to clear the ordnance within 5 working days. Upon clearance, the Contractor will resume work without requiring additional clearance actions from the US or host nation governments beyond the clearance of the specifically encountered ordnance items.
In order to minimize the possibility of encountering any subsurface ordnance, when not otherwise specified, the Contractor shall:
- minimize excavation below existing ground level,
- minimize the amount of clearing and grubbing of vegetation, and
- plan trenching routes to minimize additional excavation in areas beyond those already disturbed by construction.
8.6 INCIDENTAL DESIGN WORK: This is a Design Bid Build contract and the design and specifications of the project have been provided in the attached documents. This does not preclude the contractor from having to do incidental design work, based on the materials and methods that the contractor chooses to use in the project, or as noted in the plans and specifications.
8.6.1 DESIGNER OF RECORD: For necessary incidental design work the Contractor shall designate a Designer of Record (DOR). The DOR shall prepare necessary plans and specifications for proper execution of the project. Architectural, structural, civil, HVAC, and electrical plans and specifications shall be proofed by a separate member of the project team, a registered architect/professional engineer of the appropriate discipline(s) at the contractor’s expense. For this purpose the Contractor shall submit three
(3) sets each in English of the calculations and drawings to the selected registered engineer and three (3) sets to the COR. The registered engineer has to be approved by the COR. The COR has the right to disapprove the submitted registered engineer for the following reasons:
- Registered engineer not licensed for the appropriate discipline(s).
- Registered engineer’s office not within reasonable travel distance to the construction site.
8.6.2 DRAWINGS: The drawing set shall require “wet” signature of the Designer of Record and of the proofing engineer.
8.6.3 COMMENCEMENT OF WORK: The Contractor is not allowed to commence demolition or construction work of any kind before all the incidental designs have been approved and released. The Contractor shall coordinate his construction work with the registered engineer.
8.6.4 TECHNICAL DESIGN CRITERIA: Technical design criteria are included in the attached specifications.
Note 1: Unified Facilities Criteria (UFC) documents are available on the Internet at:
http://www.wbdg.org/ccb/browse_cat.php?o=29&c=4
22 March 2017 Page 8 of 9
Note 2: While this SOW references various source US Standards and specifications, all incidental design documents shall also meet Host Nation codes and requirements. If there is difference between US and Host Nation standards or specifications, then the most stringent of the US or the Host Nation standards or specifications shall apply. It is the designer’s responsibility to demonstrate that the Host Nation standard is equal to cited US Standards or specifications being supplanted. Should conflicts occur between the criteria provided and the codes, the final incidental design shall be based on an engineered evaluation of the conflicting codes that is submitted to and accepted by the KO, ACO or the COR.
9.0 COMMENCEMENT, EXECUTION, AND COMPLETION OF WORK
Except where otherwise addressed, the Total Performance Period for the construction and completion of all work as described in this scope shall be five hundred and forty (540) calendar days following the Notice to Proceed (NTP). The Contractor shall be required to commence construction work under this contract within fifteen (15) calendar days after the date the Contractor receives the construction NTP. The runway at Lask Air Base will be closed in 2017 and 2018 during the performance of a separate contract to overlay the existing runway. The contractor shall make every effort to construct the runway extension concurrently while this other project is underway. Any proposed deviations from this schedule must be addressed at the Pre-Construction Meeting. It is the responsibility of the Contractor to ensure the timely installation of all materials and that all trades adhere to the sequence of accomplishing the work. Refer to Section 01 32 01.00 10 “Project Schedule”.
9.1 CONSTRUCTION WORK SCHEDULE: Within ten (10) days following the Notice to Proceed the Contractor shall provide a Work Schedule showing the number and types of personnel and equipment to be used. Provide starting date, completion date, days to be worked (weekdays/weekends) and hours to be worked. The Contractors' work schedule shall provide information and dates as to what, when and how long a particular item of work will take. The schedule shall include each item of work that has to be done.
In addition the Contractor shall notify the Contracting Officer or designated Contracting Officer Representative (COR) in writing a minimum of three (3) working days in advance of when work will start.
The Contractor shall provide the names and passport number/national identification number of all individuals who will need access to the projects site not-later-than 30 days prior to the desired date to the Contractor Officer’s Representative. This list will then be coordinated with the Polish Ministry of Defense for confirmation. This list shall also include those individuals needing site access for material and equipment delivery.
The Contractor shall have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work. The Contractor will be provided, free of impediment or work interruption, and for such time as coordinated with the Contracting Officer, an area to be designated by the Contracting Officer for storage and staging of equipment.
10.0 PRECONSTRUCTION CONFERENCE
At the earliest practical time, prior to commencement of the work, the Contractor and any Sub-Contractors whose presence is necessary or requested, shall meet in conference with representatives of the Contracting Officer to discuss and develop a mutual understanding relative to the details of the administration and execution of this contract.
Base access is controlled by the Polish Ministry of Defense. Because USACE does not control base access USACE does not warranty that all personnel submitted will be granted access nor the duration that the process will take.
22 March 2017 Page 9 of 9
Discussion will include but not necessarily be limited to the Contractor's Quality Control (CQC) Program, the Contractor’s Accident Prevention Program, submittals, correspondence, schedule, access to the work site, security requirements, interface requirements, temporary facilities and services, hazards and risks, working after normal hours or on weekends or holidays, assignment of inspectors, representations, special requirements, phasing, and other aspects of this project that warrant clarification and understanding.
Contractor shall provide an initial project schedule to COR and notify the COR of any changes or delays within seven days from the Notice To Proceed (NTP).
11.0 PLAN AND SPECIFICATIONS
All work shall be performed as specified in the attached plan set and specifications.
12.0 GOVERNMENT FURNISHED UTILITIES
In accordance with FAR 52.236-14 the Contracting Officer has determined that the US Government will not provide any utilities and that the Contractor shall at their own expense provide all necessary utilities to satisfactorily conduct the work at each work site in accordance with local codes and to the satisfaction of the Contracting Officer.
13.0 GOVERNMENT FURNISHED MATERIALS AND EQUIPMENT
The Government will furnish the materials and equipment for installation of the arresting gear system by the Contractor. See plan set and specifications for detailed information.
14.0 EXISTING WORK
Existing work and grounds damaged or otherwise affected by the Contractor's operations shall be restored to a condition as good as existed before the work was commenced, except where indicated or specified otherwise, and shall be at the Contractor's expense. All debris resulting from demolition and removal operations shall be removed by the Contractor from the limits of the Government reservation at such times during the progress of the work.
15.0 CLEANING UP
Remove from the base on a day-to-day basis all light-weight scrap likely to be carried by the wind. Clean up and remove from the site all food leftover each day by Contractor's employees. The Contractor shall remove all debris from all spaces being used by the activity at the end of each shift or more frequently if required to keep the space useable.
16.0 AS BUILT DRAWINGS SUBMITTAL
As built drawings submittal shall include a complete and final set of record drawings documenting site conditions based on the contractor’s survey of the final construction performed by the D/D/B Contractor, including but not limited to shop drawings and details not included in the original design and existing utility lines or structures (both modified and unmodified) encountered in the construction footprint that were not located on the original site survey. As built drawings shall be prepared and submitted in accordance with Section 00 73 15 of the specifications.
CAD files of all construction drawings and as-built drawings shall be submitted in DWG (latest AutoCAD version) and in PDF formats.