W91328-19-R-0006-Amendment 0004_UTTR AMD 4_Division 01 Submittal Register.xlsx
XLSX spreadsheet 23 KB Posted
- Attached to
- UTTR Missile Motor Receipt & Storage Facility
- Solicitation number
- W9123819R0006
About this file
This pre-solicitation notice is for the construction of missile motor receipt and storage facilities at the Utah Test and Training Range. The project scope includes building eighteen earth-covered modular storage magazines, a 7,000 square foot motor transfer facility, and approximately fifteen miles of railroad track. The estimated cost range is between $25-100 million. The period of performance for construction is 730 days. The solicitation will be issued on or around September 23, 2019 via the Federal Business Opportunities website. The response date for proposals is on or about November 7, 2019. The procurement will be conducted under NAICS code 236220 for heavy and civil engineering construction with a size standard of $36.5 million. All questions should be directed to the identified contracting officer.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 4
| TITLE: | D5 Missile Motor Receipt/Storage Facilities | SUBMITTAL REGISTER | ||||||||||||||||
| JOB NAME: | 10121996DIV01 | |||||||||||||||||
| LOCATION: | Utah Test and Training Range | |||||||||||||||||
| CONTRACT NO: | W91238-17-D-0027 | |||||||||||||||||
| CONTRACTOR: | ||||||||||||||||||
| CONTRACTOR SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | ||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) |
| Line | Activity # | Transmittal # | Specification Section | SD # | Submittal Description | Item Submitted | Paragraph # | Classification: GOVT or A/E Reviewer | Submit | Approval Needed By | Material Needed By | Action Code | Date Of Action | Date FWD to APPR / Auth Date RCD From CONTR | Date FWD To Other Revwr | Date RCD From Other Reviewer | Action Code | Date Of Action | Mailed To CONTR/ Date RCD From APPR Authority | Remarks |
| 1 | 01 00 00 | 1 | Preconstruction Submittals | Preconstruction Quantity Survey Plan | G | |||||||||||||||
| 2 | 01 00 00 | 1 | Preconstruction Submittals | Preconstruction Access Road Survey | ||||||||||||||||
| 3 | 01 00 00 | 1 | Preconstruction Submittals | Post-construction Access Road Survey | ||||||||||||||||
| 4 | 01 00 00 | 1 | Preconstruction Submittals | Activity Hazard Analysis | ||||||||||||||||
| 5 | 01 00 00 | 1 | Preconstruction Submittals | Qualifications for Safety and Health Person(s) | G | |||||||||||||||
| 6 | 01 00 00 | 1 | Preconstruction Submittals | Contractor's Right Of Entry Agreement | 1.23 | |||||||||||||||
| 7 | 01 00 00 | 2 | Shop Drawings | Provisions of Positive Protection System | G | |||||||||||||||
| 8 | 01 00 00 | 11 | Closeout Submittals | Worker's Compensation Claims | ||||||||||||||||
| 9 | 01 11 00 | 1 | Preconstruction Submittals | Salvage Plan | 1.6 | G | ||||||||||||||
| 10 | 01 30 00 | 1 | Preconstruction Submittals | View Location Map | 1.4 | G | ||||||||||||||
| 11 | 01 30 00 | 1 | Preconstruction Submittals | Progress and Completion Pictures | 1.5 | G | ||||||||||||||
| 12 | 01 30 00 | 4 | Samples | Color Boards | 1.3 | G | ||||||||||||||
| 13 | 01 32 01 | 1 | Preconstruction Submittals | Project Scheduler Qualifications | 1.3 | G | ||||||||||||||
| 14 | 01 32 01 | 1 | Preconstruction Submittals | Preliminary Project Schedule | 3.4.1 | G | ||||||||||||||
| 15 | 01 32 01 | 1 | Preconstruction Submittals | Initial Project Schedule | 3.4.2 | G | ||||||||||||||
| 16 | 01 32 01 | 1 | Preconstruction Submittals | Periodic Schedule Update | 3.6.2 | G | ||||||||||||||
| 17 | 01 33 00 | 1 | Preconstruction Submittals | Submittal Register | 1.8 | G | ||||||||||||||
| 18 | 01 33 29 | 1 | Preconstruction Submittals | Preliminary High Performance and Sustainable Building Checklist | 1.5.3.1 | G | ||||||||||||||
| 19 | 01 33 29 | 1 | Preconstruction Submittals | Sustainability Action Plan | 1.4.1 | G | ||||||||||||||
| 20 | 01 33 29 | 1 | Preconstruction Submittals | Preliminary Sustainability eNotebook | 1.5.3.1 | G | ||||||||||||||
| 21 | 01 33 29 | 11 | Closeout Submittals | Final High Performance and Sustainable Building Checklist | 1.5.3.1 | G | ||||||||||||||
| 22 | 01 33 29 | 11 | Closeout Submittals | Final Sustainability eNotebook | 1.5.3.1 | G | ||||||||||||||
| 23 | 01 33 29 | 11 | Closeout Submittals | Amended Final Sustainability eNotebook | 1.5.3.1 | G | ||||||||||||||
| 24 | 01 33 29 | 11 | Closeout Submittals | Amended Final High Performance and Sustainable Building Checklist | 1.5.3.1 | G | ||||||||||||||
| 25 | 01 35 26 | 1 | Preconstruction Submittals | Accident Prevention Plan (APP) | 1.7 | G | ||||||||||||||
| 26 | 01 35 26 | 6 | Test Reports | Monthly Exposure Reports | 1.4 | |||||||||||||||
| 27 | 01 35 26 | 6 | Test Reports | Notifications and Reports | 1.12 | |||||||||||||||
| 28 | 01 35 26 | 6 | Test Reports | Accident Reports | 1.12.2 | G | ||||||||||||||
| 29 | 01 35 26 | 6 | Test Reports | LHE Inspection Reports | 1.12.3 | |||||||||||||||
| 30 | 01 35 26 | 7 | Certificates | Crane Operators/Riggers | 1.6.1.4 | |||||||||||||||
| 31 | 01 35 26 | 7 | Certificates | Standard Lift Plan | 1.7.2.2 | G | ||||||||||||||
| 32 | 01 35 26 | 7 | Certificates | Critical Lift Plan | 1.7.2.3 | G | ||||||||||||||
| 33 | 01 35 26 | 7 | Certificates | Activity Hazard Analysis (AHA) | 1.8 | |||||||||||||||
| 34 | 01 35 26 | 7 | Certificates | Confined Space Entry Permit | 1.9.1 | |||||||||||||||
| 35 | 01 35 26 | 7 | Certificates | Hot Work Permit | 1.9.1 | |||||||||||||||
| 36 | 01 35 26 | 7 | Certificates | Certificate of Compliance | 1.12.4 | |||||||||||||||
| 37 | 01 35 26 | 7 | Certificates | License Certificates | ||||||||||||||||
| 38 | 01 35 26 | 7 | Certificates | Radiography Operation Planning Work Sheet | G | |||||||||||||||
| 39 | 01 35 26 | 7 | Certificates | Portable Gauge Operations Planning Worksheet | G | |||||||||||||||
| 40 | 01 45 00 | 1 | Preconstruction Submittals | Contractor Quality Control (CQC) Plan | 3.2 | G | ||||||||||||||
| 41 | 01 45 00 | 1 | Preconstruction Submittals | Additional Requirements for Design Quality Control (DQC) Plan | G DO | |||||||||||||||
| 42 | 01 45 00 | 5 | Design Data | Discipline-Specific Checklists | ||||||||||||||||
| 43 | 01 45 00 | 5 | Design Data | Design Quality Control | ||||||||||||||||
| 44 | 01 45 00 | 6 | Test Reports | Verification Statement | 3.10.2 | |||||||||||||||
| 45 | 01 45 35 | 1 | Preconstruction Submittals | SIOR Letter of Acceptance | 3.1.1 | G | ||||||||||||||
| 46 | 01 45 35 | 1 | Preconstruction Submittals | Project Manual | 3.1.1 | G | ||||||||||||||
| 47 | 01 45 35 | 1 | Preconstruction Submittals | Project Manual | 3.1.1 | G | ||||||||||||||
| 48 | 01 45 35 | 1 | Preconstruction Submittals | Written Practices | 3.1.1 | |||||||||||||||
| 49 | 01 45 35 | 1 | Preconstruction Submittals | NDT Procedures and Equipment Calibration Records | 3.1.1 | |||||||||||||||
| 50 | 01 45 35 | 6 | Test Reports | Daily Reports | 3.1.1 | |||||||||||||||
| 51 | 01 45 35 | 6 | Test Reports | Daily Reports | 3.1.3 | |||||||||||||||
| 52 | 01 45 35 | 6 | Test Reports | Daily Reports | 3.1.3 | |||||||||||||||
| 53 | 01 45 35 | 6 | Test Reports | Biweekly Reports | 3.1.1 | |||||||||||||||
| 54 | 01 45 35 | 7 | Certificates | Fabrication Plant | 2.1 | |||||||||||||||
| 55 | 01 45 35 | 7 | Certificates | Certificate of Compliance | 2.1 | |||||||||||||||
| 56 | 01 45 35 | 7 | Certificates | Special Inspector of Record | 1.5.6 | G | ||||||||||||||
| 57 | 01 45 35 | 7 | Certificates | Special Inspector | 1.5 | G | ||||||||||||||
| 58 | 01 45 35 | 7 | Certificates | Qualification Records | 3.1.1 | |||||||||||||||
| 59 | 01 45 35 | 11 | Closeout Submittals | Interim Final Report | 3.1.1 | |||||||||||||||
| 60 | 01 45 35 | 11 | Closeout Submittals | Comprehensive Final Report | 3.1.1 | G | ||||||||||||||
| 61 | 01 45 35 | 11 | Closeout Submittals | Comprehensive Final Report | 3.1.3 | G | ||||||||||||||
| 62 | 01 50 00 | 1 | Preconstruction Submittals | Construction Site Plan | 1.3 | G | ||||||||||||||
| 63 | 01 50 00 | 1 | Preconstruction Submittals | Traffic Control Plan | 3.4.1 | G | ||||||||||||||
| 64 | 01 50 00 | 1 | Preconstruction Submittals | Haul Road Plan | 2.2.1 | G | ||||||||||||||
| 65 | 01 50 00 | 1 | Preconstruction Submittals | Temporary Power Design | G | |||||||||||||||
| 66 | 01 50 00 | 1 | Preconstruction Submittals | Batch Plant | 3.11 | G | ||||||||||||||
| 67 | 01 50 00 | 3 | Product Data | Backflow Preventers | 1.4 | G | ||||||||||||||
| 68 | 01 50 00 | 6 | Test Reports | Backflow Preventer Tests | ||||||||||||||||
| 69 | 01 50 00 | 7 | Certificates | Backflow Tester | 1.4.1 | |||||||||||||||
| 70 | 01 50 00 | 7 | Certificates | Backflow Preventers | 1.4 | |||||||||||||||
| 71 | 01 50 01 | 3 | Product Data | GPO Digital Photographs | G RO | |||||||||||||||
| 72 | 01 50 01 | 3 | Product Data | GPO Furniture, Fixtures and Equipment (FFE) | G RO | |||||||||||||||
| 73 | 01 50 01 | 3 | Product Data | insulation for floors, walls, and attic | G RO | |||||||||||||||
| 74 | 01 50 01 | 4 | Samples | Color | G RO | |||||||||||||||
| 75 | 01 50 01 | 4 | Samples | Skirting Material | G RO | |||||||||||||||
| 76 | 01 50 01 | 5 | Design Data | Data GPO Site Plan | G | |||||||||||||||
| 77 | 01 50 01 | 5 | Design Data | GPO Specifications Information | G RO | |||||||||||||||
| 78 | 01 50 01 | 5 | Design Data | annotated drawings and product information | G RO | |||||||||||||||
| 79 | 01 57 20 | 1 | Preconstruction Submittals | Environmental Protection Plan | 1.7 | G | ||||||||||||||
| 80 | 01 57 20 | 1 | Preconstruction Submittals | Storm Water Pollution Prevention Plan | 3.2.3 | G | ||||||||||||||
| 81 | 01 57 20 | 1 | Preconstruction Submittals | Erosion Control | 3.2.3 | G | ||||||||||||||
| 82 | 01 57 20 | 11 | Closeout Submittals | Fugitive Dust Control | 3.4.1 | |||||||||||||||
| 83 | 01 74 19 | 1 | Preconstruction Submittals | Construction Waste Management Plan | 1.7 | G | ||||||||||||||
| 84 | 01 74 19 | 6 | Test Reports | Quarterly Reports | 1.9.2 | |||||||||||||||
| 85 | 01 74 19 | 6 | Test Reports | Annual Report | 1.9.3 | |||||||||||||||
| 86 | 01 74 19 | 11 | Closeout Submittals | Final Construction Waste Diversion Report | 1.1 | S | ||||||||||||||
| 87 | 01 78 00 | 3 | Product Data | Warranty Management Plan | 1.7.1 | |||||||||||||||
| 88 | 01 78 00 | 3 | Product Data | Warranty Tags | 1.7.5 | |||||||||||||||
| 89 | 01 78 00 | 3 | Product Data | Final Cleaning | 3.8 | |||||||||||||||
| 90 | 01 78 00 | 3 | Product Data | Spare Parts Data | 1.5 | |||||||||||||||
| 91 | 01 78 00 | 8 | Manufacturer’s Instructions | Instructions | 1.7.1 | |||||||||||||||
| 92 | 01 78 00 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 3.7 | G | ||||||||||||||
| 93 | 01 78 00 | 11 | Closeout Submittals | As-Built Drawings | 3.1 | G | ||||||||||||||
| 94 | 01 78 00 | 11 | Closeout Submittals | Record Drawings | 3.3 | G | ||||||||||||||
| 95 | 01 78 00 | 11 | Closeout Submittals | As-Built Record of Equipment and Materials | 1.7.1 | |||||||||||||||
| 96 | 01 78 00 | 11 | Closeout Submittals | As-Built Record of Equipment and Materials | 3.6 | |||||||||||||||
| 97 | 01 78 00 | 11 | Closeout Submittals | Final Approved Shop Drawings | 3.4 | |||||||||||||||
| 98 | 01 78 00 | 11 | Closeout Submittals | Construction Contract Specifications | 3.5 | |||||||||||||||
| 99 | 01 78 00 | 11 | Closeout Submittals | Certification of EPA Designated Items | 2.3 | G | ||||||||||||||
| 100 | 01 78 00 | 11 | Closeout Submittals | Certification Of USDA Designated Items | 2.4 | G | ||||||||||||||
| 101 | 01 78 00 | 11 | Closeout Submittals | Interim DD FORM 1354 | 3.9 | G | ||||||||||||||
| 102 | 01 78 00 | 11 | Closeout Submittals | Checklist for DD FORM 1354 | 3.9 | G | ||||||||||||||
| 103 | 01 78 00 | 11 | Closeout Submittals | High Performance and Sustainable Building (HPSB) Checklist | 3.9 | G | ||||||||||||||
| 104 | 01 78 23 | 10 | Operation and Maintenance Data | O&M Database | 1.4 | G | ||||||||||||||
| 105 | 01 78 23 | 10 | Operation and Maintenance Data | Training Plan | 3.1.1 | G | ||||||||||||||
| 106 | 01 78 23 | 10 | Operation and Maintenance Data | Training Outline | 3.1.3 | G | ||||||||||||||
| 107 | 01 78 23 | 10 | Operation and Maintenance Data | Training Content | 3.1.2 | G | ||||||||||||||
| 108 | 01 78 23 | 11 | Closeout Submittals | Training Video Recording | 3.1.4 | G | ||||||||||||||
| 109 | 01 78 23 | 11 | Closeout Submittals | Validation of Training Completion | 3.1.6 | G | ||||||||||||||
| 110 | 01 91 00.15 | 1 | Preconstruction Submittals | Commissioning Firm | 1.7 | G DO | ||||||||||||||
| 111 | 01 91 00.15 | 1 | Preconstruction Submittals | Lead Commissioning Specialist | 1.7.1 | G DO | ||||||||||||||
| 112 | 01 91 00.15 | 1 | Preconstruction Submittals | Technical Commissioning Specialists | 1.7.2 | G DO | ||||||||||||||
| 113 | 01 91 00.15 | 1 | Preconstruction Submittals | Commissioning Firm's Contract | 1.7 | G DO | ||||||||||||||
| 114 | 01 91 00.15 | 6 | Test Reports | Interim Construction Phase Commissioning Plan | 3.1.2.1 | G DO | ||||||||||||||
| 115 | 01 91 00.15 | 6 | Test Reports | Final Construction Phase Commissioning Plan | 3.1.2.2 | G DO | ||||||||||||||
| 116 | 01 91 00.15 | 6 | Test Reports | Pre-Functional Checklists | 3.1.4.2 | G DO | ||||||||||||||
| 117 | 01 91 00.15 | 6 | Test Reports | Issues Log | 1.9 | |||||||||||||||
| 118 | 01 91 00.15 | 6 | Test Reports | Commissioning Report | 3.2 | G DO | ||||||||||||||
| 119 | 01 91 00.15 | 6 | Test Reports | Post-Construction Trend Log Report | 3.3.1 | G DO | ||||||||||||||
| 120 | 01 91 00.15 | 7 | Certificates | Certificate of Readiness | 1.1 | G DO | ||||||||||||||
| 121 | 01 91 00.15 | 10 | Operation and Maintenance Data | Training Plan | 3.1.5 | G RO | ||||||||||||||
| 122 | 01 91 00.15 | 10 | Operation and Maintenance Data | Training Attendance Rosters | 3.1.5 | G RO | ||||||||||||||
| 123 | 01 91 00.15 | 10 | Operation and Maintenance Data | Systems Manual/Computerized Maintenance Management System Manual | 3.1.6 | G DO | ||||||||||||||
| 124 | 01 91 00.15 | 10 | Operation and Maintenance Data | Maintenance and Service Life Plans | 3.1.7 | G DO | ||||||||||||||
| 125 | 01 91 00.15 | 11 | Closeout Submittals | Final Commissioning Report | 3.2 | S DO | ||||||||||||||
| 11/21/19 15:16 |