Amendment 0002 Summary of Spec Changes
View the file
Other files for this federal contract opportunity
Show all 50
NAPA RIVER DRY BYPASS, NAPA, CA has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 October 2013
Amendment 0002 Summary
Section Subpart Paragraph Change 01 57 20
ENVIRONMENTAL
PROTECTION
3.6.1.1 Solid Waste in-
situ
Added “Based on historical excavation activities and geotechnical explorations, the Contractor should expect the above materials or other non-soil material within some of the areas designated for excavation activities. This 'in-situ' solid waste shall be disposed of separately on a per-ton basis as presented in the CLIN Pricing Breakdown for In-Situ Solid Waste Removal and Disposal.”
31 00 00
EARTHWORK
3.5 UTILIZATION OF
EXCAVATED
MATERIALS
Added language that the contractor will not be allowed to dispose of solid waste material at the Napa Pipe site.
32 31 13 CHAIN
LINK FENCES
AND GATES
1.2 SUBMITTALS Deleted Bottom Rail; G
32 31 13 1.5.2 Certificates of Compliance
Deleted following and renumbered remainder:
b. PVC coating
c. Aluminum alloy coating
d. Fabric
32 31 13 2.3 FABRIC Deleted Subpart Paragraph
32 31 13 2.4 TOP AND
BOTTOM SELVAGES
Deleted Subpart Paragraph
32 31 13 2.3 LINE POSTS Deleted “Grade B: 2.375 inch O.D. pipe weighing 3.12 pounds per linear foot.”
32 31 13 2.4 END, CORNER,
AND PULL POSTS
Deleted “Grade A: 2.375 inch O.D. pipe weighing 3.65 pounds per linear foot.”
and “Grade A: 2.875 inch O.D. pipe weighing 5.79 pounds per linear foot.”
32 31 13 2.8 TENSION WIRE Replaced “fabric” with “fence.”
32 31 13 3.16.2 Top and Bottom
Tension Wire Deleted “Top and” from title and first sentence. Deleted last sentence.
32 91 00
PLANTING
PREPARATION
3.6.2 Soil Loosening
Depth
Deleted Subpart Paragraph 3.6.2
32 91 00 3.6.3 Soil Loosening Method
Deleted Subpart Paragraph 3.6.3 and renumbered following Subpart Paragraphs
Attachment 5
1 October 2013
Section Subpart Paragraph Change 32 91 00 3.6.2 Finished Soil
Surface Added “Compaction is required within the corridor in accordance with 31 00 00 Earthwork. Where there is TRM there is a compaction requirement with a lightweight roller to compact seed and soil lightly into the TRM material.”
32 91 00 App. A
HPTRM
2.1.2.1 Percussion
Driven Anchors
Added “or galvanized steel,”
32 91 00 App. A
HPTRM
3.1 PREPARATION Added “Following seeding, all areas
within the project corridor are to be compacted in accordance with Specification section 31 00 00 Earthwork.”