Instructions Attachment 4 - Price Schedule Lask AB Poland_01 May17.pdf

PDF 62 KB Posted

Attached to
Improve Runway and Support Infrastructure
Solicitation number
W912GB-17-R-0036
Issued by

About this file

Instructions Attachment 4 - Price Schedule

View the file

Other files

File Type Posted
Amendment_03.pdf PDF
Soil Boring Logs.pdf PDF
GEOTECHNICAL - ENGLISH_100%_REV01.pdf PDF
VAT Poland Tax bilingual form.pdf PDF
Amendment 02.pdf PDF
Revised Lask Spec 01 45 01.01 Additional Quality Control Personnel.pdf PDF
Revised Lask Spec 01 50 00.pdf PDF
Revised Sheet E-103_RFI.PDF PDF
Revised Lask Spec 03 30 53.pdf PDF
New Lask Spec 26 56 23.pdf PDF
VAT_SOP_ FINAL.pdf PDF
PreProposal_Slides_Runway_Improvement,_Lask_AB,_Poland_11_May_2017.ppt PPT presentation
Site_Visit_Sign_In_Roster.pdf PDF
Amendment_01_-_Clause_Update.pdf PDF
Solicitation_W912GB-17-R-0036_Airfield,_Lask_AB_Poland.pdf PDF
Instructions Attachment 3 - PastPerformanceClientForm.docx DOCX document
Attachment A - SOW Lask AB Poland_ 01010.pdf PDF
Attachment B3 - Section CU-000_100%_REV01_DRAWINGS.pdf PDF
Attachment_B6_-_Section_E-000_100__REV01_DRAWINGS.pdf PDF
Instructions Attachment 6 - Site Visit Poland Base Access Information.xlsx XLSX spreadsheet
Instructions Attachment 2 - ExperienceInfoSheet.docx DOCX document
Instructions Attachment 7 - VAT_Procedures.pdf PDF
SPECIFICATIONS_100_Lask AB_REV01A.pdf PDF
Attachment B5 - Section V-000_100%_REV01_DRAWINGS.pdf PDF
Attachment B4 - Section G-000_100%_REV01_DRAWINGS.pdf PDF
Attachment B2 - Section C-000_100%_REV01_DRAWINGS.pdf PDF
Attachment B1 - Section B-000_100%_REV01_DRAWINGS.pdf PDF
Instructions Attachment 1- ExperienceOverviewSheet.docx DOCX document
Instructions Attachment 5 - Site Visit Information - Lask Directions.pdf PDF
Site_Visit_Poland_Base_Access_Information.xlsx XLSX spreadsheet
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 00 10 00 - Bidding Schedule/Instructions to Bidders

PRICE SCHEDULE

Request for Proposal (RFP) FY15 European Reassurance Initiative: Improve Support Infrastructure

Łask Air Base, Poland 01 May 2017

This project is a construction contract.

The Offeror shall provide prices on all base items and option items. Provide prices for the completion of a construction of award items from the Notice to Proceed as described in the contract FAR Clause 52.211-10 “ COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK” according to the following schedule.

Each CLIN duration is as per the price schedule and the calendar days are from issuance of the Notice to Proceed (NTP). The total period of performance is 540 calendar days, including base items and all optional items, if awarded (exercised), from the issuance of the NTP. The contractor shall have the project fully functional and available for normal, regular use no later than the end date of the period of performance.

Prices: All prices are to be proposed in Euros.

Award of Options and Period of Performance: The Government reserves the right to award any or all options up to 120 calendar days following issuance of NTP for the base item work. Any optional work awarded shall be completed in the same period of performance as the base item except for Option Item 0001, Field Office, which shall be available for use within 15 calendar days of exercising the option unless a different period of performance is noted within a particular CLIN, as described in contract FAR Clause 52.211-10

“COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK.

Liquidated Damages: If the Contractor fails to complete the work within the time specified in the task order, the Contractor shall pay liquidated damages to the Government in the amount of € 3 , 674.00 for each calendar day of delay until the work is completed or accepted. If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

Section 00 10 00 - Bidding Schedule/Instructions to Bidders

Request for Proposal (RFP) FY15 European Reassurance Initiative: Improve Support Infrastructure

Łask Air Base, Poland 01 May 2017

BASE ITEMS: The base items include all labor, transportation, equipment, materials, permits, and any other services necessary for the work as described in the Statement of Work.

CLIN

BASE ITEM 1: Runway Extension and Hammerhead Turnaround Pad

All work associated with the construction of Runway Extension and Hammerhead Turnaround Pad including all mobilization and demobilization, administrative costs, surveys, QC, demolitions, subgrade improvements and preparation, RWY and TRNPD concrete pavement, RWY asphalt shoulders, overrun asphalt pavement and shoulders, joints, driveway, access & service roads, earthworks, topsoil placing, pavement marking, fencing, stormwater system, sub-drain system, RWY sub-drain, culverts, airfield lighting, utilities, power supply for listed systems, navaids, as described in the statement of work, specifications, and drawings except those items described in the options.

Base Item 2: Temporary Fencing and Gates

All work associated with installation, maintenance, uninstallation of temporary construction site fence along with gates as described in the statement of work, specifications, and drawings except those items described in the options, BASE ITEMS TOTAL: €

OPTIONAL ITEMS:

Option Item 1: USACE Field Office on Site

All work associated with providing Government Field office for duration of the project including utilities, maintenance and cleaning of the office space in accordance with requirements as described in the statement of work, specifications 00 73 15.01, and drawings. The USACE Field Office shall be available for use within 15 days of the exercising of Option Item 1 (CLIN 0003).

Option Item 2: Arm/Disarm Pad and Berm with lighting

All work associated with construction of the Arm/disarm pad and Berm including ground embankment, drainage layer, separation layer, topsoil, sub- drains and drainage system, lighting mast and poles, low intensity obstacle light, pavement marking, demolitions of blast protections, lighting masts, tree clearance, pavement marking removal as described in the statement of work, specifications, and drawings.

CLIN

Option Item 3: Arresting Gear

All work associated with construction of BAK 12/14 installation including shelter lab and footings, tube foundations, fairy lead beam foundations, trench trough concrete, saw cut, pavement removal, trough installation, fairlead tube, tape sweep pavement, type E joint seal, dowels, arresting gear installation, manufacturer installation drawings and support during construction and testing as described in the statement of work, specifications, and drawings.

OPTION ITEMS TOTAL: €

TOTAL PRICE – ALL BASE AND OPTION ITEMS: €

File details come from the government source that posted it. Updated .