Am0002 - W9128F21R0005.pdf

PDF 3 MB Posted

Attached to
Fort Randall Major Unit Rehabilitation Project
Solicitation number
W9128F21R0005
Issued by

About this file

This is a solicitation for the Fort Randall Major Unit Rehabilitation Project. The solicitation closes on 25 March 2021 at 2pm Central and is unrestricted and open to both large and small businesses. Site visits will be held on 12-13 January 2021 beginning at 9am, with attendance limited due to COVID-19 restrictions. Contractors must RSVP with attendee lists by 22 December and identify any non-US citizens by 17 December. The site visit will include a dewatered turbine and open penstock for inspection, an accessible generator with removed hatches and radiator, and spare parts in a warehouse. Contractors should meet at the powerhouse on their assigned date.

View the file

Other files

File Type Posted
Am0006 W9128F21R0005.pdf PDF
Am0005 W9128F-21-R-0005.pdf PDF
9104134 StandoffInsulator.pdf PDF
Am0004 W9128F-21-R-0005.pdf PDF
9040123 Penstock 16 inch.JPG JPG image
9040124 Air Depression Diaphragm Valve 1.jpg JPG image
9045637 Drawings_Headcover Access Inquiry.pdf PDF
9040124 Air Depression Diaphragm Valve 2 .jpg JPG image
9040123 Penstock 12 inch valve.JPG JPG image
Am0003 W9128F21R0005 FR MUR.pdf PDF
20210223_093629.jpg JPG image
20210223_091749.jpg JPG image
coc lab_250047.pdf PDF
0250047-PLM.pdf PDF
20210223_093204.jpg JPG image
20210223_092341.jpg JPG image
TMP_Existing Design_Component Overview.pdf PDF
Pages from Generator Test Report - Westinghouse.pdf PDF
TMP_Existing Design_Procedure.pdf PDF
TMP_Existing Design_Drawings.pdf PDF
Waterway Drawings.pdf PDF
195215A Pressure Tank.pdf PDF
195214A Pressure Tank.pdf PDF
18-C-5325_Stator Coil Windings.pdf PDF
AM0001_W9128F21R0005 - FR MUR.pdf PDF
Water Quality - Fort Randall.pdf PDF
12_13 Jan 21 Fort Randall Site Visit Presentation.pdf PDF
Site Visit Sign-In_13 Jan 21_FR Major Rehab.pdf PDF
Site Visit Sign-In_12 Jan 21_FR Major Rehab.pdf PDF
Part 1 of 2 Fort Randall MUR FINAL_ REFERENCE DRAWINGS 6-25-20.pdf PDF
Part 2 of 2 Fort Randall MUR FINAL_ REFERENCE DRAWINGS 6-25-20.pdf PDF
W9128F21R0005_Summary of Changes_Draft to Final Solicitation.pdf PDF
Fort Randall MUR FINAL_COLOR_ Contract Drawings Review 12-15-20 REDUCED.pdf PDF
Ft Randall Major Unit Rehab W9128F21R0005 Contract Specs .pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

Amendment 0002

Major Unit Rehab, Fort Randall Dam, SD

See attached documentation for content of the amendment revisions

New Date for receipt of Proposals is 20 April 2021 at 2:00 pm (local time)

Government Point of Contact: Jessica Jackson,Contract Specialist (402) 995-2052

U.S ARMY CORPS OF ENGINEERS, OMAHA DISTRICT

CONTRACTING OFFICE

1616 CAPITOL AVE.

OMAHA, NE 68102-4901

See Item 6

W9128F21R0005

02/10/2021

12/15/2020

Am #0002 - 2 (Continuation SF 30)

04 February 2021 Solicitation No. W9128F21R0005

Date of Issue: 15 December 2020 Date of Receiving Proposals: 25 March 2021

SUBJECT: Amendment No. 0002 to Request for Proposal Solicitation Package For Major Unit Rehab, Fort Randal Dam, SD.

TO: Prospective Offerors and Others Concerned

1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).

a. Specifications. (Descriptive Changes.)

(1) Section 00 10 00, SF1442 and CLIN Pricing Schedule, [delete date and time of receiving proposals shown and substitute "20 April 2021" at "2:00 pm".

(2) Section 00 10 00, following 00 10 00 Page 14 add the attached Option Timetable.

(3) Section 00 22 00 Page 13, paragraph 11.1 subparagraph 2A, see list definitions below Table 00115-1, item 4, delete “4) Ppeak is the peak generator power output/Contractor guaranteed power.” and substitute the following:

“4) Ppeak is defined as the power output at peak efficiency for a given head.”

(4) Section 00 73 00 Page 8, after paragraph 1.7 add the following new paragraph:

“1.8 MISSED CAVITATION GUARANTEE

The parties to the contract agree that the Government will incur financial damage if excessive pitting due to cavitation occurs and can not be resolved.

Recognizing that actual damages are difficult to determine with precision, the parties to the contract agree that the following sum reasonably represents the damages that the Government will incur. In the event that cavitation damage in excess of the amount allowed under SECTION 48 13 13.01 26 Paragraph 1.5.3 is discovered after the Contractor has completed one repair for previous excessive damages, the Contractor shall perform a second repair and pay to the Government a lump sum of $170,424 for each applicable unit. “

(5) Section 09 97 02.00 26 Page 37, paragraph 3.5 subparagraph d, delete “Stay vane extension (optional).” and substitute “Not Used”.

(1) Section 48 13 13.04 26 Page 57, delete paragraph 3.35 and the subsequent subparagraphs and substitute the following:

“3.35 REPLACE GENERATOR THRUST BEARING OIL COOLER

The Contractor shall replace the existing generator thrust bearing oil coolers

Am #0002 - 3 (Continuation SF 30) for all eight main units according to SECTION 42 13 19.00 26.”

b. Reference Drawing (Reissued). The following reference drawing is reissued for clarity.

(1) Sheet 18-C-53-25.

c. Reference Drawings (New). The following new reference drawings are hereby added to the request for proposal drawings and are issued with this amendment.

(1) Sheet 195214A & 195215A. (Pressure tank reference drawings)

2. This amendment is a part of the proposing papers and its receipt shall be acknowledged. All other conditions and requirements of the request for proposal remain unchanged.

3. Proposals are to be submitted electronically as described in Section 00 22 00 PROPOSAL INSTRUCTIONS, SUBMISSION REQUIREMENTS AND

EVALUATION.

4. Electric Offers will be received until 2:00 p.m., local time at place of receiving proposals, 20 April 2021, as stated in the Request For Proposal.

Attachments: Specs listed in 1.a Drawings listed in 1.b & 1.c

U.S. Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, Nebraska 68102-4901

04 Feb 2021

MFS/2184

A Price Item DESCRIPTION

TIMEFRAME WHEN

OPTIONAL ITEM MAY BE

EXERCSIED

IF EXERCISED, TIME

EXTENSION TO

COMPLETE WORK FOR

ITEM

0010 1001 Disassemble Generating Unit, Including Inspections of Components- 2 Each

NLT eighteen (18) months after the contract is awarded

2 additional years from the date of exercising the option

1002 Reassemble Generating Unit- 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1003 Operational Testing After Reassembly- 2 Each NLT eighteen (18) months after the contract is awarded No additional time

0011 1101 Furnish Francis Turbine Runner- 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1102 Pre-Disassembly Investigation- 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1103 Line Bore Wicket Gate Stem Housing- 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1104 Inspect Stay Ring - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1105 Furnish Stationary Sealing Rings - 2 Sets NLT eighteen (18) months after the contract is awarded No additional time

1106 Refurbish Headcover - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

Section 00 10 00 Appendix A

Fort Randall Major Unit Rehabilitation ‐ Optional Items

Appendix A - Page 1 Am0002

Refurbish Turbine Guide Bearing Housing and Head Cover Extension - 2 Each

NLT eighteen (18) months after the contract is awarded No additional time

1108 Refurbish Bottom Ring - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1109 Refurbish Turbine Air Inlet Valve - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

Furnish and Install All Self- Lubricating Bushings and Bearing Plates - 2 Each

NLT eighteen (18) months after the contract is awarded No additional time

Furnish and Install Turbine Shaft Sleeve - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1112 Refurbish Operating Ring - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1113 Inspect Turbine and Generator Shaft

- 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1114 Machine Turbine Shaft - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1115 Furnish and Install Main Turbine Shaft Packing Box- 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1116 Refurbish Wicket Gate Servomotor- 2 Sets NLT eighteen (18) months after the contract is awarded No additional time

1117 Inspect Thrust Runner Phase 1 - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

Appendix A - Page 2 Am0002

1118 Inspect Thrust Bearing Shoe Phase 1

- 2 Sets NLT eighteen (18) months after the contract is awarded No additional time

1119 Refurbish Turbine Guide Bearing (Installed and Spares)- 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1120 Inspect Turbine Guide Bearing Oil Pumps/Motor System - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

Furnish and Install New Turbine Guide Bearing Oil Piping, Valves, and Filters - 2 Each

NLT eighteen (18) months after the contract is awarded No additional time

Inspect, Clean, and Pressure Test Generator Air Coolers - 2 Sets NLT eighteen (18) months after the contract is awarded No additional time

Inspect and Pressure Test Thrust Bearing Oil Cooler Assembly - 2 Each

NLT eighteen (18) months after the contract is awarded No additional time

1124 Furnish and Install the 6 Inch Cooling Water Strainer - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1125 Furnish and Install the 6 Inch Cooling Water Valves - 2 Sets NLT eighteen (18) months after the contract is awarded No additional time

1126 Replace Depression Air Diaphragm Valves - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

Setup and Machining of Stay Ring Mounting Flange and O-Ring Sealing Surfaces - 2 Each

NLT eighteen (18) months after the contract is awarded No additional time

1128 Inspect Spiral Case - 2 Each NLT eighteen (18) months

Appendix A - Page 3 Am0002

1129 Inspect Discharge Ring and Draft Tube Liner- 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1130 Inspect and Repair Piezometer Tap - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1131 Replace 4-Path Penstock Flow Meter Transducers and Wiring - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1132 Replace Runner Coupling Fasteners - 2 Sets NLT eighteen (18) months after the contract is awarded No additional time

Inspect and Test High Pressure Lift System - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1134 Furnish Hydraulic Jacking System - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1135 Furnish and Install Vibration Monitoring System - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1136 Replace Turbine Pit Platform Decking and Stairway Steps - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1137 Furnish Thrust Bearing Oil Cooler Assembly - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

Furnish and Install Accumulator Tank and Associated Equipment - 2 Each

NLT eighteen (18) months after the contract is awarded No additional time

Furnish and Install Turbine Pit Piping and Associated Equipment - 2 Each

NLT eighteen (18) months

Appendix A - Page 4 Am0002

1140 Measure Penstock Geometry and Report Flow Meter Paths - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

Refurbish Set of Upper Generator Guide Bearing Pads (Installed and Spare) - 2 Sets

NLT eighteen (18) months after the contract is awarded No additional time

Refurbish Set of Lower Generator Guide Bearing Pads (Installed and Spare) - 2 Sets

NLT eighteen (18) months after the contract is awarded No additional time

1143 Replace Upper Generator Guide Bearing Oil Fill Pipe - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

Inspect Generator Brake Rings - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1145 Replace Headcover Condensing Piping

- 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1146 Furnish and Install Penstock Drain Valves - 4 Each NLT eighteen (18) months after the contract is awarded No additional time

Furnish and Install Thrust Bearing Cooler Actuators and Valves - 2 Sets

NLT eighteen (18) months after the contract is awarded No additional time

1148 Flush and Clean Unit Piping and Tanks - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1149 Painting - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

0012 1201 Re-Establish Stator Center - 2 Each NLT eighteen (18) months

Appendix A - Page 5 Am0002

Furnish Complete Set of Stator Coils, Supplies, and Accessories - 2 Each

NLT eighteen (18) months after the contract is awarded No additional time

Furnish Production Run Coils For and Perform Voltage Endurance Testing of Production Run Coils

NLT eighteen (18) months after the contract is awarded No additional time

1204 Replace Three Generator Neutral Current Transformers - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1205 Remove Stator Winding - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

Inspect, Clean, and Test Stator Core 1 each NLT eighteen (18) months after the contract is awarded No additional time

1207 Inspect, Clean, and Test Rotor - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

1208 Install and Test Stator Winding - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

Replace All Rotor Field Lead Bus Supports on a Per Unit Basis - 2 Each

NLT eighteen (18) months after the contract is awarded No additional time

1210 Perform Miscellaneous Electrical Work - 2 Each NLT eighteen (18) months after the contract is awarded No additional time

0013 1301 Perform Hydraulic Turbine Model Test with New Wicket Gates

NLT thirty (30) days after Government Approval of the Wicket Gate Mechanism Condition Analysis Report and Recommendations

30 additional days from the date of exercising the option

Appendix A - Page 6 Am0002

0014 1401 Additional Stay Ring Mounting Surface Machining

NLT forty‐five (45) days after Government Approval of each unit's Stay Ring As‐ Found Inspection Report 5 additional days

0015 1501 Additional Head Cover Flange Machining

NLT thirty (30) days after notification of base machining of head cover flange No additional time

0016 1601 Additional Bottom Ring Flange Machining

NLT thirty (30) days after notification of base machining of bottom ring flange No additional time

0017 1701 Additional Bearing Housing Machining

NLT thirty (30) days after notification of base machining of bearing housing No additional time

0018 1801 Refurbish Generator Brake Rings

NLT forty‐five (45) days after Government Approval of each unit's Generator Brake Inspection Report No additional time

0019 1901 Inspect Thrust Bearing Shoes Phase 2 (Installed and Spares)

NLT forty‐five (45) days after Government Approval of each unit's Phase 1 Inspection Report No additional time

0020 2001 Inspect Thrust Runner and Generator Shaft Phase 2

NLT forty‐five (45) days after Government Approval of each unit's Phase 1 Inspection Report No additional time

0021 2101 Refurbish Set of Thrust Bearing Shoes (Installed and Spares)

NLT forty‐five (45) days after Government Approval of each unit's Thrust Bearing Site Inspection Report No additional time

Appendix A - Page 7 Am0002

0022 2201 Resurface Thrust Bearing Runner and Backside

NLT forty‐five (45) days after Government Approval of each unit's Thrust Bearing Site Inspection Report No additional time

0023 2301 Resurface Thrust Bearing Runner Running Surface Only; Runner Separate from Generator Shaft

NLT forty‐five (45) days after Government Approval of each unit's Thrust Bearing Site Inspection Report No additional time

0024 2401 Resurface Thrust Bearing Runner Running Surface Only; Runner Mounted on Generator Shaft

NLT forty‐five (45) days after Government Approval of each unit's Thrust Bearing Site Inspection Report No additional time

0025 2501 Refurbish Generator Shaft

NLT forty‐five (45) days after Government Approval of each unit's Generator Shaft Site Inspection Report No additional time

0026 2601 Furnish New Wicket Gates (Existing Design)- 1 Set

NLT forty‐five (45) days after Government Approval of the Final Model Test Report No additional time

2602 Refurbish Wicket Gates - 7 Sets NLT forty‐five (45) days after Government Approval of the Final Model Test Report No additional time

0027 2701 Furnish New Wicket Gates (New Design)- 8 Sets

NLT forty‐five (45) days after Government Approval of the Final Model Test Report No additional time

2702 Furnish New Wicket Gate Spares (New Design)- 3 Each

NLT forty‐five (45) days after Government Approval of the Final Model Test Report No additional time

Appendix A - Page 8 Am0002

0028 2801 Furnish New Wicket Gate Operating Mechanism -8 Each

NLT sixty (60) days after Government Approval of the Wicket Gate Mechanism Condition Analysis Report and Recommendations No additional time

0029 2901 Refurbish Wicket Gate Operating Mechanism - 8 Each

NLT sixty (60) days after Government Approval of the Wicket Gate Mechanism Condition Analysis Report and Recommendations No additional time

0030 3001 Bore Wicket Gate Servomotor Cylinders

NLT forty‐five (45) days after Government approval of each unit's wicket gate servomotor inspection report No additional time

0031 3101 Chrome Plate Wicket Gate Servomotor Piston Rod

NLT forty‐five (45) days after Government approval of each unit's wicket gate servomotor inspection report No additional time

0032 3201 Design and Furnish Turbine Maintenance Platform and Gangway (Design 1)- 2 Sets

NLT ninety (90) days after Government approval of the turbine Final Model Test Report No additional time

0033 3301 Design and Furnish Turbine Maintenance Platform and Gangway (Design 2)- 2 Sets

NLT ninety (90) days after Government approval of the turbine Final Model Test Report No additional time

0034 3401 Perform Additional Stator Core Interlaminar Insulation Test NLT thirty (30) days after execution of repairs

30 additional days from date of exercising the option

Appendix A - Page 9 Am0002

0035 3501 Re-Level Sole Plates

NLT thirty (30) days after Government exercise of option to replace new stator core on each unit

3 additional weeks from the date of exercising the option

0036 3601 Furnish Main Shaft Packing Box Lantern Ring

NLT forty‐five (45) days after Government approval of each unit's lantern ring inspection report No additional time

0037 3701 Design, Furnish, and Install Thrust Bearing Platform - 8 Each

NLT ninety (90) days after Government approval of the turbine Final Model Test Report No additional time

0038 3801 Refurbish Rotor Field Poles

NLT thirty (30) days after Government Approval of the Field Winding Final Test Report No additional time

0039 3901 Refurbish Rotor Field Poles

NLT thirty (30) days after Government Approval of the Field Winding Final Test Report No additional time

0040 4001 Refurbish Rotor Field Poles

NLT thirty (30) days after Government Approval of the Field Winding Final Test Report No additional time

0041 4101 Refurbish Rotor Field Poles

NLT thirty (30) days after Government Approval of the Field Winding Final Test Report No additional time

0042 4201 Refurbish Rotor Field Poles

NLT thirty (30) days after Government Approval of the Field Winding Final Test Report No additional time

Appendix A - Page 10 Am0002

0043 4301 Refurbish Rotor Field Poles

NLT thirty (30) days after Government Approval of the Field Winding Final Test Report No additional time

0044 4401 Refurbish Rotor Field Poles

NLT thirty (30) days after Government Approval of the Field Winding Final Test Report No additional time

0045 4501 Refurbish Rotor Field Poles

NLT thirty (30) days after Government Approval of the Field Winding Final Test Report No additional time

0046 4601 Refurbish Rotor Field Poles - 1st Generator Unit

NLT thirty (30) days after Government Approval of the Field Winding Final Test Report No additional time

0047 4701 Refurbish Rotor Field Poles - 2nd Generator Unit

NLT thirty (30) days after Government Approval of the Field Winding Final Test Report No additional time

0048 4801 Refurbish Rotor Field Poles - 3rd Generator Unit

NLT thirty (30) days after Government Approval of the Field Winding Final Test Report No additional time

0049 4901 Refurbish Rotor Field Poles - 4th Generator Unit

NLT thirty (30) days after Government Approval of the Field Winding Final Test Report No additional time

0050 5001 Refurbish Rotor Field Poles - 5th Generator Unit

NLT thirty (30) days after Government Approval of the Field Winding Final Test

Appendix A - Page 11 Am0002

0051 5101 Refurbish Rotor Field Poles - 6th Generator Unit

NLT thirty (30) days after Government Approval of the Field Winding Final Test Report No additional time

0052 5201 Refurbish Rotor Field Poles - 7th Generator Unit

NLT thirty (30) days after Government Approval of the Field Winding Final Test Report No additional time

0053 5301 Refurbish Rotor Field Poles - 8th Generator Unit

NLT thirty (30) days after Government Approval of the Field Winding Final Test Report No additional time

0054 5401 Furnish Segregated Phase Bus Stand-off Insulators -

NLT thirty (30) days after Government Approval of the Bus Duct as‐found report No additional time

0055 5501 Furnish Segregated Phase Bus Stand-off Insulators

NLT thirty (30) days after Government Approval of the Bus Duct as‐found report No additional time

0056 5601 Furnish Segregated Phase Bus Stand-off Insulators

NLT thirty (30) days after Government Approval of the Bus Duct as‐found report No additional time

0057 5701 Furnish Segregated Phase Bus Stand-off Insulators

NLT thirty (30) days after Government Approval of the Bus Duct as‐found report No additional time

0058 5801 Furnish Segregated Phase Bus Stand-off Insulators

NLT thirty (30) days after Government Approval of the Bus Duct as‐found report No additional time

0059 5901 Furnish Segregated Phase Bus Stand-off Insulators

NLT thirty (30) days after Government Approval of the Bus Duct as‐found report No additional time

0060 6001 Furnish Segregated Phase Bus Stand-off Insulators

NLT thirty (30) days after Government Approval of the Bus Duct as‐found report No additional time

Appendix A - Page 12 Am0002

0061 6101 Furnish Segregated Phase Bus Stand-off Insulators

NLT thirty (30) days after Government Approval of the Bus Duct as‐found report No additional time

0062 6201 Furnish One Complete Stator Core Assembly - 2nd Generator Unit

NLT eight (8) years after contract award No additional time

0063 6301 Furnish One Complete Stator Core Assembly - 3rd Generator Unit

NLT eight (8) years after contract award No additional time

0064 6401 Furnish One Complete Stator Core Assembly - 4th Generator Unit

NLT eight (8) years after contract award No additional time

0065 6501 Furnish One Complete Stator Core Assembly - 5th Generator Unit

NLT eight (8) years after contract award No additional time

0066 6601 Furnish One Complete Stator Core Assembly - 6th Generator Unit

NLT eight (8) years after contract award No additional time

0067 6701 Furnish One Complete Stator Core Assembly - 7th Generator Unit

NLT eight (8) years after contract award No additional time

0068 6801 Furnish One Complete Stator Core Assembly - 8th Generator Unit

NLT eight (8) years after contract award No additional time

0069 6901 Remove Existing Stator Core, Install and Test New Stator Core - 2nd Generator Unit

NLT thirty (30) days after each stator core Interlaminar Insulation Test Report approved

3 additional months from the date of exercising the option

0070 7001 Remove Existing Stator Core, Install and Test New Stator Core - 3rd Generator Unit

NLT thirty (30) days after each stator core Interlaminar Insulation Test Report approved

3 additional months from the date of exercising the option

0071 7101 Remove Existing Stator Core, Install and Test New Stator Core - 4th Generator Unit

NLT thirty (30) days after each stator core Interlaminar Insulation Test Report approved

3 additional months from the date of exercising the option

0072 7201 Remove Existing Stator Core, Install and Test New Stator Core - 5th Generator Unit

NLT thirty (30) days after each stator core Interlaminar Insulation Test Report approved

3 additional months from the date of exercising the option

Appendix A - Page 13 Am0002

0073 7301 Remove Existing Stator Core, Install and Test New Stator Core - 6th Generator Unit

NLT thirty (30) days after each stator core Interlaminar Insulation Test Report approved

3 additional months from the date of exercising the option

0074 7401 Remove Existing Stator Core, Install and Test New Stator Core - 7th Generator Unit

NLT thirty (30) days after each stator core Interlaminar Insulation Test Report approved

3 additional months from the date of exercising the option

0075 7501 Remove Existing Stator Core, Install and Test New Stator Core - 8th Generator Unit

NLT thirty (30) days after each stator core Interlaminar Insulation Test Report approved

3 additional months from the date of exercising the option

0076 7601 Refurbish Rotor Field Pole Shipping

NLT thirty (30) days after Government Approval of the Field Winding Final Test

Appendix A - Page 14 Am0002

SF30
Am 0002
Appendix A Am2
18-C-5325 Stator Coil & Winding
195214A Pressure Tank
195215A Pressure Tank