This is a summary of an amendment to a solicitation for environmental services. The amendment modifies the bid/price schedules for years one through five and a six-month extension by correcting the numbering. It also modifies the table of contents and attachments to include revised forms, a sample problem, and questions and answers. Offerors are invited to provide fixed unit prices and fully burdened labor rates for 57 labor categories to support environmental cleanup services for the U.S. Army Corps of Engineers North Atlantic Division area of responsibility. The services include engineering, studies, removal actions, remedial design and implementation, operation and maintenance, and monitoring. The multiple-award task order contract will have a five-year ordering period and $230 million total estimated value, with a minimum $5,000 guarantee per contract. Up to ten contracts may be awarded, with six reserved for small businesses.

Section B corrected.

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Environmental Services (MAES) 2017, newest first.
File Type Posted
DR-16-R-0004_Conformed_Copy_with_Amendment_0004.pdf PDF
Attachment_3_Past_Performance_Questionnaire_Template_rev__10-17-16.pdf PDF
Attachment_6_-_MAES_2017_Hypothetical_Sample_Problem_rev_10072016.pdf PDF
Attachment_4_-_Experience_in_Relevant_Projects_Form_rev_10-06-2016.pdf PDF
DR-16-R-0004_Conformed_copy_of_Mod_0003_changes_10-14-16.pdf PDF
DR-16-R-0004__Mod_0003_10-14-16.pdf PDF
Attachment_11 _ProjNet_Questions_and_Answers_10-14-16.pdf PDF
Attachment_3_Past_Performance_Questionnaire_Template_rev__10-5-16.pdf PDF
Attachment_3_Past_Performance_Questionnaire_Template_rev__10-5-16.pdf PDF
Attachment_4_-_Experience_in_Relevant_Projects_Form_rev_10-06-2016.pdf PDF
Attachment_3_Past_Performance_Questionnaire_Template_rev_9-26-16.pdf PDF
Attachment_9_ProjNet_Instruction_9-26-16.docx DOCX document
Attachment_7_Hypothetical_Sample_Problem_Drawing_rev_1_09262016_.pdf PDF
DR-16-R-0004_Conformed_copy_of_Mod_0001_and_0002_9-28-16.pdf PDF
Attachment_8_Hypothetical_Sample_Problem_Bid_Schedule_rev_1_09262016_.pdf PDF
Attachment_6__Hypothetical_Sample_Problem_rev_1_09262016.pdf PDF
Attachement_5_Lobby_form_sflll.pdf PDF
DR-16-R-0004_Mod_0001_9-28-16.pdf PDF
Attachment_4_Experience_in_Relevant_Projects_Form_rev_9-22-16.pdf PDF
DR-16-R-0004_Mod_0002_9-28-16.pdf PDF
Attachment_5_Lobby_Form_Instructions.docx DOCX document
Attachment_10 _Questions_and_Answers_up_to_9-27-16.docx DOCX document
A_DR-16-R-0004_Wage_Rates_15-2383.doc DOC document
A_DR-16-R-0004_Wage_Rates_05-2247_1-5-2016_.doc DOC document
Sample_Technical_Problem.pdf PDF
Experience_in_Relevant_Projects_Form.pdf PDF
Appendix_D_-_Encl_2_Past_Performance_Questionnaire_Template.pdf PDF
B_DR-16-R-0004_RFP_for_MAES_2017_FBO_9-9-16.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This Amendment is issued to correct the numbering on the bid schedules and the blocks 5 and 7 of the PPQ. All other terms and condistions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

U 1 15

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 17-Oct-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DR-16-R-0004

X 9B. DATED (SEE ITEM 11)

09-Sep-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

17-Oct-2016

CODE

USACE, BALTIMORE

10 S. HOWARD STREET

BALTIMORE MD 21201

W912DR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DR-16-R-0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION B - SUPPLIES OR SERVICES AND PRICES

The following have been modified:

BID SCHEDULE FOR FFP AND CPFF

Bid/Price Schedule – Base (Year 1)

ITEM DESCRIPTION

Prime or Subcotractor

P or S

Unburden Labor Rate Fringe

OH

Home

OH

Field G&A

Burden Labor Rates

Burden Labor Rates

0001 Principal $ $ $ $ $ $ $

0002 Program Manager $ $ $ $ $ $ $

0003 Senior Project Manager $ $ $ $ $ $ $

0004 Junior Project Manager $ $ $ $ $ $ $

0005 Senior Environmental Engineer $ $ $ $ $ $ $

0006 Junior Environmental Engineer $ $ $ $ $ $ $

0007 Safety Engineer $ $ $ $ $ $ $

0008 Senior Civil Engineer $ $ $ $ $ $ $

0009 Junior Civil Engineer $ $ $ $ $ $ $

0010 Chemical Engineer $ $ $ $ $ $ $

0011 Geotechnical Engineer $ $ $ $ $ $ $

0012 Construction Manager $ $ $ $ $ $ $

0013 Engineering Technician $ $ $ $ $ $ $

0014 Laborer $ $ $ $ $ $ $

0015 Cost Estimator $ $ $ $ $ $ $

0016 Cost Accountant $ $ $ $ $ $ $

0017 Budget Analyst $ $ $ $ $ $ $

0018 Safety and Health Officer $ $ $ $ $ $ $

Corporate Health and Safety Officer

0020 Certified Industrial Hygienist $ $ $ $ $ $ $

0021 Senior Geologist $ $ $ $ $ $ $

0022 Junior Geologist $ $ $ $ $ $ $

0023 Senior Geophysicist $ $ $ $ $ $ $

0024 Junior Geophysicist $ $ $ $ $ $ $

0025 Senior Scientist $ $ $ $ $ $ $

0026 Junior Scientist $ $ $ $ $ $ $

0027 Senior Hydrogeologist $ $ $ $ $ $ $

0028 Junior Hydrogeologist $ $ $ $ $ $ $

0029 Senior Chemist $ $ $ $ $ $ $

0030 Junior Chemist $ $ $ $ $ $ $

0031 Spec Writer $ $ $ $ $ $ $

0032 Senior Biologist $ $ $ $ $ $ $

0033 Junior Biologist $ $ $ $ $ $ $

0034 Senior Environmental Scientist $ $ $ $ $ $ $

0035 Junior Environmental Scientist $ $ $ $ $ $ $

0036 Certified Health Physicist $ $ $ $ $ $ $

0037 Health Physicist $ $ $ $ $ $ $

0038 Regulatory Specialist $ $ $ $ $ $ $

0039 Site, Safety, and Health Officer $ $ $ $ $ $ $

Senior UXO Supervisor

(SUXOS)

0041 UXO Safety Officer (UXOSO) $ $ $ $ $ $ $

UXO Quality Control Specialist

(UXOQCS)

0043 UXO Technician III $ $ $ $ $ $ $

0044 UXO Technician II $ $ $ $ $ $ $

0045 UXO Technician I $ $ $ $ $ $ $

0046 UXO Sweep Personnel $ $ $ $ $ $ $

0047 UXO Project Manager $ $ $ $ $ $ $

0048 Quality Control Manager $ $ $ $ $ $ $

0049 Illustrator/Draftsperson $ $ $ $ $ $ $

Geographic Information Systems

(GIS)

0051 Technician (General) $ $ $ $ $ $ $

0052 Administrative Assistant $ $ $ $ $ $ $

0053 Clerical $ $ $ $ $ $ $

0054 Senior Risk Assessor $ $ $ $ $ $ $

0055 Junior Risk Assessor $ $ $ $ $ $ $

0056 Surveyor $ $ $ $ $ $ $

0057 Community Relations Specialist $ $ $ $ $ $ $

Rate Markup

Subcontracting Handling Charge Rate

Material, Supplies and Equipment Charge Rate

Transportation Charge Rate % Field Overhead Rate % Home Overhead Rate % G&A Rate %

NOTES:

* Special requirements not listed above will be negotiated on a per task order basis.

*Other Direct Costs (ODC’s) will be negotiated on a per task order basis.

*Contractor Manpower Reporting will be required and negotiated on individual task orders, either as a separate line item or as an element of your overhead costs.

* Fee will be negotiated on a per task order basis and shall not exceed 10% in accordance with FAR 15.404-4

(c) (4)(i).

* Profit will be negotiated on a per task order basis.

*For each labor iscipline, please annotate whether the disciplines provided are the Prime or Subcontractor.

Bid/Price Schedule –Year 2

ITEM DESCRIPTION

Prime or Subcotractor

P or S

Unburden Labor Rate Fringe

OH

Home

OH

Field G&A

Burden Labor Rates

Burden Labor Rates

0001 Principal $ $ $ $ $ $ $

0002 Program Manager $ $ $ $ $ $ $

0003 Senior Project Manager $ $ $ $ $ $ $

0004 Junior Project Manager $ $ $ $ $ $ $

0005 Senior Environmental Engineer $ $ $ $ $ $ $

0006 Junior Environmental Engineer $ $ $ $ $ $ $

0007 Safety Engineer $ $ $ $ $ $ $

0008 Senior Civil Engineer $ $ $ $ $ $ $

0009 Junior Civil Engineer $ $ $ $ $ $ $

0010 Chemical Engineer $ $ $ $ $ $ $

0011 Geotechnical Engineer $ $ $ $ $ $ $

0012 Construction Manager $ $ $ $ $ $ $

0013 Engineering Technician $ $ $ $ $ $ $

0014 Laborer $ $ $ $ $ $ $

0015 Cost Estimator $ $ $ $ $ $ $

0016 Cost Accountant $ $ $ $ $ $ $

0017 Budget Analyst $ $ $ $ $ $ $

0018 Safety and Health Officer $ $ $ $ $ $ $

Corporate Health and Safety Officer

0020 Certified Industrial Hygienist $ $ $ $ $ $ $

0021 Senior Geologist $ $ $ $ $ $ $

0022 Junior Geologist $ $ $ $ $ $ $

0023 Senior Geophysicist $ $ $ $ $ $ $

0024 Junior Geophysicist $ $ $ $ $ $ $

0025 Senior Scientist $ $ $ $ $ $ $

0026 Junior Scientist $ $ $ $ $ $ $

0027 Senior Hydrogeologist $ $ $ $ $ $ $

0028 Junior Hydrogeologist $ $ $ $ $ $ $

0029 Senior Chemist $ $ $ $ $ $ $

0030 Junior Chemist $ $ $ $ $ $ $

0031 Spec Writer $ $ $ $ $ $ $

0032 Senior Biologist $ $ $ $ $ $ $

0033 Junior Biologist $ $ $ $ $ $ $

0034 Senior Environmental Scientist $ $ $ $ $ $ $

0035 Junior Environmental Scientist $ $ $ $ $ $ $

0036 Certified Health Physicist $ $ $ $ $ $ $

0037 Health Physicist $ $ $ $ $ $ $

0038 Regulatory Specialist $ $ $ $ $ $ $

0039 Site, Safety, and Health Officer $ $ $ $ $ $ $

0040 Senior UXO Supervisor $ $ $ $ $ $ $

(SUXOS)

0041 UXO Safety Officer (UXOSO) $ $ $ $ $ $ $

UXO Quality Control Specialist

(UXOQCS)

0043 UXO Technician III $ $ $ $ $ $ $

0044 UXO Technician II $ $ $ $ $ $ $

0045 UXO Technician I $ $ $ $ $ $ $

0046 UXO Sweep Personnel $ $ $ $ $ $ $

0047 UXO Project Manager $ $ $ $ $ $ $

0048 Quality Control Manager $ $ $ $ $ $ $

0049 Illustrator/Draftsperson $ $ $ $ $ $ $

Geographic Information Systems (GIS)

0051 Technician (General) $ $ $ $ $ $ $

0052 Administrative Assistant $ $ $ $ $ $ $

0053 Clerical $ $ $ $ $ $ $

0054 Senior Risk Assessor $ $ $ $ $ $ $

0055 Junior Risk Assessor $ $ $ $ $ $ $

Transportation Charge Rate % Field Overhead Rate % Home Overhead Rate %

Escalation Rate(s)** %

*Other Direct Costs (ODC’s) will be negotiated on a per task order basis.

*Contractor Manpower Reporting will be required and negotiated on individual task orders, either as a separate line item or as an element of your overhead costs.

* Fee will be negotiated on a per task order basis and shall not exceed 10% in accordance with FAR 15.404-4

(c) (4)(i).

* Profit will be negotiated on a per task order basis.

*For each labor iscipline, please annotate whether the disciplines provided are the Prime or Subcontractor.

**Escalation Rate – Contractor shall indicate what escalation rate was incorporated into their proposal for this table (Year 2).

Bid/Price Schedule –Year 3

Prime or Subcotractor

P or S

Unburden Labor Rate Fringe

OH

Home

OH

Field G&A

Burden Labor Rates

Burden Labor Rates

0001 Principal $ $ $ $ $ $ $

0002 Program Manager $ $ $ $ $ $ $

0003 Senior Project Manager $ $ $ $ $ $ $

0004 Junior Project Manager $ $ $ $ $ $ $

0005 Senior Environmental Engineer $ $ $ $ $ $ $

0006 Junior Environmental Engineer $ $ $ $ $ $ $

0007 Safety Engineer $ $ $ $ $ $ $

0008 Senior Civil Engineer $ $ $ $ $ $ $

0009 Junior Civil Engineer $ $ $ $ $ $ $

0010 Chemical Engineer $ $ $ $ $ $ $

0011 Geotechnical Engineer $ $ $ $ $ $ $

0012 Construction Manager $ $ $ $ $ $ $

0013 Engineering Technician $ $ $ $ $ $ $

0014 Laborer $ $ $ $ $ $ $

0015 Cost Estimator $ $ $ $ $ $ $

0016 Cost Accountant $ $ $ $ $ $ $

0017 Budget Analyst $ $ $ $ $ $ $

0018 Safety and Health Officer $ $ $ $ $ $ $

Corporate Health and Safety Officer

0020 Certified Industrial Hygienist $ $ $ $ $ $ $

0021 Senior Geologist $ $ $ $ $ $ $

0022 Junior Geologist $ $ $ $ $ $ $

0023 Senior Geophysicist $ $ $ $ $ $ $

0024 Junior Geophysicist $ $ $ $ $ $ $

0025 Senior Scientist $ $ $ $ $ $ $

0026 Junior Scientist $ $ $ $ $ $ $

0027 Senior Hydrogeologist $ $ $ $ $ $ $

0028 Junior Hydrogeologist $ $ $ $ $ $ $

0029 Senior Chemist $ $ $ $ $ $ $

0030 Junior Chemist $ $ $ $ $ $ $

0031 Spec Writer $ $ $ $ $ $ $

0032 Senior Biologist $ $ $ $ $ $ $

0033 Junior Biologist $ $ $ $ $ $ $

0034 Senior Environmental Scientist $ $ $ $ $ $ $

0035 Junior Environmental Scientist $ $ $ $ $ $ $

0036 Certified Health Physicist $ $ $ $ $ $ $

0037 Health Physicist $ $ $ $ $ $ $

0038 Regulatory Specialist $ $ $ $ $ $ $

UXO Quality Control Specialist

(UXOQCS)

0043 UXO Technician III $ $ $ $ $ $ $

0044 UXO Technician II $ $ $ $ $ $ $

0045 UXO Technician I $ $ $ $ $ $ $

0046 UXO Sweep Personnel $ $ $ $ $ $ $

0047 UXO Project Manager $ $ $ $ $ $ $

0048 Quality Control Manager $ $ $ $ $ $ $

0049 Illustrator/Draftsperson $ $ $ $ $ $ $

Geographic Information Systems

(GIS)

0051 Technician (General) $ $ $ $ $ $ $

0052 Administrative Assistant $ $ $ $ $ $ $

0053 Clerical $ $ $ $ $ $ $

0054 Senior Risk Assessor $ $ $ $ $ $ $

0055 Junior Risk Assessor $ $ $ $ $ $ $

Transportation Charge Rate % Field Overhead Rate % Home Overhead Rate %

*Other Direct Costs (ODC’s) will be negotiated on a per task order basis.

*Contractor Manpower Reporting will be required and negotiated on individual task orders, either as a separate line item or as an element of your overhead costs.

* Fee will be negotiated on a per task order basis and shall not exceed 10% in accordance with FAR 15.404-4

(c) (4)(i).

* Profit will be negotiated on a per task order basis.

*For each labor iscipline, please annotate whether the disciplines provided are the Prime or Subcontractor.

proposal for this table (Year 3).

Bid/Price Schedule –Year 4

Prime or Subcotractor

P or S

Unburden Labor Rate Fringe

OH

Home

OH

Field G&A

Burden Labor Rates

Burden Labor Rates

0001 Principal $ $ $ $ $ $ $

0002 Program Manager $ $ $ $ $ $ $

0003 Senior Project Manager $ $ $ $ $ $ $

0004 Junior Project Manager $ $ $ $ $ $ $

0005 Senior Environmental Engineer $ $ $ $ $ $ $

0006 Junior Environmental Engineer $ $ $ $ $ $ $

0007 Safety Engineer $ $ $ $ $ $ $

0008 Senior Civil Engineer $ $ $ $ $ $ $

0009 Junior Civil Engineer $ $ $ $ $ $ $

0010 Chemical Engineer $ $ $ $ $ $ $

0011 Geotechnical Engineer $ $ $ $ $ $ $

0012 Construction Manager $ $ $ $ $ $ $

0013 Engineering Technician $ $ $ $ $ $ $

0014 Laborer $ $ $ $ $ $ $

0015 Cost Estimator $ $ $ $ $ $ $

0016 Cost Accountant $ $ $ $ $ $ $

0017 Budget Analyst $ $ $ $ $ $ $

0018 Safety and Health Officer $ $ $ $ $ $ $

Corporate Health and Safety Officer

0020 Certified Industrial Hygienist $ $ $ $ $ $ $

0021 Senior Geologist $ $ $ $ $ $ $

0022 Junior Geologist $ $ $ $ $ $ $

0023 Senior Geophysicist $ $ $ $ $ $ $

0024 Junior Geophysicist $ $ $ $ $ $ $

0025 Senior Scientist $ $ $ $ $ $ $

0026 Junior Scientist $ $ $ $ $ $ $

0027 Senior Hydrogeologist $ $ $ $ $ $ $

0028 Junior Hydrogeologist $ $ $ $ $ $ $

0029 Senior Chemist $ $ $ $ $ $ $

0030 Junior Chemist $ $ $ $ $ $ $

0031 Spec Writer $ $ $ $ $ $ $

0032 Senior Biologist $ $ $ $ $ $ $

0033 Junior Biologist $ $ $ $ $ $ $

0034 Senior Environmental Scientist $ $ $ $ $ $ $

0035 Junior Environmental Scientist $ $ $ $ $ $ $

0036 Certified Health Physicist $ $ $ $ $ $ $

0037 Health Physicist $ $ $ $ $ $ $

0038 Regulatory Specialist $ $ $ $ $ $ $

UXO Quality Control Specialist

(UXOQCS)

0043 UXO Technician III $ $ $ $ $ $ $

0044 UXO Technician II $ $ $ $ $ $ $

0045 UXO Technician I $ $ $ $ $ $ $

0046 UXO Sweep Personnel $ $ $ $ $ $ $

0047 UXO Project Manager $ $ $ $ $ $ $

0048 Quality Control Manager $ $ $ $ $ $ $

0049 Illustrator/Draftsperson $ $ $ $ $ $ $

Geographic Information Systems

(GIS)

0051 Technician (General) $ $ $ $ $ $ $

0052 Administrative Assistant $ $ $ $ $ $ $

0053 Clerical $ $ $ $ $ $ $

0054 Senior Risk Assessor $ $ $ $ $ $ $

0055 Junior Risk Assessor $ $ $ $ $ $ $

Transportation Charge Rate % Field Overhead Rate % Home Overhead Rate %

*Other Direct Costs (ODC’s) will be negotiated on a per task order basis.

*Contractor Manpower Reporting will be required and negotiated on individual task orders, either as a separate line item or as an element of your overhead costs.

* Fee will be negotiated on a per task order basis and shall not exceed 10% in accordance with FAR 15.404-4

(c) (4)(i).

* Profit will be negotiated on a per task order basis.

*For each labor iscipline, please annotate whether the disciplines provided are the Prime or Subcontractor.

proposal for this table (Year 4).

Bid/Price Schedule –Year 5

Prime or Subcotractor

P or S

Unburden Labor Rate Fringe

OH

Home

OH

Field G&A

Burden Labor Rates

Burden Labor Rates

0001 Principal $ $ $ $ $ $ $

0002 Program Manager $ $ $ $ $ $ $

0003 Senior Project Manager $ $ $ $ $ $ $

0004 Junior Project Manager $ $ $ $ $ $ $

0005 Senior Environmental Engineer $ $ $ $ $ $ $

0006 Junior Environmental Engineer $ $ $ $ $ $ $

0007 Safety Engineer $ $ $ $ $ $ $

0008 Senior Civil Engineer $ $ $ $ $ $ $

0009 Junior Civil Engineer $ $ $ $ $ $ $

0010 Chemical Engineer $ $ $ $ $ $ $

0011 Geotechnical Engineer $ $ $ $ $ $ $

0012 Construction Manager $ $ $ $ $ $ $

0013 Engineering Technician $ $ $ $ $ $ $

0014 Laborer $ $ $ $ $ $ $

0015 Cost Estimator $ $ $ $ $ $ $

0016 Cost Accountant $ $ $ $ $ $ $

0017 Budget Analyst $ $ $ $ $ $ $

0018 Safety and Health Officer $ $ $ $ $ $ $

Corporate Health and Safety Officer

0020 Certified Industrial Hygienist $ $ $ $ $ $ $

0021 Senior Geologist $ $ $ $ $ $ $

0022 Junior Geologist $ $ $ $ $ $ $

0023 Senior Geophysicist $ $ $ $ $ $ $

0024 Junior Geophysicist $ $ $ $ $ $ $

0025 Senior Scientist $ $ $ $ $ $ $

0026 Junior Scientist $ $ $ $ $ $ $

0027 Senior Hydrogeologist $ $ $ $ $ $ $

0028 Junior Hydrogeologist $ $ $ $ $ $ $

0029 Senior Chemist $ $ $ $ $ $ $

0030 Junior Chemist $ $ $ $ $ $ $

0031 Spec Writer $ $ $ $ $ $ $

0032 Senior Biologist $ $ $ $ $ $ $

0033 Junior Biologist $ $ $ $ $ $ $

0034 Senior Environmental Scientist $ $ $ $ $ $ $

0035 Junior Environmental Scientist $ $ $ $ $ $ $

0036 Certified Health Physicist $ $ $ $ $ $ $

0037 Health Physicist $ $ $ $ $ $ $

0038 Regulatory Specialist $ $ $ $ $ $ $

UXO Quality Control Specialist

(UXOQCS)

0043 UXO Technician III $ $ $ $ $ $ $

0044 UXO Technician II $ $ $ $ $ $ $

0045 UXO Technician I $ $ $ $ $ $ $

0046 UXO Sweep Personnel $ $ $ $ $ $ $

0047 UXO Project Manager $ $ $ $ $ $ $

0048 Quality Control Manager $ $ $ $ $ $ $

0049 Illustrator/Draftsperson $ $ $ $ $ $ $

Geographic Information Systems

(GIS)

0051 Technician (General) $ $ $ $ $ $ $

0052 Administrative Assistant $ $ $ $ $ $ $

0053 Clerical $ $ $ $ $ $ $

0054 Senior Risk Assessor $ $ $ $ $ $ $

0055 Junior Risk Assessor $ $ $ $ $ $ $

Transportation Charge Rate % Field Overhead Rate % Home Overhead Rate %

*Other Direct Costs (ODC’s) will be negotiated on a per task order basis.

*Contractor Manpower Reporting will be required and negotiated on individual task orders, either as a separate line item or as an element of your overhead costs.

* Fee will be negotiated on a per task order basis and shall not exceed 10% in accordance with FAR 15.404-4

(c) (4)(i).

* Profit will be negotiated on a per task order basis.

*For each labor iscipline, please annotate whether the disciplines provided are the Prime or Subcontractor.

proposal for this table (Year 5).

Bid/Price Schedule –6 month extension

Prime or Subcotractor

P or S

Unburden Labor Rate Fringe

OH

Home

OH

Field G&A

Burden Labor Rates

Burden Labor Rates

0001 Principal $ $ $ $ $ $ $

0002 Program Manager $ $ $ $ $ $ $

0003 Senior Project Manager $ $ $ $ $ $ $

0004 Junior Project Manager $ $ $ $ $ $ $

0005 Senior Environmental Engineer $ $ $ $ $ $ $

0006 Junior Environmental Engineer $ $ $ $ $ $ $

0007 Safety Engineer $ $ $ $ $ $ $

0008 Senior Civil Engineer $ $ $ $ $ $ $

0009 Junior Civil Engineer $ $ $ $ $ $ $

0010 Chemical Engineer $ $ $ $ $ $ $

0011 Geotechnical Engineer $ $ $ $ $ $ $

0012 Construction Manager $ $ $ $ $ $ $

0013 Engineering Technician $ $ $ $ $ $ $

0014 Laborer $ $ $ $ $ $ $

0015 Cost Estimator $ $ $ $ $ $ $

0016 Cost Accountant $ $ $ $ $ $ $

0017 Budget Analyst $ $ $ $ $ $ $

0018 Safety and Health Officer $ $ $ $ $ $ $

Corporate Health and Safety Officer

0020 Certified Industrial Hygienist $ $ $ $ $ $ $

0021 Senior Geologist $ $ $ $ $ $ $

0022 Junior Geologist $ $ $ $ $ $ $

0023 Senior Geophysicist $ $ $ $ $ $ $

0024 Junior Geophysicist $ $ $ $ $ $ $

0025 Senior Scientist $ $ $ $ $ $ $

0026 Junior Scientist $ $ $ $ $ $ $

0027 Senior Hydrogeologist $ $ $ $ $ $ $

0028 Junior Hydrogeologist $ $ $ $ $ $ $

0029 Senior Chemist $ $ $ $ $ $ $

0030 Junior Chemist $ $ $ $ $ $ $

0031 Spec Writer $ $ $ $ $ $ $

0032 Senior Biologist $ $ $ $ $ $ $

0033 Junior Biologist $ $ $ $ $ $ $

0034 Senior Environmental Scientist $ $ $ $ $ $ $

0035 Junior Environmental Scientist $ $ $ $ $ $ $

0036 Certified Health Physicist $ $ $ $ $ $ $

0037 Health Physicist $ $ $ $ $ $ $

0038 Regulatory Specialist $ $ $ $ $ $ $

UXO Quality Control Specialist

(UXOQCS)

0043 UXO Technician III $ $ $ $ $ $ $

0044 UXO Technician II $ $ $ $ $ $ $

0045 UXO Technician I $ $ $ $ $ $ $

0046 UXO Sweep Personnel $ $ $ $ $ $ $

0047 UXO Project Manager $ $ $ $ $ $ $

0048 Quality Control Manager $ $ $ $ $ $ $

0049 Illustrator/Draftsperson $ $ $ $ $ $ $

Geographic Information Systems

(GIS)

0051 Technician (General) $ $ $ $ $ $ $

0052 Administrative Assistant $ $ $ $ $ $ $

0053 Clerical $ $ $ $ $ $ $

0054 Senior Risk Assessor $ $ $ $ $ $ $

0055 Junior Risk Assessor $ $ $ $ $ $ $

Transportation Charge Rate % Field Overhead Rate % Home Overhead Rate %

*Other Direct Costs (ODC’s) will be negotiated on a per task order basis.

*Contractor Manpower Reporting will be required and negotiated on individual task orders, either as a separate line item or as an element of your overhead costs.

* Fee will be negotiated on a per task order basis and shall not exceed 10% in accordance with FAR 15.404-4

(c) (4)(i).

* Profit will be negotiated on a per task order basis.

*For each labor iscipline, please annotate whether the disciplines provided are the Prime or Subcontractor.

proposal for this table (6 month extension).

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The following have been modified:

EXHIBITS/ATTACHMENTS TOC

Exhibit/Attachment Table of Contents

Document Type Descpirtion Pages Date Attachment 1 Wage Rate Determination 05-2247 10 05-Jan-2016 Attachment 2 Wage Rate Determination 15-2383, Rev 1 for Sample Problem 10 13-Apr-2016

Attachment 3 Past Performance Questionaire (Revised)

4 17-Oct-2016

Attachment 4 Experience in Relevant Projet Form (Revised)

1 06-Oct-2016

Attachment 5 Lobby Form 3 Attachment 6 Sample Problem (Revised) 13 07Oct-2016 Attachment 7 Sample Problem Drawing 1 26-Sep-2016 Attachment 8 Sample Problem Bid Sheet (Revised) 1 26-Sep-2016 Attachment 9 Projnet Instructions 1 26-Sep-2016 Attachment 10 Questions and Answers 1 66 26-Sep-2016 Attachment 11 Projnet Questions and Answers

Consolidated 22 13-Oct-2016

(End of Summary of Changes)

File details come from the government source that posted it. Updated .