PWS - FY25 B1 North Plains Appendix C Performance Requirements Summary 250310.docx
DOCX document 32 KB Posted
- Attached to
- 88th RD North Plains Region PMCM
- Solicitation number
- W912DY25R0025
About this file
This Performance Work Statement (PWS) Appendix C details performance requirements for a maintenance services contract for the 88th Readiness Division's North Plains Region, covering Minnesota, North Dakota, South Dakota, and Wisconsin. The contract is a competitive set-aside for 8(a) small businesses, with a one-year base period and four one-year option periods, potentially extending up to an additional 6 months.
The PWS establishes critical performance standards across multiple operational areas, including key personnel requirements, monthly reporting, license maintenance, preventative and corrective maintenance completion rates, safety training, documentation preparation, and various mandatory annual trainings (Anti-Terrorism, Operations Security, Suspicious Activity Reporting, and Cyber Awareness). Performance thresholds are strictly defined, with specific remedies for non-compliance such as invoice deductions, potential negative CPARS ratings, and restrictions on work performance. The contract will be awarded by the Department of the Army Corps of Engineers Engineering Support Center Huntsville as a firm-fixed-price agreement.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| PWS | Appendix C | FY25 B1 North Plains Region |
| Performance Requirements Summary |
C. Performance Requirements Summary
C.1. General The rights of the Government and remedies described in this section are in addition to all other rights and remedies set forth in this contract. Specifically, the Government reserves its right under the Inspection of Services and Termination for Default clauses. Any deductions pursuant to the Performance Requirements Summary (PRS) shall reflect the reduced value of service performed under the contract. The Contractor shall not be relieved of full performance of the services hereunder and may be terminated for default based upon inadequate performance of service even if a deduction was previously taken for inadequate performance. The Government may modify the type and frequency of inspection of items.
C.1.1. Purpose The Performance Requirements Summary is designed to:
C.1.1.1.
List the contract requirements considered most critical to acceptable contract performance. (Column 1).
C.1.1.2.
List the contract paragraph number(s) which describe the requirements (Column 2).
C.1.1.3.
Define the standard of performance for each required service specified (Column 3).
C.1.1.4.
Show the maximum allowable degree of deviation or Acceptable Quality Levels (AQLs) from perfect performance that will be allowed by the Government before contract performance is considered unsatisfactory (Column 4).’
C.1.1.5.
Explain the quality assurance methods the Government will use to evaluate the Contractor’s performance in meeting the contract requirements (Column 5).
C.1.1.6.
Show the remedy available to the Contractor or Government to bring performance within the standard defined in Column 4 (Column 6).
C.1.2. Nonconformance the government will document all Contractor non-conformances.
C.1.3. Performance Requirements Summary The Performance Requirements Summary lists those services/tasks for which the Government will make deductions from payment due the Contractor when services/tasks are found to be unsatisfactory during inspections made using the checklists. These deductions are in addition to reduced invoicing described in Section 7 of the PWS and the pricing workbook.
| Performance Objective |
| PWS Paragraph |
| Performance Standard |
| Performance Threshold (maximum error rate) |
| Method of Surveillance |
| Remedy if Performance Threshold is not met |
| Provide Key Personnel |
| 3.4 |
| The Contractor shall provide a dedicated CMM, a Lead Maintenance Mechanic/M&S Supervisor, and a (part time) L1 SHO meeting all PWS requirements for positions |
| 100% (zero deviation) |
| 100% inspection |
| Deduction in invoice payment equal to contract cost of position(s) not filled until contractor provides qualified personnel |
| BaseOps Monthly Report & Monthly Safety Report |
| Appendix D |
| Contractor shall submit a BaseOps Monthly Report and a monthly Safety Report (may be a combined report) showing performance data for the previous month |
| No more than one (1) late BaseOps report or one (1) late Safety report during a performance period |
| 100% Inspection |
| Deduction of 5% of all CLINS ordered in Task Order and potentially a negative CPARS narrative |
| Maintain Licenses and Certificates |
| 3.8 |
| The Contractor will ensure that the licenses or certificates of Contractor personnel are kept current. Copies of these licenses or certifications will be provided to the COR |
| 100% (zero deviation) |
| Random Inspection |
| Contractor shall not perform work until qualified personnel are present; deduction in invoice equal to the value of work not performed and potentially a negative CPARS narrative |
| Preventative / Recurring Maintenance Completion Rate |
| 4.4 |
| The Contractor shall complete PM in the month they are scheduled and IAW required standards |
| 95% |
No more than 5% of the scheduled PM work requests are not complete in the month scheduled or IAW required standards.
| 100% Inspection |
| Potentially a negative CPARS rating; The Contractor shall not invoice for PM not performed (per the PM Cost tab of the awarded pricing workbook). The Contractor may be held liable for equipment failures if PM is not completed. If failing to complete 100% of PM becomes a recurring issue, more severe remedies will be taken. |
| Corrective Maintenance Completion Rate |
| 4.5 and Appendix H |
| The Contractor shall complete all non-long lead CM work requests within the times listed in Table H.2.1 (Appendix H); The Contractor shall annotate expected completion time for long lead SO on the SOF for KO approval; See Appendix H for additional information on long lead SO |
| 95% |
No more than 5% of the scheduled CM work requests are not complete within the times listed in Table H.2.1; 100% complete within time extension granted by the KO
| 100% Inspection |
| Reduced invoice equal to 1/2% for each business day SO not complete within the times listed in Table H.2.1 or time extension granted by the KO (e.g., 3 days late equals a 1.5% reduction) and potentially a negative CPARS narrative |
| Preparation of Service Order Documentation for Government Approval |
| 4.5 and Appendix H |
| 95% of service order documentation prepared within times listed in Table H.2.1; 100% of service order documentation prepared within time extensions approved by the KO |
| 95% |
No more than 5% of service order packages are not submitted or not submitted correctly for funding approval within the times listed in Table H.2.1; 100% complete within time extension granted by the KO
| 100% Inspection |
| Reduced invoice equal to 1/2% for each business day an acceptable SO not submitted within the times listed in Table H.2.1 (e.g., submitted 3 days late equals a 1.5% reduction) and potentially a negative CPARS narrative |
| Perform Safety Requirements |
| Section 5 |
| The Contractor shall perform checks for compliance with task order safety requirements and perform safety meetings prior to all maintenance tasks (signed AHA to document meeting) |
| 99% for the work completed |
| Random Sampling |
| 3% of all CLINs ordered and potentially a negative CPARS narrative |
| Safety Training |
| 5.5 |
| Contractor shall complete all necessary safety training for all workers before they report on-site to perform work and document this training in the BaseOps monthly report |
| 100% (zero deviation) |
| Random Sampling |
| Employee(s) not current in training shall not perform duties; reduction in invoice equal to work not performed/positions not filled and potentially a negative CPARS narrative |
| Contractor QC |
| 6.1.1 |
| The Contractor shall perform QC as required in the PWS |
| 100% (zero deviation) |
| 100% Inspection |
Contractor reported QC statistics in Monthly Report Reduced invoice equal to 1/2% for each % under the minimum required of the affected CLIN
| Rework Effectiveness |
| NA |
| 100% of completed rework accepted by the Government without further rework |
| 100% (zero deviation) |
| 100% Inspection |
| Reduced invoice equal to 25% of the work rejected by the Government and potentially a negative CPARS rating |
| AT Level I Training |
| 8.7.1 |
| All Contractor employees shall complete AT Level I training annually |
| 100% (zero deviation) |
| 100% inspection |
| Employee(s) not current in training shall not perform duties; reduction in invoice equal to work not performed and potentially a negative CPARS narrative |
| OPSEC Training |
| 8.7.2 |
| All Contractor employees shall complete OPSEC training annually |
| 100% (zero deviation) |
| 100% inspection |
| Employee(s) not current in training shall not perform duties; reduction in invoice equal to work not performed and potentially a negative CPARS narrative |
| Suspicious Activity Reporting Training |
| 8.7.3 |
| All Contractor employees shall complete iWATCH training annually |
| 100% (zero deviation) |
| 100% inspection |
| Employee(s) not current in training shall not perform duties; reduction in invoice equal to work not performed and potentially a negative CPARS narrative |
| Cyber Awareness Training |
| 8.7.4 |
| All Contractor employees shall complete Cyber Awareness training annually |
| 100% (zero deviation) |
| 100% inspection |
| Employee(s) not current in training shall not perform duties; reduction in invoice equal to work not performed and potentially a negative CPARS narrative |