Amendment # 02 – 15 December 2017
General Construction / Mechanical Construction Blanket Purchase Agreements (BPAs) - W91248-18-Q- 0500 - Amendment # 02.
The following additional information is provided.
1. Scoping date for both seed projects remains Wednesday, December 20, 2017 at 8:30 AM CST.
Proposal due date for both seed projects remains Thursday, January 04, 2018 at 2:00 PM CST.
2. Last day for questions for both seed projects is NLT, Tuesday, January 02, 2017 at 1:00 PM CST.
3. Wage Determination: SEED PROJECT #1: Install Static Control Flooring BLDG 95, Project No.
EH950076J - KY170168 (Building), dated 08/11/2017; SEED PROJECT #2: Replace Water Heaters BLDG 6761, Project No. FE160616J - TN 170098 (Building) dated 10/27/2017
4. Engineer for both seed projects is John Gunn, 270-798-9719, john.e.gunn17.civ@mail.mil.
5. The COR for seed project #1 - INSTALL STATIC CONTROL FLOORING BLDG 95, Project No. EH950076J is AJ Pau, (270) 412-7261, alika.j.pau.civ@mail.mil.
6. The COR for seed project #2 - REPLACE WATER HEATERS BLDG 6761, Project # FE160616J is Brad Curvin, (270) 412-7264, brad.curvin.civ@mail.mil.
7. The following questions and their responses are provided below:
Question #1: Will projects performed in the past 5 years at Ft. Campbell as a sub-contractor (primarily to the TOC) be acceptable for performance evaluation?
Answer #1: Yes, this experience is acceptable.
Question #2: Is there a limit to the number of pages that can be submitted in this proposal?
Answer #2: There is no limit to the number of pages to be submitted. Please ensure the pages are relevant and contain all the necessary documentation outlined in the special notice posted to FBO.
Question #2: Regarding selection criteria under 1) Technical (b) Relevant Experience: What is the maximum number of projects to be submitted showing company experience?
Answer #3: Please submit at least 3 and not more than 5 projects from within the past five (5) years that show construction experience and examples of construction projects applicable to your specialty.
mailto:john.e.gunn17.civ@mail.mil mailto:alika.j.pau.civ@mail.mil mailto:brad.curvin.civ@mail.mil