Appendix_EE_-_HVAC_Design_Narrative_ _Analysis.pdf

PDF 874 KB Posted

Attached to
Renovate Dormitory, Building 97, Thule Air Base, Greenland
Solicitation number
W912DS-14-R-0009
Issued by

About this file

Appendix EE

View the file

Other files

File Type Posted
Appendix_A_-_Active_Landfills.pdf PDF
Appendix_HH_-_Fuel_Pricing_and_DLA_Information.pdf PDF
Appendix_D_-_HWM_Plan.pdf PDF
Appendix_U_-_DBA_Waiver.pdf PDF
Appendix_T_-_FY14_-_FY17_Sealift_Rates.pdf PDF
Appendix_F_-_PPM_Plan.pdf PDF
Appendix_BB_-_Seismic_Eval_of_Exisit_Building_97_Struct.pdf PDF
Appendix_L_-_Affirmative_Proc_Plan.pdf PDF
Appendix_B_-_NFS_Material_Borrow_Site.pdf PDF
Appendix_E_-_Spill_Prevention-Response_Plan.pdf PDF
Appendix_Q_-_Shipping_Rates_Gov_Furnished_Transport.pdf PDF
Appendix_AA_-_Prelim_Code_Analysis.pdf PDF
W912DS-14-R-0009_Amendment-0002.pdf PDF
Appendix_J_-_Installation_HAZMAT_Management_Plan.pdf PDF
Appendix_FF_-_DD_Form_1391_Redacted.pdf PDF
Appendix_N_-_Asbestos_Management_Plan.pdf PDF
Appendix_DD_-_Product_Data_Sheets.pdf PDF
Appendix_P_-_Dormitory_(Unaccopanied_Housing)_Design_Guide.pdf PDF
Appendix_G_-_Solid_Waste_Mgmt_Plan.pdf PDF
Appendix_X_-_Exist_Site_Utilities_Plans.pdf PDF
Appendix_W_-_Exist_Bldg_97_Photos.pdf PDF
Appendix_K_-_FGS-GL_(Environmental_Protection).pdf PDF
Appendix_M_-_PCB_Replacement_Plan.pdf PDF
Appendix_CC_-_Drawings.pdf PDF
Appendix_H_-_Storm_Water_Mgmt_Plan.pdf PDF
Appendix_C_-_Conservation_Mgmt_Plan.pdf PDF
Appendix_I_-_Slug_Mgmt_Plan.pdf PDF
Appendix_S_-_Pacer_Goose_Shipping_Instructions.pdf PDF
Appendix_V_-_Facilities_Excellence_Plan_(Sept_2012).pdf PDF
Appendix_O_-_Lead_Paint_Management_Plan.pdf PDF
Technical_Provisions_Div._01 _General_Requirements__7-23-2014.pdf PDF
Appendix_R_-_FY13_Dormitory_Permafrost_ _Geotechnical_Investigation.pdf PDF
Appendix_GG_-_CID_24_July_14.pdf PDF
W912DS-14-R-0009-0001.pdf PDF
W912DS-14-R-0009_-_Phase-1_RFP.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HVAC SYSTEM NARRATIVE

A. Existing System

This system description is based on a review of the drawings for this building dated 15 July 1958. The primary heat source for Thule Air Base (TAB) is a central steam boiler plant located in Building 341 and 241 at the center of the base. JP-8 fuel is used to produce high pressure steam at approximately 5.2 bar (75psi). Steam is then distributed via above ground piping throughout the base to preserve the integrity of the permafrost.

A three inch high pressure (100 psi) steam line enters the First Floor Mechanical Room.

This is converted to low pressure steam at a pressure reducing station in the First Floor Mechanical Room. Low pressure steam is then provided to Heating and Ventilating Units on the First, Second, and Third Floor Mechanical Rooms. These units are rated approximately 2000 cfm. Each unit is equipped with an intake louver protected by a hood. Within each unit are two preheat coils, a reheat coil, and a humidifier. Steam condensate is collected in a condensate receiver on the First Floor and returned to the central steam boiler plant.

The Heating and Ventilating Units supply ventilation air to each dormitory unit using ductwork which is routed through cavities in the perimeter wall. Supply registers are located in this perimeter wall. Air supplied to the units is transferred to the corridor and re-enters the Mechanical Rooms via transfer grills from the Mechanical Rooms to the Corridors.

Exhaust air is collected within existing Rest Rooms and rises up shafts to two fan rooms on the third floor. Exhaust fans in these rooms discharge via roof ventilation monitors.

All existing piping, ductwork, and equipment in the building will be demolished as part of this project. Base steam and condensate will be demolished on site as far back needed to accommodate the new system.

Currently there are existing controls in the first floor mechanical room of building 97 that monitor the heat tracing of outside utilities (four sewage lines and one potable water line).

They were placed in the mechanical room due to the lack of space in the nearby utility shed #7018. These controls will be salvaged and returned to the government for future reuse and relocation.

B. Proposed HVAC System

The proposed system for the renovation of Building 97 is based on both the systems used in the “FY 13 Dormitory Project 100% submission documents dated November 5, 2012 and distribution pathways from the original drawings for Building 97 dated 15 July 1958.

SKM1,2, and 3, attached, show some features of this system.

As is appropriate for the climatic zone the building will be heated and ventilated but will not have cooling systems.

A 3” high pressure (448 kpa/65 psi) steam line and 3/4”condensate line currently serve the building. Calculations indicate that these lines have capacity to meet the loads of the

Building 97 renovation. Currently there are plans to replace high temperature steam lines with high temperature hot water lines. That project will not be completed soon enough for this project to be based on distribution of high temperature hot water.

Four steam to liquid flooded vertical heat exchangers will be provided in the new system.

One pair will provide heating hot water for room radiators. The second pair will provide 60% glycol/40% water heating fluid for Crawl Space Radiators, and for primary and defrost heating coils in heat recovery air handling units. Each heat exchanger of the pair will be sized at 100% capacity. One will be “duty” and the other will be the “standby” to provide

100% redundancy. The Design Build contractor’s design will include a provision of space so that in the future the steam based heat exchangers can be replaced with heat exchangers based on high temperature hot water.

A pair of circulating pumps will be provided associated with both hydronic loops. Each loop will have two pumps, each sized at 100% capacity. One will be the “duty and the other will be the “standby” to provide 100% redundancy. Associated with each hydronic loop are additional required components, including, but not limited to, air separators, expansion tanks, and control valves.

The heat exchangers, circulating pumps, and associated equipment may be located in either of two locations. Equipment may be in an Exterior Containerized Mechanical room or in

Interior Mechanical Rooms

a. Exterior Containerized System. Bid Option. All equipment needed to receive base steam, convert the heat energy to both hydronic loops, associated pumps, expansion tanks, control valves and DDC control system shall be built at a single location inside a standard size insulated shipping container, witness tested with government personnel as an assembly at the location of manufacture. The Exterior Containerized system shall be shipped to site, and installed adjacent to Building 97 in accordance with requirements for Exterior Mounted Equipment.

System function shall be tested again at site as part of normal construction testing and acceptance.

b. Interior Mechanical Room. Base Bid. All equipment needed to receive base steam, convert the heat energy to both hydronic loops, associated pumps, expansion tanks, control valves and DDC control system shall be built at Building 97 First Floor Mechanical Room. Testing shall be performed on site in Thule as part of the construction project.

Hydronic Radiators. There will be two types of hydronic radiators; Crawl space Radiators and Room Radiators. Crawl space radiators will be located in the Crawl Space below the first floor. They will be fed from the glycol/water hydronic loop. The purpose of these radiators is to keep plumbing and HVAC lines in the Crawl Space from freezing. Room

Radiators will be located in occupied spaces for comfort heating.

Ventilation air will be provided by energy recovery heating and ventilating units located within each floor’s mechanical room. The air intake and exhaust for the air handling unit will incorporate “arctic type outdoor hoods” and motorized air dampers to prevent entrainment of snow due to snow drift and negative system effects caused by high winds. There will be no roof penetrations as requested by Greenland Contractors (facility operators).

Dedicated Outdoor Air Ventilation Systems are to be sized to meet both the ventilation and pressurization requirements of the building, and provide tempered, filtered outdoor air to the occupied spaces, typically ducted directly to the occupied spaces.

Dedicated Outside Air Ventilation Unit with energy Recovery will include:

a. Supply fan with motor and variable frequency drive

b. Exhaust fan with motor and variable frequency drive

c. Energy recovery wheel for sensible and latent heat recovery.

d. Primary heating coil with 60% propylene glycol, 40% water heating fluid

e. Defrost coil with 60% propylene glycol, 40% water heating fluid

f. Dedicated unit DDC control panel with full communication with building DDC system.

g. Insulated R13 double wall casing

h. Casing window panels for inspection at each section.

i. Supply air acoustic silencer

j. Exhaust air acoustic silencer

k. MERV 8 exhaust filter

l. MERV 13 supply air filter with MERV 8 prefilter

Units shall have a fixed amount of exhaust air from bathrooms. They will have a variable amount of supply air for makeup of bathroom exhaust, kitchen exhaust, and dryer exhaust.

The supply air quantity will be raised depending on the number of kitchen and dryer exhaust fans which are operating. This shall not be done by measuring building pressure or using a sail switch. It shall be accomplished by positive signal by reading if the appliances are actually running (exhausting). Multiple units may be grouped together to receive a common signal if it is determined to facilitate easier controls/ operations.

BUILDING HVAC CONTROLS AND AUTOMATION

The basis of design will be Trend Control Systems Ltd. Trend provides the base wide

Energy Management and Control System (EMCS) at Thule Airbase.

A new BACnet-based Building Automation System (BAS) will be provided to control and monitor the mechanical equipment in the renovated Building 97. The new building control system will be an addition to the existing Trend Company Energy Management and Control

System (EMCS) currently installed at the Thule AFB. The new BAS will be a complete system provided with all the necessary hardware, software, and control devices. The BAS network will include controllers on the supervisory level and the unitary level. The BAS system will use BACnet-based controllers residing on a combination BACnet/IP network and

BACnet/MSTP platform. All input/output devices will communicate using the protocols and network standards as defined by ANSI/ASHRAE Standard 135-2004, BACnet.

The steam heat exchanger system will be provided with a dedicated control system. The controls associated with the new packaged redundant heat exchanger system including controller, control devices and BACnet interface will be provided by the packaged redundant heat exchanger system manufacturer. The system will communicate with the existing BAS system via a BACnet/MSTP over IP network interface for remote control and monitoring.

The air to air energy recovery ventilation unit will be controlled by a dedicated control system which is fully compatible with the base EMCS system.

Each room’s hot water radiators will be controlled by a non-electric thermostatic valve mounted on the unit, not through the BAS. The thermostat will modulate the hot water valve to maintain space temperature set point.

Domestic hot and cold water meters will be provided with BACnet communication interfaces to the BAS to allow remote reading, data storage, and trend logging. All meter information will be stored at the Supervisory Server for reporting, trend logging, archiving, and report printing.

The supply and exhaust air streams shall be provided with the following BACnet control points at a minimum: supply air intake outdoor air temperature and pressure, supply discharge air temperature and pressure, intake and exhaust air temperature at the heat-wheel, exhaust air inlet temperature and pressure, exhaust air temperature and pressure discharge before and after the defrost coil. There will also be a high limit and low limit pressure transmitter with alarm safety and shut-down for ductwork pressure safety protection at supply and exhaust duct main or fan.

Energy meters for space heating and energy meters for domestic hot water shall be provided. Each energy consumption component shall be a separate and distinct meter for data gathering purposes.

At the end of installation, functional testing, and system commissioning, the contractor will provide training to Thule base personnel on all aspects of the newly installed system, including, hardware and software.

Design Weather Parameters & MSHGs Thule - Bldg 97 06/13/2014 Jacobs Engineering 08:29AM

Hourly Analysis Program v4.61 Page 1 of 1

Design Parameters:

City Name .............................................................................................................. Thule Location ......................................................................................................... Greenland Latitude ..................................................................................................................... 76.5 Deg.

Longitude ................................................................................................................. -68.8 Deg.

Elevation ................................................................................................................. 194.0 ft Summer Design Dry-Bulb ......................................................................................... 52.0 °F Summer Coincident Wet-Bulb .................................................................................. 44.1 °F Summer Daily Range ................................................................................................. 8.4 °F Winter Design Dry-Bulb ........................................................................................... -31.0 °F Winter Design Wet-Bulb .......................................................................................... -31.0 °F Atmospheric Clearness Number ............................................................................... 1.00 Average Ground Reflectance ................................................................................... 0.20 Soil Conductivity ..................................................................................................... 0.800 BTU/(hr-ft-°F) Local Time Zone (GMT +/- N hours) .......................................................................... -1.0 hours Consider Daylight Savings Time ................................................................................ No Simulation Weather Data ...................................................................... BARROW (EXT) Current Data is ........................................................................................ User Modified Design Cooling Months .............................................................. January to December

Design Day Maximum Solar Heat Gains

(The MSHG values are expressed in BTU/(hr-ft²) )

Month N NNE NE ENE E ESE SE SSE S January 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 February 0.5 0.5 0.5 0.5 1.7 6.5 12.5 16.1 17.1 March 9.8 9.8 21.9 57.6 100.7 134.5 162.5 179.7 185.2 April 26.1 62.3 105.6 144.0 174.5 197.3 210.6 218.6 221.4 May 87.7 122.9 156.8 184.7 204.3 215.5 219.6 218.8 220.8 June 114.7 141.7 170.5 193.3 208.4 215.8 216.8 214.9 215.9 July 87.8 121.6 154.3 181.3 200.2 210.8 214.1 215.5 216.4 August 25.8 59.9 101.0 138.2 167.8 189.2 202.9 210.4 212.9 September 10.3 10.3 16.1 51.4 88.0 119.2 147.5 163.2 167.9 October 0.6 0.6 0.6 0.6 1.7 7.2 11.4 14.5 16.2 November 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 December 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Month SSW SW WSW W WNW NW NNW HOR Mult January 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.00 February 15.6 11.5 6.4 1.8 0.5 0.5 0.5 1.0 1.00 March 179.9 163.2 133.4 100.5 58.9 20.8 9.8 35.6 1.00 April 219.6 212.4 198.6 176.4 144.9 104.7 60.1 95.2 1.00 May 220.7 217.9 214.5 203.8 184.3 156.3 122.3 136.7 1.00 June 215.7 216.0 215.6 208.6 193.8 171.1 142.5 151.3 1.00 July 215.3 214.3 210.9 200.3 181.4 154.4 121.6 137.5 1.00 August 210.8 203.5 189.9 168.5 138.5 100.7 58.8 96.6 1.00 September 161.6 145.7 121.7 87.4 49.6 19.4 10.3 34.4 1.00 October 15.6 12.5 7.2 1.6 0.6 0.6 0.6 1.1 1.00 November 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.00 December 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.00

Mult. = User-defined solar multiplier factor.

Air System Design Load Summary for Bldg 97 Block Load Project Name: Thule - Bldg 97 06/13/2014 Prepared by: Jacobs Engineering 08:57AM

Hourly Analysis Program v4.61 Page 1 of 1

DESIGN COOLING DESIGN HEATING

NO COOLING DATA HEATING DATA AT DES HTG

NO COOLING OA DB / WB HEATING OA DB / WB -31.0 °F / -31.0 °F

Sensible Latent Sensible Latent

ZONE LOADS Details (BTU/hr) (BTU/hr) Details (BTU/hr) (BTU/hr)

Window & Skylight Solar Loads 1260 ft² - - 1260 ft² - -

Wall Transmission 16516 ft² - - 16516 ft² 30127 -

Roof Transmission 10402 ft² - - 10402 ft² 19626 -

Window Transmission 1260 ft² - - 1260 ft² 25956 -

Skylight Transmission 0 ft² - - 0 ft² 0 -

Door Loads 80 ft² - - 80 ft² 659 -

Floor Transmission 10402 ft² - - 10402 ft² 12857 -

Partitions 0 ft² - - 0 ft² 0 -

Ceiling 0 ft² - - 0 ft² 0 -

Overhead Lighting - - - 0 0 -

Task Lighting - - - 0 0 -

Electric Equipment - - - 0 0 -

People - - - 0 0 0

Infiltration - - - - 394483 0

Miscellaneous - - - - 0 0

Safety Factor 0% / 0% - - 20% 96742 0

>> Total Zone Loads - - - - 580449 0

Zone Conditioning - - - - 427891 0

Plenum Wall Load 0% - - 0 0 -

Plenum Roof Load 0% - - 0 0 -

Plenum Lighting Load 0% - - 0 0 -

Return Fan Load - - - 9000 CFM 0 -

Ventilation Load - - - 0 CFM 0 0

Supply Fan Load - - - 9000 CFM 0 -

Space Fan Coil Fans - - - - 0 -

Duct Heat Gain / Loss 0% - - 0% 0 -

>> Total System Loads - - - - 427891 0

Central Heating Coil - - - - 427891 -

Preheat Coil - - - - 0 -

Zone Heating Unit Coils - - - - 0 -

>> Total Conditioning - - - - 427891 0

Key: Positive values are clg loads Positive values are htg loads

Negative values are htg loads Negative values are clg loads

Space Design Load Summary for Bldg 97 1st Fl

Prepared by: Jacobs Engineering 08:37AM

TABLE 1.1.A. COMPONENT LOADS FOR SPACE '' Bldg 97 1st Fl '' IN ZONE '' Zone 1st Fl ''

COOLING DATA AT Jun 1200 HEATING DATA AT DES HTG

COOLING OA DB / WB 47.1 °F / 41.1 °F HEATING OA DB / WB -31.0 °F / -31.0 °F

OCCUPIED T-STAT 99.0 °F OCCUPIED T-STAT 72.0 °F

Sensible Latent Sensible Latent

SPACE LOADS Details (BTU/hr) (BTU/hr) Details (BTU/hr) (BTU/hr)

Window & Skylight Solar Loads 420 ft² 0 - 420 ft² - -

Wall Transmission 5452 ft² 0 - 5452 ft² 9945 -

Roof Transmission 0 ft² 0 - 0 ft² 0 -

Window Transmission 420 ft² 0 - 420 ft² 8652 -

Skylight Transmission 0 ft² 0 - 0 ft² 0 -

Door Loads 80 ft² 0 - 80 ft² 659 -

Floor Transmission 10402 ft² 0 - 10402 ft² 12857 -

Partitions 0 ft² 0 - 0 ft² 0 -

Ceiling 0 ft² 0 - 0 ft² 0 -

Overhead Lighting 0 W 0 - 0 0 -

Task Lighting 0 W 0 - 0 0 -

Electric Equipment 0 W 0 - 0 0 -

People 16 0 0 0 0 0

Infiltration - 0 0 - 131494 0

Miscellaneous - 0 0 - 0 0

Safety Factor 0% / 0% 0 0 0% 0 0

>> Total Zone Loads - 0 0 - 163607 0

TABLE 1.1.B. ENVELOPE LOADS FOR SPACE '' Bldg 97 1st Fl '' IN ZONE '' Zone 1st Fl ''

COOLING COOLING HEATING

Area U-Value Shade TRANS SOLAR TRANS

(ft²) (BTU/(hr-ft²-°F)) Coeff. (BTU/hr) (BTU/hr) (BTU/hr)

NE EXPOSURE

WALL 2152 0.018 - - 3925

WINDOW 1 192 0.200 0.887 3955

SE EXPOSURE

WALL 620 0.018 - 1131

WINDOW 1 12 0.200 0.887 247

SW EXPOSURE

WALL 2100 0.018 - 3831

WINDOW 1 204 0.200 0.887 4202

DOOR 40 0.080 - 330

NW EXPOSURE

WALL 580 0.018 - 1058

WINDOW 1 12 0.200 0.887 247

DOOR 40 0.080 - 330

Space Design Load Summary for Bldg 97 2d Fl

Prepared by: Jacobs Engineering 08:40AM

TABLE 1.1.A. COMPONENT LOADS FOR SPACE '' Bldg 97 2d Fl '' IN ZONE '' Zone 1st Fl ''

COOLING DATA AT Jun 1200 HEATING DATA AT DES HTG

COOLING OA DB / WB 47.1 °F / 41.1 °F HEATING OA DB / WB -31.0 °F / -31.0 °F

OCCUPIED T-STAT 75.0 °F OCCUPIED T-STAT 72.0 °F

Sensible Latent Sensible Latent

SPACE LOADS Details (BTU/hr) (BTU/hr) Details (BTU/hr) (BTU/hr)

Window & Skylight Solar Loads 420 ft² 0 - 420 ft² - -

Wall Transmission 5532 ft² 0 - 5532 ft² 10091 -

Roof Transmission 0 ft² 0 - 0 ft² 0 -

Window Transmission 420 ft² 0 - 420 ft² 8652 -

Skylight Transmission 0 ft² 0 - 0 ft² 0 -

Door Loads 0 ft² 0 - 0 ft² 0 -

Floor Transmission 0 ft² 0 - 0 ft² 0 -

Partitions 0 ft² 0 - 0 ft² 0 -

Ceiling 0 ft² 0 - 0 ft² 0 -

Overhead Lighting 0 W 0 - 0 0 -

Task Lighting 0 W 0 - 0 0 -

Electric Equipment 0 W 0 - 0 0 -

People 16 0 0 0 0 0

Infiltration - 0 0 - 131494 0

Miscellaneous - 0 0 - 0 0

>> Total Zone Loads - 0 0 - 150237 0

TABLE 1.1.B. ENVELOPE LOADS FOR SPACE '' Bldg 97 2d Fl '' IN ZONE '' Zone 1st Fl ''

Area U-Value Shade TRANS SOLAR TRANS

(ft²) (BTU/(hr-ft²-°F)) Coeff. (BTU/hr) (BTU/hr) (BTU/hr)

NE EXPOSURE

WALL 2152 0.018 3925

WINDOW 1 192 0.200 3955

SE EXPOSURE

WALL 620 0.018 1131

WINDOW 1 12 0.200 247

SW EXPOSURE

WALL 2140 0.018 3904

WINDOW 1 204 0.200 4202

NW EXPOSURE

WALL 620 0.018 1131

WINDOW 1 12 0.200 247

Space Design Load Summary for Bldg 97 3d Fl

Prepared by: Jacobs Engineering 08:43AM

TABLE 1.1.A. COMPONENT LOADS FOR SPACE '' Bldg 97 3d Fl '' IN ZONE '' Zone 1st Fl ''

COOLING DATA AT Jun 1200 HEATING DATA AT DES HTG

COOLING OA DB / WB 47.1 °F / 41.1 °F HEATING OA DB / WB -31.0 °F / -31.0 °F

OCCUPIED T-STAT 75.0 °F OCCUPIED T-STAT 72.0 °F

Sensible Latent Sensible Latent

SPACE LOADS Details (BTU/hr) (BTU/hr) Details (BTU/hr) (BTU/hr)

Window & Skylight Solar Loads 420 ft² 0 - 420 ft² - -

Wall Transmission 5532 ft² 0 - 5532 ft² 10091 -

Roof Transmission 10402 ft² 0 - 10402 ft² 19626 -

Window Transmission 420 ft² 0 - 420 ft² 8652 -

Skylight Transmission 0 ft² 0 - 0 ft² 0 -

Door Loads 0 ft² 0 - 0 ft² 0 -

Floor Transmission 0 ft² 0 - 0 ft² 0 -

Partitions 0 ft² 0 - 0 ft² 0 -

Ceiling 0 ft² 0 - 0 ft² 0 -

Overhead Lighting 0 W 0 - 0 0 -

Task Lighting 0 W 0 - 0 0 -

Electric Equipment 0 W 0 - 0 0 -

People 16 0 0 0 0 0

Infiltration - 0 0 - 131494 0

Miscellaneous - 0 0 - 0 0

>> Total Zone Loads - 0 0 - 169863 0

TABLE 1.1.B. ENVELOPE LOADS FOR SPACE '' Bldg 97 3d Fl '' IN ZONE '' Zone 1st Fl ''

Area U-Value Shade TRANS SOLAR TRANS

(ft²) (BTU/(hr-ft²-°F)) Coeff. (BTU/hr) (BTU/hr) (BTU/hr)

NE EXPOSURE

WALL 2152 0.018 - 3925

WINDOW 1 192 0.200 0.887 3955

SE EXPOSURE

WALL 620 0.018 - 1131

WINDOW 1 12 0.200 0.887 247

SW EXPOSURE

WALL 2140 0.018 - 3904

WINDOW 1 204 0.200 0.887 4202

NW EXPOSURE

WALL 620 0.018 - 1131

WINDOW 1 12 0.200 0.887 247

H EXPOSURE

ROOF 10402 0.018 - 19626

Wall Constructions

Jacobs Engineering 09:10AM

Bldg 97 Wall Assembly

Wall Details Outside Surface Color .......................................... Dark Absorptivity .......................................................... 0.900 Overall U-Value ................................................... 0.018 BTU/(hr-ft²-°F)

Wall Layers Details (Inside to Outside)

Thickness Density Specific Ht. R-Value Weight

Layers in lb/ft³ BTU / (lb - °F) (hr-ft²-°F)/BTU lb/ft²

Inside surface resistance 0.000 0.0 0.00 0.68500 0.0

Gypsum board 0.500 50.0 0.26 0.44803 2.1

R-30 insulation 6.000 0.5 0.20 30.00000 0.3

Air space 6.000 0.0 0.00 1.00000 0.0

R-24 insulation 4.000 0.5 0.20 24.00000 0.2

Outside surface resistance 0.000 0.0 0.00 0.33300 0.0

Totals 16.500 - 56.46603 2.5

Floor Constructions

Jacobs Engineering 09:05AM

Bldg 97 Floor Assembly

Floor Details Outside Surface Color .......................................... Dark Absorptivity .......................................................... 0.900 Overall U-Value ................................................... 0.012 BTU/(hr-ft²-°F)

Floor Layers Details (Inside to Outside)

Thickness Density Specific Ht. R-Value Weight

Layers in lb/ft³ BTU / (lb - °F) (hr-ft²-°F)/BTU lb/ft²

Inside surface resistance 0.000 0.0 0.00 0.68500 0.0

8-in LW concrete 8.000 40.0 0.20 6.66667 26.7

R-30 insulation 6.000 0.5 0.20 30.00000 0.3

Air space 6.000 0.0 0.00 1.00000 0.0

R-48 insulation 8.000 0.5 0.20 48.00000 0.3

Outside surface resistance 0.000 0.0 0.00 0.33300 0.0

Totals 28.000 - 86.68467 27.3

Window Constructions

Jacobs Engineering 09:12AM

Building 97 Glass

Window Details:

Detailed Input .......................................................... No Height .................................................................... 4.00 ft Width ..................................................................... 3.00 ft Overall U-Value ................................................... 0.200 BTU/(hr-ft²-°F) Overall Shade Coefficient ................................... 0.887

Roof Constructions

Jacobs Engineering 09:11AM

Building 97 Roof

Roof Details Outside Surface Color ..................................... Medium Absorptivity .......................................................... 0.675 Overall U-Value ................................................... 0.018 BTU/(hr-ft²-°F)

Roof Layers Details (Inside to Outside)

Thickness Density Specific Ht. R-Value Weight

Layers in lb/ft³ BTU / (lb - °F) (hr-ft²-°F)/BTU lb/ft²

Inside surface resistance 0.000 0.0 0.00 0.68500 0.0

R-36 insulation 6.000 0.5 0.20 22.73684 0.3

Air space 24.000 0.0 0.00 1.00000 0.0

Insulated Metal Panel 5.000 0.5 0.20 30.00000 0.2

Outside surface resistance 0.000 0.0 0.00 0.17000 0.0

Totals 35.000 - 54.59184 0.5

Door Constructions

Jacobs Engineering 09:12AM

Bldg 97 Door Assembly

Door Details:

Gross Area ............................................................ 20.0 ft² Door U-Value ...................................................... 0.080 BTU/(hr-ft²-°F)

Glass Details:

Glass Area .............................................................. 0.0 ft² Glass U-Value ..................................................... 0.580 BTU/(hr-ft²-°F) Glass Shade Coefficient ...................................... 0.880 Glass Shaded All Day? ........................................... No

MECH SKETCHES 1 TO 6 JUL 24.pdf
MECH test-02 SKM1 (1).pdf
MECH test-02 SKM2 (1)
MECH test-02 SKM3 (1)
MECH test-02-OLI SKM4 (1)
MECH test-02-OLI SKM5 (1)
MECH test-02-OLI SKM6 (1)
Appendix EE HVAC Thule Loads 2014 0613 revised.pdf
Weather Reports.pdf
Systems Design Report Block Load
Systems Design Report 1st Fl
Systems Design Report2d Fl
Systems Design Report 3d Fl
WALL
Floor
WINDOW
ROOF
DOOR