Volume_3_of_3_Specs_Div_13-44_5_Feb_18.pdf

PDF 3 MB Posted

Attached to
Construct Critical Infrastructure
Solicitation number
W912ER-18-R-0004
Issued by

About this file

Volume 3 of 3 Specifications

View the file

Other files

File Type Posted
AM5_Specifications_6_Apr_18.pdf PDF
UD_2.4_PACKAGE_1_LSA_DRAWINGS1_AM005_06_APR_18.pdf PDF
UD_2.4_PACKAGE_1_LSA_DRAWINGS2_AM005_06_APR_18.pdf PDF
W912ER18R0004-0005.pdf PDF
W912ER18R0004-0004.pdf PDF
AM4_Specifications_4_Apr_18.pdf PDF
UD_2.4_PACKAGE_1_LSA_DRAWINGS_AM004_04_APR_18.pdf PDF
W912ER18R0004-0003.pdf PDF
AM3_Specifications_29_Mar_18.pdf PDF
AM2_UD_2.4_-_Pkg_1_LSA_-_Cost_Breakdown_3-26-18_-_NO_COST_-_.pdf PDF
AM2_Specifications_26_Mar_18.pdf PDF
AM2_UD_2.4_-_Pkg_1_LSA_Bid_Schedule_-_3-26-18__.pdf PDF
W912ER18R0004-0002.pdf PDF
UD_2.4_PACKAGE_1_LSA_DRAWINGS_AM002_26_MAR_18.pdf PDF
W912ER-18-R-0004-01_Conformed_Copy.pdf PDF
AM1_UD_2.4_-_Package_1_Pkg_1_LSA__Cost_Breakdown_3-13-18.pdf PDF
UD_2.4_PACKAGE_1_LSA_DRAWINGS_AM001_15_MAR_18.pdf PDF
W912ER-18-R-0004-01_Modificaion.pdf PDF
AM1_Specifications_13_Mar_18.pdf PDF
Volume_1_Attachment_A.pdf PDF
Volume_2_of_3_Specs_Div_01-12_8_Feb_18.pdf PDF
Volume_1_Attachment_B.pdf PDF
Volume_1_of_3_Solicitation.pdf PDF
Volume_1_Attachment_C.pdf PDF
Volume_1_Attachment_D.xls XLS spreadsheet
Copy_of_332_AEW_Vetting_Request_Worksheet_TEMPLATE.xlsx XLSX spreadsheet
&_1575;&_1604;&_1602;&_1610;&_1575;&_1583;&_1607;_&_1575;&_1604;&_1593;&_1575;&_1605;&_1607;_&_1604;&_1604;&_1602;&_1608;&_1575;&_1578;_&_1575;&_1604;&_1605;&_1587;&_1604;&_1581;&_1607;_&_1575;&_1604;&_1575;&_1585;&_1583;&_1578;&_1610;&_1607;_(2)RJAF_Upda PDF
U.S._Contractor_Request_Template.xlsx XLSX spreadsheet
Jordanian_Information_Form.pdf PDF
RJAF_DMS_Application_Blank.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Proposal

W912ER18R0004

Specifications for

UD 2.4 – Package 1 LSA, Jordan

Volume 3 of 3 Divisions 13 - 44

US Army Corps of Engineers Middle East District

UD 2.4 - Package 1 LSA, Jordan 463243LSA

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 15 00.12 10 SUPPLEMENTARY REQUIREMENTS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 31 19.05 20 POST AWARD MEETINGS

01 32 18.12 10 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS) FOR

DESIGN-BUILD

01 33 00 SUBMITTAL PROCEDURES

01 33 00.12 10 SUBMITTAL PROCEDURES FOR DESIGN-BUILD PROJECT

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 42 15 METRIC MEASUREMENTS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 75 01.00 40 PLANT EQUIPMENT TESTING, FACILITY STARTUP AND

COMMISSIONING

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 80 00.12 10 TECHNICAL REQUIREMENTS

01 91 00.15 TOTAL BUILDING COMMISSIONING

DIVISION 03 - CONCRETE

03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING

03 15 00.00 10 CONCRETE ACCESSORIES

03 20 00.00 10 CONCRETE REINFORCING

03 30 00.00 10 CAST-IN-PLACE CONCRETE

03 35 00.00 10 CONCRETE FINISHING

03 39 00.00 10 CONCRETE CURING

03 42 13.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE

CONSTRUCTION

DIVISION 04 - MASONRY

04 20 00 UNIT MASONRY

DIVISION 05 - METALS

05 05 23.16 STRUCTURAL WELDING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 BOARD AND BLOCK INSULATION

07 52 00 MODIFIED BITUMINOUS MEMBRANE ROOFING

07 55 00 PROTECTED MEMBRANE ROOFING

07 60 00 FLASHING AND SHEET METAL

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

PROJECT TABLE OF CONTENTS Page 1

08 14 00 WOOD DOORS

08 51 13 ALUMINUM WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

DIVISION 09 - FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 24 23 CEMENT STUCCO

09 29 00 GYPSUM BOARD

09 65 00 RESILIENT FLOORING

09 90 00 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 44 16 FIRE EXTINGUISHERS

DIVISION 12 - FURNISHINGS

12 51 00 FURNITURE, FURNISHINGS AND EQUIPMENT (FFE)

DIVISION 13 - SPECIAL CONSTRUCTION

13 48 00 SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT

13 48 00.00 10 SEISMIC PROTECTION FOR MECHANICAL EQUIPMENT

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

21 30 00 FIRE PUMPS

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 08 00.00 10 COMMISSIONING OF HVAC SYSTEMS

23 23 00 REFRIGERANT PIPING

23 82 43.00 40 ELECTRIC DUCT HEATERS

23 82 46.00 40 ELECTRIC UNIT HEATERS

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT

26 08 00 APPARATUS INSPECTION AND TESTING

26 11 16 SECONDARY UNIT SUBSTATIONS

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION

26 32 14.00 10 DIESEL-GENERATOR SET, STATIONARY 15-300 KW, STANDBY

APPLICATIONS

26 36 00.00 10 AUTOMATIC TRANSFER SWITCH AND BY-PASS/ISOLATION SWITCH

26 41 00 LIGHTNING PROTECTION SYSTEM

DIVISION 27 - COMMUNICATIONS

PROJECT TABLE OF CONTENTS Page 2

27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM

27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 76.11 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM FOR

INFORMATION TRANSFER NODE (ITN) BUILDING

28 31 76.12 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM FOR FIRE

PUMP BUILDING

28 31 76.13 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM FOR PUMP

BUILDING

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 00 05 LAGOON CONSTRUCTION

31 32 12 SOIL STABILIZATION SYSTEM

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 11 20 SUBBASE COURSE

32 11 23 AGGREGATE BASE COURSE

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 15 00 AGGREGATE SURFACE COURSE

32 17 23 PAVEMENT MARKINGS

32 31 13.53 HIGH-SECURITY CHAIN LINK FENCES AND GATES

DIVISION 33 - UTILITIES

33 11 00 WATER UTILITY DISTRIBUTION PIPING

33 16 15 WATER STORAGE STEEL TANKS

33 20 00 WATER WELLS

33 30 00 SANITARY SEWERS

33 32 16 PACKAGED UTILITY WASTEWATER PUMPING STATIONS

33 40 00 STORM DRAINAGE UTILITIES

33 47 13 POND AND RESERVOIR LINERS

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

33 72 02 UNDERGROUND COMMUNICATION SYSTEM

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

DIVISION 34 - TRANSPORTATION

34 71 13.19 ACTIVE VEHICLE BARRIERS

DIVISION 44 - POLLUTION AND WASTE CONTROL EQUIPMENT

44 42 14 LAGOON AERATION EQUIPMENT

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 3

SECTION TABLE OF CONTENTS

DIVISION 13 - SPECIAL CONSTRUCTION

SECTION 13 48 00

SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT

08/08

PART 1 GENERAL

1.1 REFERENCES

1.2 SYSTEM DESCRIPTION

1.2.1 General Requirements

1.2.2 Miscellaneous Equipment and Systems

1.3 SUBMITTALS

PART 2 PRODUCTS

2.1 EQUIPMENT REQUIREMENTS

2.1.1 Rigidly Mounted Equipment

2.1.2 Nonrigid or Flexibly-Mounted Equipment

2.2 BOLTS AND NUTS

2.3 SWAY BRACING

PART 3 EXECUTION

3.1 BRACING

3.2 BUILDING DRIFT

3.3 ANCHOR BOLTS

3.3.1 Cast-In-Place

3.3.2 Expansion or Chemically Bonded Anchors

3.3.2.1 General Testing

3.3.2.2 Torque Wrench Testing

3.3.2.3 Pullout Testing

3.4 RESILIENT VIBRATION ISOLATION DEVICES

3.4.1 Resilient and Spring-Type Vibration Devices

3.4.2 Multidirectional Seismic Snubbers

3.5 SWAY BRACES FOR PIPING

3.5.1 Longitudinal Sway Bracing

3.5.2 Anchor Rods, Angles, and Bars

3.5.3 Maximum Length for Anchor Braces

3.5.4 Bolts

3.6 EQUIPMENT SWAY BRACING

3.6.1 Suspended Equipment and Light Fixtures

3.6.2 Floor or Pad Mounted Equipment

3.6.2.1 Shear Resistance

3.6.2.2 Overturning Resistance

-- End of Section Table of Contents --

SECTION 13 48 00 Page 1

SECTION 13 48 00

SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT

08/08

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASME INTERNATIONAL (ASME)

ASME B18.2.1 (2012; Errata 2013) Square and Hex Bolts and Screws (Inch Series)

ASME B18.2.2 (2015) Nuts for General Applications:

Machine Screw Nuts, Hex, Square, Hex Flange, and Coupling Nuts (Inch Series)

ASTM INTERNATIONAL (ASTM)

ASTM A153/A153M (2016) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware

ASTM A307 (2014) Standard Specification for Carbon Steel Bolts and Studs, 60 000 PSI Tensile Strength

ASTM A325M (2014) Standard Specification for Structural Bolts, Steel, Heat Treated, 830 MPa Minimum Tensile Strength (Metric)

ASTM A36/A36M (2014) Standard Specification for Carbon Structural Steel

ASTM A500/A500M (2013) Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes

ASTM A53/A53M (2012) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless

ASTM A563M (2007; R 2013) Standard Specification for Carbon and Alloy Steel Nuts (Metric)

ASTM A572/A572M (2015) Standard Specification for High-Strength Low-Alloy Columbium-Vanadium Structural Steel

ASTM A603 (1998; R 2014) Standard Specification for

SECTION 13 48 00 Page 2

Zinc-Coated Steel Structural Wire Rope

ASTM A653/A653M (2015; E 2016) Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process

ASTM E488/E488M (2015) Standard Test Methods for Strength of Anchors in Concrete and Masonry Elements

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 3-310-04 (2013) Seismic Design for Buildings

1.2 SYSTEM DESCRIPTION

1.2.1 General Requirements

Apply the requirements for seismic protection measures, described in this section, to the mechanical equipment and systems outlined in Section 13 48 00.00 10 SEISMIC PROTECTION FOR MECHANICAL EQUIPMENT, the electrical equipment and systems outlined in Section 26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT, and the miscellaneous equipment and systems listed below, in accordance with UFC 3-310-04 and additional data furnished by the Contracting Officer. Provide seismic protection measures in addition to any other requirements called for in other sections of these specifications. The design for seismic protection shall be based on a Site Class D, Seismic Design Category D, Risk Category IV, and on site response coefficients for S MS = 0.894 and S M1 = 0.595. Accomplish resistance to lateral forces induced by earthquakes without consideration of friction resulting from gravity loads. The basic force formulas, for Ground Motions A and B in UFC 3-310-04 , use the design spectral response acceleration parameters for the performance objective of the building, not for equipment in the building; therefore, corresponding adjustments to the formulas are required.

1.2.2 Miscellaneous Equipment and Systems

The bracing for the following miscellaneous equipment and systems shall be developed by the Contractor in accordance with the requirements of this specification:

Storage cabinets Ornamentations Storage Racks Signs and Billboards Shelving Furnishings Partitions

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

SD-02 Shop Drawings

SECTION 13 48 00 Page 3

Bracing; G , M Resilient Vibration Isolation Devices; G , M Equipment Requirements; G , M

SD-03 Product Data

Bracing; G , M Equipment Requirements; G , M

SD-06 Test Reports

Anchor Bolts; G , M

PART 2 PRODUCTS

2.1 EQUIPMENT REQUIREMENTS

Submit detail drawings along with calculations, catalog cuts, templates, and erection and installation details, as appropriate, for the items listed below. Indicate thickness, type, grade, class of metal, and dimensions; and show construction details, reinforcement, anchorage, and installation with relation to the building construction. For equipment and systems in buildings that have a performance objective higher than life-safety, the drawings shall be stamped by the registered engineer who stamps the calculations. Calculations shall be stamped, by a registered engineer, and verify the capability of structural members to which bracing is attached for carrying the load from the brace.

2.1.1 Rigidly Mounted Equipment

All equipment to be furnished under this contract shall be constructed and assembled to withstand the seismic forces specified in UFC 3-310-04 . For any rigid equipment which is rigidly attached on both sides of a building expansion joint, provide flexible joints for piping, electrical conduit, etc., that are capable of accommodating displacements equal to the full width of the joint in both orthogonal directions.

2.1.2 Nonrigid or Flexibly-Mounted Equipment

All equipment to be furnishedshall be constructed and assembled to resist a horizontal lateral force of 1.4 times the operating weight of the equipment at the vertical center of gravity of the equipment.

2.2 BOLTS AND NUTS

Squarehead and hexhead bolts, and heavy hexagon nuts, ASME B18.2.1 , ASME B18.2.2 , or ASTM A307 for bolts and ASTM A563M for nuts or ASTM A325M for bolts and nuts. Provide bolts and nuts galvanized in accordance with ASTM A153/A153M when used underground and/or exposed to weather.

2.3 SWAY BRACING

Material used for members listed in this section and on the drawings, shall be structural steel conforming with the following:

a. Plates, rods, and rolled shapes, ASTM A36/A36M or ASTM A572/A572M , Grade 503. If the Contractor does the design, both ASTM A36/A36Mand ASTM A572/A572M , grade 503 will be allowed.

SECTION 13 48 00 Page 4

b. Wire rope, ASTM A603.

c. Tubes, ASTM A500/A500M , Grade B.

d. Pipes, ASTM A53/A53M, Type E or S, Grade B.

e. Light gauge angles, less than 6 mm thickness, ASTM A653/A653M .

PART 3 EXECUTION

3.1 BRACING

Provide bracing conforming to the arrangements shown. Secure trapeze-type hanger with not less than two 13 mm bolts.

3.2 BUILDING DRIFT

Sway braces for a piping run shall not be attached to two dissimilar structural elements of a building that may respond differentially during an earthquake unless a flexible joint is provided.

3.3 ANCHOR BOLTS

Submit copies of test results to verify the adequacy of the specific anchor and application, as specified.

3.3.1 Cast-In-Place

Use cast-in-place anchor bolts, conforming to ASTM A307, for floor or pad mounted equipment, except as specified below. Provide one nut on each bolt. Anchor bolts shall have an embedded straight length equal to at least 12 times nominal diameter of the bolt. Anchor bolts that exceed the normal depth of equipment foundation piers or pads shall either extend into concrete floor or the foundation or be increased in depth to accommodate bolt lengths.

3.3.2 Expansion or Chemically Bonded Anchors

Do not use expansion or chemically bonded anchors: 1)Unless test data in accordance with ASTM E488/E488M has been provided to verify the adequacy of the specific anchor and application. 2)To resist pull-out in overhead and wall installations if the adhesive is manufactured with temperature sensitive epoxies and the location is accessible to a building fire.

Install expansion and chemically bonded anchors in accordance with the manufacturer's recommendations. Adjust the allowable forces for the spacing between anchor bolts and the distance between the anchor bolt and the nearest edge, as specified by the manufacturer.

3.3.2.1 General Testing

Test in place expansion and chemically bonded anchors not more than 24 hours after installation of the anchor, conducted by an independent testing agency; testing shall be performed on random anchor bolts as described below.

3.3.2.2 Torque Wrench Testing

Perform torque wrench testing on not less than 50 percent of the total

SECTION 13 48 00 Page 5 installed expansion anchors and at least one anchor for every piece of equipment containing more than two anchors. The test torque shall equal the minimum required installation torque as required by the bolt manufacturer. Calibrate torque wrenches at the beginning of each day the torque tests are performed. Recalibrate torque wrenches for each bolt diameter whenever tests are run on bolts of various diameters. Apply torque between 20 and 100 percent of wrench capacity. Reach the test torque within one half turn of the nut, except for 9 mm sleeve anchors which shall reach their torque by one quarter turn of the nut. If any anchor fails the test, test similar anchors not previously tested until 20 consecutive anchors pass. Failed anchors shall be retightened and retested to the specified torque; if the anchor still fails the test it shall be replaced.

3.3.2.3 Pullout Testing

Test expansion and chemically bonded anchors by applying a pullout load using a hydraulic ram attached to the anchor bolt. At least 5 percent of the anchors, but not less than 3 per day shall be tested. Apply the load to the anchor without removing the nut; when that is not possible, the nut shall be removed and a threaded coupler shall be installed of the same tightness as the original nut. Check the test setup to verify that the anchor is not restrained from withdrawing by the baseplate, the test fixture, or any other fixtures. The support for the testing apparatus shall be at least 1.5 times the embedment length away from the bolt being tested. Load each tested anchor to 1 times the design tension value for the anchor. The anchor shall have no observable movement at the test load. If any anchor fails the test, similar anchors not previously tested shall be tested until 20 consecutive anchors pass. Failed anchors shall be retightened and retested to the specified load; if the anchor still fails the test it shall be replaced.

3.4 RESILIENT VIBRATION ISOLATION DEVICES

Where the need for these devices is determined, based on the magnitude of the design seismic forces, selection of anchor bolts for vibration isolation devices and/or snubbers for equipment base and foundations shall follow the same procedure as in paragraph ANCHOR BOLTS, except that an equipment weight equal to five times the actual equipment weight shall be used.

3.4.1 Resilient and Spring-Type Vibration Devices

Select vibration isolation devices so that the maximum movement of equipment from the static deflection point is 13 mm.

3.4.2 Multidirectional Seismic Snubbers

Install multidirectional seismic snubbers employing elastomeric pads on floor- or slab-mounted equipment. These snubbers shall provide 6 mm free vertical and horizontal movement from the static deflection point.

Snubber medium shall consist of multiple pads of cotton duct and neoprene or other suitable materials arranged around a flanged steel trunnion so both horizontal and vertical forces are resisted by the snubber medium.

3.5 SWAY BRACES FOR PIPING

Provide transverse sway bracing for steel and copper pipe at intervals not to exceed those shown on the drawings. Transverse sway bracing for pipes

SECTION 13 48 00 Page 6 of materials other than steel and copper shall be provided at intervals not to exceed the hanger spacing as specified in Section 22 00 00 PLUMBING, GENERAL PURPOSE. Provide bracing consisting of at least one vertical angle 50 by 50 mm by 16 gauge and one diagonal angle of the same size.

3.5.1 Longitudinal Sway Bracing

Provide longitudinal sway bracing in accordance with Section 13 48 00.00 10

SEISMIC CONTROL FOR MECHANICAL EQUIPMENT.

3.5.2 Anchor Rods, Angles, and Bars

Anchor rods, angles, and bars shall be bolted to either pipe clamps or pipe flanges at one end and cast-in-place concrete or masonry insert or clip angles bolted to the steel structure on the other end. Rods shall be solid metal or pipe as specified below. Anchor rods, angles, and bars shall not exceed lengths given in the tabulation below.

3.5.3 Maximum Length for Anchor Braces

Type Size (mm) Maximum Length* (m)

Angles 38 x 38 x 6 1.5

50 x 50 x 6 2.0

64 x 38 x 6 2.5

75 x 64 x 6 2.5

75 x 75 x 6 3.0

Rods 91 1.0

22 1.0

Flat Bars 38 x 6 0.4

50 x 6 0.4

50 x 10 0.5

Pipes (40s) 25 2.0

32 2.8

40 3.2

50 4.0

3.5.4 Bolts

Bolts used for attachment of anchors to pipe and structure shall be not less than 13 mm diameter.

SECTION 13 48 00 Page 7

3.6 EQUIPMENT SWAY BRACING

3.6.1 Suspended Equipment and Light Fixtures

Provide equipment sway bracing for items supported from overhead floor or roof structural systems, including light fixtures. Braces shall consist of angles, rods, wire rope, bars, or pipes arranged as shown and secured at both ends with not less than 13 mm bolts. Provide sufficient braces for equipment to resist a horizontal force as specified in UFC 3-310-04 without exceeding safe working stress of bracing components. Provide, for approval, specific force calculations in accordance with UFC 3-310-04 for the equipment in the project. Submit details of equipment bracing for acceptance. In lieu of bracing with vertical supports, these items may be supported with hangers inclined at 45 degrees directed up and radially away from equipment and oriented symmetrically in 90-degree intervals on the horizontal plane, bisecting the angles of each corner of the equipment, provided that supporting members are properly sized to support operating weight of equipment when hangers are inclined at a 45-degree angle.

3.6.2 Floor or Pad Mounted Equipment

3.6.2.1 Shear Resistance

Bolt to the floor, floor mounted equipment. Requirements for the number and installation of bolts to resist shear forces shall be in accordance with paragraph ANCHOR BOLTS.

3.6.2.2 Overturning Resistance

Use the ratio of the overturning moment from seismic forces to the resisting moment due to gravity loads to determine if overturning forces need to be considered in the sizing of anchor bolts. Provide calculations to verify the adequacy of the anchor bolts for combined shear and overturning.

-- End of Section --

SECTION 13 48 00 Page 8

DIVISION 13 - SPECIAL CONSTRUCTION

SECTION 13 48 00.00 10

SEISMIC PROTECTION FOR MECHANICAL EQUIPMENT

10/07

PART 1 GENERAL

1.1 REFERENCES

1.2 SYSTEM DESCRIPTION

1.2.1 General Requirements

1.2.2 Mechanical Equipment

1.2.3 Mechanical Systems

1.2.4 Contractor Designed Bracing

1.2.5 Items Not Covered By This Section

1.2.5.1 Fire Protection Systems

1.2.5.2 Items Requiring No Seismic Restraints

1.3 SUBMITTALS

PART 2 PRODUCTS

2.1 EQUIPMENT REQUIREMENTS

2.1.1 Rigidly Mounted Equipment

2.1.2 Nonrigid or Flexibly-Mounted Equipment

2.2 FLEXIBLE COUPLINGS

2.3 FLEXIBLE BALL JOINTS

2.4 FLEXIBLE MECHANICAL JOINTS

2.5 MANUFACTURED BALL JOINTS

2.6 SWAY BRACING MATERIALS

PART 3 EXECUTION

3.1 COUPLING AND BRACING

3.2 BUILDING DRIFT

3.3 FLEXIBLE COUPLINGS OR JOINTS

3.3.1 Building Piping

3.3.2 Underground Piping

3.4 PIPE SLEEVES

3.5 SPREADERS

3.6 SWAY BRACES FOR PIPING

3.6.1 Transverse Sway Bracing

3.6.2 Longitudinal Sway Bracing

3.6.3 Vertical Runs

3.6.4 Clamps and Hangers

3.7 SWAY BRACES FOR DUCTS

3.7.1 Braced Ducts

3.7.2 Unbraced Ducts

SECTION 13 48 00.00 10 Page 1

SECTION 13 48 00.00 10

SEISMIC PROTECTION FOR MECHANICAL EQUIPMENT

10/07

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)

AISC 325 (2011) Steel Construction Manual

SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION

(SMACNA)

SMACNA 1981 (2008) Seismic Restraint Manual Guidelines for Mechanical Systems, 3rd Edition

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 3-310-04 (2013) Seismic Design for Buildings

1.2 SYSTEM DESCRIPTION

1.2.1 General Requirements

Apply the requirements for seismic protection measures described in this section to the mechanical equipment and systems listed below. Structural requirements shall be in accordance with Section 13 48 00 SEISMIC

PROTECTION FOR MISCELLANEOUS EQUIPMENT.

1.2.2 Mechanical Equipment

Mechanical equipment to be seismically protected shall include the following items to the extent required on the drawings or in other sections of these specifications:

Water Heaters Water Piping

Pumps with Motors Valves and Fittings for Piping

Exhaust and Return Fans Air and Refrigerant Compressors

Refrigerant Piping Air Handling Units

1.2.3 Mechanical Systems

Install the following mechanical systems as required on the drawings and other sections of these specifications and seismically protect them in

SECTION 13 48 00.00 10 Page 2 accordance with this specification:

a. All Piping Inside the Building Except as Specifically Stated Below Under "Items Not Covered By This Section".

b. All Water Supply Systems.

c. Storm and Sanitary Sewer Systems.

d. All Process Piping.

1.2.4 Contractor Designed Bracing

Submit copies of the design calculations with the drawings. Calculations shall be approved, certified, stamped and signed by a registered Professional Engineer. Calculations shall verify the capability of structural members to which bracing is attached for carrying the load from the brace. Design the bracing in accordance with UFC 3-310-04 and additional data furnished by the Contracting Officer. Resistance to lateral forces induced by earthquakes shall be accomplished without consideration of friction resulting from gravity loads. UFC 3-310-04 uses parameters for the building, not for the equipment in the building;

therefore, corresponding adjustments to the formulas shall be required.

Loadings determined using UFC 3-310-04 are based on strength design;

therefore, AISC 325 Specifications shall be used for the design. The bracing for the following mechanical equipment and systems shall be developed by the Contractor: All items listed in paragraph 1.2.3.

1.2.5 Items Not Covered By This Section

1.2.5.1 Fire Protection Systems

Seismic protection of piping for fire protection systems shall be installed as specified in Sections 21 30 00 FIRE PUMPS

1.2.5.2 Items Requiring No Seismic Restraints

Seismic restraints are not required for the following items:

a. Piping in mechanical equipment rooms less than 32 mm inside diameter.

b. Rectangular air handling ducts less than 0.56 square meters in cross sectional area.

c. Piping suspended by individual hangers 300 mm or less in length from the top of pipe to the bottom of the supporting structural member where the hanger is attached, except as noted below.

d. Ducts suspended by hangers 300 mm or less in length from the top of the duct to the bottom of the supporting structural member, except as noted below.

In exemptions f. and g. all hangers shall meet the length requirements.

If the length requirement is exceeded by one hanger in the run, the entire run shall be braced. Interior piping and ducts not listed above shall be seismically protected in accordance with the provisions of this specification.

SECTION 13 48 00.00 10 Page 3

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

SD-02 Shop Drawings

Coupling and Bracing Flexible Couplings or Joints Equipment Requirements Contractor Designed Bracing; G M

SD-03 Product Data

Coupling and Bracing; G M Equipment Requirements; G M Contractor Designed Bracing; G M

SD-07 Certificates

Flexible Ball Joints.

PART 2 PRODUCTS

2.1 EQUIPMENT REQUIREMENTS

Submit copies of the design calculations with the detail drawings.

Calculations shall be stamped by a registered engineer and shall verify the capability of structural members to which bracing is attached for carrying the load from the brace.

2.1.1 Rigidly Mounted Equipment

Air handling units to be furnished under this contract shall be constructed and assembled to withstand the seismic forces specified in UFC 3-310-04 . Each item of rigid equipment shall be entirely located and rigidly attached on one side only of a building expansion joint. Piping, duct, electrical conduit, etc., which cross the expansion joint shall be provided with flexible joints that are capable of accommodating displacements equal to the full width of the joint in both orthogonal directions.

2.1.2 Nonrigid or Flexibly-Mounted Equipment

The following specific items of equipment to be furnished: Any piece of equipment attached to ductwork or piping shall be constructed and assembled to resist a horizontal lateral force of 1.4 times the operating weight of the equipment at the vertical center of gravity of the equipment.

2.2 FLEXIBLE COUPLINGS

Flexible couplings shall have same pressure and temperature ratings as adjoining pipe.

SECTION 13 48 00.00 10 Page 4

2.3 FLEXIBLE BALL JOINTS

Flexible ball joints shall have cast or wrought steel casing and ball parts capable of 360-degree rotation with not less than 15-degree angular movement. Flexible ball joints shall be certified to be suitable for the service intended by the manufacturer. Information verifying experience at not less than 3 locations of 2 years' satisfactory operation in a similar application shall be submitted.

2.4 FLEXIBLE MECHANICAL JOINTS

a. Mechanical couplings for steel or cast iron pipe shall be of the sleeve type and shall provide a tight flexible joint under all reasonable conditions, such as pipe movement caused by expansion, contraction, slight settling or shifting of the ground, minor variations in trench gradients, and traffic vibrations. Where permitted in other sections of these specifications, joints utilizing split-half couplings with grooved or shouldered pipe ends may be used.

b. Sleeve-type couplings shall be used for joining plain-end pipe sections. The coupling shall consist of one steel middle ring, two steel followers, two gaskets, and necessary steel bolts and nuts to compress the gaskets.

2.5 MANUFACTURED BALL JOINTS

Manufactured ball joints shall be as recommended by the manufacturer for the intended use, and shall be approved by the Contracting Officer before installation.

2.6 SWAY BRACING MATERIALS

Sway bracing materials (e.g. rods, plates, rope, angles, etc.) shall be as specified in Section 13 48 00 SEISMIC PROTECTION FOR MISCELLANEOUS

EQUIPMENT.

PART 3 EXECUTION

3.1 COUPLING AND BRACING

a. Submit detail drawings, as specified here and throughout this specification, along with catalog cuts, templates, and erection and installation details, as appropriate, for the items listed.

Submittals shall be complete in detail; shall indicate thickness, type, grade, class of metal, and dimensions; and shall show construction details, reinforcement, anchorage, and installation with relation to the building construction.

b. Coupling installation shall conform to the details shown on the drawings. Provisions of this paragraph apply to all piping within a

1.5 m line around outside of building unless buried in the ground.

Piping grouped for support on trapeze-type hangers shall be braced at the most frequent interval as determined by applying the requirements of this specification to each piping run on the common support.

c. Bracing components shall be sized as required for the total load carried by the common supports. Bracing rigidly attached to pipe flanges, or similar, shall not be used where it would interfere with thermal expansion of piping.

SECTION 13 48 00.00 10 Page 5

3.2 BUILDING DRIFT

Joints capable of accommodating seismic displacements shall be provided for vertical piping between floors of the building, where pipes pass through a building seismic or expansion joint, or where rigidly supported pipes connect to equipment with vibration isolators. Horizontal piping across expansion joints shall accommodate the resultant of the drifts of each building unit in each orthogonal direction. For threaded piping, swing joints made of the same piping material shall be provided. For piping with manufactured ball joints the seismic drift shall be 0.015 meters per meter of height above the base where the seismic separation occurs; this drift value shall be used in place of the expansion given in the manufacturer's selection table.

3.3 FLEXIBLE COUPLINGS OR JOINTS

3.3.1 Building Piping

Flexible couplings or joints in building piping shall be provided at bottom of all pipe risers for pipe larger than 90 mm in diameter.

Flexible couplings or joints shall be braced laterally without interfering with the action of the flexible coupling or joint. Cast iron waste and vent piping need only comply with these provisions when caulked joints are used. Flexible bell and spigot pipe joints using rubber gaskets may be used at each branch adjacent to tees and elbows for underground waste piping inside of building to satisfy these requirements.

3.3.2 Underground Piping

Underground piping and 100 mm or larger conduit, except heat distribution system, shall have flexible couplings installed where the piping enters the building. The couplings shall accommodate 5 mm of relative movement between the pipe and the building in any direction. Additional flexible couplings shall be provided where shown on the drawings.

3.4 PIPE SLEEVES

Pipe sleeves in interior non-fire rated walls shall be sized as indicated on the drawings to provide clearances that will permit differential movement of piping without the piping striking the pipe sleeve. Pipe sleeves in fire rated walls shall be in accordance with the contract drawings.

3.5 SPREADERS

Spreaders shall be provided between adjacent piping runs to prevent contact during seismic activity whenever pipe or insulated pipe surfaces are less than 100 mm apart. Spreaders shall be applied at same interval as sway braces at an equal distance between the sway braces. If rack type hangers are used where the pipes are restrained from contact by mounting to the rack, spreaders are not required for pipes mounted in the rack.

Spreaders shall be applied to surface of bare pipe and over insulation on insulated pipes utilizing high-density inserts and pipe protection shields in accordance with the contract drawings.

3.6 SWAY BRACES FOR PIPING

Sway braces shall be provided to prevent movement of the pipes under

SECTION 13 48 00.00 10 Page 6 seismic loading. Braces shall be provided in both the longitudinal and transverse directions, relative to the axis of the pipe. The bracing shall not interfere with thermal expansion requirements for the pipes as described in other sections of these specifications.

3.6.1 Transverse Sway Bracing

Transverse sway bracing for steel and copper pipe shall be provided as specified in Section 13 48 00 SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT. All runs (length of pipe between end joints) shall have a minimum of two transverse braces. Transverse sway bracing for pipes of materials other than steel and copper shall be provided at intervals not to exceed the hanger spacing as specified in the contract drawings.

3.6.2 Longitudinal Sway Bracing

Longitudinal sway bracing shall be provided at 12 m intervals unless otherwise indicated. All runs (length of pipe between end joints) shall have one longitudinal brace minimum. Sway braces shall be constructed in accordance with the drawings. Branch lines, walls, or floors shall not be used as sway braces.

3.6.3 Vertical Runs

Run is defined as length of pipe between end joints. Vertical runs of piping shall be braced at not more than 3 m vertical intervals. Braces for vertical runs shall be above the center of gravity of the segment being braced. All sway braces shall be constructed in accordance with the drawings. Sway braces shall attach to the structural system and shall not be connected to branch lines, walls, or floors.

3.6.4 Clamps and Hangers

Clamps or hangers on uninsulated pipes shall be applied directly to pipe.

Insulated piping shall have clamps or hangers applied over insulation in accordance with the contract drawings.

3.7 SWAY BRACES FOR DUCTS

3.7.1 Braced Ducts

Bracing details and spacing for rectangular and round ducts shall be in accordance with SMACNA 1981, including Appendix E. However, the design seismic loadings for these items shall not be less than loadings obtained using the procedures in UFC 3-310-04 .

3.7.2 Unbraced Ducts

Hangers for unbraced ducts shall be attached to the duct within 50 mm of the top of the duct in accordance with SMACNA 1981. Unbraced ducts shall be installed with a 150 mm minimum clearance to vertical ceiling hanger wires.

SECTION 13 48 00.00 10 Page 7

DIVISION 21 - FIRE SUPPRESSION

SECTION 21 13 13.00 10

WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

05/09

PART 1 GENERAL

1.1 REFERENCES

1.2 SYSTEM DESCRIPTION

1.2.1 Hydraulic Design

1.2.1.1 Hose Demand

1.2.1.2 Basis for Calculations

1.2.1.3 Hydraulic Calculations

1.2.2 Sprinkler Coverage

1.3 SUBMITTALS

1.4 QUALITY ASSURANCE

1.4.1 Fire Protection Specialist

1.4.2 Sprinkler System Installer

1.4.3 Shop Drawings

1.5 DELIVERY, STORAGE, AND HANDLING

1.6 EXTRA MATERIALS

PART 2 PRODUCTS

2.1 STANDARD PRODUCTS

2.2 NAMEPLATES

2.3 REQUIREMENTS FOR FIRE PROTECTION SERVICE

2.4 UNDERGROUND PIPING COMPONENTS

2.4.1 Pipe

2.4.2 Fittings and Gaskets

2.4.3 Gate Valve and Indicator Posts

2.5 ABOVEGROUND PIPING COMPONENTS

2.5.1 Steel Piping Components

2.5.1.1 Steel Pipe

2.5.1.2 Fittings for Non-Grooved Steel Pipe

2.5.1.3 Grooved Mechanical Joints and Fittings

2.5.1.4 Flanges

2.5.1.5 Bolts, Nut, and Washers

2.5.2 Pipe Hangers

2.5.3 Valves

2.5.3.1 Control Valve and Gate Valve

2.5.3.2 Check Valve

2.6 ALARM CHECK VALVE ASSEMBLY

2.7 WATERFLOW ALARM

2.8 ALARM INITIATING AND SUPERVISORY DEVICES

2.8.1 Sprinkler Waterflow Indicator Switch, Vane Type

2.8.2 Sprinkler Pressure (Waterflow) Alarm Switch

2.8.3 Valve Supervisory (Tamper) Switch

2.9 FIRE DEPARTMENT CONNECTION

2.10 SPRINKLERS

2.10.1 Pendent Sprinkler

SECTION 21 13 13.00 10 Page 1

2.10.2 Upright Sprinkler

2.11 ACCESSORIES

2.11.1 Sprinkler Cabinet

2.11.2 Identification Sign

2.12 DOUBLE-CHECK VALVE BACKFLOW PREVENTION ASSEMBLY

PART 3 EXECUTION

3.1 FIELD MEASUREMENTS

3.2 INSTALLATION REQUIREMENTS

3.3 INSPECTION BY FIRE PROTECTION SPECIALIST

3.4 ABOVEGROUND PIPING INSTALLATION

3.4.1 Protection of Piping Against Earthquake Damage

3.4.2 Piping in Exposed Areas

3.4.3 Piping in Finished Areas

3.4.4 Pendent Sprinklers

3.4.5 Upright Sprinklers

3.4.6 Pipe Joints

3.4.7 Reducers

3.4.8 Pipe Penetrations

3.4.9 Escutcheons

3.4.10 Inspector's Test Connection

3.4.11 Drains

3.4.12 Installation of Fire Department Connection

3.4.13 Identification Signs

3.5 UNDERGROUND PIPING INSTALLATION

3.6 ELECTRICAL WORK

3.7 PIPE COLOR CODE MARKING

3.8 PRELIMINARY TESTS

3.8.1 Underground Piping

3.8.1.1 Flushing

3.8.1.2 Hydrostatic Testing

3.8.2 Aboveground Piping

3.8.2.1 Hydrostatic Testing

3.8.2.2 Backflow Prevention Assembly Forward Flow Test

3.8.3 Testing of Alarm Devices

3.8.4 Main Drain Flow Test

3.9 FINAL ACCEPTANCE TEST

3.10 ONSITE TRAINING

SECTION 21 13 13.00 10 Page 2

SECTION 21 13 13.00 10

WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

05/09

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF SANITARY ENGINEERING (ASSE)

ASSE 1015 (2011) Performance Requirements for Double Check Backflow Prevention Assemblies and Double Check Fire Protection Backflow Prevention Assemblies - (ANSI approved 2010)

AMERICAN WATER WORKS ASSOCIATION (AWWA)

AWWA C104/A21.4 (2016) Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water

AWWA C110/A21.10 (2012) Ductile-Iron and Gray-Iron Fittings for Water

AWWA C111/A21.11 (2017) Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings

AWWA C151/A21.51 (2017) Ductile-Iron Pipe, Centrifugally Cast

AWWA C203 (2008) Coal-Tar Protective Coatings and Linings for Steel Water Pipelines - Enamel and Tape - Hot-Applied

ASME INTERNATIONAL (ASME)

ASME B16.1 (2015) Gray Iron Pipe Flanges and Flanged Fittings Classes 25, 125, and 250

ASME B16.11 (2011) Forged Fittings, Socket-Welding and Threaded

ASME B16.21 (2011) Nonmetallic Flat Gaskets for Pipe Flanges

ASME B16.3 (2011) Malleable Iron Threaded Fittings, Classes 150 and 300

ASME B16.4 (2011) Standard for Gray Iron Threaded Fittings; Classes 125 and 250

SECTION 21 13 13.00 10 Page 3

ASME B16.9 (2012) Standard for Factory-Made Wrought Steel Buttwelding Fittings

ASTM INTERNATIONAL (ASTM)

ASTM A135/A135M (2009; R2014) Standard Specification for Electric-Resistance-Welded Steel Pipe

ASTM A183 (2014) Standard Specification for Carbon Steel Track Bolts and Nuts

ASTM A193/A193M (2016) Standard Specification for Alloy-Steel and Stainless Steel Bolting Materials for High-Temperature Service and Other Special Purpose Applications

ASTM A449 (2014) Standard Specification for Hex Cap Screws, Bolts, and Studs, Steel, Heat Treated, 120/105/90 ksi Minimum Tensile Strength, General Use

ASTM A47/A47M (1999; R 2014) Standard Specification for Ferritic Malleable Iron Castings

ASTM A53/A53M (2012) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless

ASTM A536 (1984; R 2014) Standard Specification for Ductile Iron Castings

ASTM A795/A795M (2013) Standard Specification for Black and Hot-Dipped Zinc-Coated (Galvanized) Welded and Seamless Steel Pipe for Fire Protection Use

ASTM F436M (2011) Hardened Steel Washers (Metric)

FM GLOBAL (FM)

FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/

MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE AND FITTINGS

INDUSTRY (MSS)

MSS SP-71 (2011; Errata 2013) Gray Iron Swing Check Valves, Flanged and Threaded Ends

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 101 (2015; ERTA 2016) Life Safety Code

NFPA 13 (2016; TIA 16-1; TIA 16-2; TIA 16-3 2016;

Errata 17-1; Errata 17-2) Standard for the Installation of Sprinkler Systems

NFPA 1963 (2014) Standard for Fire Hose Connections

SECTION 21 13 13.00 10 Page 4

NFPA 24 (2013) Standard for the Installation of Private Fire Service Mains and Their Appurtenances

NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES

(NICET)

NICET 1014-7 (2010) Program Detail Manual for Certification in the Field of Fire Protection Engineering Technology (Field Code 003) Subfield of Automatic Sprinkler System Layout

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 3-310-04 (2013) Seismic Design for Buildings

UNDERWRITERS LABORATORIES (UL)

UL Bld Mat Dir (updated continuously online) Building Materials Directory

UL Fire Prot Dir (2012) Fire Protection Equipment Directory

1.2 SYSTEM DESCRIPTION

Furnish piping offsets, fittings, and any other accessories as required to provide a complete installation and to eliminate interference with other construction. Install sprinkler system over and under ducts, piping and platforms when such equipment can negatively effect or disrupt the sprinkler discharge pattern and coverage. Provide wet pipe sprinkler system in all areas of the building. Except as modified herein, the system shall be designed and installed in accordance with NFPA 13 . Pipe sizes which are not indicated on drawings shall be determined by hydraulic calculation. Design any portions of the sprinkler system that are not indicated on the drawings including locating sprinklers, piping and equipment, and size piping and equipment when this information is not indicated on the drawings or is not specified herein. The design of the sprinkler system shall be based on hydraulic calculations, and the other provisions specified herein.

1.2.1 Hydraulic Design

Hydraulically design the system to discharge a minimum density of 8.2 L/min per square meter over the hydraulically most demanding 232 square m of floor area. The minimum pipe size for branch lines in gridded systems shall be 32 mm. Hydraulic calculations shall be in accordance with the Area/Density Method of NFPA 13 . Water velocity in the piping shall not exceed 6 m/s.

1.2.1.1 Hose Demand

Add an allowance for exterior hose streams of 950 L/min to the sprinkler system demand at the fire hydrant shown on the drawings closest to the point where the water service enters the building.

1.2.1.2 Basis for Calculations

The design of the system shall be based upon a water supply with a static

SECTION 21 13 13.00 10 Page 5 pressure of 5.4 BAR, and a flow of 3850 L/min at a residual pressure of

5.0 BAR. Water supply shall be presumed available at the base of the riser.

Hydraulic calculations shall be based upon the Hazen-Williams formula with a "C" value of 120 for steel piping, 150 for copper tubing, 140 for new cement-lined ductile-iron piping, and 100 for existing underground piping.

Hydraulic calculations shall be based on operation of the fire pump(s) provided in Section 21 30 00 FIRE PUMPS.

1.2.1.3 Hydraulic Calculations

Submit hydraulic calculations, including a drawing showing hydraulic reference points and pipe segments and as outlined in NFPA 13 , except that calculations shall be performed by computer using software intended specifically for fire protection system design using the design data shown on the drawings. Software that uses k-factors for typical branch lines is not acceptable. Calculations shall be based on the water supply data shown on the drawings to substantiate that the design area used in the calculations is the most demanding hydraulically. Water supply curves and system requirements shall be plotted on semi-logarithmic graph paper so as to present a summary of the complete hydraulic calculation. Provide a summary sheet listing sprinklers in the design area and their respective hydraulic reference points, elevations, actual discharge pressures and actual flows. Elevations of hydraulic reference points (nodes) shall be indicated. Documentation shall identify each pipe individually and the nodes connected thereto. Indicate the diameter, length, flow, velocity, friction loss, number and type fittings, total friction loss in the pipe, equivalent pipe length and Hazen-Williams coefficient for each pipe. For gridded systems, calculations shall show peaking of demand area friction loss to verify that the hydraulically most demanding area is being used.

Also for gridded systems, a flow diagram indicating the quantity and direction of flows shall be included. A drawing showing hydraulic reference points (nodes) and pipe designations used in the calculations shall be included and shall be independent of shop drawings.

1.2.2 Sprinkler Coverage

Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall provide coverage throughout 100 percent of the building. This includes, but is not limited to, telephone rooms, electrical equipment rooms, boiler rooms, switchgear rooms, transformer rooms, and other electrical and mechanical spaces.

Coverage per sprinkler shall be in accordance with NFPA 13 , but shall not exceed 9 square m for extra hazard occupancies, 12 square m for ordinary hazard occupancies, and 21 square m for light hazard occupancies.

Exceptions are as follows:

a. Sprinklers may be omitted from small rooms which are exempted for specific occupancies in accordance with NFPA 101 .

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

SECTION 21 13 13.00 10 Page 6

Shop Drawings; G M As-Built Drawings

SD-03 Product Data

Fire Protection Related Submittals Materials and Equipment; G M Spare Parts Preliminary Tests; G M Final Acceptance Test; G M Onsite Training; G M Fire Protection Specialist; G M Sprinkler System Installer; G M

SD-05 Design Data

Sway Bracing; G M Hydraulic Calculations; G M

SD-06 Test Reports

Preliminary Test Report Final Acceptance Test Report

SD-07 Certificates

Inspection by Fire Protection Specialist

SD-10 Operation and Maintenance Data

Operating and Maintenance Manuals; G R

1.4 QUALITY ASSURANCE

Compliance with referenced NFPA standards is mandatory. In the event of a conflict between specific provisions of this specification and applicable NFPA standards, this specification governS. Interpret reference to "authority having jurisdiction" to mean the Contracting Officer.

1.4.1 Fire Protection Specialist

Perform work specified in this section under the supervision of and certified by the Fire Protection Specialist who is an individual registered professional engineer who has passed the fire protection engineering written examination administered by the National Council of Examiners for Engineering and Surveys (NCEES) or who is certified as a Level IV Technician by National Institute for Certification in Engineering Technologies (NICET) in the Automatic Sprinkler System Layout subfield of Fire Protection Engineering Technology in accordance with NICET 1014-7 .

Submit the name and documentation of certification of the proposed Fire Protection Specialists, no later than 14 days after the Notice to Proceed and prior to the submittal of the sprinkler system drawings and hydraulic calculations. The Fire Protection Specialist shall prepare and submit a list of the fire protection related submittals, no later than 7 days after the approval of the Fire Protection Specialist, from the Contract Submittal Register that relate to the successful installation of the sprinkler systems(s). The submittals identified on this list shall be accompanied by a letter of approval signed and dated by the Fire Protection Specialist when submitted to the Government. The Fire

SECTION 21 13 13.00 10 Page 7

Protection Specialist shall be regularly engaged in the design and installation of the type and complexity of system specified in the contract documents, and shall have served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months.

1.4.2 Sprinkler System Installer

Work specified in this section shall be performed by the Sprinkler System Installer who is regularly engaged in the installation of the type and complexity of system specified in the contract documents, and who has served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months.

Submit the name and documentation of certification of the proposed Sprinkler System Installer, concurrent with submittal of the Fire Protection Specialist Qualifications.

1.4.3 Shop Drawings

Shop Drawings shall conform to the requirements established for working plans as prescribed in NFPA 13 . Submit 3 copies of the Sprinkler System shop drawings, no later than 21 days prior to the start of sprinkler system installation. Drawings shall include plan and elevation views demonstrating that the equipment will fit the allotted spaces with clearance for installation and maintenance. Each set of drawings shall include the following:

a. Descriptive index of drawings in the submittal with drawings listed in sequence by drawing number. A legend identifying device symbols, nomenclature, and conventions used.

b. Floor plans drawn to a scale not less than 1:100 which clearly show locations of sprinklers, risers, pipe hangers, seismic separation assemblies, sway bracing, inspector's test connections, drains, and other applicable details necessary to clearly describe the proposed arrangement. Each type of fitting used and the locations of bushings, reducing couplings, and welded joints shall be indicated.

c. Actual center-to-center dimensions between sprinklers on branch lines and between branch lines; from end sprinklers to adjacent walls; from walls to branch lines; from sprinkler feed mains, cross-mains and branch lines to finished floor and roof or ceiling. A detail shall show the dimension from the sprinkler and sprinkler deflector to the ceiling in finished areas.

d. Longitudinal and transverse building sections showing typical branch line and cross-main pipe routing as well as elevation of each typical sprinkler above finished floor.