This amendment to the solicitation modifies the requirements for a design-build remodel of courtrooms at Fort Huachuca Division. Key details include:
-
The solicitation is for design and construction services to remodel courtrooms at Fort Huachuca Division. Proposals are due by August 7, 2023 at 12:00PM MST.
-
The amendment provides updated attachments including architectural drawings, technical specifications, and photos of the existing facility. Instructions are included to extract relevant CAD files from the PDF portfolio.
-
Evaluation criteria and submission requirements remain unchanged. Offerors must acknowledge this amendment per the instructions on the modified SF30 form.
-
The issuing office name has been updated, and the list of attachments has been revised to include 34 attachments providing additional information for offerors to consider when preparing proposals.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACC-APG
MAVERICK SIRAGUSA BLDG 22208
FT HUACHUCA AZ 85613
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provi ded herei n, all t erms and condit ions of t he document refere nced in Item 9A or 10A, as heretofore change d, remai ns unchanged and in ful l force and effect .
15A. NAME AND TIT LE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
ST ANDARD FORM 30 (Rev. 10-83) Prescr ibed by GSA
FAR (48 CFR) 53.243
The purpose of amendment 0002 is as follows:
14.1 Updated Section 01 00 00 List of Attachments w ith Attachment J-34 fh-az52120-01s2017.
14.2 Added Instructions to Open PDF Portfolio under section 01 00 00.
14.3 Proposal due date is still 07 August 2023, 12:00PM MST Time.
14.4 The SF 1442, Solicitation, Of fer, and Aw ard is to be completed by all Offerors and duly executed w ith an electronic or PDF scanned signature by an official authorized to bind the company in accordance w ith FAR 4.102. All amendments must be acknow ledged by all Offerors in accordance w ith the instructions on the Standard Form 30 or 1442, Amendment of Solicitation.
1. CO NTRACT ID CODE P AGE OF P AGES
1 3
16A. NAME AND T ITLE OF CONTRACTING OFFICER (Type or print)
16C. DAT E SIGNED
BY 04-Aug-2023
16B. UNITED ST AT ES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contract ing Officer )(Signature of person authorized t o sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, Count y, Stat e and Zip Code) X W9124A23R0011
X 9B. DAT ED (SEE IT EM 11)
21-Jun-2023
10B. DAT ED (SEE IT EM 13)
9A. AMENDMENT OF SOLICITAT ION NO.
11. THIS IT EM ONLY APPLIES T O AMENDMENT S OF SOLICITATIONS
X The above numbered soli cit ati on i s amended as set forth in It em 14. The hour and date specified for rece ipt of Offer is ext ended, X is not extended.
Offer must acknowl edge rece ipt of t his amendment pri or to the hour and date specified in the sol ici tat ion or as amended by one of t he fol lowing methods:
(a) By compl eti ng Items 8 and 15, and returning copi es of the amendment ; (b) By acknowledgi ng recei pt of thi s a mendment on each copy of t he offer submit ted;
or (c) By s epara te let ter or t elegram whi ch i ncludes a refe rence t o t he s olic ita tion and amendment numbers . FA ILURE OF YOU R A CKNOWLEDGMENT TO BE RECEIVED AT TH E P LACE D ESIGNATED FOR TH E RECEIPT OF OFFERS P RIO R TO THE HOUR AN D DATE SP ECIFIED MA Y RESULT IN
REJECTIO N OF YOUR OFFER. If by vir tue of thi s amendment you desire t o change an offer already submit ted, s uch c hange ma y be made by t ele gram or let ter, provided each t elegram or l ett er makes reference to the sol ici tat ion and this amendment , and is re ceived prior to the openi ng hour and dat e speci fi ed.
12. ACCOUNTING AND APPROPRIATION DAT A (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORT H IN ITEM 14 ARE MADE IN THE
CONT RACT ORDER NO. IN ITEM 10A.
B. T HE ABOVE NUMBERED CONT RACT /ORDER IS MODIFIED T O REFLECT THE ADMINIST RATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORT H IN ITEM 14, PURSUANT TO T HE AUTHORITY OF FAR 43.103(B).
C. T HIS SUPPLEMENT AL AGREEMENT IS ENT ERED INTO PURSUANT TO AUTHORITY OF:
D. OT HER (Specify type of modification and authorit y)
E. IMPORTANT: Contract or is not, is required to sign this document and return copies t o the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/cont ract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/ MODIFICATION NO. 5. P ROJECT NO .(If appli cable)
6. ISSUED BY
3. EFFECTIVE DATE
04-Aug-2023
CODE
ACC- APG
CONSTRUCTION 600AUGER ST BLDG 22208
FT HUACHUCA AZ 85613
W9124A 7. AD MINISTERED BY (If other t han item 6)
4. REQUISITION/PU RCHASE REQ. NO.
CODE W9124A
FACILITY CODECODE
EMAIL:TEL:
W9124A23R0011
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The Issued By organization has changed from
ACC-APG
MAVERICK SIRAGUSA BLDG 22208
FT HUACHUCA AZ 85613
to
ACC-APG
NADIA FIRESTONE BLDG 22208
FT HUACHUCA AZ 85613
SECTION 01 00 00 - GENERAL REQUIREMENTS
The following have been added by full text:
INSTRUCTIONS TO OPEN PDF PORTF
Instructions to Open PDF Portfolio:
To extract attachment J-34 fh-az52120-01s2017:
- IF visable, first click on “enable all features” at the top of adobe when you open the portfolio
- Then highlight the file
- Then right click on it and select “extract from portfolio”
- You will be asked to provide a location to save.
- The file should then be able to be opened – MUST have AutoCAD on your computer.
The following have been modified:
LIST OF ATTACHMENTS
LIST OF ATTACHMENTS:
J-01 SOO Updated 7-21-2023 J-02 OSJA Courtroom Plan J-03 OSJA AnnexCourtroom (current layout) J-04 Plumbing drawing (soil & vent, domestic water Isometrics) J-05 Enlarged Restroom Plumbing Plan J-06 Facility AS-BUILT DWGs J-07 Asbestos and lead base paint reports J-08 Technical exhibit J-09 JUDICIAL CENTER (JC) Standard Design Reference Document J-10 Questions Template
W9124A23R0011
J-11 Past Performance Questionnaire J-12 52.204-9 Personnel Log J-13 Map to Murr Recreational Center J-14 FFE-listing furniture J-15 LED light-nameplate-typical-nameplate J-16 Sewer-Water Points J-17 Electric Meter Only No Other Utilities Available J-18 Ecb_2018_17 J-19 Fire Hydrant 521-2 J-20 Proposed Fire Water Line J-21 Fort Huachuca Fire Department Requirements J-22 Fort Huachuca Energy Efficiency Water Conservation Design Construct Guidelines J-23 Pavilion-1 J-24 Additional Photos-Ahu-Plate-Switchgear-Boiler-Panelboards-Exterior-Parking J-25 Photos Of B52120 Hvac Vav J-26 Hvac-Drawings J-27 Architectural Finishes J-28 Building 52120 Outside Photos J-29 Building 52120 Photos of Rooms J-30 Building 52120 Utility Photo Locations J-31 Building 52150 Photos of Representative VAVs J-32 Questions and Answers J-33 Sign-In Sheet 6.26.23 J-34 fh-az52120-01s2017
(End of Summary of Changes)