Amendment 0003 W912DW24R0019 (AFD Powerhouse Bridge Crane).pdf
PDF 369 KB Posted
- Solicitation number
- W912DW24R0019
About this file
This document is Amendment 0003 to Solicitation W912DW24R0019 for the Albeni Falls Dam (AFD) Powerhouse Bridge Crane Rehabilitation project in Oldtown, ID. The amendment extends the solicitation due date to October 11, 2024 and revises multiple sections of the specifications, drawings, and attachments, including the price schedule, scope of work, submittal requirements, safety requirements, and below-the-hook lifting device details. Key changes include adding new reference drawings, updating bridge crane and electrical rehabilitation requirements, and providing additional safety guidance. The solicitation is issued by the U.S. Army Corps of Engineers Seattle District for the rehabilitation of the 250-ton bridge crane at the AFD powerhouse. The project includes engineering design, crane rehabilitation, load testing, spare parts, and training. Pricing for base bid and optional items is required.
View the file
Other files
Show 40 more
Latest 50 of 65 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendmend 0003
Please See Continuation Pages:
1. CONTRACT ID CODE PAGE OF PAGES
1 12
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 06-Sep-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DW24R0019
X 9B. DATED (SEE ITEM 11)
06-Jun-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
06-Sep-2024
CODE
USA ENGINEER DISTRICT, SEATTLE
ATTN: CENWS-CT
4735 EAST MARGINAL WAY SOUTH, BLDG. 1202
SEATTLE WA 98134-2388
W912DW 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DW24R0019
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0003
Summary of Changes for Amendment 0003
1. Solicitation due date has been extended to 11 October 2024.
2. Section 00 10 00 Price Schedule has been revised in red and underlined.
3. Specification Project Table of Contents has been revised in red and underlined. Attached file Table of Contents R0003.
4. Specification 01 11 00.01 28 Conceptual Design Information has been added. Attached file 01 11 00.01 28 R0003.
5. Specification 01 33 16.00 28 Design Data (Design After Award) have been added. Changes are shown underline and in red. Attached file 01 33 16.00 28 R0003.
6. Specification Submittal Register has been revised in highlighted. Attached file Submittal Register R0003
7. Specification 01 11 00.00 26 Summary of Work: Section 1.2.1 Project Description has been revised in red and underlined. Attached file 01 11 00.00 26 R0003.
8. Specification 01 22 00.00 26 Measure and Payment Procedures: Sections 1.3.12 to 1.3.22 have been revised in red and underlined. Attached file 01 22 00.00 26 R0003.
9. Specification 01 35 26 Government Safety Requirements:
• Section 3.4.2 Safe Clearance has been revised in red and underlined. Attached file 01 35 26 R0003.
• CENWS ODA HECP Appendix D attachment has been added in its entirety. Attached file CENWS ODA HECP Appendix D R0003.
• CENWS ODA HECP Local Supplement attachment has been added in its entirety. Attached file CENWS ODA HECP Local Supplement R0003.
• HECP NWS 11519 attachment has been added in its entirety. Attached file HECP NWS 11519 Revision 2 R0003.
• AFD Fall Protection Submittal attachment has been added in its entirety. Attached file AFD Fall Protection Submittal R0003.
10. Specification 41 22 13.72 26 Bridge Crane Mechanical and Structural Rehabilitation: Section 1.5 Submission of Crane Design Data has been revised in red and underlined. Attached file 41 22 13.72 26 R0003.
11. Specification 41 22 13.75 26 Lifting Device Load Testing has been revised in red and underlined. Attached file 41 22 13.75 26 R0003.
12. Specification 41 22 13.76 26 Optional Below-The-Hook Lifting Devices: Sections 1.1 and1.4 have been revised in red and underlined. Attached file 41 22 13.76 26 R0003.
13. Section 00 70 00, clause 252-236-7001, paragraph e Index to Drawings has been revised in red.
14. G-002 has been revised in the clouded box. Attached file G-002 R0003
15. Plan Drawing Plate Number G-202 New Electrical Equipment Layout has been revised in the clouded box.
Attached file G-202 R0003
16. Plan Drawing Plate Number G-203 Bridge Crane Overview – Install has been revised in the clouded box.
Attached file G-203 R0003
17. Plan Drawing Plate Number M-101 Trolley Overview – Install has been revised in the clouded box. Attached file M-101 R0003
18. Plan Reference Drawing E-52-18-1_101 Loading Diagrams has been added. Attached file E-52-18-1-101 R0003.
19. Plan Reference Drawing E-52-18-3_56 Concrete Outline Superstructure Roof Plan and Section has been added.
Attached file E-52-18-3-56 R0003.
20. Plan Reference Drawing E-52-18-3_57 Concrete Outline Superstructure Roof Plan and Section has been added.
Attached file E-52-18-3-57 R0003.
21. PLAN Reference Drawing E-52-18-3_66 Concrete Outline Superstructure Transverse Sections and Details has been added. Attached file E-52-18-3-66 R0003.
22. Plan Reference Drawing E-52-18-4_99 Concrete Reinforcement Superstructure Downstream Wall Control and Service Bay has been added. Attached file E-52-18-4-99 R0003.
23. Plan Reference Drawing E-52-18-4_100 Concrete Reinforcement Superstructure Downstream Wall Control and Service Bay has been added. Attached file E-52-18-4-100 R0003.
24. Plan Reference Drawing E-52-18-4_101 Concrete Reinforcement Superstructure Generator Room Upstream Wall Above 2104.5 has been added. Attached file E-52-18-4-101 R0003.
25. Plan Reference Drawing E-52-18-4_102 Concrete Reinforcement Superstructure Generator Room Upstream Wall Above 2104.5 has been added. Attached file E-52-18-4-102 R0003.
26. Plan Reference Drawing E-52-18-5_8 Miscellaneous Metal Work Crane Access Ladders and Handrail has been added. Attached file E-52-18-5-8 R0003.
27. Plan Reference Drawing E-52-18-7_1 Roof and Deck Plan has been added. Attached file E-52-18-7-1 R0003.
28. Plan Reference Drawing E-52-18-7_4 Floor Plan EL 2047 and EL 2042 has been added. Attached file E-52-18- 7-4 R0003.
29. Plan Reference Drawing E-52-20-2_9 Arrangement Transverse Section THRU Unit No 2 has been added.
Attached file E-52-20-2-9 R0003.
30. Plan Reference Drawing E-52-20-2_11 Arrangement Plan Generator Floor EL 2060 has been added. Attached file E-52-20-2-11 R0003.
31. Plan Reference Drawing E-52-20-7_2 Floor Plans EL 2095.00 and EL 2080.00 has been added. Attached file E- 52.20-7-2 R0003.
32. Plan Reference Drawing Plate 39619 Lifting Device For Main Shaft & Inner Head Cover has been added.
Attached file Reference Drawing Plate 39619 R0003.
33. Plan Reference Photo Downstream Corbel HLL has been added. Attached file Downstream Corbell HLL R0003.
34. Plan Reference Photo Upstream Corbel HLL has been added. Attached file Upstream Corbell HLL R0003
35. Plan Reference Photo North Bridge Crane Trolley HLL has been added. Attached file North Bridge Crane Trolley Rail HLL R0003
36. Plan Reference Photo South Bridge Crane Trolley HLL has been added. Attached file South Bridge Crane Trolley Rail HLL.
37. Plan Reference Photo B has been added. Attached file Photo B R0003
38. Plan Reference Photo C has been added. Attached file Photo C R0003
39. Plan Reference Photo D has been added. Attached file Photo D R0003
40. Plan Reference Photo E has been added. Attached file Photo E R0003
41. Plan Reference Photo G has been added. Attached file Photo G R0003
42. Plan Reference Photo I has been added. Attached file Photo I R0003
43. Plan Reference Photo J has been added. Attached file Photo J R0003
44. The attached revised sections are to be replaced in their entirety. All portions of the revised sections shall apply whether or not changes have been indicated.
45. IMPORTANT NOTICE: Bidders must acknowledge receipt of this amendment by numbers and date on offer.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 13-Sep-2024 02:00 PM to 11-Oct-2024 02:00 PM.
The following have been modified:
PRICE SCHEDULE
SECTION 00 10 00
PRICE SCHEDULE
Allbeni Falls Dam (AFD) Powerhouse Bridge Crane Rehab
CLIN DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT
Base Bid Items
0001 Crane Rehabilitation Engineering and Design Effort 1 JOB $__________ $__________
0002 Mobilization and Demobilization 1 JOB $__________ $__________
0003 Electrical Rehabilitation 1 JOB $__________ $__________
0004 Mechanical & Structural Rehabilitation 1 JOB $__________ $__________
0005 Enlarge the Powerhouse Crane Access Door 1 JOB $__________ $__________
0006 New Crane Runway Conductor 1 JOB $__________ $__________
0007 Performance and Load Testing of the 250 Ton Bridge Crane 1 JOB $__________ $__________
0008 Training 1 JOB $__________ $__________
0009 Spare Parts 1 JOB $__________ $__________
0010 Inspect, Load Test and Certify Below the Hook Lifting Device 1 JOB $__________ $__________
0011 Furnish As-Built Drawings 1 JOB $__________ $50,000.00
0012 Furnish O&M Manuals 1 JOB $__________ $50,000.00
0013 Design Personnel Fall Protection System 1 JOB $__________ $__________
0014 Install Personnel Fall Protection System 1 JOB $__________ $__________
TOTAL AMOUNT FOR BASE ITEMS
CLIN DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT
Optional Items
0015 Repair Below the Hook Devices 300 Inch $__________ $__________
0016 New 250-Ton Lifting Beam 1 JOB $__________ $__________
0017 New Generator Rotor Less Shaft Below the Hook Device 1 JOB $__________ $__________
0018 New Generator Shaft Only Below the Hook Device 1 JOB $__________ $__________
0019 New Intermediate Shaft and Guide Bearing Below the Hook Device 1 JOB $__________ $__________
New Lifting Links and Pins for Runner Shaft Head Cover Below the Hook Device Certify
1 JOB $__________ $__________
0021 New Single Leg (Sling hook/Grab hook)(SSG) Below the Hook Device 1 JOB $__________ $__________
0022 Bridge Truck Open Gear Replacement 1 JOB $__________ $__________
0023 Bridge Truck Shaft for Gears BD and BE 1 JOB $__________ $__________
0024 New Lifting Device for Main Shaft & Inner Hed Cover 1 JOB $__________ $__________
TOTAL AMOUNT FOR OPTIONAL ITEMS
TOTAL OF BASE AND OPTIONAL ITEMS $______________________
Notes:
1. In the event there is a difference between a unit price and the extended total, the unit price will be held to be the intended offer. If the offeror shows only the total price, but fails to enter a unit price, the total divided by the estimated quantity will be held to be the intended unit price.
2. Any price for items indicated above which are unbalanced as to price may be rejected as non-responsive.
An unbalanced bid is one which is based on price significantly less than cost for some work and price which is significantly overstated for other work.
3. 100% Design Projects requirements cannot be altered, changed, or re-designed in any way. No alternate design requirement will be accepted.
4. Award of optional items will be made in Clause 52.217-7 OPTION FOR INCREASED QUANTITY.
5. The dollar amount established in Contract Line Items Nos. 0011 and 0012 shall not be revised by the Offerors.
6. See Section 01 22 00 (Measurement and Payment) for definition of unit pricing.
-- End of Document --
SECTION 00 70 00 - CONDITIONS OF THE CONTRACT
The following have been modified:
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
INDEX OF DRAWINGS
AFD POWERHOUSE BRIDGE CRANE
DRAWING NO. E-52-18-125, DATED 1 DEC 2023o
SHEET
NUMBE
R
PLATE
NUMBER TITLE REVISION
NUMBER
DATE
1 G-001 PROJECT LOCATION AND VICINITY MAP
2 G-002 INDEX TO DRAWINGS 1 9/52024
3 G-101 EXTERIOR STAGING AREA
4 G-102 CONTRACTOR STAGING AND WORK AREAS
5 G-201 BRIDGE CRANE DEMOLITION
R
PLATE
NUMBER TITLE REVISION
NUMBER
DATE
6 G-202 NEW ELECTRICAL EQUIPMENT LAYOUT-INSTALL 1 9/5/2024
7 G-203 BRIDGE CRANE OVERVIEW - INSTALL
8 SD201 POWERHOUSE DOOR MODIFICATION
9 S-101 BRIDGE PLATFORM EXTENSION - INSTALL
10 S-501 CAB - STRUCTURAL
M-101 TROLLEY OVERVIEW--MECHANICAL--
INSTALL
1 9/5/2024
12 M-102 AUXILIARY HOIST COMPONENTS - INSTALL
13 M-103 MAIN HOIST COMPONENTS - INSTALL
14 M-104 BRIDGE DRIVE - INSTALL
15 E-202 NEW CAB DIMENSION AND FIT - INSTALL
16 E-501 NEW CAB OPERATOR CHAIR - INSTALL
17 E-502 NEW RADIO CONTROL - INSTALL
18 E-601 ONE LINE DIAGRAM - INSTALL
REFERENCES
1 E-52-10-1 LOADING DIAGRAMS
2 E-52-18-1_1 GENERAL INDEX
3 E-52-18-1_101 LOADING DIAGRAMS 1 9/5/2024
4 E-52-18-2_1 ARRANGEMENT – TRANSVERSE SECTIONS
5 E-52-18-2_2 ARRANGEMENT–LONGITUDINAL SECTIONS
6 E-52-18-2_3 ARRANGEMENT –GENERAL PLAN
E-52-18-2_4 ARRANGEMENT – SUPERSTRUCTURE PLAN
AND MISC SECTIONS
8 E-52-18-2_5 ARRANGEMENT–PLAN–GENERATOR FLOOR
9 E-52-18-2_6 PLAN TURBINE FLOOR
10 E-52-18-2_7 PLAN DISTRIBUTORS EL 20230
11 E-52-18-2_8 PLAN THRU ACCESS GALLERY
E-52-18-3_44 CONCRETE OUTLINE ASSEMBLY BAY
MONOLITH – UPSTREAM PLAN AT EL. 2097
E-52-18-3_45 CONCRETE OUTLINE ASSEMBLY BAY
MONOLITH – UPSTREAM PLAN AT EL. 2060
E-52-18-3_46 CONCRETE OUTLINE ASSEMBLY BAY
MONOLITH – UPSTREAM SECTIONS
R
PLATE
NUMBER TITLE REVISION
NUMBER
DATE
E-52-18-3_47 CONCRETE OUTLINE ASSEMBLY BAY
MONOLITH – DOWNSTREAM PLAN AT EL. 2060
E-52-18-3_48 CONCRETE OUTLINE ASSEMBLY BAY
MONOLITH – DOWNSTREAM PLAN AT EL. 2042
AND 2047
E-52-18-3_49 ASSEMBLY BAY MONOLITH - DOWNSTREAM
- PLAN AT EL. 203
E-52-18-3_50 ASSEMBLY BAY MONOLITH - DOWNSTREAM
LONGITUDINAL SECTION AND DETAILS
E-52-18-3_51 ASSEMBLY BAY MONOLITH - DOWNSTREAM
LONGITUDINAL SECTIONS
E-52-18-3_52 ASSEMBLY BAY MONOLITH - DOWNSTREAM
TRANSVERSE SECTIONS
E-52-18-3_53 ASSEMBLY BAY MONOLITH - DOWNSTREAM
TRANSVERSE SECTION
E-52-18-3_56 CONCRETE OUTLINE SUPERSTRUCTURE ROOF
PLAN AND SECTION
1 9/5/2024
E-52-18-3_57 CONCRETE OUTLINE SUPERSTRUCTURE ROOF
PLAN AND SECTION
1 9/5/2024
E-52-18-3_66 CONCRETE OUTLINE SUPERSTRUCTURE
TRANSVERSE SECTIONS AND DETAILS
1 9/5/2024
E-52-18-4-93 CONCRETE REINFORCEMENT,
SUPERSTRUCTURE WEST END WALL
E-52-18-4-94 CONCRETE REINFORCEMENT,
SUPERSTRUCTURE EAST END WALL
E.52.18.4_99 CONCRETE REINFORCEMENT SUPERSTRUCTURE
DOWNSTREAM WALL CONTROL AND SERVICE
BAY
1 9/5/2024
E.52.18.4_100 CONCRETE REINFORCEMENT SUPERSTRUCTURE
DOWNSTREAM WALL CONTROL AND SERVICE
BAY
1 9/5/2024
E.52.18.4_101 CONCRETE REINFORCEMENT SUPERSTRUCTURE
GENERATOR ROOM UPSTREAM WALL ABOVE
2104.5
1 9/5/2024
E.52.18.4_102 CONCRETE REINFORCEMENT SUPERSTRUCTURE
GENERATOR ROOM UPSTREAM WALL ABOVE
2104.5
1 9/5/2024
E-52-18-5_8 MISCELLANEOUS METAL WORK CRANE ACCESS
LADDERS AND HANDRAIL
1 9/5/2024
E-52-18-5_11 CRANE RAIL AND TRACK LAYOUTS AND
DETAILS
E-52-18-6_1 STRUCTURAL STEEL – SUPERSTRUCTURE
FRAMES
R
PLATE
NUMBER TITLE REVISION
NUMBER
DATE
34 E-52-18-7_1 ROOF AND DECK PLAN 1 9/5/2024
35 E-52-18-7_4 FLOOR PLAN EL 2047 AND EL 2042 1 9/5/2024
E-52-18-7_9 ARCHITECTURAL, ELEVATIONS AND
DETAILS
E-52-18-8_15 MECHANICAL EQUIPMENT – 250 TON BRIDGE
CRANE
E-52-20-2_9 ARRANGEMENT TRANSVERSE SECTION THRU
UNIT NO 2
1 9/5/2024
39 E-52-20-2_11 ARRANGEMENT PLAN GENERATOR FLOOR EL 2060 1 9/5/2024
40 E-52-20-7_2 FLOOR PLANS EL 2095.00 AND EL 2080.00 1 9/5/2024
AFP-10-6-
1H21-60
440V AUCILIARY POWER SINGLE LINE
WIRING DIAGRAM
42 466_1 GENERAL DRAWING
43 466_1A GENERAL DRAWING - TROLLEY
44 466_2A GENERAL ARRANGEMENT – TROLLEY
45 466_2B GENERAL ARRANGEMENT – TROLLEY
46 466_3A MAINT HOIST ASSEMBLY
47 466_3B MAINT HOIST DRUM DETAIL
48 466_4A AUX HOIST ASSEMBLY
49 466_4B AUX HOIST DETAILS
50 466_5A TROLLEY DRIVE ASSEMBLY
51 466_6A GENERAL ARRANGEMENT BRIDGE DRIVE
52 466_6B BRIDGE DRIVE DETAIL
53 466_6C BRIDGE DRIVE DETAILS
54 466_6D BRIDGE DRIVE DETAILS
55 466_9A GENERAL ARRANGEMENT – BRIDGE GIRDER
56 466_9B TYPICAL DETAILS – BRIDGE GIRDER
57 466_10A GENERAL ARRANGEMENT – LIFTING BEAM
58 466_10B MAIN BLOCK ASSEMBLY
59 466_10C LIFTING BEAM DETAILS
60 466_10D 20 TON BLOCK ASSEMBLY
61 466_11R ELECTRICAL DIAGRAM
62 466_12A TROLLEY AND BRIDGE BUMPER ASSEMBLY
63 466_12B TROLLEY AND BRIDGE BUMPER DETAILS
R
PLATE
NUMBER TITLE REVISION
NUMBER
DATE
466_13A GENERAL ARRANGEMENT – SIDE CONTACT
COLLECTOR 250 AMP
65 466_13C MISCELLANEOUS
66 466_S1R STRESS ANALYSIS
67 1001_1D3 CONNECTION FOR HOIST
1001_2D3 CONNECTIONS FOR TROLLEY CONTROL
PANEL
69 1001_3D3 CONNECTIONS FOR BRIDGE CONTROLLER
70 1001_4D4 ELEMENTARY DIAGRAM
71 T5138771 HANDLING OF GENERATOR PARTS
72 T5138774 WEIGHTS AND DIMENSIONS
73 162D885 LIFTING DEVICE – GEN SHAFT ONLY
74 182C367 LIFTING DEVICE – GEN ROTOR LESS SHAFT
39618 DETAILS OF LIFTING LINKS AND PINS FOR
RUNNER SHAFT HEAD COVER ETC
39619 LIFTING DEVICE FOR MAIN SHAFT & INNER HEAD
COVER
38986
ARRANGEMENT AND DETAILS LIFTING
DEVICE INTERMEDIATE SHAFT AND GUIDE
BEARING
9/5/2024
AFD-24-RE POWERHOUSE BRIDGE CRANE ACCESS
HATCH
1 8/12/2024
79 - ACCESS HATCH 1.pdf 1 8/12/2024
80 - ACCESS HATCH 2.pdf 1 8/12/2024
81 - ACCESS HATCH 3.pdf 1 8/12/2024
82 - ACCESS HATCH 4.pdf 1 8/12/2024
83 - DOWNSTREAM CORBEL HLL.pdf 1 9/5/2024
84 - UPSTREAM CORBEL HLL.pdf 1 9/5/2024
85 - NORTH BRIDGE CRANE TROLLEY RAIL HLL.pdf 1 9/5/2024
86 - SOUTH BRIDGE CRANE TROLLEY RAIL HLL.pdf 1 9/5/2024
87 - PHOTO B 1 9/5/2024
88 - PHOTO C 1 9/5/2024
89 - PHOTO D 1 9/5/2024
90 - PHOTO E 1 9/5/2024
91 - PHOTO G 1 9/5/2024
R
PLATE
NUMBER TITLE REVISION
NUMBER
DATE
92 - PHOTO I 1 9/5/2024
93 - PHOTO J 1 9/5/2024
(End of clause)
(End of Summary of Changes)
| TOTAL OF BASE AND OPTIONAL ITEMS $______________________ |
| Notes: |
| INDEX OF DRAWINGS |
| AFD POWERHOUSE BRIDGE CRANE |
| DRAWING NO. E-52-18-125, DATED 1 DEC 2023o |
File details come from the government source that posted it. Updated .