W91328-19-R-0006-Amendment 0004_UTTR RTA_Package 1 MSM Submittal Register.xlsx
XLSX spreadsheet 84 KB Posted
- Attached to
- UTTR Missile Motor Receipt & Storage Facility
- Solicitation number
- W9123819R0006
About this file
This document provides details for a federal solicitation seeking construction services. The U.S. Army Corps of Engineers Engineering District Sacramento will issue a request for proposal on or about September 23, 2019 for the design and construction of an eighteen magazine Missile Motor Receipt and Storage Facility at the Utah Test and Training Range in Hill AFB, Utah. The estimated value of the contract is between $25 million to $100 million. Construction is required to be completed within 730 calendar days of award. Services include site preparation, paving, security fencing, railroad track construction, and the construction of support facilities including a 7,000 square foot Motor Transfer Facility. The solicitation will be available for download at FedBizOpps and no paper copies will be provided. The response deadline is on or about November 7, 2019. The solicitation is unrestricted and will be conducted under NAICS code 236220 with a size standard of $36.5 million.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W91328-17-D-0027_UTTR RTA_Packa
| TITLE: | Motor Storage Magazines | SUBMITTAL REGISTER | ||||||||||||||||
| JOB NAME: | D5 Missile Motor Receipt/Storage Facilities, UTTR | |||||||||||||||||
| LOCATION: | Utah Test and Training Range | |||||||||||||||||
| CONTRACT NO: | W91238-17-D-0027 | |||||||||||||||||
| CONTRACTOR: | ||||||||||||||||||
| CONTRACTOR SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | ||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) |
| Line | Activity # | Transmittal # | Specification Section | SD # | Submittal Description | Item Submitted | Paragraph # | Classification: GOVT or A/E Reviewer | Submit | Approval Needed By | Material Needed By | Action Code | Date Of Action | Date FWD to APPR / Auth Date RCD From CONTR | Date FWD To Other Revwr | Date RCD From Other Reviewer | Action Code | Date Of Action | Mailed To CONTR/ Date RCD From APPR Authority | Remarks |
| 1 | 01 45 35 | 1 | Preconstruction Submittals | SIOR Letter of Acceptance | 3.1.1 | G | ||||||||||||||
| 2 | 01 45 35 | 1 | Preconstruction Submittals | Project Manual | 3.1.1 | G | ||||||||||||||
| 3 | 01 45 35 | 1 | Preconstruction Submittals | Project Manual | 3.1.1 | G | ||||||||||||||
| 4 | 01 45 35 | 1 | Preconstruction Submittals | Written Practices | 3.1.1 | |||||||||||||||
| 5 | 01 45 35 | 1 | Preconstruction Submittals | NDT Procedures and Equipment Calibration Records | 3.1.1 | |||||||||||||||
| 6 | 01 45 35 | 6 | Test Reports | Daily Reports | 3.1.1 | |||||||||||||||
| 7 | 01 45 35 | 6 | Test Reports | Daily Reports | 3.1.3 | |||||||||||||||
| 8 | 01 45 35 | 6 | Test Reports | Daily Reports | 3.1.3 | |||||||||||||||
| 9 | 01 45 35 | 6 | Test Reports | Biweekly Reports | 3.1.1 | |||||||||||||||
| 10 | 01 45 35 | 7 | Certificates | Fabrication Plant | 2.1 | |||||||||||||||
| 11 | 01 45 35 | 7 | Certificates | Certificate of Compliance | 2.1 | |||||||||||||||
| 12 | 01 45 35 | 7 | Certificates | Special Inspector of Record | 1.5.6 | G | ||||||||||||||
| 13 | 01 45 35 | 7 | Certificates | Special Inspector | 1.5 | G | ||||||||||||||
| 14 | 01 45 35 | 7 | Certificates | Qualification Records | 3.1.1 | |||||||||||||||
| 15 | 01 45 35 | 11 | Closeout Submittals | Interim Final Report | 3.1.1 | |||||||||||||||
| 16 | 01 45 35 | 11 | Closeout Submittals | Comprehensive Final Report | 3.1.1 | G | ||||||||||||||
| 17 | 01 45 35 | 11 | Closeout Submittals | Comprehensive Final Report | 3.1.3 | G | ||||||||||||||
| 18 | 01 91 00.15 | 1 | Preconstruction Submittals | Commissioning Firm | 1.7 | G DO | ||||||||||||||
| 19 | 01 91 00.15 | 1 | Preconstruction Submittals | Lead Commissioning Specialist | 1.7.1 | G DO | ||||||||||||||
| 20 | 01 91 00.15 | 1 | Preconstruction Submittals | Technical Commissioning Specialists | 1.7.2 | G DO | ||||||||||||||
| 21 | 01 91 00.15 | 1 | Preconstruction Submittals | Commissioning Firm's Contract | 1.7 | G DO | ||||||||||||||
| 22 | 01 91 00.15 | 6 | Test Reports | Interim Construction Phase Commissioning Plan | 3.1.2.1 | G DO | ||||||||||||||
| 23 | 01 91 00.15 | 6 | Test Reports | Final Construction Phase Commissioning Plan | 3.1.2.2 | G DO | ||||||||||||||
| 24 | 01 91 00.15 | 6 | Test Reports | Pre-Functional Checklists | 3.1.4.2 | G DO | ||||||||||||||
| 25 | 01 91 00.15 | 6 | Test Reports | Issues Log | 1.9 | |||||||||||||||
| 26 | 01 91 00.15 | 6 | Test Reports | Commissioning Report | 3.2 | G DO | ||||||||||||||
| 27 | 01 91 00.15 | 6 | Test Reports | Post-Construction Trend Log Report | 3.3.1 | G DO | ||||||||||||||
| 28 | 01 91 00.15 | 7 | Certificates | Certificate of Readiness | 1.1 | G DO | ||||||||||||||
| 29 | 01 91 00.15 | 10 | Operation and Maintenance Data | Training Plan | 3.1.5 | G RO | ||||||||||||||
| 30 | 01 91 00.15 | 10 | Operation and Maintenance Data | Training Attendance Rosters | 3.1.5 | G RO | ||||||||||||||
| 31 | 01 91 00.15 | 10 | Operation and Maintenance Data | Systems Manual/Computerized Maintenance Management System Manual | 3.1.6 | G DO | ||||||||||||||
| 32 | 01 91 00.15 | 10 | Operation and Maintenance Data | Maintenance and Service Life Plans | 3.1.7 | G DO | ||||||||||||||
| 33 | 01 91 00.15 | 11 | Closeout Submittals | Final Commissioning Report | 3.2 | S DO | ||||||||||||||
| 34 | 03 11 13 | 2 | Shop Drawings | Formwork | 2.2.1 | G | ||||||||||||||
| 35 | 03 11 13 | 2 | Shop Drawings | Formwork | 3.1.1 | G | ||||||||||||||
| 36 | 03 11 13 | 2 | Shop Drawings | Form Removal Schedule | 2.2.1 | G | ||||||||||||||
| 37 | 03 11 13 | 3 | Product Data | Form Materials | 2.2 | |||||||||||||||
| 38 | 03 11 13 | 4 | Samples | Sample Panels | 1.3 | G | ||||||||||||||
| 39 | 03 11 13 | 5 | Design Data | Calculations | 2.1 | |||||||||||||||
| 40 | 03 11 13 | 6 | Test Reports | Inspection | 3.2 | |||||||||||||||
| 41 | 03 15 00 | 3 | Product Data | Preformed Expansion Joint Filler | 2.1 | |||||||||||||||
| 42 | 03 15 00 | 3 | Product Data | Sealant | 2.2 | |||||||||||||||
| 43 | 03 15 00 | 4 | Samples | Field-Molded Type | 2.2.1 | |||||||||||||||
| 44 | 03 15 00 | 7 | Certificates | Preformed Expansion Joint Filler | 2.1 | |||||||||||||||
| 45 | 03 15 00 | 7 | Certificates | Sealant | 2.2 | |||||||||||||||
| 46 | 03 20 00 | 2 | Shop Drawings | Reinforcement | 3.1 | G | ||||||||||||||
| 47 | 03 20 00 | 2 | Shop Drawings | Electrical Bonding Details and Locations of Bonding Connection Points | G | |||||||||||||||
| 48 | 03 20 00 | 3 | Product Data | Reinforcing Steel | 2.1 | G | ||||||||||||||
| 49 | 03 20 00 | 6 | Test Reports | Tests, Inspections, and Verifications | 2.5 | G | ||||||||||||||
| 50 | 03 20 00 | 7 | Certificates | Reinforcing Steel | 2.1 | |||||||||||||||
| 51 | 03 30 00 | 1 | Preconstruction Submittals | Quality Control Plan | 1.5.2 | G | ||||||||||||||
| 52 | 03 30 00 | 1 | Preconstruction Submittals | Laboratory Accreditation | 1.5.1 | |||||||||||||||
| 53 | 03 30 00 | 1 | Preconstruction Submittals | Sampling Plan | 3.9.5.6 | G | ||||||||||||||
| 54 | 03 30 00 | 3 | Product Data | Recycled Content Products | Part 2 | |||||||||||||||
| 55 | 03 30 00 | 3 | Product Data | Cementitious Materials | 2.2 | |||||||||||||||
| 56 | 03 30 00 | 3 | Product Data | Vapor Retarder | 2.11 | |||||||||||||||
| 57 | 03 30 00 | 3 | Product Data | Floor Finish | 2.1.5 | |||||||||||||||
| 58 | 03 30 00 | 3 | Product Data | Floor Hardener | 2.9 | |||||||||||||||
| 59 | 03 30 00 | 3 | Product Data | Chemical Admixtures | 2.4 | |||||||||||||||
| 60 | 03 30 00 | 4 | Samples | Surface Retarder | 2.4.4 | |||||||||||||||
| 61 | 03 30 00 | 5 | Design Data | Mixture Proportions | 2.1.1 | G | ||||||||||||||
| 62 | 03 30 00 | 6 | Test Reports | Mixture Proportions | 2.1.1 | G | ||||||||||||||
| 63 | 03 30 00 | 6 | Test Reports | Testing and Inspection for CQC | 3.9 | G | ||||||||||||||
| 64 | 03 30 00 | 6 | Test Reports | Fly Ash | 2.2.2 | |||||||||||||||
| 65 | 03 30 00 | 6 | Test Reports | Ground Granulated Blast-Furnace (GGBF) Slag | 2.2.5 | |||||||||||||||
| 66 | 03 30 00 | 6 | Test Reports | Aggregates | 2.3 | |||||||||||||||
| 67 | 03 30 00 | 6 | Test Reports | Air Content | 3.9.5.1 | |||||||||||||||
| 68 | 03 30 00 | 6 | Test Reports | Slump | 3.9.5.3 | |||||||||||||||
| 69 | 03 30 00 | 6 | Test Reports | Compressive Strength | 3.9.5.6 | |||||||||||||||
| 70 | 03 30 00 | 6 | Test Reports | Water | 2.5 | |||||||||||||||
| 71 | 03 30 00 | 7 | Certificates | Contractor Quality Control personnel | 1.5 | |||||||||||||||
| 72 | 03 30 00 | 7 | Certificates | Ready-Mix Plant | 3.2.1 | |||||||||||||||
| 73 | 03 35 00 | 3 | Product Data | Recycled Content Products | Part 2 | |||||||||||||||
| 74 | 03 35 00 | 4 | Samples | Field Test Panels | 1.3.1 | |||||||||||||||
| 75 | 03 35 00 | 4 | Samples | Sample Wall Panels | 1.3.1.1 | |||||||||||||||
| 76 | 03 35 00 | 4 | Samples | Slab Panels | 1.3.1.2 | |||||||||||||||
| 77 | 03 39 00 | 3 | Product Data | Curing Materials | 2.1 | |||||||||||||||
| 78 | 03 39 00 | 6 | Test Reports | Testing and Inspection for CQC | 3.2 | |||||||||||||||
| 79 | 03 39 00 | 8 | Manufacturer’s Instructions | Curing Compound | 2.1 | |||||||||||||||
| 80 | 03 45 33 | 2 | Shop Drawings | Drawings of Precast Members | 2.1.1.2 | G | ||||||||||||||
| 81 | 03 45 33 | 2 | Shop Drawings | Electrical Bonding Details and Locations of Bonding Connection Points | 2.1.1.2 | G | ||||||||||||||
| 82 | 03 45 33 | 3 | Product Data | Inserts | 2.2.8 | |||||||||||||||
| 83 | 03 45 33 | 4 | Samples | Surface Finish | 2.3.9 | |||||||||||||||
| 84 | 03 45 33 | 5 | Design Data | Design Calculations | 2.1.1.2 | G | ||||||||||||||
| 85 | 03 45 33 | 5 | Design Data | Concrete Mix Design | 1.4.3 | G | ||||||||||||||
| 86 | 03 45 33 | 6 | Test Reports | Concrete Mix Design | 1.4.3 | G | ||||||||||||||
| 87 | 03 45 33 | 6 | Test Reports | Fly Ash | 2.2.2.1 | |||||||||||||||
| 88 | 03 45 33 | 6 | Test Reports | Pozzolan | 2.2.2.2 | |||||||||||||||
| 89 | 03 45 33 | 6 | Test Reports | Ground Granulated Blast-Furnace Slag | 2.2.2.4 | |||||||||||||||
| 90 | 03 45 33 | 6 | Test Reports | Aggregates | 2.2.4 | |||||||||||||||
| 91 | 03 45 33 | 6 | Test Reports | Water | 2.2.3 | |||||||||||||||
| 92 | 03 45 33 | 7 | Certificates | Quality Control Procedures | 2.3 | |||||||||||||||
| 93 | 03 45 33 | 7 | Certificates | Construction Records | 3.12 | G | ||||||||||||||
| 94 | 03 45 33 | 7 | Certificates | Erector's Post Audit Declaration | 1.4.1.3 | |||||||||||||||
| 95 | 03 45 33 | 11 | Closeout Submittals | Batch Ticket | 1.4.4 | |||||||||||||||
| 96 | 03 45 33 | 11 | Closeout Submittals | Recycled Content for Fly Ash and Pozzolan | 2.2.1 | S | ||||||||||||||
| 97 | 03 45 33 | 11 | Closeout Submittals | Recycled Content for Ground Iron Blast-Furnace Slag | 2.2.1 | S | ||||||||||||||
| 98 | 05 05 23.13 | 1 | Preconstruction Submittals | Personnel Qualification | 1.4.1 | G | ||||||||||||||
| 99 | 05 05 23.13 | 1 | Preconstruction Submittals | Procedure Description | 1.4.3 | G | ||||||||||||||
| 100 | 05 05 23.13 | 3 | Product Data | Ultrasonic Inspection | 1.4.1 | |||||||||||||||
| 101 | 05 05 23.13 | 6 | Test Reports | Equipment Qualifications | 1.4.5 | |||||||||||||||
| 102 | 05 05 23.13 | 6 | Test Reports | Inspection Test Reports | 3.4.1 | |||||||||||||||
| 103 | 05 05 23.16 | 1 | Preconstruction Submittals | Welding Quality Assurance Plan | 3.2 | |||||||||||||||
| 104 | 05 05 23.16 | 3 | Product Data | Welding Procedure Qualifications | 1.3 | G | ||||||||||||||
| 105 | 05 05 23.16 | 3 | Product Data | Welder, Welding Operator, and Tacker Qualification | 1.3.5 | |||||||||||||||
| 106 | 05 05 23.16 | 3 | Product Data | Inspector Qualification | 1.3.6 | |||||||||||||||
| 107 | 05 05 23.16 | 3 | Product Data | Previous Qualifications | 1.3.2 | |||||||||||||||
| 108 | 05 05 23.16 | 3 | Product Data | Pre-Qualified Procedures | 1.3.3 | |||||||||||||||
| 109 | 05 05 23.16 | 3 | Product Data | Welding Electrodes and Rods | 2.2 | |||||||||||||||
| 110 | 05 05 23.16 | 6 | Test Reports | Nondestructive Testing | 3.3 | |||||||||||||||
| 111 | 05 05 23.16 | 7 | Certificates | Certified Welding Procedure Specifications (WPS) | 1.3.1 | |||||||||||||||
| 112 | 05 05 23.16 | 7 | Certificates | Certified Brazing Procedure Specifications (BPS) | 1.3.1 | |||||||||||||||
| 113 | 05 05 23.16 | 7 | Certificates | Certified Procedure Qualification Records (PQR) | 1.3.1 | |||||||||||||||
| 114 | 05 05 23.16 | 7 | Certificates | Certified Welder Performance Qualifications (WPQ) | 1.3.1 | |||||||||||||||
| 115 | 05 05 23.16 | 7 | Certificates | Certified Brazer Performance Qualifications (BPQ) | 1.3.1 | |||||||||||||||
| 116 | 05 12 00 | 1 | Preconstruction Submittals | Erection Drawings | 1.3.1.1 | G | ||||||||||||||
| 117 | 05 12 00 | 2 | Shop Drawings | Fabrication Drawings | 1.3.2 | G | ||||||||||||||
| 118 | 05 12 00 | 3 | Product Data | Shop Primer | 2.6.2 | |||||||||||||||
| 119 | 05 12 00 | 3 | Product Data | Welding Electrodes and Rods | 2.4.1 | |||||||||||||||
| 120 | 05 12 00 | 3 | Product Data | Direct Tension Indicator Washers | 2.3.2.3 | |||||||||||||||
| 121 | 05 12 00 | 3 | Product Data | Non-Shrink Grout | 2.4.2 | |||||||||||||||
| 122 | 05 12 00 | 6 | Test Reports | Class B Coating | 2.6.2 | |||||||||||||||
| 123 | 05 12 00 | 6 | Test Reports | Bolts, Nuts, and Washers | 2.3 | |||||||||||||||
| 124 | 05 12 00 | 6 | Test Reports | Weld Inspection Reports | 3.7.1.2 | |||||||||||||||
| 125 | 05 12 00 | 6 | Test Reports | Direct Tension Indicator Washer Inspection Reports | 3.7.2.1 | |||||||||||||||
| 126 | 05 12 00 | 6 | Test Reports | Bolt Testing Reports | 3.7.3.1 | |||||||||||||||
| 127 | 05 12 00 | 6 | Test Reports | Embrittlement Test Reports | 3.7.4 | |||||||||||||||
| 128 | 05 12 00 | 7 | Certificates | Steel | 2.2 | |||||||||||||||
| 129 | 05 12 00 | 7 | Certificates | Bolts, Nuts, and Washers | 2.3 | |||||||||||||||
| 130 | 05 12 00 | 7 | Certificates | Galvanizing | 2.5 | |||||||||||||||
| 131 | 05 12 00 | 7 | Certificates | Welding Procedures and Qualifications | 1.3.3.1 | |||||||||||||||
| 132 | 05 50 13 | 2 | Shop Drawings | Structural Steel Door Frames | 2.11 | G | ||||||||||||||
| 133 | 05 50 13 | 2 | Shop Drawings | Expansion Joint Covers | 2.5 | G | ||||||||||||||
| 134 | 05 50 13 | 2 | Shop Drawings | Bollards/Pipe Guards | 2.7 | G | ||||||||||||||
| 135 | 05 50 13 | 2 | Shop Drawings | Angles and Plates | 2.9 | G | ||||||||||||||
| 136 | 05 50 13 | 3 | Product Data | Corner Guards | 2.3 | |||||||||||||||
| 137 | 05 50 13 | 3 | Product Data | Cover Plates and Frames | 2.4 | G | ||||||||||||||
| 138 | 05 50 13 | 3 | Product Data | Expansion Joint Covers | 2.5 | G | ||||||||||||||
| 139 | 05 50 13 | 3 | Product Data | Floor Gratings | 2.6 | G | ||||||||||||||
| 140 | 05 50 13 | 3 | Product Data | Structural Steel Door Frames | 2.11 | G | ||||||||||||||
| 141 | 05 50 13 | 3 | Product Data | Downspout Terminations | 2.8 | G | ||||||||||||||
| 142 | 05 50 13 | 4 | Samples | Expansion Joint Covers | 2.5 | |||||||||||||||
| 143 | 05 50 13 | 4 | Samples | Control-Joint Covers | ||||||||||||||||
| 144 | 05 52 00 | 2 | Shop Drawings | Fabrication Drawings | 1.2.1 | G | ||||||||||||||
| 145 | 05 52 00 | 2 | Shop Drawings | Iron and Steel Hardware | 3.2 | G | ||||||||||||||
| 146 | 05 52 00 | 2 | Shop Drawings | Steel Shapes, Plates, Bars and Strips | 3.2 | G | ||||||||||||||
| 147 | 05 52 00 | 3 | Product Data | Structural-Steel Plates, Shapes, and Bars | 2.2.1 | G | ||||||||||||||
| 148 | 05 52 00 | 3 | Product Data | Concrete Inserts | 2.2.3 | G | ||||||||||||||
| 149 | 05 52 00 | 3 | Product Data | Protective Coating | 2.1.2 | G | ||||||||||||||
| 150 | 05 52 00 | 3 | Product Data | Aluminum Railings and Handrails | 2.2.5 | G | ||||||||||||||
| 151 | 05 52 00 | 3 | Product Data | Anchorage and Fastening Systems | 1.2.1 | G | ||||||||||||||
| 152 | 05 52 00 | 7 | Certificates | Welding Procedures | 1.4.1 | G | ||||||||||||||
| 153 | 05 52 00 | 7 | Certificates | Welder Qualification | 1.4.2 | G | ||||||||||||||
| 154 | 05 52 00 | 8 | Manufacturer’s Instructions | Installation Instructions | 3.2 | |||||||||||||||
| 155 | 07 11 13 | 7 | Certificates | Materials | 1.3 | |||||||||||||||
| 156 | 07 19 00 | 3 | Product Data | Water Repellents | 2.2 | |||||||||||||||
| 157 | 07 19 00 | 6 | Test Reports | Water Absorption | 1.3.2 | |||||||||||||||
| 158 | 07 19 00 | 6 | Test Reports | Water Absorption | 2.3.1 | |||||||||||||||
| 159 | 07 19 00 | 6 | Test Reports | Accelerated Weathering | 2.3.1 | |||||||||||||||
| 160 | 07 19 00 | 6 | Test Reports | Resistance to Chloride Ion Penetration | 2.3.1 | |||||||||||||||
| 161 | 07 19 00 | 6 | Test Reports | Moisture Vapor Transmission | 1.3.2 | |||||||||||||||
| 162 | 07 19 00 | 6 | Test Reports | Moisture Vapor Transmission | 2.3.1 | |||||||||||||||
| 163 | 07 19 00 | 6 | Test Reports | Scaling Resistance | 2.3.1 | |||||||||||||||
| 164 | 07 19 00 | 6 | Test Reports | Water Penetration and Leakage | 1.3.2 | |||||||||||||||
| 165 | 07 19 00 | 7 | Certificates | Manufacturer's Qualifications | 1.3.1 | |||||||||||||||
| 166 | 07 19 00 | 7 | Certificates | Applicator's Qualifications | 1.3.1 | |||||||||||||||
| 167 | 07 19 00 | 7 | Certificates | Evidence of Acceptable Variation | 1.3.3 | |||||||||||||||
| 168 | 07 19 00 | 7 | Certificates | Warranty | 1.12 | |||||||||||||||
| 169 | 07 19 00 | 8 | Manufacturer’s Instructions | Application | 3.4 | |||||||||||||||
| 170 | 07 19 00 | 8 | Manufacturer’s Instructions | Safety Data Sheets | 1.7.1 | |||||||||||||||
| 171 | 07 27 10 | 4 | Samples | Mock-Up | 3.1.2 | G | ||||||||||||||
| 172 | 07 27 10 | 6 | Test Reports | Testing and Inspection | 3.1.3 | G RO | ||||||||||||||
| 173 | 07 60 00 | 2 | Shop Drawings | Exposed Sheet Metal | 2.1.1 | G | ||||||||||||||
| 174 | 07 60 00 | 2 | Shop Drawings | Expansion Joints | 3.1.20 | G | ||||||||||||||
| 175 | 07 60 00 | 2 | Shop Drawings | Fasciae | 2.1.1 | G | ||||||||||||||
| 176 | 07 60 00 | 2 | Shop Drawings | Splash Pans | 3.1.16 | G | ||||||||||||||
| 177 | 07 60 00 | 2 | Shop Drawings | Base Flashing | 3.1.9 | G | ||||||||||||||
| 178 | 07 60 00 | 2 | Shop Drawings | Counterflashing | 3.1.10 | G | ||||||||||||||
| 179 | 07 60 00 | 2 | Shop Drawings | Flashing at Roof Penetrations and Equipment Supports | 3.1.21 | G | ||||||||||||||
| 180 | 07 60 00 | 2 | Shop Drawings | Reglets | 2.1.9 | G | ||||||||||||||
| 181 | 07 60 00 | 2 | Shop Drawings | Drip Edges | 3.1.14 | G | ||||||||||||||
| 182 | 07 60 00 | 2 | Shop Drawings | Open Valley Flashing | 3.1.17 | G | ||||||||||||||
| 183 | 07 60 00 | 2 | Shop Drawings | Eave Flashing | 3.1.18 | G | ||||||||||||||
| 184 | 07 60 00 | 3 | Product Data | Roof Finishes | 2.1.7 | G | ||||||||||||||
| 185 | 07 60 00 | 4 | Samples | Finish Samples | 1.4.2 | G | ||||||||||||||
| 186 | 07 60 00 | 8 | Manufacturer’s Instructions | Instructions for Installation | 1.4.3 | G | ||||||||||||||
| 187 | 07 60 00 | 8 | Manufacturer’s Instructions | Quality Control Plan | 3.5 | G | ||||||||||||||
| 188 | 07 60 00 | 10 | Operation and Maintenance Data | Cleaning and Maintenance | 1.4.3 | G | ||||||||||||||
| 189 | 07 84 00 | 2 | Shop Drawings | Firestopping System | 2.1 | G | ||||||||||||||
| 190 | 07 84 00 | 3 | Product Data | Firestopping Materials | 2.2 | G | ||||||||||||||
| 191 | 07 84 00 | 6 | Test Reports | Inspection | 3.3 | G | ||||||||||||||
| 192 | 07 84 00 | 7 | Certificates | Inspector Qualifications | 1.5.2 | |||||||||||||||
| 193 | 07 84 00 | 7 | Certificates | Firestopping Materials | 2.2 | |||||||||||||||
| 194 | 07 84 00 | 7 | Certificates | Installer Qualifications | 1.5.1 | G | ||||||||||||||
| 195 | 07 92 00 | 3 | Product Data | Sealants | 2.2 | |||||||||||||||
| 196 | 07 92 00 | 3 | Product Data | Primers | 2.3 | |||||||||||||||
| 197 | 07 92 00 | 3 | Product Data | Bond Breakers | 2.4 | |||||||||||||||
| 198 | 07 92 00 | 3 | Product Data | Backstops | 2.5 | |||||||||||||||
| 199 | 07 92 00 | 7 | Certificates | Indoor Air Quality | 1.4.1 | G | ||||||||||||||
| 200 | 07 92 00 | 7 | Certificates | Sealants | 2.2 | |||||||||||||||
| 201 | 07 92 00 | 11 | Closeout Submittals | Indoor Air Quality For Interior Sealants | 2.2.1 | S | ||||||||||||||
| 202 | 07 92 00 | 11 | Closeout Submittals | Indoor Air Quality For Interior Floor Joint Sealants | 2.2.3 | S | ||||||||||||||
| 203 | 08 11 13 | 2 | Shop Drawings | Doors | 2.1 | G | ||||||||||||||
| 204 | 08 11 13 | 2 | Shop Drawings | Doors | 2.1 | G | ||||||||||||||
| 205 | 08 11 13 | 2 | Shop Drawings | Frames | 2.4 | G | ||||||||||||||
| 206 | 08 11 13 | 2 | Shop Drawings | Frames | 2.4 | G | ||||||||||||||
| 207 | 08 11 13 | 2 | Shop Drawings | Accessories | 2.2 | |||||||||||||||
| 208 | 08 11 13 | 2 | Shop Drawings | Weatherstripping | 2.5 | |||||||||||||||
| 209 | 08 11 13 | 3 | Product Data | Doors | 2.1 | G | ||||||||||||||
| 210 | 08 11 13 | 3 | Product Data | Frames | 2.4 | G | ||||||||||||||
| 211 | 08 11 13 | 3 | Product Data | Accessories | 2.2 | |||||||||||||||
| 212 | 08 11 13 | 3 | Product Data | Weatherstripping | 2.5 | |||||||||||||||
| 213 | 08 39 53 | 2 | Shop Drawings | Blast Resistant Door | 1.2 | G | ||||||||||||||
| 214 | 08 39 53 | 2 | Shop Drawings | Trolley Rail Beam | 2.3.1.3 | G | ||||||||||||||
| 215 | 08 39 53 | 2 | Shop Drawings | Trolleys | 2.3.1 | G | ||||||||||||||
| 216 | 08 39 53 | 3 | Product Data | Trolleys | 2.3.1 | G | ||||||||||||||
| 217 | 08 39 53 | 4 | Samples | Air Line Supports | G | |||||||||||||||
| 218 | 08 39 53 | 5 | Design Data | Electric Motor Operator | 2.3.1.1 | G | ||||||||||||||
| 219 | 08 39 53 | 5 | Design Data | Auxiliary Manual Operator | 2.3.1.2 | G | ||||||||||||||
| 220 | 08 39 53 | 6 | Test Reports | Seal System | G | |||||||||||||||
| 221 | 08 39 53 | 6 | Test Reports | Operational Test | G | |||||||||||||||
| 222 | 08 39 53 | 7 | Certificates | Manufacturer Certificates | ||||||||||||||||
| 223 | 08 39 53 | 7 | Certificates | Welder Certificates | ||||||||||||||||
| 224 | 08 39 53 | 8 | Manufacturer’s Instructions | Welding Procedure | G | |||||||||||||||
| 225 | 08 39 53 | 10 | Operation and Maintenance Data | Blast Resistant Door | 1.2 | G | ||||||||||||||
| 226 | 08 39 53 | 10 | Operation and Maintenance Data | Door Operating System, Data Package | G | |||||||||||||||
| 227 | 08 39 53 | 10 | Operation and Maintenance Data | Seals, Data Package | G | |||||||||||||||
| 228 | 08 39 53 | 10 | Operation and Maintenance Data | Compressor and Desiccant Air Filter, Data Package | G | |||||||||||||||
| 229 | 08 71 00 | 2 | Shop Drawings | Manufacturer's Detail Drawings | 1.3 | G | ||||||||||||||
| 230 | 08 71 00 | 2 | Shop Drawings | Verification of Existing Conditions | 1.3 | G | ||||||||||||||
| 231 | 08 71 00 | 2 | Shop Drawings | Hardware Schedule | 1.5 | G | ||||||||||||||
| 232 | 08 71 00 | 2 | Shop Drawings | Keying System | 2.3.5 | G | ||||||||||||||
| 233 | 08 71 00 | 3 | Product Data | Hardware Items | 2.3 | G | ||||||||||||||
| 234 | 08 71 00 | 8 | Manufacturer’s Instructions | Installation | 3.1 | |||||||||||||||
| 235 | 08 71 00 | 10 | Operation and Maintenance Data | Hardware Schedule | 1.5 | G | ||||||||||||||
| 236 | 08 71 00 | 11 | Closeout Submittals | Key Bitting | 1.6.1 | |||||||||||||||
| 237 | 08 91 00 | 2 | Shop Drawings | Wall louvers | 1.4 | |||||||||||||||
| 238 | 08 91 00 | 2 | Shop Drawings | Wall louvers | 1.5 | |||||||||||||||
| 239 | 08 91 00 | 3 | Product Data | Metal Wall Louvers | 2.2 | |||||||||||||||
| 240 | 08 91 00 | 4 | Samples | Wall louvers | 1.4 | G | ||||||||||||||
| 241 | 08 91 00 | 4 | Samples | Wall louvers | 1.5 | G | ||||||||||||||
| 242 | 08 91 00 | 4 | Samples | Door louvers | 1.5 | G | ||||||||||||||
| 243 | 09 96 00 | 1 | Preconstruction Submittals | Equipment List | 1.3 | |||||||||||||||
| 244 | 09 96 00 | 3 | Product Data | Heat-Resistant Coatings | 2.1.1 | |||||||||||||||
| 245 | 09 96 00 | 3 | Product Data | Epoxy Coatings | 2.2.1 | |||||||||||||||
| 246 | 09 96 00 | 3 | Product Data | Polyurethane Coatings | 2.2.2 | |||||||||||||||
| 247 | 09 96 00 | 4 | Samples | Color Chips | 1.3 | |||||||||||||||
| 248 | 09 96 00 | 7 | Certificates | Heat-Resistant Coatings | 2.1.1 | |||||||||||||||
| 249 | 09 96 00 | 7 | Certificates | Epoxy Coatings | 2.2.1 | |||||||||||||||
| 250 | 09 96 00 | 7 | Certificates | Polyurethane Coatings | 2.2.2 | |||||||||||||||
| 251 | 09 96 00 | 7 | Certificates | Manufacturer's Printed Instructions | 3.1.4 | |||||||||||||||
| 252 | 10 14 00.10 | 2 | Shop Drawings | Approved Detail Drawings | 3.1 | G | ||||||||||||||
| 253 | 10 14 00.10 | 3 | Product Data | Modular Exterior Signage System | 2.1 | |||||||||||||||
| 254 | 10 14 00.10 | 3 | Product Data | Installation | 3.1 | |||||||||||||||
| 255 | 10 14 00.10 | 3 | Product Data | Exterior Signage | 1.2 | G | ||||||||||||||
| 256 | 10 14 00.10 | 3 | Product Data | Wind Load Requirements | 1.2.1 | |||||||||||||||
| 257 | 10 14 00.10 | 4 | Samples | Exterior Signage | 1.2 | G | ||||||||||||||
| 258 | 10 14 00.10 | 10 | Operation and Maintenance Data | Protection and Cleaning | 3.1.2 | G | ||||||||||||||
| 259 | 13 48 00 | 2 | Shop Drawings | Bracing | 3.1 | G | ||||||||||||||
| 260 | 13 48 00 | 2 | Shop Drawings | Resilient Vibration Isolation Devices | 3.4 | G | ||||||||||||||
| 261 | 13 48 00 | 2 | Shop Drawings | Equipment Requirements | 2.1 | G | ||||||||||||||
| 262 | 13 48 00 | 3 | Product Data | Bracing | 3.1 | G | ||||||||||||||
| 263 | 13 48 00 | 3 | Product Data | Equipment Requirements | 2.1 | G | ||||||||||||||
| 264 | 13 48 00 | 3 | Product Data | Anchor Bolts | 3.3 | G | ||||||||||||||
| 265 | 13 48 00 | 3 | Product Data | Vibration Isolators | 2.1.2 | G | ||||||||||||||
| 266 | 13 48 00 | 3 | Product Data | Snubbers | 3.4.2 | G | ||||||||||||||
| 267 | 13 48 00 | 5 | Design Data | Design Calculations | 1.2.3 | G | ||||||||||||||
| 268 | 13 48 00 | 6 | Test Reports | Anchor Bolts | 3.3 | G | ||||||||||||||
| 269 | 13 48 00 | 7 | Certificates | ICC ES AC156 Shake Table Test | 3.6 | G | ||||||||||||||
| 270 | 22 00 00 | 3 | Product Data | Recycled Content for Cast Iron Pipe | 2.1 | S | ||||||||||||||
| 271 | 22 00 00 | 3 | Product Data | Welding | ||||||||||||||||
| 272 | 22 00 00 | 3 | Product Data | Vibration-Absorbing Features | 3.2 | G | ||||||||||||||
| 273 | 22 00 00 | 3 | Product Data | Plumbing System | 3.3.1 | |||||||||||||||
| 274 | 22 00 00 | 6 | Test Reports | Tests, Flushing and Disinfection | 3.3 | |||||||||||||||
| 275 | 22 00 00 | 7 | Certificates | Materials and Equipment | 1.3 | |||||||||||||||
| 276 | 22 00 00 | 7 | Certificates | Bolts | ||||||||||||||||
| 277 | 22 00 00 | 10 | Operation and Maintenance Data | Plumbing System | 3.3.1 | G | ||||||||||||||
| 278 | 23 00 00 | 2 | Shop Drawings | Detail Drawings | 1.4.3 | G | ||||||||||||||
| 279 | 23 00 00 | 3 | Product Data | Duct Access Doors | 2.9.2 | G | ||||||||||||||
| 280 | 23 00 00 | 3 | Product Data | Fire Dampers | 2.9.3 | |||||||||||||||
| 281 | 23 00 00 | 3 | Product Data | Registers and Grilles | 2.9.5.1 | |||||||||||||||
| 282 | 23 00 00 | 3 | Product Data | Louvers | 2.9.6 | |||||||||||||||
| 283 | 23 00 00 | 3 | Product Data | In-Line Centrifugal Fans | 2.10.1.1 | |||||||||||||||
| 284 | 23 00 00 | 3 | Product Data | Diagrams | 1.2.1.2 | G | ||||||||||||||
| 285 | 23 00 00 | 6 | Test Reports | Performance Tests | 3.1 | G | ||||||||||||||
| 286 | 23 00 00 | 6 | Test Reports | Damper Acceptance Test | 3.8 | G | ||||||||||||||
| 287 | 23 00 00 | 7 | Certificates | Bolts | 1.4.1 | |||||||||||||||
| 288 | 23 00 00 | 8 | Manufacturer’s Instructions | Manufacturer's Installation Instructions | 3.2 | |||||||||||||||
| 289 | 23 00 00 | 8 | Manufacturer’s Instructions | Operation and Maintenance Training | 3.12.2 | |||||||||||||||
| 290 | 23 00 00 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 3.12.1 | G | ||||||||||||||
| 291 | 23 00 00 | 10 | Operation and Maintenance Data | Fire Dampers | 2.9.3 | G | ||||||||||||||
| 292 | 23 00 00 | 11 | Closeout Submittals | Indoor Air Quality During Construction | 3.11 | S | ||||||||||||||
| 293 | 23 05 48 | 2 | Shop Drawings | Installation Drawings | 1.2 | G | ||||||||||||||
| 294 | 23 05 48 | 2 | Shop Drawings | Outline Drawings | 1.2 | G | ||||||||||||||
| 295 | 23 05 48 | 3 | Product Data | Equipment and Performance Data | 1.2 | |||||||||||||||
| 296 | 23 05 48 | 3 | Product Data | Isolators | 2.2.1 | G | ||||||||||||||
| 297 | 23 05 48 | 6 | Test Reports | Type of Isolator | 2.4 | G | ||||||||||||||
| 298 | 23 05 48 | 6 | Test Reports | Type of Base | 2.4 | |||||||||||||||
| 299 | 23 05 48 | 6 | Test Reports | Allowable Deflection | 2.4 | G | ||||||||||||||
| 300 | 23 05 48 | 6 | Test Reports | Measured Deflection | 2.4 | G | ||||||||||||||
| 301 | 23 05 48.19 | 2 | Shop Drawings | Coupling and Bracing | 3.1 | |||||||||||||||
| 302 | 23 05 48.19 | 2 | Shop Drawings | Flexible Couplings or Joints | 3.3 | |||||||||||||||
| 303 | 23 05 48.19 | 2 | Shop Drawings | Equipment Restraint | 2.2 | |||||||||||||||
| 304 | 23 05 48.19 | 2 | Shop Drawings | Contractor Designed Bracing | 1.2.4 | G | ||||||||||||||
| 305 | 23 05 48.19 | 3 | Product Data | Coupling and Bracing | 3.1 | G | ||||||||||||||
| 306 | 23 05 48.19 | 3 | Product Data | Flexible Couplings Or Joints | 3.3 | G | ||||||||||||||
| 307 | 23 05 48.19 | 3 | Product Data | Equipment Restraint | 2.2 | G | ||||||||||||||
| 308 | 23 05 48.19 | 3 | Product Data | Contractor Designed Bracing | 1.2.4 | G | ||||||||||||||
| 309 | 23 05 48.19 | 3 | Product Data | Anchor Bolts | 3.9 | |||||||||||||||
| 310 | 23 05 48.19 | 5 | Design Data | Design Calculations | 1.2.4 | G | ||||||||||||||
| 311 | 23 05 48.19 | 6 | Test Reports | Anchor Bolts | 3.9 | G | ||||||||||||||
| 312 | 23 05 93 | 1 | Preconstruction Submittals | Independent TAB Agency and Personnel Qualifications | 1.5.1 | G | ||||||||||||||
| 313 | 23 05 93 | 1 | Preconstruction Submittals | TAB Design Review Report | 1.6.1.1 | G | ||||||||||||||
| 314 | 23 05 93 | 1 | Preconstruction Submittals | TAB Firm | 1.5.8.1 | G | ||||||||||||||
| 315 | 23 05 93 | 1 | Preconstruction Submittals | TAB Team Assistants | 1.2 | G | ||||||||||||||
| 316 | 23 05 93 | 1 | Preconstruction Submittals | TAB Team Engineer | 1.2 | G | ||||||||||||||
| 317 | 23 05 93 | 1 | Preconstruction Submittals | TAB Specialist | 1.5.8.2 | G | ||||||||||||||
| 318 | 23 05 93 | 1 | Preconstruction Submittals | TAB Team Field Leader | 1.2 | G | ||||||||||||||
| 319 | 23 05 93 | 2 | Shop Drawings | TAB Schematic Drawings and Report Forms | 1.3.2 | G | ||||||||||||||
| 320 | 23 05 93 | 3 | Product Data | Equipment and Performance Data | 1.3 | G | ||||||||||||||
| 321 | 23 05 93 | 3 | Product Data | TAB Related HVAC Submittals | 1.5.1.3 | G | ||||||||||||||
| 322 | 23 05 93 | 3 | Product Data | TAB Related HVAC Submittals | 1.5.8.4 | G | ||||||||||||||
| 323 | 23 05 93 | 3 | Product Data | TAB Procedures | 1.5.6 | G | ||||||||||||||
| 324 | 23 05 93 | 3 | Product Data | Calibration | 1.5.6 | G | ||||||||||||||
| 325 | 23 05 93 | 3 | Product Data | Systems Readiness Check | 1.3.2 | G | ||||||||||||||
| 326 | 23 05 93 | 3 | Product Data | TAB Execution | 1.5.2 | G | ||||||||||||||
| 327 | 23 05 93 | 3 | Product Data | TAB Verification | 1.5.2.3 | G | ||||||||||||||
| 328 | 23 05 93 | 6 | Test Reports | Completed Pre-Final DALT Report | 3.3.5 | G | ||||||||||||||
| 329 | 23 05 93 | 6 | Test Reports | Certified Final DALT Report | 3.3.8 | G | ||||||||||||||
| 330 | 23 05 93 | 6 | Test Reports | Prerequisite HVAC Work Checkout List | 1.5.3.1 | G | ||||||||||||||
| 331 | 23 05 93 | 6 | Test Reports | Prerequisite HVAC Work Checkout List | 1.5.3.1 | G | ||||||||||||||
| 332 | 23 05 93 | 6 | Test Reports | Prerequisite HVAC Work Checkout List | 1.5.3.1 | G | ||||||||||||||
| 333 | 23 05 93 | 6 | Test Reports | Proportional Balancing | 3.4.4.1 | G | ||||||||||||||
| 334 | 23 05 93 | 6 | Test Reports | Proportional Balancing | 3.7 | G | ||||||||||||||
| 335 | 23 05 93 | 6 | Test Reports | Season 1 | 3.4.4.2 | G | ||||||||||||||
| 336 | 23 05 93 | 6 | Test Reports | Season 1 | 3.7 | G | ||||||||||||||
| 337 | 23 05 93 | 6 | Test Reports | Season 2 | 3.4.4.2 | G | ||||||||||||||
| 338 | 23 05 93 | 6 | Test Reports | Season 2 | 3.7 | G | ||||||||||||||
| 339 | 23 05 93 | 6 | Test Reports | TAB Design Review Report | 1.6.1.1 | G | ||||||||||||||
| 340 | 23 05 93 | 6 | Test Reports | TAB Report for Season 1 | 1.5.9.2 | G | ||||||||||||||
| 341 | 23 05 93 | 6 | Test Reports | TAB Report for Season 2 | 1.5.9.2 | G | ||||||||||||||
| 342 | 23 05 93 | 7 | Certificates | Independent TAB Agency and Personnel Qualifications | 1.5.1 | G | ||||||||||||||
| 343 | 23 05 93 | 7 | Certificates | DALT and TAB Submittal and Work Schedule | 1.6.1 | G | ||||||||||||||
| 344 | 23 05 93 | 7 | Certificates | TAB Pre-Field Engineering Report | 1.5.3.1 | G | ||||||||||||||
| 345 | 23 05 93 | 7 | Certificates | TAB Pre-Field Engineering Report | 1.6.1.3 | G | ||||||||||||||
| 346 | 23 05 93 | 7 | Certificates | Instrument Calibration Certificates | 1.5.5 | G | ||||||||||||||
| 347 | 23 05 93 | 7 | Certificates | DALT and TAB Procedures Summary | 3.7 | G | ||||||||||||||
| 348 | 23 05 93 | 7 | Certificates | Completed Pre-Final DALT Work Checklist | 3.7 | G | ||||||||||||||
| 349 | 23 05 93 | 7 | Certificates | Advance Notice of Pre-Final DALT Field Work | 3.3.2 | G | ||||||||||||||
| 350 | 23 05 93 | 7 | Certificates | Proportional Balancing | 3.4.4.1 | G | ||||||||||||||
| 351 | 23 05 93 | 7 | Certificates | Proportional Balancing | 3.7 | G | ||||||||||||||
| 352 | 23 05 93 | 7 | Certificates | Season 1 | 3.4.4.2 | G | ||||||||||||||
| 353 | 23 05 93 | 7 | Certificates | Season 1 | 3.7 | G | ||||||||||||||
| 354 | 23 05 93 | 7 | Certificates | Season 2 | 3.4.4.2 | G | ||||||||||||||
| 355 | 23 05 93 | 7 | Certificates | Season 2 | 3.7 | G | ||||||||||||||
| 356 | 23 05 93 | 7 | Certificates | TAB Firm | 1.5.8.1 | G | ||||||||||||||
| 357 | 23 05 93 | 7 | Certificates | Design Review Report | 1.3.2 | G | ||||||||||||||
| 358 | 23 05 93 | 7 | Certificates | Pre-field DALT Preliminary Notification | 1.6.1.2 | G | ||||||||||||||
| 359 | 23 05 93 | 7 | Certificates | Advanced Notice for Season 1 TAB Field Work | 1.6.1 | G | ||||||||||||||
| 360 | 23 05 93 | 7 | Certificates | Prerequisite HVAC Work Check Out List For Season 1 | 1.6.1 | G | ||||||||||||||
| 361 | 23 05 93 | 7 | Certificates | Advanced Notice for Season 2 TAB Field Work | 1.6.1 | G | ||||||||||||||
| 362 | 23 05 93 | 7 | Certificates | Prerequisite HVAC Work Check Out List For Season 2 | 1.6.1 | G | ||||||||||||||
| 363 | 23 07 00 | 2 | Shop Drawings | MICA Plates | 3.2.2.4 | G | ||||||||||||||
| 364 | 23 07 00 | 2 | Shop Drawings | Pipe Insulation Systems | 2.3 | |||||||||||||||
| 365 | 23 07 00 | 2 | Shop Drawings | Pipe Insulation Systems | 3.2 | |||||||||||||||
| 366 | 23 07 00 | 2 | Shop Drawings | Duct Insulation Systems | 3.3 | |||||||||||||||
| 367 | 23 07 00 | 2 | Shop Drawings | Recycled content for insulation materials | 2.3.1 | S | ||||||||||||||
| 368 | 23 07 00 | 3 | Product Data | Pipe Insulation Systems | 2.3 | G | ||||||||||||||
| 369 | 23 07 00 | 3 | Product Data | Pipe Insulation Systems | 3.2 | G | ||||||||||||||
| 370 | 23 07 00 | 3 | Product Data | Duct Insulation Systems | 3.3 | G | ||||||||||||||
| 371 | 23 07 00 | 4 | Samples | Thermal Insulation | 2.2.1.2 | G | ||||||||||||||
| 372 | 23 07 00 | 4 | Samples | Display Samples | 3.1.1 | G | ||||||||||||||
| 373 | 23 07 00 | 7 | Certificates | Indoor air quality for adhesives | 2.2.1 | S | ||||||||||||||
| 374 | 23 07 00 | 8 | Manufacturer’s Instructions | Pipe Insulation Systems | 2.3 | G | ||||||||||||||
| 375 | 23 07 00 | 8 | Manufacturer’s Instructions | Pipe Insulation Systems | 3.2 | G | ||||||||||||||
| 376 | 23 07 00 | 8 | Manufacturer’s Instructions | Duct Insulation Systems | 3.3 | G | ||||||||||||||
| 377 | 23 09 00 | 2 | Shop Drawings | DDC Contractor Design Drawings | 3.3 | G | ||||||||||||||
| 378 | 23 09 00 | 2 | Shop Drawings | Draft As-Built Drawings | 3.3 | G | ||||||||||||||
| 379 | 23 09 00 | 2 | Shop Drawings | Final As-Built Drawings | 3.3 | G | ||||||||||||||
| 380 | 23 09 00 | 2 | Shop Drawings | Controller Application Programs | 1.8.4 | G | ||||||||||||||
| 381 | 23 09 00 | 2 | Shop Drawings | Manufacturer's Product Data | 2.2 | G | ||||||||||||||
| 382 | 23 09 00 | 6 | Test Reports | Start-Up Testing Report | 3.5.2 | G | ||||||||||||||
| 383 | 23 09 00 | 6 | Test Reports | PVT Procedures | 3.6.1 | G | ||||||||||||||
| 384 | 23 09 00 | 6 | Test Reports | PVT Report | 3.6.3 | G | ||||||||||||||
| 385 | 23 09 00 | 6 | Test Reports | Pre-Construction Quality Control (QC) Checklist | 1.9.1 | G | ||||||||||||||
| 386 | 23 09 00 | 6 | Test Reports | Post-Construction Quality Control (QC) Checklist | 1.9.2 | G | ||||||||||||||
| 387 | 23 09 00 | 10 | Operation and Maintenance Data | Operation and Maintenance (O&M) Instructions | 3.7 | G | ||||||||||||||
| 388 | 23 09 00 | 10 | Operation and Maintenance Data | Training Documentation | 3.9.1 | G | ||||||||||||||
| 389 | 23 09 00 | 11 | Closeout Submittals | Closeout Quality Control (QC) Checklist | 1.9.3 | G | ||||||||||||||
| 390 | 23 11 25 | 2 | Shop Drawings | Gas Piping System | 1.5.3 | G | ||||||||||||||
| 391 | 23 11 25 | 2 | Shop Drawings | Gas Piping System | 2.2 | G | ||||||||||||||
| 392 | 23 11 25 | 2 | Shop Drawings | Gas Piping System | 3.3 | G | ||||||||||||||
| 393 | 23 11 25 | 3 | Product Data | Pipe and Fittings | 1.6.1 | G | ||||||||||||||
| 394 | 23 11 25 | 3 | Product Data | Gas Equipment Connectors | 1.5.3 | G | ||||||||||||||
| 395 | 23 11 25 | 3 | Product Data | Gas Piping System | 1.5.3 | G | ||||||||||||||
| 396 | 23 11 25 | 3 | Product Data | Gas Piping System | 2.2 | G | ||||||||||||||
| 397 | 23 11 25 | 3 | Product Data | Gas Piping System | 3.3 | G | ||||||||||||||
| 398 | 23 11 25 | 3 | Product Data | Pipe Coating Materials | 2.1 | G | ||||||||||||||
| 399 | 23 11 25 | 3 | Product Data | Pressure Regulators | 2.7.1 | G | ||||||||||||||
| 400 | 23 11 25 | 3 | Product Data | Risers | 2.4 | G | ||||||||||||||
| 401 | 23 11 25 | 3 | Product Data | Transition Fittings | 2.2.8 | G | ||||||||||||||
| 402 | 23 11 25 | 3 | Product Data | Valves | 2.3 | G | ||||||||||||||
| 403 | 23 11 25 | 3 | Product Data | Warning and Identification Tape | 2.2.5 | G | ||||||||||||||
| 404 | 23 11 25 | 3 | Product Data | Gas Meter | 2.7.2 | G | ||||||||||||||
| 405 | 23 11 25 | 6 | Test Reports | Testing | 3.15 | G | ||||||||||||||
| 406 | 23 11 25 | 6 | Test Reports | Pressure Tests | 3.15.1 | G | ||||||||||||||
| 407 | 23 11 25 | 6 | Test Reports | Test with Gas | 3.15.2 | G | ||||||||||||||
| 408 | 23 11 25 | 7 | Certificates | Welders Procedures and Qualifications | 1.5.1 | G | ||||||||||||||
| 409 | 23 11 25 | 7 | Certificates | Assigned Number, Letter, or Symbol | 1.5.1 | G | ||||||||||||||
| 410 | 23 11 25 | 8 | Manufacturer’s Instructions | PE Pipe and Fittings | 1.5.2 | G | ||||||||||||||
| 411 | 23 11 25 | 8 | Manufacturer’s Instructions | Pipe Coating Materials | 2.1 | G | ||||||||||||||
| 412 | 23 11 25 | 10 | Operation and Maintenance Data | Gas Facility System and Equipment Operation | 1.3.1 | G | ||||||||||||||
| 413 | 23 11 25 | 10 | Operation and Maintenance Data | Gas Facility System Maintenance | 1.3.2 | G | ||||||||||||||
| 414 | 23 11 25 | 10 | Operation and Maintenance Data | Gas Facility Equipment Maintenance | 1.3.3 | G | ||||||||||||||
| 415 | 23 31 13 | 1 | Preconstruction Submittals | Material, Equipment, and Fixture Lists | Part 2 | G | ||||||||||||||
| 416 | 23 31 13 | 2 | Shop Drawings | Connection Diagrams | 2.1 | G | ||||||||||||||
| 417 | 23 31 13 | 2 | Shop Drawings | Offset Fitting Configurations | 2.2.1 | G | ||||||||||||||
| 418 | 23 31 13 | 2 | Shop Drawings | Detailed Underground Ductwork Shop Drawings | 2.3.4 | G | ||||||||||||||
| 419 | 23 31 13 | 3 | Product Data | Galvanized Steel Ductwork Materials | 2.3.1 | G | ||||||||||||||
| 420 | 23 31 13 | 3 | Product Data | HDPE Underground Ductwork Materials | 2.3.4 | G | ||||||||||||||
| 421 | 23 31 13 | 3 | Product Data | Underground Ductwork Sealants and Gaskets | 2.3.4 | G | ||||||||||||||
| 422 | 23 31 13 | 3 | Product Data | Modular Compression Seals | 2.3.4.1 | G | ||||||||||||||
| 423 | 23 31 13 | 3 | Product Data | Brazing Materials | 2.3.2 | |||||||||||||||
| 424 | 23 31 13 | 3 | Product Data | Mill-Rolled Reinforcing and Supporting Materials | 2.3.3 | |||||||||||||||
| 425 | 23 31 13 | 3 | Product Data | Round Sheet Metal Duct Fittings | 2.2.1 | G | ||||||||||||||
| 426 | 23 31 13 | 3 | Product Data | Turning Vanes | 2.2.2 | G | ||||||||||||||
| 427 | 23 31 13 | 3 | Product Data | Flexible Connectors | 2.2.4 | G | ||||||||||||||
| 428 | 23 31 13 | 3 | Product Data | Motor Operated Dampers | 2.2.8 | G | ||||||||||||||
| 429 | 23 31 13 | 3 | Product Data | Fire Dampers and Wall Collars | 2.2.9 | G | ||||||||||||||
| 430 | 23 31 13 | 3 | Product Data | Manual Volume Dampers | 2.2.7 | G | ||||||||||||||
| 431 | 23 31 13 | 6 | Test Reports | Ductwork Leakage Tests | 3.4.1 | G | ||||||||||||||
| 432 | 23 31 13 | 7 | Certificates | Listing of Product Installations | 1.3 | |||||||||||||||
| 433 | 23 31 13 | 7 | Certificates | Galvanized Steel Ductwork Materials | 2.3.1 | |||||||||||||||
| 434 | 23 31 13 | 7 | Certificates | Brazing Materials | 2.3.2 | |||||||||||||||
| 435 | 23 31 13 | 7 | Certificates | Mill-Rolled Reinforcing and Supporting Materials | 2.3.3 | |||||||||||||||
| 436 | 23 31 13 | 7 | Certificates | Round Sheet Metal Duct Fittings | 2.2.1 | |||||||||||||||
| 437 | 23 31 13 | 7 | Certificates | Turning Vanes | 2.2.2 | |||||||||||||||
| 438 | 23 31 13 | 7 | Certificates | Dampers | 2.2.3 | |||||||||||||||
| 439 | 23 31 13 | 7 | Certificates | Flexible Connectors | 2.2.4 | |||||||||||||||
| 440 | 23 31 13 | 7 | Certificates | Bolts for Underground Ductwork | 2.3.4 | G | ||||||||||||||
| 441 | 23 31 13 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 3.5.1 | G | ||||||||||||||
| 442 | 23 31 13 | 10 | Operation and Maintenance Data | Motor Operated Dampers | 2.2.8 | G | ||||||||||||||
| 443 | 23 31 13 | 11 | Closeout Submittals | Record Drawings | 3.5.2 | G | ||||||||||||||
| 444 | 23 54 16 | 2 | Shop Drawings | Detail Drawings | 1.3 | |||||||||||||||
| 445 | 23 54 16 | 2 | Shop Drawings | Installation | 3.2 | |||||||||||||||
| 446 | 23 54 16 | 3 | Product Data | Spare Parts | 1.5 | |||||||||||||||
| 447 | 23 54 16 | 3 | Product Data | Self-Contained Furnace | 2.4 | G | ||||||||||||||
| 448 | 23 54 16 | 6 | Test Reports | Testing, Adjusting, and Balancing | 3.4 | |||||||||||||||
| 449 | 23 54 16 | 10 | Operation and Maintenance Data | Operation And Maintenance Instructions | 3.3 | G | ||||||||||||||
| 450 | 23 81 00.00 | 2 | Shop Drawings | Field-Assembled Refrigerant Piping | 2.4.1 | |||||||||||||||
| 451 | 23 81 00.00 | 2 | Shop Drawings | Control System Wiring Diagrams | 1.4.2 | |||||||||||||||
| 452 | 23 81 00.00 | 3 | Product Data | Air Conditioners | 2.1 | |||||||||||||||
| 453 | 23 81 00.00 | 3 | Product Data | Energy Star Label for Split-System Type Air Conditioners | 2.1.1 | S | ||||||||||||||
| 454 | 23 81 00.00 | 3 | Product Data | Refrigerant | 1.5 | |||||||||||||||
| 455 | 23 81 00.00 | 3 | Product Data | Refrigerant Piping and Accessories | 2.4 | |||||||||||||||
| 456 | 23 81 00.00 | 3 | Product Data | Coatings for Finned Tube Coils | 2.2 | |||||||||||||||
| 457 | 23 81 00.00 | 6 | Test Reports | Salt-Spray Tests | 2.6.1 | |||||||||||||||
| 458 | 23 81 00.00 | 6 | Test Reports | Start-Up and Initial Operational Tests | 3.5.3 | |||||||||||||||
| 459 | 23 81 00.00 | 7 | Certificates | Ozone Depleting Substances Technician Certification | 1.4.6 | |||||||||||||||
| 460 | 23 81 00.00 | 8 | Manufacturer’s Instructions | Air Conditioners | 2.1 | |||||||||||||||
| 461 | 23 81 00.00 | 8 | Manufacturer’s Instructions | Refrigerant Piping and Accessories | 2.4 | |||||||||||||||
| 462 | 23 81 00.00 | 10 | Operation and Maintenance Data | Air Conditioners | 2.1 | |||||||||||||||
| 463 | 23 81 00.00 | 11 | Closeout Submittals | Posted Operating Instructions | 1.4.4 | |||||||||||||||
| 464 | 23 83 00 | 2 | Shop Drawings | Heater installation drawing | 3.1 | |||||||||||||||
| 465 | 23 83 00 | 2 | Shop Drawings | Electric Radiant Snow Melt System | 2.2 | G | ||||||||||||||
| 466 | 23 83 00 | 3 | Product Data | Electric Unit Heaters | 2.1 | G | ||||||||||||||
| 467 | 23 83 00 | 3 | Product Data | Thermostat | 2.1.6 | |||||||||||||||
| 468 | 23 83 00 | 3 | Product Data | Electric Radiant Snow Melt System | 2.2 | G | ||||||||||||||
| 469 | 23 83 00 | 10 | Operation and Maintenance Data | Electric unit heaters | 2.1 | |||||||||||||||
| 470 | 23 83 00 | 10 | Operation and Maintenance Data | Electric Radiant Snow Melt System | 2.2 | |||||||||||||||
| 471 | 26 05 00 | 1 | Preconstruction Submittals | Material, Equipment, and Fixture Lists | 2.1 | |||||||||||||||
| 472 | 26 05 00 | 3 | Product Data | Conduits and Raceways | 2.1.1 | G | ||||||||||||||
| 473 | 26 05 00 | 3 | Product Data | Wire and Cable | 2.1.3 | G | ||||||||||||||
| 474 | 26 05 00 | 3 | Product Data | Splices and Connectors | 3.2.1.9 | G | ||||||||||||||
| 475 | 26 05 00 | 3 | Product Data | Switches | 2.1.4 | G | ||||||||||||||
| 476 | 26 05 00 | 3 | Product Data | Receptacles | 2.1.5 | G | ||||||||||||||
| 477 | 26 05 00 | 3 | Product Data | Outlet Boxes, Pull Boxes and Junction Boxes | 2.1.6 | G | ||||||||||||||
| 478 | 26 05 00 | 3 | Product Data | Circuit Breakers | 2.1.8 | G | ||||||||||||||
| 479 | 26 05 00 | 3 | Product Data | Panelboards | 2.1.7 | G | ||||||||||||||
| 480 | 26 05 00 | 3 | Product Data | Lamps and Lighting Fixtures | 2.1.9 | G | ||||||||||||||
| 481 | 26 05 00 | 3 | Product Data | Dry-Type Distribution Transformers | 2.1.12 | G | ||||||||||||||
| 482 | 26 05 00 | 6 | Test Reports | Continuity Test | 3.3 | G | ||||||||||||||
| 483 | 26 05 00 | 6 | Test Reports | Phase-Rotation Tests | 3.3 | G | ||||||||||||||
| 484 | 26 05 00 | 6 | Test Reports | Insulation Resistance Test | 3.3 | G | ||||||||||||||
| 485 | 26 05 00 | 8 | Manufacturer’s Instructions | Manufacturer's Instructions | 3.1 | |||||||||||||||
| 486 | 26 05 48 | 2 | Shop Drawings | Lighting Fixtures in Buildings | 3.2 | |||||||||||||||
| 487 | 26 05 48 | 2 | Shop Drawings | Equipment Requirements | 1.3 | |||||||||||||||
| 488 | 26 05 48 | 3 | Product Data | Lighting Fixtures in Buildings | 3.2 | G | ||||||||||||||
| 489 | 26 05 48 | 3 | Product Data | Equipment Requirements | 1.3 | G | ||||||||||||||
| 490 | 26 05 48 | 3 | Product Data | Contractor Designed Bracing | 1.2.4 | G | ||||||||||||||
| 491 | 26 08 00 | 6 | Test Reports | Acceptance tests and inspections | 3.1 | G | ||||||||||||||
| 492 | 26 08 00 | 7 | Certificates | Qualifications | 1.4.1 | G | ||||||||||||||
| 493 | 26 08 00 | 7 | Certificates | Acceptance test and inspections procedure | 1.4.3 | G | ||||||||||||||
| 494 | 26 20 00 | 2 | Shop Drawings | Panelboards | 2.12 | G | ||||||||||||||
| 495 | 26 20 00 | 2 | Shop Drawings | Transformers | 2.14 | G | ||||||||||||||
| 496 | 26 20 00 | 2 | Shop Drawings | Cable trays | 2.3 | G | ||||||||||||||
| 497 | 26 20 00 | 2 | Shop Drawings | Generator Docking Station | 2.3 | G | ||||||||||||||
| 498 | 26 20 00 | 2 | Shop Drawings | Generator Docking Station | 3.1.16 | G | ||||||||||||||
| 499 | 26 20 00 | 2 | Shop Drawings | Generator Docking Station | 3.5.7 | G | ||||||||||||||
| 500 | 26 20 00 | 2 | Shop Drawings | Wireways | 2.25 | G | ||||||||||||||
| 501 | 26 20 00 | 2 | Shop Drawings | Marking strips | 3.1.8.1 | G | ||||||||||||||
| 502 | 26 20 00 | 3 | Product Data | Receptacles | 2.11 | G | ||||||||||||||
| 503 | 26 20 00 | 3 | Product Data | Circuit breakers | 2.12.3 | G | ||||||||||||||
| 504 | 26 20 00 | 3 | Product Data | Switches | 2.9 | G | ||||||||||||||
| 505 | 26 20 00 | 3 | Product Data | Transformers | 2.14 | G | ||||||||||||||
| 506 | 26 20 00 | 3 | Product Data | Enclosed circuit breakers | 2.13 | G | ||||||||||||||
| 507 | 26 20 00 | 3 | Product Data | Motor controllers | 2.16 | G | ||||||||||||||
| 508 | 26 20 00 | 3 | Product Data | Manual motor starters | 2.17 | G | ||||||||||||||
| 509 | 26 20 00 | 3 | Product Data | Grounding Busbar | 2.20.3 | G | ||||||||||||||
| 510 | 26 20 00 | 3 | Product Data | Surge protective devices | 2.26 | G | ||||||||||||||
| 511 | 26 20 00 | 3 | Product Data | Generator Docking Station | 2.3 | G | ||||||||||||||
| 512 | 26 20 00 | 3 | Product Data | Generator Docking Station | 3.1.16 | G | ||||||||||||||
| 513 | 26 20 00 | 3 | Product Data | Generator Docking Station | 3.5.7 | G | ||||||||||||||
| 514 | 26 20 00 | 6 | Test Reports | 600-volt wiring test | 3.5.2 | G | ||||||||||||||
| 515 | 26 20 00 | 6 | Test Reports | Grounding system test | 3.5.5 | G | ||||||||||||||
| 516 | 26 20 00 | 6 | Test Reports | Transformer tests | 3.5.3 | G | ||||||||||||||
| 517 | 26 20 00 | 6 | Test Reports | Ground-fault receptacle test | 3.5.4 | G | ||||||||||||||
| 518 | 26 20 00 | 7 | Certificates | Fuses | 2.1 | G | ||||||||||||||
| 519 | 26 20 00 | 9 | Manufacturer’s Field Reports | Transformer factory tests | 2.28.1 | |||||||||||||||
| 520 | 26 20 00 | 10 | Operation and Maintenance Data | Electrical Systems | 1.5.1 | G | ||||||||||||||
| 521 | 26 27 13.10 | 3 | Product Data | Power Meters | 2.1 | G | ||||||||||||||
| 522 | 26 27 13.10 | 3 | Product Data | Current | 2.1.3 | G | ||||||||||||||
| 523 | 26 27 13.10 | 3 | Product Data | Potential Transformer | 2.1.2 | G | ||||||||||||||
| 524 | 26 27 13.10 | 3 | Product Data | Communications Module | 2.2.2 | G | ||||||||||||||
| 525 | 26 27 13.10 | 3 | Product Data | Protocol Modules | 1.6.1 | G | ||||||||||||||
| 526 | 26 27 13.10 | 3 | Product Data | Data Recorder | 1.6.2 | G | ||||||||||||||
| 527 | 26 27 13.10 | 3 | Product Data | Modem | 1.6.2 | G | ||||||||||||||
| 528 | 26 27 13.10 | 6 | Test Reports | Acceptance Checks and Tests | 3.3.1 | G | ||||||||||||||
| 529 | 26 27 13.10 | 10 | Operation and Maintenance Data | Power Meters | 2.1 | G | ||||||||||||||
| 530 | 26 27 13.10 | 10 | Operation and Maintenance Data | Communications Module | 2.2.2 | G | ||||||||||||||
| 531 | 26 27 13.10 | 10 | Operation and Maintenance Data | Protocol Modules | 1.6.1 | G | ||||||||||||||
| 532 | 26 27 13.10 | 10 | Operation and Maintenance Data | Data Recorder | 1.6.2 | G | ||||||||||||||
| 533 | 26 27 13.10 | 10 | Operation and Maintenance Data | Modem | 1.6.2 | G | ||||||||||||||
| 534 | 26 27 13.10 | 11 | Closeout Submittals | System Function Verification | 3.3.2 | G | ||||||||||||||
| 535 | 26 28 01 | 3 | Product Data | Fault Current Analysis | 2.1 | |||||||||||||||
| 536 | 26 28 01 | 3 | Product Data | Protective Device Coordination Study | 2.1 | |||||||||||||||
| 537 | 26 28 01 | 3 | Product Data | Arc Flash Hazard Analysis | 2.1 | |||||||||||||||
| 538 | 26 28 01 | 3 | Product Data | System Coordinator | 1.4.1 | |||||||||||||||
| 539 | 26 28 01 | 3 | Product Data | Installation | 3.2 | |||||||||||||||
| 540 | 26 28 01 | 6 | Test Reports | Field Testing | 3.3 | |||||||||||||||
| 541 | 26 41 00 | 2 | Shop Drawings | Overall lightning protection system | 1.4.1.1 | G | ||||||||||||||
| 542 | 26 41 00 | 2 | Shop Drawings | Each major component | 1.4.1.2 | G | ||||||||||||||
| 543 | 26 41 00 | 6 | Test Reports | Lightning Protection and Grounding System Test Plan | 1.4.3 | G | ||||||||||||||
| 544 | 26 41 00 | 6 | Test Reports | Lightning Protection and Grounding System Test | 3.4.1 | G | ||||||||||||||
| 545 | 26 41 00 | 7 | Certificates | Lightning Protection System Installers Documentation | 1.2.3 | G | ||||||||||||||
| 546 | 26 41 00 | 7 | Certificates | Component UL Listed and Labeled | 1.4.2 | G | ||||||||||||||
| 547 | 26 41 00 | 7 | Certificates | Lightning protection system inspection certificate | 1.4.4 | G | ||||||||||||||
| 548 | 26 51 00 | 2 | Shop Drawings | Luminaire Drawings | 1.5.1 | G | ||||||||||||||
| 549 | 26 51 00 | 2 | Shop Drawings | Occupancy/Vacancy Sensor Coverage Layout | 1.5.2 | G | ||||||||||||||
| 550 | 26 51 00 | 3 | Product Data | Luminaires | 2.2 | G | ||||||||||||||
| 551 | 26 51 00 | 3 | Product Data | Light Sources | 2.4 | G | ||||||||||||||
| 552 | 26 51 00 | 3 | Product Data | Drivers, Ballasts and Generators | 2.3 | G | ||||||||||||||
| 553 | 26 51 00 | 3 | Product Data | LED Luminaire Warranty | 1.6.1 | G | ||||||||||||||
| 554 | 26 51 00 | 3 | Product Data | Luminaire Design Data | 1.5.4 | G | ||||||||||||||
| 555 | 26 51 00 | 3 | Product Data | Vacancy Sensors | 2.5.3.2 | G | ||||||||||||||
| 556 | 26 51 00 | 3 | Product Data | Dimming Controllers (Dimmers) | 2.5.2 | G | ||||||||||||||
| 557 | 26 51 00 | 3 | Product Data | Lighting Contactor | 2.5.4 | G | ||||||||||||||
| 558 | 26 51 00 | 3 | Product Data | Timeswitch | 2.5.5 | G | ||||||||||||||
| 559 | 26 51 00 | 3 | Product Data | Power Hook Luminaire Hangers | 2.8 | G | ||||||||||||||
| 560 | 26 51 00 | 3 | Product Data | Exit Signs | 2.6.1 | G | ||||||||||||||
| 561 | 26 51 00 | 3 | Product Data | LED Emergency Drivers | 2.6.2 | G | ||||||||||||||
| 562 | 26 51 00 | 3 | Product Data | Occupancy Sensors | 2.5.3.1 | G | ||||||||||||||
| 563 | 26 51 00 | 6 | Test Reports | LED Luminaire - IES LM-79 Test Report | 1.5.5 | G | ||||||||||||||
| 564 | 26 51 00 | 6 | Test Reports | LED Light Source - IES LM-80 Test Report | 1.5.6 | G | ||||||||||||||
| 565 | 26 51 00 | 6 | Test Reports | LED Light Source - IES TM-21 Test Report | 1.5.7 | G | ||||||||||||||
| 566 | 26 51 00 | 6 | Test Reports | Occupancy/Vacancy Sensor Verification Tests | 1.5.8 | G | ||||||||||||||
| 567 | 26 51 00 | 6 | Test Reports | Energy Efficiency | 1.5.11.3 | G | ||||||||||||||
| 568 | 26 51 00 | 7 | Certificates | Luminaire Useful Life Certificate | 1.6.1.1 | G | ||||||||||||||
| 569 | 26 51 00 | 7 | Certificates | LED Driver and Dimming Switch Compatibility Certificate | 1.5.3 | G | ||||||||||||||
| 570 | 26 56 00 | 1 | Preconstruction Submittals | Photometric Plan | 1.5.2 | G | ||||||||||||||
| 571 | 26 56 00 | 1 | Preconstruction Submittals | LED Luminaire Warranty | 1.7.1 | G | ||||||||||||||
| 572 | 26 56 00 | 2 | Shop Drawings | Luminaire Drawings | 1.5.1.1 | G | ||||||||||||||
| 573 | 26 56 00 | 2 | Shop Drawings | Poles | 1.5.1.2 | G | ||||||||||||||
| 574 | 26 56 00 | 3 | Product Data | LED, Luminaires | 2.2 | G | ||||||||||||||
| 575 | 26 56 00 | 3 | Product Data | Luminaire Light Sources | 2.2.2 | G | ||||||||||||||
| 576 | 26 56 00 | 3 | Product Data | Luminaire Power Supply Units (Drivers) | 2.2.3 | G | ||||||||||||||
| 577 | 26 56 00 | 3 | Product Data | Lighting Contactor | 2.3.3 | G | ||||||||||||||
| 578 | 26 56 00 | 3 | Product Data | Time Switch | 2.3.2 | G | ||||||||||||||
| 579 | 26 56 00 | 3 | Product Data | Photocell | 2.3.1 | G | ||||||||||||||
| 580 | 26 56 00 | 3 | Product Data | Aluminum Poles | 2.4.1 | G | ||||||||||||||
| 581 | 26 56 00 | 3 | Product Data | Steel Poles | 2.4.2 | G | ||||||||||||||
| 582 | 26 56 00 | 3 | Product Data | Brackets | 2.5 | |||||||||||||||
| 583 | 26 56 00 | 5 | Design Data | Design Data for Luminaires | 1.5.3 | G | ||||||||||||||
| 584 | 26 56 00 | 6 | Test Reports | LED Luminaire - IES LM-79 Test Report | 1.5.4 | G | ||||||||||||||
| 585 | 26 56 00 | 6 | Test Reports | LED Light Source - IES LM-80 Test Report | 1.5.5 | G | ||||||||||||||
| 586 | 26 56 00 | 6 | Test Reports | Operating Test | 3.2 | |||||||||||||||
| 587 | 26 56 00 | 7 | Certificates | Luminaire Useful Life Certificate | 1.7.1 | G | ||||||||||||||
| 588 | 26 56 00 | 10 | Operation and Maintenance Data | Operational Service | 1.8 | |||||||||||||||
| 589 | 27 10 00 | 2 | Shop Drawings | Telecommunications drawings | 1.6.1.1 | G | ||||||||||||||
| 590 | 27 10 00 | 2 | Shop Drawings | Telecommunications Space Drawings | 1.6.1.2 | G | ||||||||||||||
| 591 | 27 10 00 | 3 | Product Data | Telecommunications cabling | 2.3 | G | ||||||||||||||
| 592 | 27 10 00 | 3 | Product Data | Patch panels | 2.4.4 | G | ||||||||||||||
| 593 | 27 10 00 | 3 | Product Data | Telecommunications outlet/connector assemblies | 2.5 | G | ||||||||||||||
| 594 | 27 10 00 | 3 | Product Data | Equipment support frame | 2.4.2 | G | ||||||||||||||
| 595 | 27 10 00 | 6 | Test Reports | Telecommunications cabling testing | 3.5.1 | G | ||||||||||||||
| 596 | 27 10 00 | 7 | Certificates | Telecommunications Contractor | 1.6.2.1 | G | ||||||||||||||
| 597 | 27 10 00 | 7 | Certificates | Key Personnel | 1.6.2.2 | G | ||||||||||||||
| 598 | 27 10 00 | 7 | Certificates | Manufacturer Qualifications | 1.6.2.3 | G | ||||||||||||||
| 599 | 27 10 00 | 7 | Certificates | Test plan | 1.6.3 | G | ||||||||||||||
| 600 | 27 10 00 | 9 | Manufacturer’s Field Reports | Factory reel tests | 2.10.1 | G | ||||||||||||||
| 601 | 27 10 00 | 10 | Operation and Maintenance Data | Telecommunications cabling and pathway system | 1.10.1 | G | ||||||||||||||
| 602 | 27 10 00 | 11 | Closeout Submittals | Record Documentation | 1.10.2 | G | ||||||||||||||
| 603 | 28 08 10 | 5 | Design Data | Test Plan | 3.1 | G | ||||||||||||||
| 604 | 28 08 10 | 6 | Test Reports | Draft Test Report | 3.2.2 | |||||||||||||||
| 605 | 28 08 10 | 6 | Test Reports | Final Test Report | 3.4 | G | ||||||||||||||
| 606 | 28 08 10 | 7 | Certificates | Qualifications | 1.5.1 | |||||||||||||||
| 607 | 28 10 05 | 2 | Shop Drawings | ESS Components | 1.3.3.1 | G | ||||||||||||||
| 608 | 28 10 05 | 2 | Shop Drawings | Overall System Schematic | 1.3.3.2 | G | ||||||||||||||
| 609 | 28 10 05 | 3 | Product Data | Access Control Devices | 2.3.2 | G | ||||||||||||||
| 610 | 28 10 05 | 3 | Product Data | Communications Interface Devices | 2.4 | G | ||||||||||||||
| 611 | 28 10 05 | 3 | Product Data | Network Switch | 2.4.3 | G | ||||||||||||||
| 612 | 28 10 05 | 3 | Product Data | ESS Transmission | 2.4.4 | G | ||||||||||||||
| 613 | 28 10 05 | 3 | Product Data | Batteries | 2.5.1 | G | ||||||||||||||
| 614 | 28 10 05 | 3 | Product Data | Component Enclosure | 2.7 | G | ||||||||||||||
| 615 | 28 10 05 | 3 | Product Data | Equipment Rack | 2.8 | G | ||||||||||||||
| 616 | 28 10 05 | 5 | Design Data | Backup Battery Capacity Calculations | 1.5.1 | G | ||||||||||||||
| 617 | 28 10 05 | 7 | Certificates | Contractor Qualifications | 1.3.4.1 | G | ||||||||||||||
| 618 | 28 10 05 | 10 | Operation and Maintenance Data | ESS Components | 1.3.3.1 | G | ||||||||||||||
| 619 | 28 10 05 | 11 | Closeout Submittals | As-Built Drawings | 1.6 | G | ||||||||||||||
| 620 | 28 31 64 | 2 | Shop Drawings | Detail Drawings | 1.3.2 | |||||||||||||||
| 621 | 28 31 64 | 3 | Product Data | Storage Batteries | 2.5 | |||||||||||||||
| 622 | 28 31 64 | 3 | Product Data | Low Battery Voltage | 2.1.2 | |||||||||||||||
| 623 | 28 31 64 | 3 | Product Data | Special Tools and Spare Parts | 1.6 | |||||||||||||||
| 624 | 28 31 64 | 3 | Product Data | Technical Data and Computer Software | 1.4 | G | ||||||||||||||
| 625 | 28 31 64 | 3 | Product Data | Training | 3.5 | |||||||||||||||
| 626 | 28 31 64 | 3 | Product Data | Testing | 3.6 | |||||||||||||||
| 627 | 28 31 64 | 6 | Test Reports | Testing | 3.6 | |||||||||||||||
| 628 | 28 31 64 | 7 | Certificates | Equipment | 2.4 | |||||||||||||||
| 629 | 28 31 64 | 7 | Certificates | Qualifications | 1.3.1 | |||||||||||||||
| 630 | 28 31 64 | 10 | Operation and Maintenance Data | Operating and Maintenance Instructions | 3.5 | G | ||||||||||||||
| 631 | 28 50 00 | 2 | Shop Drawings | Installation | 3.3 | G | ||||||||||||||
| 632 | 28 50 00 | 2 | Shop Drawings | Equipment | G | |||||||||||||||
| 633 | 28 50 00 | 3 | Product Data | Loops | 2.2 | G | ||||||||||||||
| 634 | 28 50 00 | 3 | Product Data | Controller Mode Switch | 2.3 | G | ||||||||||||||
| 635 | 28 50 00 | 3 | Product Data | Controller Sensitivity Switch | 2.4 | G | ||||||||||||||
| 636 | 28 50 00 | 3 | Product Data | Controller Presence Switch | 2.5 | G | ||||||||||||||
| 637 | 28 50 00 | 3 | Product Data | Controller Tune Switch | 2.6 | G | ||||||||||||||
| 638 | 28 50 00 | 6 | Test Reports | Field Testing | 3.5 | |||||||||||||||
| 639 | 28 50 00 | 10 | Operation and Maintenance Data | Operating And Maintenance Instructions | G | |||||||||||||||
| 640 | 31 00 00 | 1 | Preconstruction Submittals | Shoring | 3.5 | G | ||||||||||||||
| 641 | 31 00 00 | 3 | Product Data | Utilization of Excavated Materials | 3.8 | G | ||||||||||||||
| 642 | 31 00 00 | 3 | Product Data | Roadway Shoulder Construction | 3.15 | |||||||||||||||
| 643 | 31 00 00 | 6 | Test Reports | Testing | 3.18 | |||||||||||||||
| 644 | 31 00 00 | 6 | Test Reports | Borrow Site Testing | 2.1 | |||||||||||||||
| 645 | 31 00 00 | 6 | Test Reports | Proof Rolling Form | 3.7.5 | |||||||||||||||
| 646 | 31 00 00 | 7 | Certificates | Testing | 3.18 | |||||||||||||||
| 647 | 31 05 19 | 3 | Product Data | Manufacturing Quality Control Sampling and Testing | 2.2 | |||||||||||||||
| 648 | 31 05 19 | 4 | Samples | Quality Assurance Samples and Tests | 3.1 | |||||||||||||||
| 649 | 31 05 19 | 7 | Certificates | Geotextile | 2.1.1 | |||||||||||||||
| 650 | 31 11 00 | 1 | Preconstruction Submittals | Herbicide Application Plan | 3.1.1 | |||||||||||||||
| 651 | 31 11 00 | 3 | Product Data | Nonsaleable Materials | 3.4.1 | G | ||||||||||||||
| 652 | 31 11 00 | 3 | Product Data | Herbicides | 1.3.2 | G | ||||||||||||||
| 653 | 31 11 00 | 7 | Certificates | Qualifications | 1.3.2 | G | ||||||||||||||
| 654 | 31 11 00 | 11 | Closeout Submittals | Pest Management Report | 3.5.1 | |||||||||||||||
| 655 | 32 01 19 | 3 | Product Data | Equipment | 3.1 | |||||||||||||||
| 656 | 32 01 19 | 4 | Samples | Materials | 1.3.1 | G | ||||||||||||||
| 657 | 32 11 23 | 3 | Product Data | Plant, Equipment, and Tools | 1.4 | G | ||||||||||||||
| 658 | 32 11 23 | 6 | Test Reports | Initial Tests | 2.3.1 | G | ||||||||||||||
| 659 | 32 11 23 | 6 | Test Reports | In-Place Tests | 3.12.1 | G | ||||||||||||||
| 660 | 32 12 13 | 3 | Product Data | Local/Regional Materials | 2.2.2 | |||||||||||||||
| 661 | 32 12 13 | 6 | Test Reports | Sampling and Testing | 3.7 | |||||||||||||||
| 662 | 32 12 16 | 3 | Product Data | Mix Design | 2.4 | G | ||||||||||||||
| 663 | 32 12 16 | 3 | Product Data | Quality Control | 3.1 | G | ||||||||||||||
| 664 | 32 12 16 | 3 | Product Data | Material Acceptance | 3.11 | G | ||||||||||||||
| 665 | 32 12 16 | 3 | Product Data | Percent Payment | 1.1.3 | G | ||||||||||||||
| 666 | 32 12 16 | 4 | Samples | Asphalt Cement Binder | 2.3 | |||||||||||||||
| 667 | 32 12 16 | 4 | Samples | Aggregates | 2.2 |