Sample Task Order Amendment 0003.pdf
PDF 218 KB Posted
- Solicitation number
- W912EF26QA059
About this file
This is a Sample Task Order for cost comparison purposes only, detailing dive operation specifications for underwater inspection of turbine intake transducers at two U.S. Army Corps of Engineers (USACE) dam facilities. The work is scheduled for Lower Monumental Dam in Walla Walla, Washington (September 21-23, 2026) and John Day Dam in Portland, Oregon (September 28-30, 2026). The contractor will conduct a three-day underwater inspection at each site with no installation or construction tasks involved, operating Monday through Wednesday with one dive evolution per day.
The scope requires surface-supplied air diving operations consisting of one deep dive to 146 feet and one shallow dive to 40 feet, utilizing a five-person diving team including a non-diving Dive Supervisor, two working Divers, one Standby Diver, and one Tender, with an additional Qualified Diver added for basic 8-hour workdays. Specific schedule line items are identified for cost comparison for each location and activity phase: mobilization/demobilization, Day 0 predive preparation, Day 1 deep inspection, Day 2 supplemental deep inspection with assumed 2 hours of Dive Supervisor overtime, and Day 3 shallow inspection and final verification. The contractor must provide a workboat capable of accommodating the dive crew and two USACE personnel, carrying all equipment, providing a stable surface-supplied air working platform, maintaining sufficient freeboard, and possessing adequate horsepower for river navigation. Mobilization and demobilization are excluded from dive day calculations, with each task order charged only one mob/demobilization fee regardless of duration.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SAMPLE TASK ORDER
TO BE USED FOR COST COMPARISON ONLY
DIVE OPERATION SPECIFICATIONS forௗ
Turbine Intake TransducerௗInspection
For Walla Walla: Lower Monumental Dam (21-23 September 2026)ௗ
For Portland:ௗJohn Day Dam Dive (28-30 Septemberௗ2026)
Scope of work:
The dive team will conduct underwater inspection of LowerௗMonumental and John DayௗDamௗTurbine Intake Transducers (three days at each site). Noௗinstallation or construction tasks will be performed. Assume all work will take place Monday-Wednesday with one dive evolution per day.
The dives will consist of the following:ௗ
Surface supplied air with one deep dive toௗ146 ftௗand one shallow dive toௗ40 ft using a five-personௗdiving team consisting of aௗnon-divingௗDive Supervisor, two workingௗDivers, oneௗStandby Diver, and oneௗTender.ௗ
Add an additional Qualified Diver to theௗ5-personௗdive team for a basicௗ8-hourௗworkday.ௗ
Note: For price comparison use Schedule line items identified below.
Schedule
Mobilization / Demobilization:ௗContractor will mobilize and demobilize all personnel, dive equipment, chamber, and support gearௗtoௗLower Monumental Damௗ(21-23 Sept 2026)ௗandௗJohn Day Damௗ(28-30 Septௗ2026). Workboat transport, launch, and recovery are included. Mobilization and demobilization time is excluded from the dive day.ௗEach task order will have only one mob/demobilization charge whether it runs one or several days.ௗ
Workboat requirements:ௗVessel must accommodate the dive crew andௗ2ௗUSACE personnel, carry all equipment, provide a stable SSA working platform, have suƯicient freeboard, andௗpossessௗadequate horsepowerௗforௗriverௗnavigation.ௗௗ
For price comparison use the following line items:
0004AD for Walla Walla, Lower Monumental
0028AD for Portland, John Day
Day 0 Mobilization
Mobilize workboats, Conduct predive brief, equipment checks, communications test, and emergency drills.ௗ Confirm USACE site access and lockout/tagout asௗrequired.ௗ
For price comparison use the following line items:
0003AD for Walla Walla, Lower Monumental
0027AF for Portland, John Day
Day 1 Deep Inspectionௗ
Dive 1:ௗ146 ft SSA. Perform methodical inspection of transducer mounting and surrounding structure, clean surfaces as needed for inspection, captureௗhigh-resolutionௗvideo and stills, and take measurements of any anomalies.ௗ Topsides: review video andௗdetermineௗif supplemental deep documentation isௗrequired.ௗ Assume work can be done in one dive evolution.
For price comparison use the following line items:
0001AA, 0001AB, and 0001AC, and 0002AA for Walla Walla, Lower Monumental
0025AA, 0025AB, and 0025AC, and 0026AA for Portland, John Day
Day 2 Supplemental Deep Inspectionௗ
Dive 2:ௗ146 ft SSA. Reinspect areas of concern, perform detailed probing or measurement, and captureௗadditionalௗvideo and stills.ௗ Topsides: prepare for shallow transition inspection and cable run verification.ௗ Assume work can be done in one dive evolution.
For price comparison use the following line items:
0001AA, 0001AB, and 0001AC, and 0002AA for Walla Walla, Lower Monumental
0025AA, 0025AB, and 0025AC, and 0026AA for Portland, John Day
Assume Dive Supervisor had to work 2 hours of overtime using the following line items:
0007 for Walla Walla, Lower Monumental 0031 for Portland, John Day
Day 3 Shallow Inspection and Final Verificationௗ
Dive 3:ௗ40 ft SSA. Inspect cable routing, clamps, supports, and shallow transition points, perform final video sweep, and verify no snag or entrapment hazards remain. Topsides:
finalizeௗinspection report, compile video and stills, and prepare for demobilization.ௗAssume work can be done in one dive evolution.
For price comparison use the following line items:
0001AA, 0002AA for Walla Walla, Lower Monumental
0025AA, 0026AA for Portland, John Day
Day 4 Demobilizationௗ
Demobilize chamber, equipment, and workboat. Completeௗpost-operationௗinspections and reports.ௗ