GENERAL NOTES:
CODED NOTES:
7. SPRINKLER SYSTEMS SHALL BE HYDRAULICALLY CALCULATED. EACH SYSTEM SHALL
BE CALCULATED TO PROVIDE 10 PSI SAFETY FACTOR.
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
1. FOR SYMBOLS, LEGEND AND ABREVIATIONS SEE DRAWING F-001
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
2. EACH FLOOR WILL BE PROVIDED WITH COMBINATION CLASS I FIRE STANDPIPE SYSTEM
AND/OR SPRINKLER CONTROL VALVE ASSEMBLY.
3. OCCUPANCY CLASSIFICATION: LIGHT HAZARD:CLASSROOMS, OFFICE SPACES,
LOBBIES, CORRIDORS, TOILETS, ETC.
4. OCCUPANCY CLASSIFICATION: ORDINARY GROUP I HAZARD: ALL MECHANICAL AREAS,
INCLUDING BOILERS & PLUMBING ROOMS, STORAGE ROOMS, DATA CENTER,
COMMUNICATION & ELECTRICAL ROOMS, JANITOR CLOSET, RESEARCH ROOMS, ETC.
6. SPRINKLER HEAD COVERAGE: MAXIMUM COVERAGE PER SPRINKLER HEAD SHALL BE
BASED ON 225 SQ. FT.FOR LIGHT HAZARD OCCUPANCY AND 130 SQ. FT. FOR ORDINARY
HAZARD.
8. DESIGN SHALL BE BASED ON 3000 SQ. FT.- DESIGN AREA DEDUCTION SHALL BE
PERMITTED PER NFPA-13 FOR THE LIGHT HAZARD OCCUPANCY.
9. SPRINKLER SYSTEM CALCULATIONS SHALL INCLUDE BUILDING DOMESTIC WATER
DEMANDS.
2. ALL SPRINKLER HEADS SHALL BE ORDINARY TEMPERATURE RATING (155 F)
5. PROVIDE CABINET WITH SPARE SPRINKLER HEADS OF EACH TYPE AND TEMPERATURE.
6. ADD 30% OF REMOTE AREA FOR DRY SPRINKLER SYSTEM.
7. EACH BUILDING WILL BE FULLY SPRINKLERED AND PROVIDED WITH FIRE STANDPIPE
SYSTEMS.
8. CONTRACTOR TO PROVIDE UPDATED FLOW TEST PRIOR TO STARTING SYSTEM
DESIGN.
9. PROVIDE AT NO EXTRA COST ALL ADDITIONAL PIPING AND FITTINGS REQUIRED TO
OFFSET SYSTEM TO AVOID STRUCTUTAL, ARCHITECTURAL, MECHANICAL AND
ELECTRICAL INTERFERENCES WHETHER INDICATED OR NOT, BEFORE INSTALLING
WORK.
10. ALL PIPING SHALL RUN CLOSE TO BEAMS, WALLS AND SLABS, CONCEALED ABOVE
HUNG CEILING AND WITHIN FURRED SPACES.
11. THE SPRINKLER SYSTEM IS AN AUTOMATIC WET PIPE TYPE. THE AUTOMATIC WATER
SOURCE IS A FIRE PUMP TAKING SUCTION FROM DIRECT CONNECTION TO THE FIRE
MAIN AND THE AUXILIARY WATER SOURCES ARE 4" STORZ FOR FIRE DEPARTMENT
CONNECTION.
12. CONTRACTOR SHALL COORDINATE ALL WORK INVOLVED IN SPACE CONDITIONS
BEFORE PROCEEDING.
13. INSTALL SPRINKLER HEADS ABOVE AND BELOW DUCTS 4'-0" WIDE AND LARGER.
10. SPRINKLER HEADS LOCATED CLOSE TO THE HEATER, STEAM PIPING OR OTHER HEAT
SOURCE SHALL BE TEMPERATURE RATING AS REQUIRED PER NFPA-13.
3. ALL VALVES IN FIRE PROTECTION SYSTEMS SHALL BE PAINTED RED BY
MANUFACTURER.
4. INSTALL CONTROL VALVES LESS THAN 7'-0"A.F.F., WHERE POSSIBLE. WHERE CONTROL
VALVES ARE INSTALLED AT OR ABOVE 7'-0" A.F.F., INSTALL STEEL LADDER.
COORDINATE REQUIREMENTS OF STEEL LADDER WITH ARCHITECTURAL PLANS AND
SPECS.
11. WEST POINT FIRE PROTECTION SYSTEMS SHALL BE BRACED PER THE SEISMIC ZONE
AND CALCULATIONS SHALL BE SUBMITTED FOR VERIFICATION .
12. INSTALL WIRE CAGE ON SPRINKLER HEADS INSTALLED BELOW 7'-0".
13. TEST FIRE PROTECTION SYSTEMS AS REQUIRED PER NFPA.
14. IN LIGHT HAZARD OCCUPANCY SPRINKLER HEADS SHALL BE QUICK RESPONCE WITH A
K FACTOR OF 5.6.
15. COMPLY WITH THE ARMY CORPS OF ENGINEERING MANUAL EM-385-1-1, SAFETY AND
HEALTH REQUIREMENTS MANUAL AND NFPA-241, SAFEGUARDING CONSTRUCTION,
ALTERATION AND DEMOLITION OPERATIONS AND USMA WEST POINT'S FIRE
REGULATIONS.
5. OCCUPANCY CLASSIFICATION: ORDINARY GROUP II HAZARD: MODERN PHYSICS
WORKROOM, LAB'S, MACHINE & WOOD SHOPS, ETC.
A
B
D
C
E
AF
A6
A7
AG
AH
AJ
AK
A8
A5
AE
AL
AM
AN
A5.4
A4.7
AS
AR
A10
A9
AP
AS.5
A10.8A11.5A12.3
AT
A12 A11
A10.5
69 SF
Space
742 SF
CLASSROOM
B-S03
251 SF
OFFICE
B-S05
55 SF
TOILET
B-S09
469 SF
PLUMBING
B-S08
335 SF
CORRIDOR
B-SC2
71 SF
STOR
B-S04
27 SF
JAN
B-S10
112 SF
STAIR B2
B-SS2
319 SF
CORRIDOR
B-SC1
31 SF
Space
FIRE HOSE
VALVE IN CABINET,
SEE DWG. F-301
FLOOR CONTROL
ASSEMBLY, SEE
F301 FOR DETAIL
6"
4"
4" STORZ FIRE DEPARTMENT
CONNECTION
4" CHECK VALVE WITH
3/4" ABD
1"
6" COMBINED
FSP/SP UP
2" DRAIN
6" COMBINED
FSP/SP DN
FSP
S P
FSP
FOR CONTINUATION SEE DWG F-101E
F O R C O N T
IN
U A T
IO
N S E E D W G F -1 C
FOR CONTINUATION SEE DWG F-101C
F O R C O N T
IN
U A T
IO
N S E E D W G F -1 C
MOST REMOTE AREA OF
HYDRAULIC CALCULATIONS,
ORDINARY HAZARD GROUP I,
3000 SQ. FT., 0.15 DENSITY
NAS
4096 SF
MECHANICAL
B-S01
OH-1
OH-1
OH-1
OH-1
OH-1
L
L
L
L
L
L
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
TS
1" UP
SHEET
REFERENCE
NUMBER
SHEET OF
D E S
IG
N E D B Y
D W N B Y
C H K B Y
S U B M
IT
T E D B Y
D A T E
S O L
IC
IT
A T
IO
N N O
C O N T R A C T N O
F
IL
E N A M E
P L O T T E D B Y
S
IZ
E
P L O T D A T E
D A T E
D E S C R
IP
T
IO
N
M A R K
A P P R
US ARMY CORPS
OF ENGINEERS
NEW YORK DISTRICT
1 2 3 4 5
D
C
B
A
U .S A R M Y E N G
IN
E E R D
IS
T R
IC
T
N E W Y O R K h tt p \w w w .n a n .u s a c e .a rm y .m il a rc h it e c ts e n g in e e rs p la n n e rs
W
E S T N A T
IO
N W
ID
E B L V D
C O L U M B U S O H
IO
.4 .4 f a x .4 .0 h tt p /w w w .u rs c o rp .c o m
S C
IE
N C E C E N T E R
(F Y -B L D G
U N
IT
E D S T A T E S M
IL
IT
A R Y A C A D E M Y
W E S T P O
IN
T N Y
A R C H D
P A R K A V E N U E S O U T H
N E W Y O R K N Y -1
.7 .4 f a x .5 .5 w w w .s tv in c .c o m
W D S -1 -D -0
/1 /2 :1 :3 A M
F-101B
S U B -B A S E M E N T A R E A B
F
IR
E P R O T E C T
IO
N
IR N
J G
L M
A P R
IL
PLAN
NORTH
0 4 8 162
SCALE: 1/8" = 1'-0"
SUB-BASEMENT PLAN-
AREA B FIRE PROTECTION
B1312.7 B12 B11.2 B11 B9.8 B9 B8.2 B8
BU
BT
BS
BR.7
BQ.5
BQ
BP
BN
BM
BR
BR.8
BS.8
BV
B1B7 B6 B5 B4 B3 B2 F O R C O N T
IN
U A T
IO
N S E E D W G F -1 B
FOR CONTINUATION SEE DWG F-101B
S P
S P
CHEM
ENGINEERING
C-S01
FUTURE NMR
C-S03
DATA COMM
C-S05
WRITE UP
C-S02
PLUMBING
C-S06
CORRIDOR
C-SC2
CORRIDOR
C-SC3
OH-2
OH-2
OH-1 OH-1
L
L
LL
4" SPRINKLER
CROSS MAIN
A
B
D
C
E
GENERAL NOTES:
CODED NOTES:
7. SPRINKLER SYSTEMS SHALL BE HYDRAULICALLY CALCULATED. EACH SYSTEM SHALL
BE CALCULATED TO PROVIDE 10 PSI SAFETY FACTOR.
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
1. FOR SYMBOLS, LEGEND AND ABREVIATIONS SEE DRAWING F-001
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
2. EACH FLOOR WILL BE PROVIDED WITH COMBINATION CLASS I FIRE STANDPIPE SYSTEM
AND/OR SPRINKLER CONTROL VALVE ASSEMBLY.
3. OCCUPANCY CLASSIFICATION: LIGHT HAZARD:CLASSROOMS, OFFICE SPACES,
LOBBIES, CORRIDORS, TOILETS, ETC.
4. OCCUPANCY CLASSIFICATION: ORDINARY GROUP I HAZARD: ALL MECHANICAL AREAS,
INCLUDING BOILERS & PLUMBING ROOMS, STORAGE ROOMS, DATA CENTER,
COMMUNICATION & ELECTRICAL ROOMS, JANITOR CLOSET, RESEARCH ROOMS, ETC.
6. SPRINKLER HEAD COVERAGE: MAXIMUM COVERAGE PER SPRINKLER HEAD SHALL BE
BASED ON 225 SQ. FT.FOR LIGHT HAZARD OCCUPANCY AND 130 SQ. FT. FOR ORDINARY
HAZARD.
8. DESIGN SHALL BE BASED ON 3000 SQ. FT.- DESIGN AREA DEDUCTION SHALL BE
PERMITTED PER NFPA-13 FOR THE LIGTH HAZARD OCCUPANCY.
9. SPRINKLER SYSTEM CALCULATIONS SHALL INCLUDE BUILDING DOMESTIC WATER
DEMANDS.
2. ALL SPRINKLER HEADS SHALL BE ORDINARY TEMPERATURE RATING (155 F)
5. PROVIDE CABINET WITH SPARE SPRINKLER HEADS OF EACH TYPE AND TEMPERATURE.
6. ADD 30% OF REMOTE AREA FOR DRY SPRINKLER SYSTEM.
7. EACH BUILDING WILL BE FULLY SPRINKLERED AND PROVIDED WITH FIRE STANDPIPE
SYSTEMS.
8. CONTRACTOR TO PROVIDE UPDATED FLOW TEST PRIOR TO STARTING SYSTEM
DESIGN.
9. PROVIDE AT NO EXTRA COST ALL ADDITIONAL PIPING AND FITTINGS REQUIRED TO
OFFSET SYSTEM TO AVOID STRUCTUTAL, ARCHITECTURAL, MECHANICAL AND
ELECTRICAL INTERFERENCES WHETHER INDICATED OR NOT, BEFORE INSTALLING
WORK.
10. ALL PIPING SHALL RUN CLOSE TO BEAMS, WALLS AND SLABS, CONCEALED ABOVE
HUNG CEILING AND WITHIN FURRED SPACES.
11. THE SPRINKLER SYSTEM IS AN AUTOMATIC WET PIPE TYPE. THE AUTOMATIC WATER
SOURCE IS A FIRE PUMP TAKING SUCTION FROM DIRECT CONNECTION TO THE FIRE
MAIN AND THE AUXILIARY WATER SOURCES ARE 4" STORZ FOR FIRE DEPARTMENT
CONNECTION.
12. CONTRACTOR SHALL COORDINATE ALL WORK INVOLVED IN SPACE CONDITIONS
BEFORE PROCEEDING.
13. INSTALL SPRINKLER HEADS ABOVE AND BELOW DUCTS 4'-0" WIDE AND LARGER.
10. SPRINKLER HEADS LOCATED CLOSE TO THE HEATER, STEAM PIPING OR OTHER HEAT
SOURCE SHALL BE TEMPERATURE RATING AS REQUIRED PER NFPA-13.
3. ALL VALVES IN FIRE PROTECTION SYSTEMS SHALL BE PAINTED RED BY
MANUFACTURER.
4. INSTALL CONTROL VALVES LESS THAN 7'-0" A.F.F, WHERE POSSIBLE. WHERE CONTROL
VALVES ARE INSTALLED AT OR ABOVE 7'-0" A.F.F., INSTALL STEEL LADDER.
COORDINATE REQUIREMNETS OF STEEL LADDER WITH ARCHITECTURAL PLANS AND
SPECS.
11. WEST POINT FIRE PROTECTION SYSTEMS SHALL BE BRACED PER THE SEISMIC ZONE
AND CALCULATIONS SHALL BE SUBMITTED FOR VERIFICATION .
12. INSTALL WIRE CAGE ON SPRINKLER HEADS INSTALLED BELOW 7'-0".
13. TEST FIRE PROTECTION SYSTEMS AS REQUIRED PER NFPA.
14. IN LIGHT HAZARD OCCUPANCY SPRINKLER HEADS SHALL BE QUICK RESPONCE WITH A
K FACTOR OF 5.6.
15. COMPLY WITH THE ARMY CORPS OF ENGINEERING MANUAL EM-385-1-1, SAFETY AND
HEALTH REQUIREMENTS MANUAL AND NFPA-241, SAFEGUARDING CONSTRUCTION,
ALTERATION AND DEMOLITION OPERATIONS AND USMA WEST POINT'S FIRE
REGULATIONS.
5. OCCUPANCY CLASSIFICATION: ORDINARY GROUP II HAZARD: MODERN PHYSICS
WORKROOM, LAB'S, MACHINE & WOOD SHOPS, ETC.
SHEET
REFERENCE
NUMBER
SHEET OF
D E S
IG
N E D B Y
D W N B Y
C H K B Y
S U B M
IT
T E D B Y
D A T E
S O L
IC
IT
A T
IO
N N O
C O N T R A C T N O
F
IL
E N A M E
P L O T T E D B Y
S
IZ
E
P L O T D A T E
D A T E
D E S C R
IP
T
IO
N
M A R K
A P P R
US ARMY CORPS
OF ENGINEERS
NEW YORK DISTRICT
1 2 3 4 5
D
C
B
A
U .S A R M Y E N G
IN
E E R D
IS
T R
IC
T
N E W Y O R K h tt p \w w w .n a n .u s a c e .a rm y .m il a rc h it e c ts e n g in e e rs p la n n e rs
W
E S T N A T
IO
N W
ID
E B L V D
C O L U M B U S O H
IO
.4 .4 f a x .4 .0 h tt p /w w w .u rs c o rp .c o m
S C
IE
N
C E C
E N
T E R
(F Y -B
L D
G
U N
IT
E D S T A T E S M
IL
IT
A R Y A C A D E M Y
W E S T P O
IN
T N Y
A R C H D
P A R K A V E N U E S O U T H
N E W Y O R K N Y -1
.7 .4 f a x .5 .5 w w w .s tv in c .c o m
W D S -1 -D -0
/1 /2 :4 :1 A M
F-101C
S U B -B A S E M E N T P L A N A R E A C
F
IR
E P R O T E C T
IO
N
IR N
J G
L M
A P R
IL
PLAN
NORTH
0 4 8 162
SCALE: 1/8" = 1'-0"
SUB-BASEMENT PLAN-
AREA C FIRE PROTECTION
A
B
D
C
E
CA
CC
CD
CF
CG
CB
CH
C1C2C4 C1.9C4.1 C3
NAS
STEAM TUNNEL
B - S07
GENERAL NOTES:
CODED NOTES:
7. SPRINKLER SYSTEMS SHALL BE HYDRAULICALLY CALCULATED. EACH SYSTEM SHALL
BE CALCULATED TO PROVIDE 10 PSI SAFETY FACTOR.
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
1. FOR SYMBOLS, LEGEND AND ABREVIATIONS SEE DRAWING F-001
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
2. EACH FLOOR WILL BE PROVIDED WITH COMBINATION CLASS I FIRE STANDPIPE SYSTEM
AND/OR SPRINKLER CONTROL VALVE ASSEMBLY.
3. OCCUPANCY CLASSIFICATION: LIGHT HAZARD:CLASSROOMS, OFFICE SPACES,
LOBBIES, CORRIDORS, TOILETS, ETC.
4. OCCUPANCY CLASSIFICATION: ORDINARY GROUP I HAZARD: ALL MECHANICAL AREAS,
INCLUDING BOILERS & PLUMBING ROOMS, STORAGE ROOMS, DATA CENTER,
COMMUNICATION & ELECTRICAL ROOMS, JANITOR CLOSET, RESEARCH ROOMS, ETC.
6. SPRINKLER HEAD COVERAGE: MAXIMUM COVERAGE PER SPRINKLER HEAD SHALL BE
BASED ON 225 SQ. FT.FOR LIGHT HAZARD OCCUPANCY AND 130 SQ. FT. FOR ORDINARY
HAZARD.
8. DESIGN SHALL BE BASED ON 3000 SQ. FT.- DESIGN AREA DEDUCTION SHALL BE
PERMITTED PER NFPA-13 FOR THE LIGTH HAZARD OCCUPANCY.
9. SPRINKLER SYSTEM CALCULATIONS SHALL INCLUDE BUILDING DOMESTIC WATER
DEMANDS.
2. ALL SPRINKLER HEADS SHALL BE ORDINARY TEMPERATURE RATING (155 F)
5. PROVIDE CABINET WITH SPARE SPRINKLER HEADS OF EACH TYPE AND TEMPERATURE.
6. ADD 30% OF REMOTE AREA FOR DRY SPRINKLER SYSTEM.
7. EACH BUILDING WILL BE FULLY SPRINKLERED AND PROVIDED WITH FIRE STANDPIPE
SYSTEMS.
8. CONTRACTOR TO PROVIDE UPDATED FLOW TEST PRIOR TO STARTING SYSTEM
DESIGN.
9. PROVIDE AT NO EXTRA COST ALL ADDITIONAL PIPING AND FITTINGS REQUIRED TO
OFFSET SYSTEM TO AVOID STRUCTUTAL, ARCHITECTURAL, MECHANICAL AND
ELECTRICAL INTERFERENCES WHETHER INDICATED OR NOT, BEFORE INSTALLING
WORK.
10. ALL PIPING SHALL RUN CLOSE TO BEAMS, WALLS AND SLABS, CONCEALED ABOVE
HUNG CEILING AND WITHIN FURRED SPACES.
11. THE SPRINKLER SYSTEM IS AN AUTOMATIC WET PIPE TYPE. THE AUTOMATIC WATER
SOURCE IS A FIRE PUMP TAKING SUCTION FROM DIRECT CONNECTION TO THE FIRE
MAIN AND THE AUXILIARY WATER SOURCES ARE 4" STORZ FOR FIRE DEPARTMENT
CONNECTION.
12. CONTRACTOR SHALL COORDINATE ALL WORK INVOLVED IN SPACE CONDITIONS
BEFORE PROCEEDING.
13. INSTALL SPRINKLER HEADS ABOVE AND BELOW DUCTS 4'-0" WIDE AND LARGER.
10. SPRINKLER HEADS LOCATED CLOSE TO THE HEATER, STEAM PIPING OR OTHER HEAT
SOURCE SHALL BE TEMPERATURE RATING AS REQUIRED PER NFPA-13.
3. ALL VALVES IN FIRE PROTECTION SYSTEMS SHALL BE PAINTED RED BY
MANUFACTURER.
4. INSTALL CONTROL VALVES LESS THAN 7'-0" A.F.F., WHERE POSSIBLE. WHERE CONTROL
VALVES ARE INSTALLED AT OR ABOVE 7'-0" A.F.F., INSTALL STEEL LADDER.
COORDINATEREQUIREMENTS OF STEEL LADDER WITH ARCHITECTURAL PLANS AND
SPECS.
11. WEST POINT FIRE PROTECTION SYSTEMS SHALL BE BRACED PER THE SEISMIC ZONE
AND CALCULATIONS SHALL BE SUBMITTED FOR VERIFICATION .
12. INSTALL WIRE CAGE ON SPRINKLER HEADS INSTALLED BELOW 7'-0".
13. TEST FIRE PROTECTION SYSTEMS AS REQUIRED PER NFPA.
14. IN LIGHT HAZARD OCCUPANCY SPRINKLER HEADS SHALL BE QUICK RESPONCE WITH A
K FACTOR OF 5.6.
15. COMPLY WITH THE ARMY CORPS OF ENGINEERING MANUAL EM-385-1-1, SAFETY AND
HEALTH REQUIREMENTS MANUAL AND NFPA-241, SAFEGUARDING CONSTRUCTION,
ALTERATION AND DEMOLITION OPERATIONS AND USMA WEST POINT'S FIRE
REGULATIONS.
5. OCCUPANCY CLASSIFICATION: ORDINARY GROUP II HAZARD: MODERN PHYSICS
WORKROOM, LAB'S, MACHINE & WOOD SHOPS, ETC.
SHEET
REFERENCE
NUMBER
SHEET OF
D E S
IG
N E D B Y
D W N B Y
C H K B Y
S U B M
IT
T E D B Y
D A T E
S O L
IC
IT
A T
IO
N N O
C O N T R A C T N O
F
IL
E N A M E
P L O T T E D B Y
S
IZ
E
P L O T D A T E
D A T E
D E S C R
IP
T
IO
N
M A R K
A P P R
US ARMY CORPS
OF ENGINEERS
NEW YORK DISTRICT
1 2 3 4 5
D
C
B
A
U .S A R M Y E N G
IN
E E R D
IS
T R
IC
T
N E W Y O R K h tt p \w w w .n a n .u s a c e .a rm y .m il a rc h it e c ts e n g in e e rs p la n n e rs
W E S T N A T
IO
N W
ID
E B L V D
C O L U M B U S O H
IO
.4 .4 f a x .4 .0 h tt p /w w w .u rs c o rp .c o m
S C
IE
N C E C E N T E R
(F Y -B L D G
U N
IT
E D S T A T E S M
IL
IT
A R Y A C A D E M Y
W E S T P O
IN
T N Y
A R C H D
P A R K A V E N U E S O U T H
N E W Y O R K N Y -1
.7 .4 f a x .5 .5 w w w .s tv in c .c o m
W D S -1 -D -0
/1 /2 :0 :1 A M
F-101E
S U B -B A S E M E N T A R E A E
F
IR
E P R O T E C T
IO
N
IR N
J G
L M
A P R
IL
PLAN
NORTH
0 4 8 162
SCALE: 1/8" = 1'-0"
SUB-BASEMENT - AREA E
FIRE PROTECTION
D
C
E
A2A4
AF
A6
A7
AG
AH
AJ
AK
A8
A5
AA
AD
AE
AC
AB
A1
AL
AM
A5.4
AS
AR
A10
A9
AS.5
AA.6
AT
A10.5
178 SF
ELEC
B-B01 139 SF
SUPPLY TECH
B-B03
291 SF
STAIR B2
B-BS2
184 SF
GAS HOLDING
B-B02
322 SF
CORRIDOR
B-BC7
683 SF
CLASSROOM
B-B17
475 SF
BLDG MAINT/
STOR
B-B09
170 SF
SAFETY SPLY
TECH
B-B05
717 SF
CLASSROOM
B-B16
133 SF
CORRIDOR
B-BC8
83 SF
JAN BREAK
B-B04
68 SF
TOILET
B-B15
716 SF
CLASSROOM
B-B13
697 SF
CLASSROOM
B-B11
Not Enclosed
CORRIDOR
B-BC5
663 SF
CLASSROOM
B-B06
663 SF
CLASSROOM
B-B10
866 SF
CORRIDOR
B-BC6
144 SF
STOR
B-B14
643 SF
CLASSROOM
B-B12
6" COMBINED
FSP/SP UP& DN
FIRE HOSE
VALVE IN CABINET
TO SPRINKLERS
6" UP
EXISTING 6"
COMBINED FSP/SP UP
(PHASE 1) TO REMAIN
FIRE HOSE VALVE IN CABINET
SEE DWG F-301
FSP
2" DRAIN DN
TO PHASE 1
FSP
EXIST. RISER CONTROL VALVE
WITH TAMPER SWITCH TO REMAIN
F O R C O N T
IN
U A T
IO
N S E E D W G F -1 C
F O R C O N T
IN
U A T
IO
N S E E D W G F -1 C
224 SF
STAIR B1
B-BS1
178 SF
ELEC
B-B01
OH-1
L
L
L
L
L
L
L
L
L
L
L
L
L
L
L
L
L
OH-1
OH-1
OH-1
OH-1
41 43
MOST REMOTE AREA OF
HYDRAULIC CALCULATIONS,
LIGHT HAZARD, 3000 SQ. FT.,
0.1 DENSITY
1"
1"
1 1/2"
1 1/2"
1 1/2"
2"
2"
1"
1"
1"
1"
2"
1 1/2"
1"
1"
2"
4"
1" UP & DN
CONNECT NEW 6" FIRE
MAIN TO 6" EXIST. PIPING
A6
A7
A5
AL
AM
AN
A5.4
A4.7 A9
AP
A9.5
683 SF
CLASSROOM
B-B17
133 SF
CORRIDOR
B-BC8
F O R C O N T
IN
U A T
IO
N S E E D W G F -1 C
L
L
GENERAL NOTES:
CODED NOTES:
7. SPRINKLER SYSTEMS SHALL BE HYDRAULICALLY CALCULATED. EACH SYSTEM SHALL
BE CALCULATED TO PROVIDE 10 PSI SAFETY FACTOR.
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
1. FOR SYMBOLS, LEGEND AND ABREVIATIONS SEE DRAWING F-001
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
2. EACH FLOOR WILL BE PROVIDED WITH COMBINATION CLASS I FIRE STANDPIPE SYSTEM
AND/OR SPRINKLER CONTROL VALVE ASSEMBLY.
3. OCCUPANCY CLASSIFICATION: LIGHT HAZARD:CLASSROOMS, OFFICE SPACES,
LOBBIES, CORRIDORS, TOILETS, ETC.
4. OCCUPANCY CLASSIFICATION: ORDINARY GROUP I HAZARD: ALL MECHANICAL AREAS,
INCLUDING BOILERS & PLUMBING ROOMS, STORAGE ROOMS, DATA CENTER,
COMMUNICATION & ELECTRICAL ROOMS, JANITOR CLOSET, RESEARCH ROOMS, ETC.
6. SPRINKLER HEAD COVERAGE: MAXIMUM COVERAGE PER SPRINKLER HEAD SHALL BE
BASED ON 225 SQ. FT.FOR LIGHT HAZARD OCCUPANCY AND 130 SQ. FT. FOR ORDINARY
HAZARD.
8. DESIGN SHALL BE BASED ON 3000 SQ. FT.- DESIGN AREA DEDUCTION SHALL BE
PERMITTED PER NFPA-13 FOR THE LIGHT HAZARD OCCUPANCY.
9. SPRINKLER SYSTEM CALCULATIONS SHALL INCLUDE BUILDING DOMESTIC WATER
DEMANDS.
2. ALL SPRINKLER HEADS SHALL BE ORDINARY TEMPERATURE RATING (155 F)
5. PROVIDE CABINET WITH SPARE SPRINKLER HEADS OF EACH TYPE AND TEMPERATURE.
6. ADD 30% OF REMOTE AREA FOR DRY SPRINKLER SYSTEM.
7. EACH BUILDING WILL BE FULLY SPRINKLERED AND PROVIDED WITH FIRE STANDPIPE
SYSTEMS.
8. CONTRACTOR TO PROVIDE UPDATED FLOW TEST PRIOR TO STARTING SYSTEM
DESIGN.
9. PROVIDE AT NO EXTRA COST ALL ADDITIONAL PIPING AND FITTINGS REQUIRED TO
OFFSET SYSTEM TO AVOID STRUCTUTAL, ARCHITECTURAL, MECHANICAL AND
ELECTRICAL INTERFERENCES WHETHER INDICATED OR NOT, BEFORE INSTALLING
WORK.
10. ALL PIPING SHALL RUN CLOSE TO BEAMS, WALLS AND SLABS, CONCEALED ABOVE
HUNG CEILING AND WITHIN FURRED SPACES.
11. THE SPRINKLER SYSTEM IS AN AUTOMATIC WET PIPE TYPE. THE AUTOMATIC WATER
SOURCE IS A FIRE PUMP TAKIN SUCTION FROM DIRECT CONNECTION TO THE FIRE
MAIN AND THE AUXILIARY WATER SOURCES ARE 4" STORZ FOR FIRE DEPARTMENT
CONNECTION.
12. CONTRACTOR SHALL COORDINATE ALL WORK INVOLVED IN SPACE CONDITIONS
BEFORE PROCEEDING.
13. INSTALL SPRINKLER HEADS ABOVE AND BELOW DUCTS 4'-0" WIDE AND LARGER.
10. SPRINKLER HEADS LOCATED CLOSE TO THE HEATER, STEAM PIPING OR OTHER HEAT
SOURCE SHALL BE TEMPERATURE RATING AS REQUIRED PER NFPA-13.
3. ALL VALVES IN FIRE PROTECTION SYSTEMS SHALL BE PAINTED RED BY
MANUFACTURER.
4. INSTALL CONTROL VALVES LESS THAN 7'-0"A.F.F., WHERE POSSIBLE. WHERE CONTROL
VALVES ARE INSTALLED AT OR ABOVE 7'-0" A.F.F., INSTALL STEEL LADDER.
COORDINATE REQUIREMENTS OF STEEL LADDER WITH ARCHITECTURAL PLANS AND
SPECS.
11. WEST POINT FIRE PROTECTION SYSTEMS SHALL BE BRACED PER THE SEISMIC ZONE
AND CALCULATIONS SHALL BE SUBMITTED FOR VERIFICATION .
12. INSTALL WIRE CAGE ON SPRINKLER HEADS INSTALLED BELOW 7'-0".
13. TEST FIRE PROTECTION SYSTEMS AS REQUIRED PER NFPA.
14. IN LIGHT HAZARD OCCUPANCY SPRINKLER HEADS SHALL BE QUICK RESPONCE WITH A
K FACTOR OF 5.6.
15. COMPLY WITH THE ARMY CORPS OF ENGINEERING MANUAL EM-385-1-1, SAFETY AND
HEALTH REQUIREMENTS MANUAL AND NFPA-241, SAFEGUARDING CONSTRUCTION,
ALTERATION AND DEMOLITION OPERATIONS AND USMA WEST POINT'S FIRE
REGULATIONS.
5. OCCUPANCY CLASSIFICATION: ORDINARY GROUP II HAZARD: MODERN PHYSICS
WORKROOM, LAB'S, MACHINE & WOOD SHOPS, ETC.
SHEET
REFERENCE
NUMBER
SHEET OF
D E S
IG
N E D B Y
D W N B Y
C H K B Y
S U B M
IT
T E D B Y
D A T E
S O L
IC
IT
A T
IO
N N O
C O N T R A C T N O
F
IL
E N A M E
P L O T T E D B Y
S
IZ
E
P L O T D A T E
D A T E
D E S C R
IP
T
IO
N
M A R K
A P P R
US ARMY CORPS
OF ENGINEERS
NEW YORK DISTRICT
1 2 3 4 5
D
C
B
A
U .S A R M Y E N G
IN
E E R D
IS
T R
IC
T
N E W Y O R K h tt p \w w w .n a n .u s a c e .a rm y .m il a rc h it e c ts e n g in e e rs p la n n e rs
W
E S T N A T
IO
N W
ID
E B L V D
C O L U M B U S O H
IO
.4 .4 f a x .4 .0 h tt p /w w w .u rs c o rp .c o m
S C
IE
N C E C E N T E R
(F Y -B L D G
U N
IT
E D S T A T E S M
IL
IT
A R Y A C A D E M Y
W E S T P O
IN
T N Y
A R C H D
P A R K A V E N U E S O U T H
N E W Y O R K N Y -1
.7 .4 f a x .5 .5 w w w .s tv in c .c o m
W D S -1 -D -0
/1 /2 :1 :4 A M
F-102B
B A S E M E N T A R E A B F
IR
E P R O T E C T
IO
N
IR N
J G
L M
A P R
IL
PLAN
NORTH
0 4 8 162
SCALE: 1/8" = 1'-0"
BASEMENT FLOOR PLAN-
D
C
E
B1312.7 B12 B11.2B11 B9.8 B9 B8.2 B8
BU
BT
BS
BR.7
BQ.5
BQ
BP
BN
BM
BR
BR.8
BS.8
BV
B1B7 B6 B5 B4 B3 B2
JAN
C-B06
BLDG STOR SPT
C-B05
WOMEN
C-B18
PREP/ STOR
D-B11
COMM
C-B03
ELEC
C-B04
Space
D-2C269
Space
D-2C270
PHYSICS
CLASSRM
C-B08
NUCL ENGR LAB
C-B17
CORRIDOR
C-BC1
Space
D-2C285
MAIN ELEC SERV
C-B10
PHYSICS
WORKRM
D-B12
PHYSICS
CLASSRM
C-B01
RSO LAB
C-B16
WOMEN SHOWER
ENTRY
C-B19
MODERN PHYSICS
WORKRM
C-B02
Space
D-2C304
ANTE
C-B14
SUB-CRIT NUC
FACIL
C-B15
CORRIDOR
C-BC3
CORRIDOR
C-BC4
RAD DETECT
LAB/CLSRM
C-B12
STORAGE
C-B11
CORRIDOR
C-BC5
MEN
C-B07
PHYSICS
WORKRM
C-B09
6" FSP UP
FIRE HOSE VALVE IN
CABINET, SEE DWG. F-301
FSP
F O R C O N T
IN
U A T
IO
N S E E D W G F -1 B
F O R C O N T
IN
U A T
IO
N S E E D W G F -1 E
FOR CONTINUATION SEE DWG F-102E
OH-2
L
OH-1
OH-1
OH-1OH-1
OH-1
OH-1
OH-1
L L
L
L
L
L
L
L
L
L
OH-1
L
OH-2
OH-2 OH-2
OH-2
OH-2
4" SPRINKLER CROSS MAIN
4"
4" 4"
FOR CONTINUATION SEE DWG F-102D GENERAL NOTES:
CODED NOTES:
7. SPRINKLER SYSTEMS SHALL BE HYDRAULICALLY CALCULATED. EACH SYSTEM SHALL
BE CALCULATED TO PROVIDE 10 PSI SAFETY FACTOR.
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
1. FOR SYMBOLS, LEGEND AND ABREVIATIONS SEE DRAWING F-001
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
2. EACH FLOOR WILL BE PROVIDED WITH COMBINATION CLASS I FIRE STANDPIPE SYSTEM
AND/OR SPRINKLER CONTROL VALVE ASSEMBLY.
3. OCCUPANCY CLASSIFICATION: LIGHT HAZARD:CLASSROOMS, OFFICE SPACES,
LOBBIES, CORRIDORS, TOILETS, ETC.
4. OCCUPANCY CLASSIFICATION: ORDINARY GROUP I HAZARD: ALL MECHANICAL AREAS,
INCLUDING BOILERS & PLUMBING ROOMS, STORAGE ROOMS, DATA CENTER,
COMMUNICATION & ELECTRICAL ROOMS, JANITOR CLOSET, RESEARCH ROOMS, ETC.
6. SPRINKLER HEAD COVERAGE: MAXIMUM COVERAGE PER SPRINKLER HEAD SHALL BE
BASED ON 225 SQ. FT.FOR LIGHT HAZARD OCCUPANCY AND 130 SQ. FT. FOR ORDINARY
HAZARD.
8. DESIGN SHALL BE BASED ON 3000 SQ. FT.- DESIGN AREA DEDUCTION SHALL BE
PERMITTED PER NFPA-13 FOR THE LIGTH HAZARD OCCUPANCY.
9. SPRINKLER SYSTEM CALCULATIONS SHALL INCLUDE BUILDING DOMESTIC WATER
DEMANDS.
2. ALL SPRINKLER HEADS SHALL BE ORDINARY TEMPERATURE RATING (155 F)
5. PROVIDE CABINET WITH SPARE SPRINKLER HEADS OF EACH TYPE AND TEMPERATURE.
6. ADD 30% OF REMOTE AREA FOR DRY SPRINKLER SYSTEM.
7. EACH BUILDING WILL BE FULLY SPRINKLERED AND PROVIDED WITH FIRE STANDPIPE
SYSTEMS.
8. CONTRACTOR TO PROVIDE UPDATED FLOW TEST PRIOR TO STARTING SYSTEM
DESIGN.
9. PROVIDE AT NO EXTRA COST ALL ADDITIONAL PIPING AND FITTINGS REQUIRED TO
OFFSET SYSTEM TO AVOID STRUCTUTAL, ARCHITECTURAL, MECHANICAL AND
ELECTRICAL INTERFERENCES WHETHER INDICATED OR NOT, BEFORE INSTALLING
WORK.
10. ALL PIPING SHALL RUN CLOSE TO BEAMS, WALLS AND SLABS, CONCEALED ABOVE
HUNG CEILING AND WITHIN FURRED SPACES.
11. THE SPRINKLER SYSTEM IS AN AUTOMATIC WET PIPE TYPE. THE AUTOMATIC WATER
SOURCE IS A FIRE PUMP TAKING SUCTION FROM DIRECT CONNECTION TO THE FIRE
MAIN AND THE AUXILIARY WATER SOURCES ARE 4" STORZ FOR FIRE DEPARTMENT
CONNECTION.
12. CONTRACTOR SHALL COORDINATE ALL WORK INVOLVED IN SPACE CONDITIONS
BEFORE PROCEEDING.
13. INSTALL SPRINKLER HEADS ABOVE AND BELOW DUCTS 4'-0" WIDE AND LARGER.
10. SPRINKLER HEADS LOCATED CLOSE TO THE HEATER, STEAM PIPING OR OTHER HEAT
SOURCE SHALL BE TEMPERATURE RATING AS REQUIRED PER NFPA-13.
3. ALL VALVES IN FIRE PROTECTION SYSTEMS SHALL BE PAINTED RED BY
MANUFACTURER.
4. INSTALL CONTROL VALVES LESS THAN 7'-0" A.F.F, WHERE POSSIBLE. WHERE CONTROL
VALVES ARE INSTALLED AT OR ABOVE 7'-0" A.F.F., INSTALL STEEL LADDER.
COORDINATE REQUIREMNETS OF STEEL LADDER WITH ARCHITECTURAL PLANS AND
SPECS.
11. WEST POINT FIRE PROTECTION SYSTEMS SHALL BE BRACED PER THE SEISMIC ZONE
AND CALCULATIONS SHALL BE SUBMITTED FOR VERIFICATION .
12. INSTALL WIRE CAGE ON SPRINKLER HEADS INSTALLED BELOW 7'-0".
13. TEST FIRE PROTECTION SYSTEMS AS REQUIRED PER NFPA.
14. IN LIGHT HAZARD OCCUPANCY SPRINKLER HEADS SHALL BE QUICK RESPONCE WITH A
K FACTOR OF 5.6.
15. COMPLY WITH THE ARMY CORPS OF ENGINEERING MANUAL EM-385-1-1, SAFETY AND
HEALTH REQUIREMENTS MANUAL AND NFPA-241, SAFEGUARDING CONSTRUCTION,
ALTERATION AND DEMOLITION OPERATIONS AND USMA WEST POINT'S FIRE
REGULATIONS.
5. OCCUPANCY CLASSIFICATION: ORDINARY GROUP II HAZARD: MODERN PHYSICS
WORKROOM, LAB'S, MACHINE & WOOD SHOPS, ETC.
14. DRAIN TROUGHS SHALL BE PROVIDED BELOW ANY PIPING ROUTED DIRECTLY OVER
ELECTRICAL EQUIPMENT.
SHEET
REFERENCE
NUMBER
SHEET OF
D E S
IG
N E D B Y
D W N B Y
C H K B Y
S U B M
IT
T E D B Y
D A T E
S O L
IC
IT
A T
IO
N N O
C O N T R A C T N O
F
IL
E N A M E
P L O T T E D B Y
S
IZ
E
P L O T D A T E
D A T E
D E S C R
IP
T
IO
N
M A R K
A P P R
US ARMY CORPS
OF ENGINEERS
NEW YORK DISTRICT
1 2 3 4 5
D
C
B
A
U .S A R M Y E N G
IN
E E R D
IS
T R
IC
T
N E W Y O R K h tt p \w w w .n a n .u s a c e .a rm y .m il a rc h it e c ts e n g in e e rs p la n n e rs
W
E S T N A T
IO
N W
ID
E B L V D
C O L U M B U S O H
IO
.4 .4 f a x .4 .0 h tt p /w w w .u rs c o rp .c o m
S C
IE
N
C E C
E N
T E R
(F Y -B
L D
G
U N
IT
E D S T A T E S M
IL
IT
A R Y A C A D E M Y
W E S T P O
IN
T N Y
A R C H D
P A R K A V E N U E S O U T H
N E W Y O R K N Y -1
.7 .4 f a x .5 .5 w w w .s tv in c .c o m
W D S -1 -D -0
/1 /2 :4 :1 A M
F-102C
B A S E M E N T P L A N A R E A C
F
IR
E P R O T E C T
IO
N
IR N
J G
L M
A P R
IL
PLAN
NORTH
0 4 8 162
SCALE: 1/8" = 1'-0"
BASEMENT PLAN -
D
C
E
B1312.7 B12 B11 B9 B8.2 B8
BL
BK
BJ
BH
BG
BF
BE
BD
BC
BB
BA
ELECTRONICS
D-B06
WELDING RM
D-B05
MACHINE SHOP
D-B02
CORRIDOR
D-BC1
JAN
D-B08
GEN STOR
D-B07
FXD EXPERIMTL
PHYSICS
D-B09
MATL SCI ACCEL
LAB
D-B01
MODERN PHYSICS
WORKRM
D-B10
307 SF
CLEAN RM/ PREP
STOR
D-B04
WOOD SHOP
D-B03
CORRIDOR
D-BC3
6" COMBINED
FSP/SP UP
FIRE HOSE VALVE IN
CABINET, SE DWG.
F-301
SPRINKLER
CONTROL VALVE,
SEE DWG. F-301
FSP
FOR CONTINUATION SEE DWG F-102C
F O R C O N T I N U A T
IO
N S E E D W G F -1 E
OH-2
L
OH-1
L
L
L
L
OH-2
OH-2
OH-2
OH-1
OH-1
OH-1
OH-1
OH-1
4"
4" SPRINKLER CROSS MAIN
GENERAL NOTES:
CODED NOTES:
7. SPRINKLER SYSTEMS SHALL BE HYDRAULICALLY CALCULATED. EACH SYSTEM SHALL
BE CALCULATED TO PROVIDE 10 PSI SAFETY FACTOR.
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
1. FOR SYMBOLS, LEGEND AND ABREVIATIONS SEE DRAWING F-001
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
2. EACH FLOOR WILL BE PROVIDED WITH COMBINATION CLASS I FIRE STANDPIPE SYSTEM
AND/OR SPRINKLER CONTROL VALVE ASSEMBLY.
3. OCCUPANCY CLASSIFICATION: LIGHT HAZARD:CLASSROOMS, OFFICE SPACES,
LOBBIES, CORRIDORS, TOILETS, ETC.
4. OCCUPANCY CLASSIFICATION: ORDINARY GROUP I HAZARD: ALL MECHANICAL AREAS,
INCLUDING BOILERS & PLUMBING ROOMS, STORAGE ROOMS, DATA CENTER,
COMMUNICATION & ELECTRICAL ROOMS, JANITOR CLOSET, RESEARCH ROOMS, ETC.
6. SPRINKLER HEAD COVERAGE: MAXIMUM COVERAGE PER SPRINKLER HEAD SHALL BE
BASED ON 225 SQ. FT.FOR LIGHT HAZARD OCCUPANCY AND 130 SQ. FT. FOR ORDINARY
HAZARD.
8. DESIGN SHALL BE BASED ON 3000 SQ. FT.- DESIGN AREA DEDUCTION SHALL BE
PERMITTED PER NFPA-13 FOR THE LIGTH HAZARD OCCUPANCY.
9. SPRINKLER SYSTEM CALCULATIONS SHALL INCLUDE BUILDING DOMESTIC WATER
DEMANDS.
2. ALL SPRINKLER HEADS SHALL BE ORDINARY TEMPERATURE RATING (155 F)
5. PROVIDE CABINET WITH SPARE SPRINKLER HEADS OF EACH TYPE AND TEMPERATURE.
6. ADD 30% OF REMOTE AREA FOR DRY SPRINKLER SYSTEM.
7. EACH BUILDING WILL BE FULLY SPRINKLERED AND PROVIDED WITH FIRE STANDPIPE
SYSTEMS.
8. CONTRACTOR TO PROVIDE UPDATED FLOW TEST PRIOR TO STARTING SYSTEM
DESIGN.
9. PROVIDE AT NO EXTRA COST ALL ADDITIONAL PIPING AND FITTINGS REQUIRED TO
OFFSET SYSTEM TO AVOID STRUCTUTAL, ARCHITECTURAL, MECHANICAL AND
ELECTRICAL INTERFERENCES WHETHER INDICATED OR NOT, BEFORE INSTALLING
WORK.
10. ALL PIPING SHALL RUN CLOSE TO BEAMS, WALLS AND SLABS, CONCEALED ABOVE
HUNG CEILING AND WITHIN FURRED SPACES.
11. THE SPRINKLER SYSTEM IS AN AUTOMATIC WET PIPE TYPE. THE AUTOMATIC WATER
SOURCE IS A FIRE PUMP TAKING SUCTION FROM DIRECT CONNECTION TO THE FIRE
MAIN AND THE AUXILIARY WATER SOURCES ARE 4" STORZ FOR FIRE DEPARTMENT
CONNECTION.
12. CONTRACTOR SHALL COORDINATE ALL WORK INVOLVED IN SPACE CONDITIONS
BEFORE PROCEEDING.
13. INSTALL SPRINKLER HEADS ABOVE AND BELOW DUCTS 4'-0" WIDE AND LARGER.
10. SPRINKLER HEADS LOCATED CLOSE TO THE HEATER, STEAM PIPING OR OTHER HEAT
SOURCE SHALL BE TEMPERATURE RATING AS REQUIRED PER NFPA-13.
3. ALL VALVES IN FIRE PROTECTION SYSTEMS SHALL BE PAINTED RED BY
MANUFACTURER.
4. INSTALL CONTROL VALVES LESS THAN 7'-0" A.F.F, WHERE POSSIBLE. WHERE CONTROL
VALVES ARE INSTALLED AT OR ABOVE 7'-0" A.F.F., INSTALL STEEL LADDER.
COORDINATE REQUIREMNETS OF STEEL LADDER WITH ARCHITECTURAL PLANS AND
SPECS.
11. WEST POINT FIRE PROTECTION SYSTEMS SHALL BE BRACED PER THE SEISMIC ZONE
AND CALCULATIONS SHALL BE SUBMITTED FOR VERIFICATION .
12. INSTALL WIRE CAGE ON SPRINKLER HEADS INSTALLED BELOW 7'-0".
13. TEST FIRE PROTECTION SYSTEMS AS REQUIRED PER NFPA.
14. IN LIGHT HAZARD OCCUPANCY SPRINKLER HEADS SHALL BE QUICK RESPONCE WITH A
K FACTOR OF 5.6.
15. COMPLY WITH THE ARMY CORPS OF ENGINEERING MANUAL EM-385-1-1, SAFETY AND
HEALTH REQUIREMENTS MANUAL AND NFPA-241, SAFEGUARDING CONSTRUCTION,
ALTERATION AND DEMOLITION OPERATIONS AND USMA WEST POINT'S FIRE
REGULATIONS.
5. OCCUPANCY CLASSIFICATION: ORDINARY GROUP II HAZARD: MODERN PHYSICS
WORKROOM, LAB'S, MACHINE & WOOD SHOPS, ETC.
SHEET
REFERENCE
NUMBER
SHEET OF
D E S
IG
N E D B Y
D W N B Y
C H K B Y
S U B M
IT
T E D B Y
D A T E
S O L
IC
IT
A T
IO
N N O
C O N T R A C T N O
F
IL
E N A M E
P L O T T E D B Y
S
IZ
E
P L O T D A T E
D A T E
D E S C R
IP
T
IO
N
M A R K
A P P R
US ARMY CORPS
OF ENGINEERS
NEW YORK DISTRICT
1 2 3 4 5
D
C
B
A
U .S A R M Y E N G
IN
E E R D
IS
T R
IC
T
N E W Y O R K h tt p \w w w .n a n .u s a c e .a rm y .m il a rc h it e c ts e n g in e e rs p la n n e rs
W
E S T N A T
IO
N W
ID
E B L V D
C O L U M B U S O H
IO
.4 .4 f a x .4 .0 h tt p /w w w .u rs c o rp .c o m
S C
IE
N
C E C
E N
T E R
(F Y -B
L D
G
U N
IT
E D S T A T E S M
IL
IT
A R Y A C A D E M Y
W E S T P O
IN
T N Y
A R C H D
P A R K A V E N U E S O U T H
N E W Y O R K N Y -1
.7 .4 f a x .5 .5 w w w .s tv in c .c o m
W D S -1 -D -0
/1 /2 :4 :1 A M
F-102D
B A S E M E N T P L A N A R E A D
F
IR
E P R O T E C T
IO
N
IR N
J G
L M
A P R
IL
PLAN
NORTH
0 4 8 162
SCALE: 1/8" = 1'-0"
BASEMENT PLAN -
AREA D FIRE PROTECTION
OS OS OS
OS
OS
OS OS
OS
OS
OS
OS OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
A
B
D
C
E
CA
CC
CD
CF
CG
CB
CH
C1C2C4 C1.9C4.1 C3
LASER RES/CHEM
E-B03
CORRIDOR
E-BC3
Space
LASER
RESEARCH
E-B05
LASER
RESEARCH
E-B04
HIGH ENERGY
LASER
RESEARCH
E-B07
CORRIDOR-1
E-BC1-1
LASER EQUIP
STOR/REPAIR
E-B06
OH-1
OH-1
OH-1
OH-1
OH-1
OH-1
L
L
L
OH-2
CORRIDOR
E-BC2
CADET PROJECT
LAB
E-B01
MATCHLINE. FOR CONTINUATION SEE DWG. F-102B
M A T C H L
IN
E F O R C O N T
IN
U A T
IO
N S E E D W G F -1 D
M A T C H L
IN
E F O R C O N T
IN
U A T
IO
N S E E D W G F -1 C
M A T C H L
IN
E F O R C O N T
IN
U A T
IO
N S E E D W G F -1 B
PHASE 1 AREA
GENERAL NOTES:
CODED NOTES:
7. SPRINKLER SYSTEMS SHALL BE HYDRAULICALLY CALCULATED. EACH SYSTEM SHALL
BE CALCULATED TO PROVIDE 10 PSI SAFETY FACTOR.
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
1. FOR SYMBOLS, LEGEND AND ABREVIATIONS SEE DRAWING F-001
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
2. EACH FLOOR WILL BE PROVIDED WITH COMBINATION CLASS I FIRE STANDPIPE SYSTEM
AND/OR SPRINKLER CONTROL VALVE ASSEMBLY.
3. OCCUPANCY CLASSIFICATION: LIGHT HAZARD:CLASSROOMS, OFFICE SPACES,
LOBBIES, CORRIDORS, TOILETS, ETC.
4. OCCUPANCY CLASSIFICATION: ORDINARY GROUP I HAZARD: ALL MECHANICAL AREAS,
INCLUDING BOILERS & PLUMBING ROOMS, STORAGE ROOMS, DATA CENTER,
COMMUNICATION & ELECTRICAL ROOMS, JANITOR CLOSET, RESEARCH ROOMS, ETC.
6. SPRINKLER HEAD COVERAGE: MAXIMUM COVERAGE PER SPRINKLER HEAD SHALL BE
BASED ON 225 SQ. FT.FOR LIGHT HAZARD OCCUPANCY AND 130 SQ. FT. FOR ORDINARY
HAZARD.
8. DESIGN SHALL BE BASED ON 3000 SQ. FT.- DESIGN AREA DEDUCTION SHALL BE
PERMITTED PER NFPA-13 FOR THE LIGTH HAZARD OCCUPANCY.
9. SPRINKLER SYSTEM CALCULATIONS SHALL INCLUDE BUILDING DOMESTIC WATER
DEMANDS.
2. ALL SPRINKLER HEADS SHALL BE ORDINARY TEMPERATURE RATING (155 F)
5. PROVIDE CABINET WITH SPARE SPRINKLER HEADS OF EACH TYPE AND TEMPERATURE.
6. ADD 30% OF REMOTE AREA FOR DRY SPRINKLER SYSTEM.
7. EACH BUILDING WILL BE FULLY SPRINKLERED AND PROVIDED WITH FIRE STANDPIPE
SYSTEMS.
8. CONTRACTOR TO PROVIDE UPDATED FLOW TEST PRIOR TO STARTING SYSTEM
DESIGN.
9. PROVIDE AT NO EXTRA COST ALL ADDITIONAL PIPING AND FITTINGS REQUIRED TO
OFFSET SYSTEM TO AVOID STRUCTUTAL, ARCHITECTURAL, MECHANICAL AND
ELECTRICAL INTERFERENCES WHETHER INDICATED OR NOT, BEFORE INSTALLING
WORK.
10. ALL PIPING SHALL RUN CLOSE TO BEAMS, WALLS AND SLABS, CONCEALED ABOVE
HUNG CEILING AND WITHIN FURRED SPACES.
11. THE SPRINKLER SYSTEM IS AN AUTOMATIC WET PIPE TYPE. THE AUTOMATIC WATER
SOURCE IS A FIRE PUMP TAKING SUCTION FROM DIRECT CONNECTION TO THE FIRE
MAIN AND THE AUXILIARY WATER SOURCES ARE 4" STORZ FOR FIRE DEPARTMENT
CONNECTION.
12. CONTRACTOR SHALL COORDINATE ALL WORK INVOLVED IN SPACE CONDITIONS
BEFORE PROCEEDING.
13. INSTALL SPRINKLER HEADS ABOVE AND BELOW DUCTS 4'-0" WIDE AND LARGER.
10. SPRINKLER HEADS LOCATED CLOSE TO THE HEATER, STEAM PIPING OR OTHER HEAT
SOURCE SHALL BE TEMPERATURE RATING AS REQUIRED PER NFPA-13.
3. ALL VALVES IN FIRE PROTECTION SYSTEMS SHALL BE PAINTED RED BY
MANUFACTURER.
4. INSTALL CONTROL VALVES LESS THAN 7'-0" A.F.F., WHERE POSSIBLE. WHERE CONTROL
VALVES ARE INSTALLED AT OR ABOVE 7'-0" A.F.F., INSTALL STEEL LADDER.
COORDINATEREQUIREMENTS OF STEEL LADDER WITH ARCHITECTURAL PLANS AND
SPECS.
11. WEST POINT FIRE PROTECTION SYSTEMS SHALL BE BRACED PER THE SEISMIC ZONE
AND CALCULATIONS SHALL BE SUBMITTED FOR VERIFICATION .
12. INSTALL WIRE CAGE ON SPRINKLER HEADS INSTALLED BELOW 7'-0".
13. TEST FIRE PROTECTION SYSTEMS AS REQUIRED PER NFPA.
14. IN LIGHT HAZARD OCCUPANCY SPRINKLER HEADS SHALL BE QUICK RESPONCE WITH A
K FACTOR OF 5.6.
15. COMPLY WITH THE ARMY CORPS OF ENGINEERING MANUAL EM-385-1-1, SAFETY AND
HEALTH REQUIREMENTS MANUAL AND NFPA-241, SAFEGUARDING CONSTRUCTION,
ALTERATION AND DEMOLITION OPERATIONS AND USMA WEST POINT'S FIRE
REGULATIONS.
5. OCCUPANCY CLASSIFICATION: ORDINARY GROUP II HAZARD: MODERN PHYSICS
WORKROOM, LAB'S, MACHINE & WOOD SHOPS, ETC.
SHEET
REFERENCE
NUMBER
SHEET OF
D E S
IG
N E D B Y
D W N B Y
C H K B Y
S U B M
IT
T E D B Y
D A T E
S O L
IC
IT
A T
IO
N N O
C O N T R A C T N O
F
IL
E N A M E
P L O T T E D B Y
S
IZ
E
P L O T D A T E
D A T E
D E S C R
IP
T
IO
N
M A R K
A P P R
US ARMY CORPS
OF ENGINEERS
NEW YORK DISTRICT
1 2 3 4 5
D
C
B
A
U .S A R M Y E N G
IN
E E R D
IS
T R
IC
T
N E W Y O R K h tt p \w w w .n a n .u s a c e .a rm y .m il a rc h it e c ts e n g in e e rs p la n n e rs
W E S T N A T
IO
N W
ID
E B L V D
C O L U M B U S O H
IO
.4 .4 f a x .4 .0 h tt p /w w w .u rs c o rp .c o m
S C
IE
N C E C E N T E R
(F Y -B L D G
U N
IT
E D S T A T E S M
IL
IT
A R Y A C A D E M Y
W E S T P O
IN
T N Y
A R C H D
P A R K A V E N U E S O U T H
N E W Y O R K N Y -1
.7 .4 f a x .5 .5 w w w .s tv in c .c o m
W D S -1 -D -0
/1 /2 :0 :1 A M
F-102E
B A S E M E N T A R E A E F
IR
E P R O T E C T
IO
N
IR N
J G
L M
A P R
IL
PLAN
NORTH
0 4 8 162
SCALE: 1/8" = 1'-0"
BASEMENT - AREA E
D
C
E
A2A4
AF
A6
A7
AG
AH
AJ
AK
A8
A5
AA
AD
AE
AC
AB
A1
AL
A5.4
AS
AR
A10
AS.5
AA.6
A9.5A10.8A11.5A12.3
AT
A12 A11
A10.5
1171 SF
PREP STOR
B-103
Redundant Space
GEN & ADVNCD
CHEM
B-104
1235 SF
GEN & ADVNCD
CHEM
B-107
1152 SF
GEN & ADVNCD
CHEM
B-108
506 SF
CADET READ RM
B-102
147 SF
COMM
B-114
673 SF
CLASSROOM
B-109
60 SF
TOILET
B-110
317 SF
STAIR B1
B-1S1
241 SF
MEN
B-112
661 SF
CLASSROOM
B-111
148 SF
CORRIDOR
B-1C4
314 SF
STAIRS B2
B-1S2
1147 SF
CORRIDOR
B-1C2
6" COMBINED
FSP/SP UP
SPRINKLER CONTROL
ASSEMBLY,
SEE F-301
RISER CONTROL
VALVE WITH TS,SEE
DRAWING F-301
CONN. 6" FIRE
MAIN DN
FIRE HOSE VALVE
IN CABINET
FOR CONTINUATION
SEE DWG F-103C
EXIST. 6"COMB. FSP/SP
RISER TO REMAIN
EXIST. SPRINKLER
CONTROL VALVE TO REMAIN
FIRE HOSE VALVE
IN CABINET, SEE DWG. F-301
2"DRAIN
FSP
F F F
F
F
F
F
6"
6"6"
FSP
S P
S P
FOR CONTINUATION SEE DWG F-103E
F O R C O N T
IN
U A T
IO
N S E E D W G F -1 C
F O R C O N T
IN
U A T
IO
N S E E D W G F -1 C
FOR CONTINUATION SEE DWG F-103C
L
OH-2
OH-2
OH-2
OH-2
OH-1
OH-1
OH-1
OH-1
L
L
L
L
L
L
L
L
MOST REMOTE AREA OF
HYDRAULIC CALCULATIONS,
ORDINARY HAZARD GROUP I,
3000 SQ. FT., 0.15 DENSITY
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
2"
6"
4"
4"
2 1/2"
4" SP
1" UP & DN
GENERAL NOTES:
CODED NOTES:
7. SPRINKLER SYSTEMS SHALL BE HYDRAULICALLY CALCULATED. EACH SYSTEM SHALL
BE CALCULATED TO PROVIDE 10 PSI SAFETY FACTOR.
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
1. FOR SYMBOLS, LEGEND AND ABREVIATIONS SEE DRAWING F-001
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
2. EACH FLOOR WILL BE PROVIDED WITH COMBINATION CLASS I FIRE STANDPIPE SYSTEM
AND/OR SPRINKLER CONTROL VALVE ASSEMBLY.
3. OCCUPANCY CLASSIFICATION: LIGHT HAZARD:CLASSROOMS, OFFICE SPACES,
LOBBIES, CORRIDORS, TOILETS, ETC.
4. OCCUPANCY CLASSIFICATION: ORDINARY GROUP I HAZARD: ALL MECHANICAL AREAS,
INCLUDING BOILERS & PLUMBING ROOMS, STORAGE ROOMS, DATA CENTER,
COMMUNICATION & ELECTRICAL ROOMS, JANITOR CLOSET, RESEARCH ROOMS, ETC.
6. SPRINKLER HEAD COVERAGE: MAXIMUM COVERAGE PER SPRINKLER HEAD SHALL BE
BASED ON 225 SQ. FT.FOR LIGHT HAZARD OCCUPANCY AND 130 SQ. FT. FOR ORDINARY
HAZARD.
8. DESIGN SHALL BE BASED ON 3000 SQ. FT.- DESIGN AREA DEDUCTION SHALL BE
PERMITTED PER NFPA-13 FOR THE LIGHT HAZARD OCCUPANCY.
9. SPRINKLER SYSTEM CALCULATIONS SHALL INCLUDE BUILDING DOMESTIC WATER
DEMANDS.
2. ALL SPRINKLER HEADS SHALL BE ORDINARY TEMPERATURE RATING (155 F)
5. PROVIDE CABINET WITH SPARE SPRINKLER HEADS OF EACH TYPE AND TEMPERATURE.
6. ADD 30% OF REMOTE AREA FOR DRY SPRINKLER SYSTEM.
7. EACH BUILDING WILL BE FULLY SPRINKLERED AND PROVIDED WITH FIRE STANDPIPE
SYSTEMS.
8. CONTRACTOR TO PROVIDE UPDATED FLOW TEST PRIOR TO STARTING SYSTEM
DESIGN.
9. PROVIDE AT NO EXTRA COST ALL ADDITIONAL PIPING AND FITTINGS REQUIRED TO
OFFSET SYSTEM TO AVOID STRUCTUTAL, ARCHITECTURAL, MECHANICAL AND
ELECTRICAL INTERFERENCES WHETHER INDICATED OR NOT, BEFORE INSTALLING
WORK.
10. ALL PIPING SHALL RUN CLOSE TO BEAMS, WALLS AND SLABS, CONCEALED ABOVE
HUNG CEILING AND WITHIN FURRED SPACES.
11. THE SPRINKLER SYSTEM IS AN AUTOMATIC WET PIPE TYPE. THE AUTOMATIC WATER
SOURCE IS A FIRE PUMP TAKIN SUCTION FROM DIRECT CONNECTION TO THE FIRE
MAIN AND THE AUXILIARY WATER SOURCES ARE 4" STORZ FOR FIRE DEPARTMENT
CONNECTION.
12. CONTRACTOR SHALL COORDINATE ALL WORK INVOLVED IN SPACE CONDITIONS
BEFORE PROCEEDING.
13. INSTALL SPRINKLER HEADS ABOVE AND BELOW DUCTS 4'-0" WIDE AND LARGER.
10. SPRINKLER HEADS LOCATED CLOSE TO THE HEATER, STEAM PIPING OR OTHER HEAT
SOURCE SHALL BE TEMPERATURE RATING AS REQUIRED PER NFPA-13.
3. ALL VALVES IN FIRE PROTECTION SYSTEMS SHALL BE PAINTED RED BY
MANUFACTURER.
4. INSTALL CONTROL VALVES LESS THAN 7'-0"A.F.F., WHERE POSSIBLE. WHERE CONTROL
VALVES ARE INSTALLED AT OR ABOVE 7'-0" A.F.F., INSTALL STEEL LADDER.
COORDINATE REQUIREMENTS OF STEEL LADDER WITH ARCHITECTURAL PLANS AND
SPECS.
11. WEST POINT FIRE PROTECTION SYSTEMS SHALL BE BRACED PER THE SEISMIC ZONE
AND CALCULATIONS SHALL BE SUBMITTED FOR VERIFICATION .
12. INSTALL WIRE CAGE ON SPRINKLER HEADS INSTALLED BELOW 7'-0".
13. TEST FIRE PROTECTION SYSTEMS AS REQUIRED PER NFPA.
14. IN LIGHT HAZARD OCCUPANCY SPRINKLER HEADS SHALL BE QUICK RESPONCE WITH A
K FACTOR OF 5.6.
15. COMPLY WITH THE ARMY CORPS OF ENGINEERING MANUAL EM-385-1-1, SAFETY AND
HEALTH REQUIREMENTS MANUAL AND NFPA-241, SAFEGUARDING CONSTRUCTION,
ALTERATION AND DEMOLITION OPERATIONS AND USMA WEST POINT'S FIRE
REGULATIONS.
5. OCCUPANCY CLASSIFICATION: ORDINARY GROUP II HAZARD: MODERN PHYSICS
WORKROOM, LAB'S, MACHINE & WOOD SHOPS, ETC.
SHEET
REFERENCE
NUMBER
SHEET OF
D E S
IG
N E D B Y
D W N B Y
C H K B Y
S U B M
IT
T E D B Y
D A T E
S O L
IC
IT
A T
IO
N N O
C O N T R A C T N O
F
IL
E N A M E
P L O T T E D B Y
S
IZ
E
P L O T D A T E
D A T E
D E S C R
IP
T
IO
N
M A R K
A P P R
US ARMY CORPS
OF ENGINEERS
NEW YORK DISTRICT
1 2 3 4 5
D
C
B
A
U .S A R M Y E N G
IN
E E R D
IS
T R
IC
T
N E W Y O R K h tt p \w w w .n a n .u s a c e .a rm y .m il a rc h it e c ts e n g in e e rs p la n n e rs
W
E S T N A T
IO
N W
ID
E B L V D
C O L U M B U S O H
IO
.4 .4 f a x .4 .0 h tt p /w w w .u rs c o rp .c o m
S C
IE
N C E C E N T E R
(F Y -B L D G
U N
IT
E D S T A T E S M
IL
IT
A R Y A C A D E M Y
W E S T P O
IN
T N Y
A R C H D
P A R K A V E N U E S O U T H
N E W Y O R K N Y -1
.7 .4 f a x .5 .5 w w w .s tv in c .c o m
W D S -1 -D -0
/1 /2 :1 :4 A M
F-103B
F
IR
S T F L O O R P L A N A R E A B
F
IR
E P R O T E C T
IO
N
IR N
J G
L M
A P R
IL
PLAN
NORTH
0 4 8 162
SCALE: 1/8" = 1'-0"
FIRST FLOOR PLAN -
D
C
E
B1312.7 B12 B11.2 B11 B9.8 B9 B8.2 B8
BU
BT
BS
BR.7
BQ.5
BQ
BP
BN
BM
BR
BR.8
BS.8
BV
B1B7 B6 B5 B4 B3 B2
SPRINKLER CONTROL
VALVE, SEE DWG. F-301
6" COMBINED FSP/SP
UP
FIRE HOSE VALVE
IN CABINET, SEE DWG. F-301
RISER CONTROL VALVE
WITH TAMPER SWITCH
6"
FOR CONTINUATION SEE F-103B
6" FSP
UP/DOWN
FSP
FIRE HOSE
VALVE
IN CABINET
FSP
141 SF
CORRIDOR
C-1C4
79 SF
STAIR C2
C-1S2
124 SF
COMM
C-105
199 SF
ELEC
C-106
3484 SF
QUANT
CHEM/PHYS CHEM
C-107
547 SF
PREP/ STOR
C-108
295 SF
INSTR BREAK RM
C-104
15 SF
Space
C-B49
802 SF
PHYSICS
WORKRM
C-102
622 SF
PHYSICS
CLASSRM
C-103
53 SF
VESTIBULE
C-113
578 SF
PREP/ STOR
C-110
4140 SF
GEN & ADVNCD
CHEM
C-109
619 SF
CORRIDOR
C-1C1
429 SF
CORRIDOR
C-1C3
529 SF
STAIR D2
D-1S2
112 SF
VESTIBULE
D-111
657 SF
NUC ENG
CLASSRM
C-101
RISER CONTROL VALVE W/TS
S P
6" F
F
F4 S P
F O R C O N T
IN
U A T
IO
N S E E D W G F -1 B
F O R C O N T
IN
U A T
IO
N S E E D W G F -1 B
FOR CONTINUATION SEE F-103B
OH-2
L
OH-1
L
L
L
L
L
L
L
L
L
OH-1
OH-1OH-1
L
L
L
OH-2
OH-2
S P K R C R O S S M A
IN
4" 4"
S P K R C R O S S M A
IN
F O R C O N T
IN
U A T
IO
N S E E D W G F -1 E
6" SP
SP SP
FOR CONTINUATION SEE DWG F-103D
GENERAL NOTES:
CODED NOTES:
7. SPRINKLER SYSTEMS SHALL BE HYDRAULICALLY CALCULATED. EACH SYSTEM SHALL
BE CALCULATED TO PROVIDE 10 PSI SAFETY FACTOR.
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
1. FOR SYMBOLS, LEGEND AND ABREVIATIONS SEE DRAWING F-001
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
2. EACH FLOOR WILL BE PROVIDED WITH COMBINATION CLASS I FIRE STANDPIPE SYSTEM
AND/OR SPRINKLER CONTROL VALVE ASSEMBLY.
3. OCCUPANCY CLASSIFICATION: LIGHT HAZARD:CLASSROOMS, OFFICE SPACES,
LOBBIES, CORRIDORS, TOILETS, ETC.
4. OCCUPANCY CLASSIFICATION: ORDINARY GROUP I HAZARD: ALL MECHANICAL AREAS,
INCLUDING BOILERS & PLUMBING ROOMS, STORAGE ROOMS, DATA CENTER,
COMMUNICATION & ELECTRICAL ROOMS, JANITOR CLOSET, RESEARCH ROOMS, ETC.
6. SPRINKLER HEAD COVERAGE: MAXIMUM COVERAGE PER SPRINKLER HEAD SHALL BE
BASED ON 225 SQ. FT.FOR LIGHT HAZARD OCCUPANCY AND 130 SQ. FT. FOR ORDINARY
HAZARD.
8. DESIGN SHALL BE BASED ON 3000 SQ. FT.- DESIGN AREA DEDUCTION SHALL BE
PERMITTED PER NFPA-13 FOR THE LIGTH HAZARD OCCUPANCY.
9. SPRINKLER SYSTEM CALCULATIONS SHALL INCLUDE BUILDING DOMESTIC WATER
DEMANDS.
2. ALL SPRINKLER HEADS SHALL BE ORDINARY TEMPERATURE RATING (155 F)
5. PROVIDE CABINET WITH SPARE SPRINKLER HEADS OF EACH TYPE AND TEMPERATURE.
6. ADD 30% OF REMOTE AREA FOR DRY SPRINKLER SYSTEM.
7. EACH BUILDING WILL BE FULLY SPRINKLERED AND PROVIDED WITH FIRE STANDPIPE
SYSTEMS.
8. CONTRACTOR TO PROVIDE UPDATED FLOW TEST PRIOR TO STARTING SYSTEM
DESIGN.
9. PROVIDE AT NO EXTRA COST ALL ADDITIONAL PIPING AND FITTINGS REQUIRED TO
OFFSET SYSTEM TO AVOID STRUCTUTAL, ARCHITECTURAL, MECHANICAL AND
ELECTRICAL INTERFERENCES WHETHER INDICATED OR NOT, BEFORE INSTALLING
WORK.
10. ALL PIPING SHALL RUN CLOSE TO BEAMS, WALLS AND SLABS, CONCEALED ABOVE
HUNG CEILING AND WITHIN FURRED SPACES.
11. THE SPRINKLER SYSTEM IS AN AUTOMATIC WET PIPE TYPE. THE AUTOMATIC WATER
SOURCE IS A FIRE PUMP TAKING SUCTION FROM DIRECT CONNECTION TO THE FIRE
MAIN AND THE AUXILIARY WATER SOURCES ARE 4" STORZ FOR FIRE DEPARTMENT
CONNECTION.
12. CONTRACTOR SHALL COORDINATE ALL WORK INVOLVED IN SPACE CONDITIONS
BEFORE PROCEEDING.
13. INSTALL SPRINKLER HEADS ABOVE AND BELOW DUCTS 4'-0" WIDE AND LARGER.
10. SPRINKLER HEADS LOCATED CLOSE TO THE HEATER, STEAM PIPING OR OTHER HEAT
SOURCE SHALL BE TEMPERATURE RATING AS REQUIRED PER NFPA-13.
3. ALL VALVES IN FIRE PROTECTION SYSTEMS SHALL BE PAINTED RED BY
MANUFACTURER.
4. INSTALL CONTROL VALVES LESS THAN 7'-0" A.F.F, WHERE POSSIBLE. WHERE CONTROL
VALVES ARE INSTALLED AT OR ABOVE 7'-0" A.F.F., INSTALL STEEL LADDER.
COORDINATE REQUIREMNETS OF STEEL LADDER WITH ARCHITECTURAL PLANS AND
SPECS.
11. WEST POINT FIRE PROTECTION SYSTEMS SHALL BE BRACED PER THE SEISMIC ZONE
AND CALCULATIONS SHALL BE SUBMITTED FOR VERIFICATION .
12. INSTALL WIRE CAGE ON SPRINKLER HEADS INSTALLED BELOW 7'-0".
13. TEST FIRE PROTECTION SYSTEMS AS REQUIRED PER NFPA.
14. IN LIGHT HAZARD OCCUPANCY SPRINKLER HEADS SHALL BE QUICK RESPONCE WITH A
K FACTOR OF 5.6.
15. COMPLY WITH THE ARMY CORPS OF ENGINEERING MANUAL EM-385-1-1, SAFETY AND
HEALTH REQUIREMENTS MANUAL AND NFPA-241, SAFEGUARDING CONSTRUCTION,
ALTERATION AND DEMOLITION OPERATIONS AND USMA WEST POINT'S FIRE
REGULATIONS.
5. OCCUPANCY CLASSIFICATION: ORDINARY GROUP II HAZARD: MODERN PHYSICS
WORKROOM, LAB'S, MACHINE & WOOD SHOPS, ETC.
SHEET
REFERENCE
NUMBER
SHEET OF
D E S
IG
N E D B Y
D W N B Y
C H K B Y
S U B M
IT
T E D B Y
D A T E
S O L
IC
IT
A T
IO
N N O
C O N T R A C T N O
F
IL
E N A M E
P L O T T E D B Y
S
IZ
E
P L O T D A T E
D A T E
D E S C R
IP
T
IO
N
M A R K
A P P R
US ARMY CORPS
OF ENGINEERS
NEW YORK DISTRICT
1 2 3 4 5
D
C
B
A
U .S A R M Y E N G
IN
E E R D
IS
T R
IC
T
N E W Y O R K h tt p \w w w .n a n .u s a c e .a rm y .m il a rc h it e c ts e n g in e e rs p la n n e rs
W
E S T N A T
IO
N W
ID
E B L V D
C O L U M B U S O H
IO
.4 .4 f a x .4 .0 h tt p /w w w .u rs c o rp .c o m
S C
IE
N
C E C
E N
T E R
(F Y -B
L D
G
U N
IT
E D S T A T E S M
IL
IT
A R Y A C A D E M Y
W E S T P O
IN
T N Y
A R C H D
P A R K A V E N U E S O U T H
N E W Y O R K N Y -1
.7 .4 f a x .5 .5 w w w .s tv in c .c o m
W D S -1 -D -0
/1 /2 :4 :2 A M
F-103C
F
IR
S T F L O O R P L A N A R E A C
F
IR
E P R O T E C T
IO
N
IR N
J G
L M
A P R
IL
PLAN
NORTH
0 4 8 162
SCALE: 1/8" = 1'-0"
D
C
E
B1312.7 B12
B11.2
B11.2 B11
B9.8
B9 B8.2 B8
BL
BK
BJ
BH
BG
BF
BE
BD
BC
BB
BA
FIRE HOSE VALVE
IN CABINET, SEE
DWG. F-301
CONN. 6" FIRE MAIN TO
EXIST. 6" MAIN(PHASE 1)
6"
6"
FSP
1005 SF
PHYSICS
WORKRM
D-102
695 SF
PHYSICS
CLASSRM
D-101
105 SF
JAN
D-106
696 SF
PHYSICS
CLASSRM
D-104
53 SF
VESTIBULE
D-112
618 SF
CORRIDOR
D-1C3
391 SF
STAIR D1
D-1S1
180 SF
INTERACTIVE
LEARNING
D-103
448 SF
CORRIDOR
D-1C1
806 SF
PHYSICS
WORKRM
D-110
1258 SF
Space
C-B87
615 SF
PHYSICS
CLASSRM
D-109
4" DN TO FDC
CONTROL VALVE
W/ TAMPER SWITCH
S P
F
F
S P
FOR CONTINUATION SEE DWG F-103C
FOR CONTINUATION
SEE PHASE 1
FOR CONTINUATION SEE
DWG. F-103E
OH-2
L
OH-1
L
L
L
L
L
L
L
OH-2
OH-2
L
L
PHYSICS
WORKRM
D-105
S P K R C R O S S M A
IN
GENERAL NOTES:
CODED NOTES:
7. SPRINKLER SYSTEMS SHALL BE HYDRAULICALLY CALCULATED. EACH SYSTEM SHALL
BE CALCULATED TO PROVIDE 10 PSI SAFETY FACTOR.
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
1. FOR SYMBOLS, LEGEND AND ABREVIATIONS SEE DRAWING F-001
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
2. EACH FLOOR WILL BE PROVIDED WITH COMBINATION CLASS I FIRE STANDPIPE SYSTEM
AND/OR SPRINKLER CONTROL VALVE ASSEMBLY.
3. OCCUPANCY CLASSIFICATION: LIGHT HAZARD:CLASSROOMS, OFFICE SPACES,
LOBBIES, CORRIDORS, TOILETS, ETC.
4. OCCUPANCY CLASSIFICATION: ORDINARY GROUP I HAZARD: ALL MECHANICAL AREAS,
INCLUDING BOILERS & PLUMBING ROOMS, STORAGE ROOMS, DATA CENTER,
COMMUNICATION & ELECTRICAL ROOMS, JANITOR CLOSET, RESEARCH ROOMS, ETC.
6. SPRINKLER HEAD COVERAGE: MAXIMUM COVERAGE PER SPRINKLER HEAD SHALL BE
BASED ON 225 SQ. FT.FOR LIGHT HAZARD OCCUPANCY AND 130 SQ. FT. FOR ORDINARY
HAZARD.
8. DESIGN SHALL BE BASED ON 3000 SQ. FT.- DESIGN AREA DEDUCTION SHALL BE
PERMITTED PER NFPA-13 FOR THE LIGTH HAZARD OCCUPANCY.
9. SPRINKLER SYSTEM CALCULATIONS SHALL INCLUDE BUILDING DOMESTIC WATER
DEMANDS.
2. ALL SPRINKLER HEADS SHALL BE ORDINARY TEMPERATURE RATING (155 F)
5. PROVIDE CABINET WITH SPARE SPRINKLER HEADS OF EACH TYPE AND TEMPERATURE.
6. ADD 30% OF REMOTE AREA FOR DRY SPRINKLER SYSTEM.
7. EACH BUILDING WILL BE FULLY SPRINKLERED AND PROVIDED WITH FIRE STANDPIPE
SYSTEMS.
8. CONTRACTOR TO PROVIDE UPDATED FLOW TEST PRIOR TO STARTING SYSTEM
DESIGN.
9. PROVIDE AT NO EXTRA COST ALL ADDITIONAL PIPING AND FITTINGS REQUIRED TO
OFFSET SYSTEM TO AVOID STRUCTUTAL, ARCHITECTURAL, MECHANICAL AND
ELECTRICAL INTERFERENCES WHETHER INDICATED OR NOT, BEFORE INSTALLING
WORK.
10. ALL PIPING SHALL RUN CLOSE TO BEAMS, WALLS AND SLABS, CONCEALED ABOVE
HUNG CEILING AND WITHIN FURRED SPACES.
11. THE SPRINKLER SYSTEM IS AN AUTOMATIC WET PIPE TYPE. THE AUTOMATIC WATER
SOURCE IS A FIRE PUMP TAKING SUCTION FROM DIRECT CONNECTION TO THE FIRE
MAIN AND THE AUXILIARY WATER SOURCES ARE 4" STORZ FOR FIRE DEPARTMENT
CONNECTION.
12. CONTRACTOR SHALL COORDINATE ALL WORK INVOLVED IN SPACE CONDITIONS
BEFORE PROCEEDING.
13. INSTALL SPRINKLER HEADS ABOVE AND BELOW DUCTS 4'-0" WIDE AND LARGER.
10. SPRINKLER HEADS LOCATED CLOSE TO THE HEATER, STEAM PIPING OR OTHER HEAT
SOURCE SHALL BE TEMPERATURE RATING AS REQUIRED PER NFPA-13.
3. ALL VALVES IN FIRE PROTECTION SYSTEMS SHALL BE PAINTED RED BY
MANUFACTURER.
4. INSTALL CONTROL VALVES LESS THAN 7'-0" A.F.F, WHERE POSSIBLE. WHERE CONTROL
VALVES ARE INSTALLED AT OR ABOVE 7'-0" A.F.F., INSTALL STEEL LADDER.
COORDINATE REQUIREMNETS OF STEEL LADDER WITH ARCHITECTURAL PLANS AND
SPECS.
11. WEST POINT FIRE PROTECTION SYSTEMS SHALL BE BRACED PER THE SEISMIC ZONE
AND CALCULATIONS SHALL BE SUBMITTED FOR VERIFICATION .
12. INSTALL WIRE CAGE ON SPRINKLER HEADS INSTALLED BELOW 7'-0".
13. TEST FIRE PROTECTION SYSTEMS AS REQUIRED PER NFPA.
14. IN LIGHT HAZARD OCCUPANCY SPRINKLER HEADS SHALL BE QUICK RESPONCE WITH A
K FACTOR OF 5.6.
15. COMPLY WITH THE ARMY CORPS OF ENGINEERING MANUAL EM-385-1-1, SAFETY AND
HEALTH REQUIREMENTS MANUAL AND NFPA-241, SAFEGUARDING CONSTRUCTION,
ALTERATION AND DEMOLITION OPERATIONS AND USMA WEST POINT'S FIRE
REGULATIONS.
5. OCCUPANCY CLASSIFICATION: ORDINARY GROUP II HAZARD: MODERN PHYSICS
WORKROOM, LAB'S, MACHINE & WOOD SHOPS, ETC.
SHEET
REFERENCE
NUMBER
SHEET OF
D E S
IG
N E D B Y
D W N B Y
C H K B Y
S U B M
IT
T E D B Y
D A T E
S O L
IC
IT
A T
IO
N N O
C O N T R A C T N O
F
IL
E N A M E
P L O T T E D B Y
S
IZ
E
P L O T D A T E
D A T E
D E S C R
IP
T
IO
N
M A R K
A P P R
US ARMY CORPS
OF ENGINEERS
NEW YORK DISTRICT
1 2 3 4 5
D
C
B
A
U .S A R M Y E N G
IN
E E R D
IS
T R
IC
T
N E W Y O R K h tt p \w w w .n a n .u s a c e .a rm y .m il a rc h it e c ts e n g in e e rs p la n n e rs
W
E S T N A T
IO
N W
ID
E B L V D
C O L U M B U S O H
IO
.4 .4 f a x .4 .0 h tt p /w w w .u rs c o rp .c o m
S C
IE
N
C E C
E N
T E R
(F Y -B
L D
G
U N
IT
E D S T A T E S M
IL
IT
A R Y A C A D E M Y
W E S T P O
IN
T N Y
A R C H D
P A R K A V E N U E S O U T H
N E W Y O R K N Y -1
.7 .4 f a x .5 .5 w w w .s tv in c .c o m
W D S -1 -D -0
/1 /2 :4 :2 A M
F-103D
F
IR
S T F L O O R P L A N A R E A D
F
IR
E P R O T E C T
IO
N
IR N
J G
L M
A P R
IL
PLAN
NORTH
0 4 8 162
SCALE: 1/8" = 1'-0"
OS
OS
OS
OS
OS
OS
OS
OS
OS OS
OS
OS
OS
OS
OS
OS
A
B
D
C
E
CA
CC
CD
CF
CG
CB
CH
C1C2C4 C1.9C4.1 C3
SUPP T-1
E-107-1
MEN
E-105
OFC/WRK/MAIL/RES
E-109
CONF RM/TECH
JOURN
E-119
SR FACULTY
E-112
SR FACULTY
E-111
SR FACULTY
E-110
SR FACULTY
E-113
FACULTY
E-117
FACULTY
E-116
FILES
E-102
CORRIDOR
E-1C2
CORRIDOR
E-1C1
CORRIDOR
E-1C4
FACULTY
E-118
OFFICE
E-103
L
L
L
L
L
L
L
L
L
L
L
L
L
OH-1
OH-1
L
OH-1
MATCHLINE. FOR CONTINUATION SEE DWG. F-103B
M A T C H L
IN
E F O R C O N T
IN
U A T
IO
N S E E D W G F -1 D
M A T C H L
IN
E F O R C O N T
IN
U A T
IO
N S E E D W G F -1 C
1/2" 1/2"
1/2" 1/2"
1/2"
GENERAL NOTES:
CODED NOTES:
7. SPRINKLER SYSTEMS SHALL BE HYDRAULICALLY CALCULATED. EACH SYSTEM SHALL
BE CALCULATED TO PROVIDE 10 PSI SAFETY FACTOR.
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
1. FOR SYMBOLS, LEGEND AND ABREVIATIONS SEE DRAWING F-001
1. FIRE PROTECTION DESIGN SHALL BE BASED ON THE REQUIREMENTS OF UFC3-600-01
AND NFPA-13 &14.
2. EACH FLOOR WILL BE PROVIDED WITH COMBINATION CLASS I FIRE STANDPIPE SYSTEM
AND/OR SPRINKLER CONTROL VALVE ASSEMBLY.
3. OCCUPANCY CLASSIFICATION: LIGHT HAZARD:CLASSROOMS, OFFICE SPACES,
LOBBIES, CORRIDORS, TOILETS, ETC.
4. OCCUPANCY CLASSIFICATION:…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .