W912DS19B0008-Amendment_00004.pdf

PDF 2 MB Posted

Attached to
Renovation and Modernization of Bradley Barracks, West Point, New York
Solicitation number
W912DS19B0008
Issued by

About this file

Amendment 0004

View the file

Other files

File Type Posted
Bid_Abstract.pdf PDF
W912DS19B0008-0009.pdf PDF
Amendment_0008.pdf PDF
Amendment_0008_28_50_00_Emergency_Radio_Communicaiton_Enhanced_System.pdf PDF
Amendment_0007_Q22_RFI_8134159.pdf PDF
Amendment_0007.pdf PDF
Amendment_0007_Q8_Geotechnical_Report_Bradley_Barracks.pdf PDF
Amendment_0007_Q21_Tube_Bundle_Sizing_Form.pdf PDF
Amendment_0007_Q16_corian_lav_810p_RFI_8137732.pdf PDF
Amendment_0006.pdf PDF
Amendment_0005.pdf PDF
Site_Visit_Sign_In_Sheet.pdf PDF
Specs_Book_1_of_4_v1.pdf PDF
Specs_Book_4_of_4_v1.pdf PDF
Specs_Book_2_of_4_v1.pdf PDF
Specs_Book_3_of_4_v1.pdf PDF
Amendment_0003.pdf PDF
Amendment_0001.pdf PDF
Amendment_0002.pdf PDF
W912DS-19-B-0008_Solicitation.pdf PDF
W912DS-19-B-0008_Specs_Book_4_of_4.pdf PDF
W912DS-19-B-0008_Specs_Book_3_of_4.pdf PDF
W912DS-19-B-0008_Drawings_-_Volume_4_of_5.pdf PDF
W912DS-19-B-0008_Drawings_-_Volume_5_of_5.pdf PDF
W912DS-19-B-0008_Specs_Book_1_of_4.pdf PDF
W912DS-19-B-0008_Drawings_-_Volume_3_of_5.pdf PDF
W912DS-19-B-0008_Specs_Book_2_of_4.pdf PDF
W912DS-19-B-0008_Drawings_-_Volume_1_of_5_v1.pdf PDF
W912DS-19-B-0008_Drawings_-_Volume_2_of_5.pdf PDF
Bradley_Barracks_West_Point_Security_Manifest.xlsx XLSX spreadsheet
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

Bid opening date is hereby extended to 27 August 2019 at 2:00 P.M. EST

Ans er questions for Informational purposes onl

NOTE: Bidders must acknow ledge receipt of this amendment by date specified in the bid (or as amended) by one of the follow ing methods: In the space provided on the SF 1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENT BY DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE

MODIFICATION OF BID, OR LATE WITHDRAWAL OF BID (FAR 14.304)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 09-Aug-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS19B0008

X 9B. DATED (SEE ITEM 11)

12-Jul-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

09-Aug-2019

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS19B0008

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

(End of Summary of Changes)

Bradley Barracks, West Point

W912DS-19-B-0008

Amendment 0004

(Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors "for information only" and do not revise the solicitation, plans or specifications.)

Question 1: In response to the above referenced project, Metal Sales Manufacturing Corporation

(MSMC) is submitting its substitution for the Concealed Fastened Smooth Finish Metal Wall Panels with two stiffening ribs, as instructed in the specification.

Attached for your review and consideration is MSMC's proposed Soffit/Wall Metal Panel System with 2

V‐Grooves identified in the CSI 1.5C Substitution Request Form, along with MSMC's Condensed

Technical Reference guide and Warranty information.

Answer 1: 1. Substitution must be a "SHPO" approved metal panel to match other recently installed roof screens on historically designated West Point buildings. See attached basis of design single "V" groove smooth panel with factory applied finish and concealed fasteners. See BOD attached:

a. (CENTRIA IW Series Wall System: IW-14A).

Question 2: Please advise if existing elevators can be utilized for construction personnel and materials.

Answer 2: Confirmed for use with the existing elevators only. New elevators cannot utilized for construction personnel and materials.

Question 3:

1.) Drawing CG-101 SHEET KEYNOTES 2 indicates inlet protection. There are many existing catch basin structures indicated on the drawing however, only a few are tagged with key note 2. Please advise is all or only the flagged catch basin structures require in let protection.

2.) Drawing CG-101 SHEET KEYNOTES 1 indicates convert MH Frame and cover to open grate. Please advise the quantity.

Answer 3: 1. The manholes/inlets requiring protection will be structures labeled as open grates, labeled with a keynote, or showing an inlet protection symbol over them. Drainage manholes DMH 143I29A and DMH 1445J29A are being converted from solid cover to open grate and will also need inlet protection once converted. Also refer to General Note #8 and #9 on sheet C-001 of the contract drawings.

2. There are two structures, DMH 143I29A and DMH 1445J29A, that will require a conversion to an open grate.

Question 4: Please confirm that the courtyard area enclosed within the contract limit lines per contract dcouments can/will be utilized for construction lay down area, staging, trailer(s) location etc..

Answer 4: Safe Cadet egress and emergency vehicle access shall be provided throughout the duration of the project. The contracting laydown/staging area can be located within the fenced areas dependent on the Phase as shown on the contract drawings. Keynotes 14 and 20 on sheet CS- 101 of the contract drawings indicates the phasing for the temporary construction fence.

Coordinate with the Contracting Officer throughout the duration of the project if additional area is required. General Note #3 on sheet C-001 of the contract drawings identifies the requirement for a phasing plan/sequence of construction prior to construction.

Question 5: The specified A.O. Smith Model HWGV-1100A-EDS-1042 steam to water domestic heaters specified does not come with 1100 gallon storage but rather 1000 gallon. Is this acceptable or is there an alternative heater that should be provided instead? Please advise.

Answer 5: The A/E of Record has spoken with the A.O.Smith manufacturer representative and they have informed us that the 1100 gallon storage tank can be custom made to the contract specifications. The contractor will have to provide to A.O.Smith what specification is needed for the storage tank on the project. All other components provided with the storage tank will stay the same as the contract documents specifies.

Question 6: 1.) Please provide photographs for all of the fixtures noted to be restored and refurbished.

2.)The drawings indicate the use of controlled receptacles in the Collaboration Rooms. Please provide a detail as to what is controlling these receptacles.

3.) Spec section 26 20 00 3.1.3 Wiring methods does not list MC Cable as an acceptable method of wiring. Past Barracks projects have utilized MC Cable in dry hollow partitions and above hung ceilings.

Please advise if MC Cable can be utilized as a wiring method for this project.

Answer 6: 1. Attached are photographs of the fixtures to be refurbished, Contactor is responsible for visiting in the site and confirming all existing conditions.

2. Receptacles are controlled by room occupancy sensors. Refer to Interior lighting control schedule on Drawing EL-601.

3. Wiring methods shall be as specified in Section 262000. MC cable is not acceptable.

Question 7: Please confirm that each and all existing column must be reinforced per detail 1/S302 with sections A/S-302 & B/S-302.

Answer 7: No, the proposed locations of the shear capitals are shown in both overall and partial plans. Capitals are likely to only occur below (thus supporting) the fifth, sixth, and roof levels.

Capitals are shown with a dashed box and keynoted on each overall and partial plan where applicable. Per Concrete Repair Note D. 3. - CONTRACTOR SHALL INCLUDE AS A BASE

QUANTITY OF INDIVIDUAL COLUMN CAPITALS IN THEIR BID... LOCATIONS SHOWN

IN PLAN ARE TO BE VERIFIED BY THE EOR AFTER REMOVAL OF BUILDING FINISHES.

See plans for quantity take-off and estimated locations, although locations are subject to change based on building conditions.

Question 8: Drawing S-002, Concrete Repair Notes, paragraph F, subparagraph 1 refers to installation of 750 CF of self-leveling grout (18,000 SF with an average depth of ½"). We calculated 31,816 SF and 1,325 CF for FIRST floor only which is double for whole building. Please advise.

Answer 8: The self-leveling grout is for structural repairs only and is independent of any other floor leveling, mortar beds, or other cementitious toppings required throughout the construction documents. This quantity of self-leveling grout is to be used in areas with honeycombing or voids, insufficient rebar cover, or to correct limited areas of extreme elevations changes not intended from the original construction. The quantity is accurate for bid purposes and the limited locations needed for application will be determined during construction.

Question 9: Is the contractor required to provide full conduit systems for each CCTV camera back to the head end or are conduit pathways to accessible ceilings for open cable installations acceptable?

Answer 9: Conduit pathways shall be installed from j-box to above nearest accessible corridor ceiling for open cable installation back to nearest telecom room.

Question 10: Window schedule on sheet A-620 states there are (11) type F windows. We have only been able to locate (3) windows (@ game room B010). Please provide locations of the remaining (8) ea type F windows.

Answer 10: There are a total of (11) Type F windows in the project, the (3) in the Game Room in the Basement, (1) in the Janitor's Office (B017) in the Basement and the other (7) are located at the Collab Rooms on each floor, with (2) Collab Rooms on Floor 4.

Question 11: Are there two site visit dates? Aug 5 per Amendment 2 and Aug 1 per Amendment 3?

Answer 11: No, there is only one Site Visit date, Aug 1, 2019. Amendment 0003 revised the site visit date to be Aug 1, 2019.

Question 12: Regarding the historical windows, the specified Peerless 9150 windows have been discontinued. Will the Army Core accept an equal or other alternate to what is called out in the Spec?

Answer 12: A Peerless 9150 (Single-Hung) window or equal is acceptable for this project. The basis of design is the Peerless 9150 (Single-Hung). Which is a window type that was customized for West Point and SHPO approval and used on all previous CBUP barracks renovations.

The product is not listed on the website but is also not discontinued.

This has been confirmed with the Upstate NewYork Peerless Products Sales Representative. Please see below:

"Hi Eric, as we discussed earlier, Peerless IS quoting the Bradley Barracks project.

Peerless will be quoting the same exact window as used in the last 6 Barracks projects at West Point, no exceptions will be taken...

The 9150 Single Hung quotation is being prepared right now, for four requested sub bidders, as specified in the contract documents.

Our standard West Point window material quote for the 9150 SH will be sent out this week, pending any postponement.

Please let me if there is anything more you would need"

Thank you

John Kimball - Upstate NY Sales Peerless Products

Question 13: Is there an existing Fire Alarm Vendor in the building? If so, please provide manufacturers info including phone number for contact.

Answer 13: Per the specifications the existing fire alarm vendor is Monaco.

Question 14: Planting details on LP501 show aged shredded hardwood bark mulch at all plantings. All plantings are located within planters as shown on LP101. Is aged shredded hardwood bark mulch required in the planting beds over the new topsoil?

Answer 14: Shredded hardwood mulch is required to be installed in the planters, across the full planter surface. Shurb Planting, Typical detail, on LP501, "Aged Shredded Hardwood Bark Mulch, 3" Depth Across Entire Planter". Mulch is required to maintain moisture in the topsoil and minimize weed germination.

Question 15: Please provide the anticipated award date.

Answer 15: Anticipated award date is on or before 30-Sept-2019.

Question 16: We kindly request a two (2) week bid extension. Due to the size and complexity of the project, unanswered RFI's and in anticipation of future Amendments, we feel there is not adequate time to prepare accurate and competitive price proposals. We feel it would be in the owners best interest to grant a (2) week bid extension.

Answer 16: Amendment 0004 will extend the bid due date to 27-AUG-2019.

Question 17: Bid Item CLIN 0002 indicates that the CLIN should be for 5,000 LF of structural repair to existing cracks in addition to the base bid of 35,000 LS. Please confirm that the 35,000 LF quantity should be included in the base bid under CLIN 0001 and CLIN 0002 should only be for 5000 LF.

Answer 17: No, the base bid includes 30,000 LF of gravity and injection epoxy repairs. Both CLIN 0002 and CLIN 0003 are options for an additional 5,000 LF of gravity and injection epoxy repairs on top of the base bid. Both of CLIN 0002 and CLIN 0003 are for only 5,000 LF of repairs.

Question 18: Bid item CLIN 0003 indicates that the CLIN should be for 5,000 LF do structural repair to existing cracks in addition to the base bid of 40,000 LF. Please confirm that the 40,000 LF quantity should be included in the base bid under CLIN 0001 and CLIN 0003 should only be for 5,000 LF. In addition please further explain the difference between CLN 0002 and CLIN 0003.

Answer 18: No, the base bid includes 30,000 LF of gravity and injection epoxy repairs. Both CLIN 0002 and CLIN 0003 are options for an additional 5,000 LF of gravity and injection epoxy repairs on top of the base bid. Both of CLIN 0002 and CLIN 0003 are for only 5,000 LF of repairs.

Question 19: Bid item CLIN 0004 indicates that the CLIN should be for 750SF of structural repair to spoiled surfaces in addition to the base bid of 4,750 SF. Please confirm that the 4,750 SF quantity should be included in the base bid under CLIN 0001 and CLIN 0004 should only be for 750 SF.

Answer 19: No, the base bid includes 4,000 SF of spalled surface repairs. Both CLIN 0004 and CLIN 0005 are options for an additional 750 SF of spalled surface repairs on top of the base bid.

Both of CLIN 0004 and CLIN 0005 are for only 750 SF of repairs.

Question 20: Bid item CLIN 0005 indicates that the CLIN should be for 750 SF of structural repair to spailed surfaces in addition to the base bid of 5,500 SF. Please confirm that the 5,500 SF quantity should be included in the base bid under CLIN 0001 and CLIN 0005 should only be for 750 SF. In addition please further explain the difference between CLIN 0004 and CLIN 0005.

Answer 20: No, the base bid includes 4,000 SF of spalled surface repairs. Both CLIN 0004 and CLIN 0005 are options for an additional 750 SF of spalled surface repairs on top of the base bid.

Both of CLIN 0004 and CLIN 0005 are for only 750 SF of repairs.

Question 21: Bid item CLIN 0006 indicates that the CLIN should be for 5,000 SF of structural repair to flexural repairs in addition to the base bid of 25,000 SF. Please confirm that the 25,000 SF quantity should be included in the base bid under CLIN 0001 and CLIN 0006 should only be for 5,000 SF.

Answer 21: No, the base bid includes 20,000 SF of bi-directional and uni-directional FRP repairs.

Both CLIN 0006 and CLIN 0007 are options for an additional 5,000 SF of FRP repairs on top of the base bid. Both of CLIN 0006 and CLIN 0007 are for only 5,000 SF of repairs.

Question 22: Bid item CLIN 0007 indicates that the CLIN should be for 5,000 SF of structural repair to the flexural repairs in addition to the base bid of30,000 SF. Please confirm that the 30,000 SF quantity should be included I in the base bid under CLIN 0001 and CLIN 0007 should only be for 5,000 SF.

Please further explain the difference between CLIN 0006 and 0007.

Answer 22: No, the base bid includes 20,000 SF of bi-directional and uni-directional FRP repairs.

Both CLIN 0006 and CLIN 0007 are options for an additional 5,000 SF of FRP repairs on top of the base bid. Both of CLIN 0006 and CLIN 0007 are for only 5,000 SF of repairs.

Question 23: Please extend the bid date past the Labor Day weekend, we are getting a lot of resistance from the subcontractors dust to the summer holidays and we want to make sure the Government receives competitive bids.

Answer 23: Amendment 0004 will extend the bid due date to 27-AUG-2019.

Question 24: Please extend the RFI due date.

Answer 24: The RFI due date has been extended to 14-Aug-2019.

Amendment 0004
Amendment 0004_Bidder QA