Revised Lask Spec 01 50 00.pdf
PDF 50 KB Posted
- Attached to
- Improve Runway and Support Infrastructure Federal contract opportunity
- Solicitation number
- W912GB-17-R-0036
About this file
Spec 01 50 00
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 50 00 Page 1
PART 1 GENERAL
SECTION 01 50 00
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C511 (2007) Standard for Reduced-Pressure
Principle Backflow Prevention Assembly
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 241 (2013; Errata 2015) Standard for Safeguarding Construction, Alteration, and Demolition Operations
NFPA 70 (2014; AMD 1 2013; Errata 1 2013; AMD 2
2013; Errata 2 2013; AMD 3 2014; Errata 3-4 2014; AMD 4-6 2014) National Electrical Code
U.S. FEDERAL AVIATION ADMINISTRATION (FAA)
FAA AC 70/7460-1 (2015; Rev L) Obstruction Marking and
Lighting
U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)
MUTCD (2009) Manual on Uniform Traffic Control Devices
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Construction Site Plan; G Traffic Control Plan; G
SD-06 Test Reports
Backflow Preventer Tests
SD-07 Certificates Backflow Tester Certification Backflow Preventers Certificate of Full Approval
SECTION 01 50 00 Page 2
1.3 CONSTRUCTION SITE PLAN
Prior to the start of work, submit a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.
1.4 BACKFLOW PREVENTERS CERTIFICATE
Certificate of Full Approval attesting that the design, size and make of each backflow preventer has satisfactorily passed the complete sequence of performance testing and evaluation for the respective level of approval.
1.4.1 Backflow Tester Certificate
Prior to testing, submit to the Contracting Officer certification issued by the local regulatory agency attesting that the backflow tester has successfully completed a certification course sponsored by the regulatory agency. Tester must not be affiliated with any company participating in any other phase of this Contract.
Install the backflow devices in accordance with the following requirements:
PN-EN 806-2:2005 (U) – For design of internal portable water systems PN-EN 806-5:2012 – Maintenance of internal portable water systems PN-EN 1717 – Prevention of backflow contamination in internal portable water installations
All installed backflow protection devices have to have certificate of PZH (Państwowy Zakład Higieny = National Hygiene Institute) or other certificate of accredited lab.
1.4.2 Backflow Prevention Training Certificate
Submit a certificate recognized by the local authority that states the Contractor has completed at least 10 hours of training in backflow preventer installations. The certificate must be current.
PART 2 PRODUCTS
2.1 TEMPORARY SIGNAGE
2.1.1 Bulletin Board
Immediately upon beginning of work, provide a weatherproof glass-covered bulletin board not less than 915 by 1220 mm in size for displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the contract, Wage Rate Information poster, and other information approved by the Contracting Officer.
2.1.2 Project and Safety Signs
SECTION 01 50 00 Page 3
The requirements for the signs, their content, and location are as specified in Section 01 58 00 PROJECT IDENTIFICATION. Erect signs within 15 days after receipt of the notice to proceed. Correct the data required by the safety sign daily, with light colored metallic or non-metallic numerals.
2.2 TEMPORARY TRAFFIC CONTROL
2.2.1 Haul Roads
Construct access and haul roads necessary for proper prosecution of the work under this contract. Construct with suitable grades and widths;
sharp curves, blind corners, and dangerous cross traffic are to be avoided. Provide necessary lighting, signs, barricades, and distinctive markings for the safe movement of traffic. The method of dust control, although optional, must be adequate to ensure safe operation at all times.
Location, grade, width, and alignment of construction and hauling roads are subject to approval by the Contracting Officer. Lighting must be adequate to assure full and clear visibility for full width of haul road and work areas during any night work operations.
2.2.2 Barricades
Erect and maintain temporary barricades to limit public access to hazardous areas. Whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic barricades will be required. Securely place barricades clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.
2.2.3 Fencing
Provide fencing along the construction site at all open excavations and tunnels to control access by unauthorized people.
a. The safety fencing must be a high visibility orange colored, high density polyethylene grid or approved equal, a minimum of 1.2 m high and maximum mesh size of 50 mm, supported and tightly secured to steel posts located on maximum 3 m centers, constructed at the approved location. Install fencing to be able to restrain a force of at least
114.00 kg against it.
2.2.4 Temporary Wiring
Provide temporary wiring in accordance with NFPA 241 and NFPA 70. Include frequent inspection of all equipment and apparatus.
2.2.5 Backflow Preventers
Reduced pressure principle type conforming to the applicable requirements AWWA C511. Provide backflow preventers complete with 65 kg flanged cast iron, brass mounted gate valve and strainer, 304 stainless steel or bronze, internal parts.
PART 3 EXECUTION
3.1 EMPLOYEE PARKING
SECTION 01 50 00 Page 4
Contractor employees will park privately owned vehicles in an area designated by the Contracting Officer. This area will be within reasonable walking distance of the construction site. Contractor employee parking must not interfere with existing and established parking requirements of the government installation.
3.2 TEMPORARY BULLETIN BOARD
Locate the bulletin board at the project site in a conspicuous place easily accessible to all employees, as approved by the Contracting Officer.
3.3 AVAILABILITY AND USE OF UTILITY SERVICES
3.3.1 Temporary Utilities
Provide temporary utilities required for construction. Materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.
3.3.2 Sanitation
Provide and maintain within the construction area minimum field-type sanitary facilities approved by the Contracting Officer and periodically empty wastes into a municipal, district, or station sanitary sewage system, or remove waste to a commercial facility. Obtain approval from the system owner prior to discharge into any municipal, district, or commercial sanitary sewer system. Any penalties and / or fines associated with improper discharge will be the responsibility of the Contractor. Coordinate with the Contracting Officer and follow station regulations and procedures when discharging into the station sanitary sewer system. Maintain these conveniences at all times without nuisance.
Include provisions for pest control and elimination of odors. Government toilet facilities will not be available to Contractor's personnel.
3.3.3 Telephone
Make arrangements and pay all costs for telephone facilities desired.
3.3.4 Obstruction Lighting of Cranes
Provide a minimum of 2 aviation red or high intensity white obstruction lights on temporary structures (including cranes) over 30 meter above ground level. Light construction and installation must comply with FAA AC 70/7460-1. Lights must be operational during periods of reduced visibility, darkness, and as directed by the Contracting Officer.
3.3.5 Fire Protection
Provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials daily to minimize potential hazards.
3.4 TRAFFIC PROVISIONS
3.4.1 Maintenance of Traffic
a. Conduct operations in a manner that will not close any thoroughfare or
SECTION 01 50 00 Page 5 interfere in any way with traffic on railways or highways except with written permission of the Contracting Officer at least 15 calendar days prior to the proposed modification date, and provide a Traffic Control Plan detailing the proposed controls to traffic movement for approval. The plan must be in accordance with host country regulations and the MUTCD, Part VI. Make all notifications and obtain any permits required for modification to traffic movements outside Station's jurisdiction. Contractor may move oversized and slow-moving vehicles to the worksite provided requirements of the highway authority have been met.
b. Conduct work so as to minimize obstruction of traffic, and maintain traffic on at least half of the roadway width at all times. Obtain approval from the Contracting Officer prior to starting any activity that will obstruct traffic.
c. Provide, erect, and maintain, at contractors expense, lights, barriers, signals, passageways, detours, and other items, that may be required by the Life Safety Signage, overhead protection authority having jurisdiction.
3.4.2 Protection of Traffic
Maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment the work, and the erection and maintenance of adequate warning, danger, and direction signs, will be as required by the local authorities having jurisdiction. Protect the traveling public from damage to person and property. Minimize the interference with public traffic on roads selected for hauling material to and from the site. Investigate the adequacy of existing roads and their allowable load limit. Contractor is responsible for the repair of any damage to roads caused by construction operations.
3.4.3 Rush Hour Restrictions
Do not interfere with the peak traffic flows preceding and during normal operations without notification to and approval by the Contracting Officer.
3.4.4 Dust Control
Dust control methods and procedures must be approved by the Contracting Officer. Treat dust abatement on access roads with applications of calcium chloride, water sprinklers, or similar methods or treatment.
3.5 CONTRACTOR'S TEMPORARY FACILITIES
Contractor-owned or -leased trailers must be identified by Government assigned numbers. Size and location of the number will comply with the contract requirements and drawings. Apply the number to the trailer within 14 calendar days of notification, or sooner, if directed by the Government.
3.5.1 Safety
Protect the integrity of any installed safety systems or personnel safety
SECTION 01 50 00 Page 6 devices. If entrance into systems serving safety devices is required, the Contractor must obtain prior approval from the Contracting Officer.
If it is temporarily necessary to remove or disable personnel safety devices in order to accomplish contract requirements, provide alternative means of protection prior to removing or disabling any permanently installed safety devices or equipment and obtain approval from the Contracting Officer.
3.5.2 Administrative Field Offices
Provide and maintain administrative field office facilities within the construction area at the designated site. Government office and warehouse facilities will not be available to the Contractor's personnel.
3.5.3 Storage Area
Construct a temporary 1.8 m high chain link fence around trailers and materials. Include plastic strip inserts, colored green or brown, so that visibility through the fence is obstructed. Fence posts may be driven, in lieu of concrete bases, where soil conditions permit. Do not place or store Trailers, materials, or equipment outside the fenced area unless such trailers, materials, or equipment are assigned a separate and distinct storage area by the Contracting Officer away from the vicinity of the construction site but within the installation boundaries. Trailers, equipment, or materials must not be open to public view with the exception of those items which are in support of ongoing work on any given day. Do not stockpile materials outside the fence in preparation for the next day's work. Park mobile equipment, such as tractors, wheeled lifting equipment, cranes, trucks, and like equipment within the fenced area at the end of each work day.
3.5.4 Supplemental Storage Area
Upon Contractor's request, the Contracting Officer will designate another or supplemental area for the Contractor's use and storage of trailers, equipment, and materials. This area may not be in close proximity of the construction site but will be within the installation boundaries.
Fencing of materials or equipment will not be required at this site;
however, the Contractor is responsible for cleanliness and orderliness of the area used and for the security of any material or equipment stored in this area. Utilities will not be provided to this area by the Government.
3.5.5 Appearance of Trailers
a. Trailers utilized by the Contractor for administrative or material storage purposes must present a clean and neat exterior appearance and be in a state of good repair. Trailers which, in the opinion of the Contracting Officer, require exterior painting or maintenance will not be allowed on installation property.
b. Maintain the temporary facilities. Failure to do so will be sufficient reason to require their removal.
3.5.6 Maintenance of Storage Area
Keep fencing in a state of good repair and proper alignment. Grassed or unpaved areas, which are not established roadways, will be covered with a layer of gravel as necessary to prevent rutting and the tracking of mud
SECTION 01 50 00 Page 7 onto paved or established roadways, should the Contractor elect to traverse them with construction equipment or other vehicles; gravel gradation will be at the Contractor's discretion. Mow and maintain grass located within the boundaries of the construction site for the duration of the project. Grass and vegetation along fences, buildings, under trailers, and in areas not accessible to mowers will be edged or trimmed neatly.
3.5.7 Security Provisions
Provide adequate outside security lighting at the Contractor's temporary facilities. The Contractor will be responsible for the security of its own equipment; in addition, the Contractor will notify the appropriate law enforcement agency requesting periodic security checks of the temporary project field office.
3.5.8 Weather Protection of Temporary Facilities and Stored Materials.
Take necessary precautions to ensure that roof openings and other critical openings in the building are monitored carefully. Take immediate actions required to seal off such openings when rain or other detrimental weather is imminent, and at the end of each workday.
Ensure that the openings are completely sealed off to protect materials and equipment in the building from damage.
3.5.8.1 Building and Site Storm Protection
When a warning of high winds is issued, take precautions to minimize danger to persons, and protect the work and nearby Government property.
Precautions must include, but are not limited to, closing openings;
removing loose materials, tools and equipment from exposed locations; and removing or securing scaffolding and other temporary work. Close openings in the work when storms of lesser intensity pose a threat to the work or any nearby Government property.
3.6 GOVERNMENT FIELD OFFICE
3.6.1 Quality Control Manager Records and Field Office
Provide on the jobsite an office with approximately 18 square meter of useful floor area for the exclusive use of the QC Manager. Provide a weathertight structure with adequate heating and cooling, toilet facilities, lighting, ventilation, a 1200 by 2400 mm plan table, a standard size office desk and chair, computer station, and working communications facilities. Provide either a 1,500 watt radiant heater and a window-mounted air conditioner rated at 2.6 kW minimum or a window-mounted heat pump of the same minimum heating and cooling ratings. Provide a door with a cylinder lock and windows with locking hardware. Make utility connections. Locate as directed. File quality control records in the office and make available at all times to the Government. After completion of the work, remove the entire structure from the site.
3.6.2 Trailer-Type Mobile Office
The Contractor may, at its option, furnish and maintain a trailer-type mobile office acceptable to the Contracting Officer and providing as a minimum the facilities specified above. Securely anchor the trailer to the ground at all four corners to guard against movement during high winds.
3.7 PLANT COMMUNICATION
SECTION 01 50 00 Page 8
Whenever the Contractor has the individual elements of its plant so located that operation by normal voice between these elements is not satisfactory, the Contractor must install a satisfactory means of communication, such as telephone or other suitable devices and made available for use by Government personnel.
3.8 TEMPORARY PROJECT SAFETY FENCING
As soon as practicable, but not later than 15 days after the date established for commencement of work, furnish and erect temporary project safety fencing at the work site. Maintain the safety fencing during the life of the contract and, upon completion and acceptance of the work, will become the property of the Contractor and be removed from the work site.
3.9 CLEANUP
Remove construction debris, waste materials, packaging material and the like from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways must be cleaned away. Store any salvageable materials resulting from demolition activities within the fenced area described above or at the supplemental storage area. Neatly stack stored materials not in trailers, whether new or salvaged.
3.10 RESTORATION OF STORAGE AREA
Upon completion of the project remove the bulletin board, signs, barricades, haul roads, and any other temporary products from the site.
After removal of trailers, materials, and equipment from within the fenced area, remove the fence that will become the property of the Contractor.
Restore areas used by the Contractor for the storage of equipment or material, or other use to the original or better condition. Remove gravel used to traverse grassed areas and restore the area to its original condition, including top soil and seeding as necessary.
-- End of Section --
File details come from the government source that posted it. Updated .