This document contains an amendment to a solicitation for the Fort Randall Major Unit Rehabilitation Project. The solicitation is seeking proposals for rehabilitation of units at Fort Randall Dam in South Dakota. Key details include an extended deadline for proposal submission of May 11, 2021; modifications to specification sections and requirements; and an updated site visit schedule from January 12-13, 2021 with COVID-19 restrictions. Offerors are advised to acknowledge receipt of this amendment.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
Amendment 0005
Major Unit Rehab, Fort Randall Dam, SD
See attached documentation for content of the amendment revisions
New Date for receipt of Proposals is 11 May 2021 at 2:00 pm (local time)
Government Point of Contact: Jessica Jackson, Contract Specialist (402) 995-2052
U.S ARMY CORPS OF ENGINEERS, OMAHA DISTRICT
CONTRACTING OFFICE
1616 CAPITOL AVE.
OMAHA, NE 68102-4901
See Item 6
W9128F21R0005
04/09/2021
12/15/2020
Am #0005 - 2 (Continuation SF 30)
09 April 2021 Solicitation No. W9128F21R0005
Date of Issue: 15 December 2020 New Date of Receiving Proposals: 11 May 2021
SUBJECT: Amendment No. 0005 to Request for Proposal Solicitation Package For Major Unit Rehab, Fort Randal Dam, SD.
TO: Prospective Offerors and Others Concerned
1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).
a. Specifications. (Descriptive Changes.)
(1) Section 00 10 00, SF1442 and CLIN Pricing Schedule, delete date and time of receiving proposals shown and substitute "11 May 2021" at "2:00".
(2) Section 00 21 00 Page 15, Paragraph 1.19.1, replace first sentence with: “Questions relating to the proposal are to be submitted via Bidder Inquiry in ProjNet at: https://www.projnet.org/projnet/ No Later 4:00 PM, CDT, 29 Apr 2021, in order that they may be given consideration or actions taken prior to receipt of offers.”
(3) Section 00 22 00 Page 6, paragraph 7.1, line 2, add the following sentence after the first sentence: “The required comprehensive Gantt chart schedule and CPARS/PPQ documentation will not be counted towards the 250-page Volume 1 page limit. “
(4) Section 00 22 00 Page 15, paragraph 12, line 2, replace “by the Offeror in the past ten years” with “by the Offeror in the past six (6) years”.
(5) Section 00 22 00 Page 17-18, paragraph 13.1.2, deleted the second paragraph and substitute the following:
“The work plan shall include a comprehensive schedule in Gantt chart format and including descriptive literature, showing a planned schedule to complete the project by the specified contract completion date. A Gantt chart size of 11x17 is acceptable. The comprehensive Gantt chart schedule shall not be counted towards the 75-page PMP limit. The Gantt chart should be accompanied with a narrative addressing production rates, weather days, periods of non-work, planned outages and address methods to be utilized to keep the project on schedule. All major features of work outlined in paragraph 13.1.2.1 shall be included. Constraints to be used for schedule development are outlined in paragraph 13.1.2.2. For proposal evaluation purposes only, the Offeror should use a non-binding Contract Notice to Proceed (NTP) date of October 13, 2021.”
(6) Section 01 22 00.00 10 Page 47, paragraph 1.2.82.1, Replace second sentence with: "The payments will be paid IAW the cost loaded schedule for the CLINs affected by the adjustment."
2. This amendment is a part of the proposing papers and its receipt shall be acknowledged. All other conditions and requirements of the request for proposal
Am #0005 - 3 (Continuation SF 30) remain unchanged.
3. Proposals are to be submitted electronically as described in Section 00 22 00 PROPOSAL INSTRUCTIONS, SUBMISSION REQUIREMENTS AND
EVALUATION.
4. Electric Offers will be received until 2:00 p.m., local time at place of receiving proposals, 11 May 2021, as stated in the Request For Proposal.
U.S. Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, Nebraska 68102-4901
09 Apr 2021
MFS/2184