A01.2_Specifications_AMD_0001.pdf
PDF 20 MB Posted
- Attached to
- NAPA RIVER DRY BYPASS, NAPA, CA Federal contract opportunity
- Solicitation number
- W91238-13-R-0032
About this file
Attachment 1 Revised Specification
View the file
Other files for this federal contract opportunity
Show all 50
NAPA RIVER DRY BYPASS, NAPA, CA has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DISTRIBUTION STATEMENT A
Approved for public release; distribution is unlimited
REQUEST FOR PROPOSAL (RFP)
NAPA RIVER DRY BYPASS
NAPA RIVER/NAPA CREEK
FLOOD PROTECTION PROJECT
NAPA COUNTY, CALIFORNIA
RFP NO. W91238-13-R-0032
SPECIFICATION NO. 1839
DESIGN FILE NO. NA-04 0052
L2CTANVM
Typewritten Text
L2CTANVM
Typewritten Text Attachment 1 13 September 2013
L2CTANVM
Typewritten Text
NAPA RIVER DRY BYPASS, FLOOD PROTECTION PROJECT 1839ORIG
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 14 00 WORK RESTRICTIONS
01 22 00 MEASUREMENT AND PAYMENT
01 32 00 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR
CONTAMINATED SITES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.10 QUALITY CONTROL SYSTEM (QCS)
01 45 00 QUALITY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 20 ENVIRONMENTAL PROTECTION
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 86 26.07 RELIABILITY CENTERED ACCEPTANCE FOR ELECTRICAL SYSTEMS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS
DIVISION 03 - CONCRETE
03 11 13 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 20 00 CONCRETE REINFORCING
03 30 00 CAST-IN-PLACE CONCRETE
03 40 00 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE
CONSTRUCTION
03 41 16 PRECAST CONCRETE SLABS
DIVISION 05 - METALS
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 20 00 FINISH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 92 00 JOINT SEALANTS
DIVISION 26 - ELECTRICAL
26 00 00 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 00 COMMON WORK RESULTS FOR ELECTRICAL
26 56 23 AREA LIGHTING
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 05 19 GEOTEXTILE
PROJECT TABLE OF CONTENTS Page 1
31 09 13 GEOTECHNICAL INSTRUMENTATION AND MONITORING
31 11 00 CLEARING AND GRUBBING
31 32 11 SOIL SURFACE EROSION CONTROL
31 32 39 BIOENGINEERING PRACTICES FOR STREAM BANK AND SHORELINE
STABILIZATION
31 41 16 METAL SHEET PILING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 24 GRADED CRUSHED AGGREGATE BASE COURSE FOR PERVIOUS AND
FLEXIBLE PAVEMENT
32 12 17 HOT MIX BITUMINOUS PAVEMENT
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS
32 17 23 PAVEMENT MARKINGS
32 31 13 CHAIN LINK FENCES AND GATES
32 84 24 IRRIGATION SPRINKLER SYSTEMS
32 91 00 PLANTING PREPARATION
32 92 19 SEEDING
32 93 00 PLANTING
DIVISION 33 - UTILITIES
33 11 00 WATER DISTRIBUTION
33 30 00 SANITARY SEWERS
33 40 00 STORM DRAINAGE UTILITIES
33 70 02 ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 16.59 HYDRAULIC CLOSURE GATES
35 31 19 STONE, CHANNEL, SHORELINE/COASTAL PROTECTION FOR
STRUCTURES
35 42 00 BIOENGINEERED BANK PROTECTION - ROOTWADS
35 42 34 REINFORCED SOIL SLOPE
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.1 SPECIAL SCHEDULING REQUIREMENTS
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
1.2.1.1 Subcontractors and Personnel Contacts
1.2.1.2 Identification Badges and Installation Access
1.2.1.3 Employee List
1.2.2 Working Hours
1.2.3 Work Outside Regular Hours
1.2.4 Exclusionary Period
1.2.5 Utility Cutovers and Interruptions
1.3 Citizenship Requirements
1.4 RELATED REQUIREMENTS
1.4.1 Utilities
1.4.2 Contractor Access to Private Property Parcels
1.4.3 Contractor Access and Use of City of Napa and County of Napa
Parcels
1.4.4 Contractor Access and Use of City Streets
1.4.5 Activity Regulations
1.4.6 Subcontractors and Personnel Contacts
1.4.7 Utility Cutovers and Interruptions
1.5 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.6 PARTNERING
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
01 14 00 - 1
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.1 SPECIAL SCHEDULING REQUIREMENTS
a. The Stormwater Pollution Prevention Plan (SWPPP) shall be ready for operation as approved by Contracting Officer and required review agencies before work is commenced, however the Contractor shall wait for the California Water Board to issue a Waste Discharge Identification (WDID) number before work may begin. The process to obtain a WDID number may take up to 28 days.
Also as part of the SWPPP approval process, the Contractor is required to submit a Dewatering Plan. After USACE approval, the Dewatering Plan must be submitted to the resource agencies for review. The Contractor will need to allow for a 60 day review.
b. All utilities will remain in operation during the entire construction period unless approved by the Contracting Officer and Utility. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the activity. These utilities include: water, power, gas, electrical, cable television, sewer, ect.
c. Permission to interrupt any active roads, railroads, and/or utility service shall be requested in writing a minimum of 15 working days prior to the desired date of interruption.
d. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
The following conditions apply:
(1) No work can occur on the banks or bed of Napa Creek or Napa River channels except between June 1 and October 15.
(2) Tidal changes in the Napa River.
(3) No pile driving shall occur other than between the regular work hours as noted below or on the weekend without written approval from the City of Napa and the Contracting Officer.
(4) No impact driving will be allowed in the Napa River and Napa Creek.
(5) Water line installation and service line work on McKinstry Street;
work per request of the City of Napa shall be 9:00 PM to 5:00 AM.
Water service shall be maintained to business and residences during 5:00AM to 9:00PM.
(6) Contractor to develop a Construction Phasing Schedule for project and submit for review and approval by the Contracting Officer in
01 14 00 - 2 accordance with Section 01 33 00. Schedule and Project Phasing shall be approved prior to starting construction. Any changes to the approved Construction Phasing Schedule or major changes to the project schedule must be approved by the USACE, City of Napa, and the Napa Flood Control District.
(7) Fifteen working days before the preconstruction meeting the Contractor's Project Manager shall schedule an in person meeting with the USACE PM at the Sacramento District Office.
(8) Thirty working days prior to beginning construction, the Contractor shall schedule a pre-construction site survey of the project with the Contracting Officer and Napa Flood Control District. The purpose of this site survey is to review and document project existing conditions. The Contractor shall develop and submit a report documenting the existing conditions including project photographs within 15 working days to the Contracting Officer and Napa Flood Control District. The project survey shall include but not be limited to: adjacent buildings, roadways, public and private improvements, haul routes, ect.
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification. All Contractor personnel and equipment must park in approved staging areas. Any Contractor or sub-contractor vehicles parked on the street will be ticketed.
This project is an urgan construction project and staging and phasing are critical elements as there are no provided staging and storage yards or accommodating worker parking other than the designated work area. The Contractor will need to plan and phase accordingly knowing that the sponsor or the City of Napa will not provide additional storage yards or land to complete the project. If private property in the City of Napa is to be used for construction staging or storage, written approval from the Contracting Officer and the City of Napa is required prior to such use.
1.2.1.1 Subcontractors and Personnel Contacts
Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.2.1.2 Identification Badges and Installation Access
Identification badges, if required by the Contracting Officer, will be furnished without charge. Application for and use of badges will be as directed. Furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for all personnel requesting badges. This form is available at http://www.uscis.gov/portal/site/uscis by searching or selecting Employment Verification (Form I-9). Immediately report instances
01 14 00 - 3 of lost or stolen badges to the Contracting Officer.
All badges must be returned or accounted for to the Contracting Officer upon expiration of the badge or contract, or termination of the employee.
1.2.1.3 Employee List
The Contractor shall provide to the Contracting officer, in writing, the names of two designated representatives authorized to request personnel and vehicle passes for employees and subcontractor's employees prior to commencement of work under this contract. A copy of these requirements will be provided at the preconstruction meeting.
1.2.2 Working Hours
Construction activities throughout the entire duration of the project shall be limited to the hours of 7:00 AM to 7:00 PM, Monday through Friday. There shall be no start up of machines nor equipment prior to 8:00 AM Monday through Friday; no delivery of materials nor equipment proir to 7:30 AM nor past 5:00 PM, Monday through Friday; no services of equipment past 6:45 PM, Monday through Friday; and construction on weekends or legal holidays shall be limited to the hours of 8:00 AM to 4:00 PM, unless the Contractor submits a written request and that request is approved by the City Manager, or his/her designee, pursuant to Section 8.08.025 and
8.08.050 of the City Municipal Code. If the request to work outside of the designated hours is approved, the Contractor may be required to pay the cost of providing inspection services for the work being performed. If inspection services are not available for the requested change, the City Engineer may deny the request.
Water line installation and service line work on McKinstry Street, per request from the City of Napa shall be between 9:00pm and 5:00am.
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer and City of Napa approval. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress
1.2.4 Exclusionary Period
No work shall be performed during the period 7:00 PM to 7:00 AM, inclusive, excluding the water line and service work on McKinstry Street,without prior written approval of the Contracting Officer. This period has not been considered in computing the time allowed for he performance of this contract.
1.2.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service,and electric service shall be considered utility cutovers
01 14 00 - 4 pursuant to the paragraph entitled "Work Outside Regular Hours."
1.3 Citizenship Requirements
Work under this contract is restricted to U.S. citizens.
1.4 RELATED REQUIREMENTS
The Napa Pipe - Soil Disposal Plan included in 01 57 20 ENVIRONMENTAL PROTECTION also includes requirements related to this specification.
Additional mitigations and requirements for operations at the Napa Pipe Soil Disposal Area as permitted by the County of Napa can be found in the attachment to Section 01 57 20 of these specifications. The Contractor shall comply with these requirements for soil disposal activities outlined in the above documents, contained elsewhere in these specifications and as directed by the Contracting Officer.
1.4.1 Utilities
This contract will affect overhead and underground utilities operated by PG&E, AT&T, Napa Sanitation District, City of Napa Water Department, and the City of Napa. Deviations and modifications to Staging and Phasing initiated by the Contractor, wll require pre-approval from the Contracting Officer and all Utilities identified herein.
All charges related to utility relocations beyond what is shown on the plans or any shut downs are the responsibility of the Contractor.
Coordination of construction activities affecting overhead and underground facilities with City of Napa, PG&E, AT&T, Napa Sanitation District, and Comcast shall be required of the Contractor so as to not adversely affect construction schedule, street closure duration nor the prosecution of work. Delays to contract schedule due to scheduling conflicts and delays will not be allowed. Thirty day advance notification to the Contracting Officer and utilities representatives of the overhead and underground work affecting these utilities shall be provided. Contacts are as follows:
Utility Name E-Mail Phone
PG&E Steve Bovaid spb4@pge.com (707) 257-5906
AT&T Robert Keating BK6559@att.com (707) 258-3779
Comcast Paul Alabona paul.alabona@cablecomllc.net (707) 425-1604
City of Napa Steve Crego scrego@cityofnapa.org (707) 257-9588
Napa Sanitation District
Robin Gamble rgamble@napasan.com (707) 258-6000
City of Napa Water Department
Megan Thomas mthomas@cityofnapa.org (707) 257-9341
General Temporary Shutdown Coordination Restrictions: Contractor will give 60 day early notice to the COR and utilities listed herein before any scheduled temporary utility shutdown. Utilities and COR will be invited by the Contractor to a pre-construction meeting for the area of work 30 days before scheduled temporary shutdown. Contractor will provide to utilities and COR a final 72 hour notice prior the scheduled temporary shutdown. Any short term outages or relocations will be coordinated by the Contractor and evaluated/approved by the COR following submittal of overall work-plan.
01 14 00 - 5
Coordinate with and get approval from utility companies about planned utility cutovers and interruptions a minimum of 45 calendar days prior to the planned interruption.
The commercial businesses within the project work areas will remain in operation during the entire construction period. The Contractor shall conduct operations so as to cause the least possible interference with normal operations of the activity. At least one access to commercial business entrances shall be maintained throughout the duration of construction work and interruportion to business utilities such as water supply, electrical power will not be allowed.
Permission to interrupt any activity roads, railroads, and/or utility services shall be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
Private driveways may be impacted for a maximum of 21 days. Commercial driveways and access must remain in operation.
1.4.2 Contractor Access to Private Property Parcels
Notification must be provided to Andrew Butler at the Napa Flood Control District by email or written notice 7 days before any entrance on to a private parcel Temporary Work Area Easement. Napa Flood Control District phone number: (707) 259-8600.
All Temporary Construction Easements (TE) have a 16 month duration from when property is first entered. Contact the Flood Control District a minimum of 4 business days before entrance is required.
The TE next to the Oxbow Market only has a 60 day total duration.
Private driveways may be impacted for a maximum of 21 days. Commercial driveways and access must remain in operation.
1.4.3 Contractor Access and Use of City of Napa and County of Napa Parcels
Occupation duration extension or non-Phase temporary occupation will require Contractor to obtain Right-of-Entry Permit from Owner. Contractor to provide Contracting Officer's Representative with copies of all Entry and Encroachment Permits. Contractor can obtain Right-of-Way maps and Owner Contact through Napa County Flood Control and Water Conservation District.
1.4.4 Contractor Access and Use of City Streets
Construction work areas for this project include streets and Right-of-way under jurisdiction of the City of Napa. Partial and Full street closures will be required. The Contractor is required to minimize Street Closure durations as mitigation for impacts to businesses and residents. The Contractor shall obtain Encroachment Permits from Napa County Flood Control and Water Conservation District (707) 259-8671 and the City of Napa, Department of Public Works, Jason Holley (707) 257-9372. The Contractor shall comply with all terms and conditions of the Encroachment Permit.
A copy of the NCFCWCD permit application and draft City of Napa Encroachment permit conditions are included at the end of this section for the Contractors information.
01 14 00 - 6
A Street Closure Signage Plan must be submitted to the City for approval 30 days before closure of any streets. This plan must include adequate signage to notify residents of changing travel options. CMS boards, flagment, and other traffic devices may be required based on the Contractor's proposal.
The following table provides a list of street or access closures, phase and duration for Contractor occupation:
Location Phase/Stage Duration
McKinstry Street Phase 1 0 Days
McKinstry Street Phase 3 0 Days
McKinstry Street Phase 2 45 Days
McKinstry Street Oxbow Market Access
Phase 2 60 Days
Occupation duration extension or non-Phase temporary occupation will require Contractor to obtain Encroachment Permit from the City. Contractor to provide Contracting Officer's Representative with copies of all Encroachment Permits. See Phasing Information Plan, Contract Drawings sheet G-114.
All remaining closures shown on the Drawings and not listed above are considered short term to be covered under the terms and conditions of the Encroachment Permit.
As part of the bypass project the Contractor shall obtain encroachment permits from NCFCWCD and the City of Napa for entry onto their respective property. The Contractor will have full responsiblity for compliance with all of these conditions. Attached is an example of the Encraochment Permit and draft Permit conditions.
1.4.5 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.
1.4.6 Subcontractors and Personnel Contacts
Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.4.7 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
01 14 00 - 7
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, traffic signals, street lighting, railroad signals, other communication services, and irrigation services shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
1.5 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the CONTRACT CLAUSE, Section 00 72 00, entitled "DEFAULT (FIXED-PRICE CONSTRUCTION)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS BASED ON (5) DAY WORK
WEEK
STATE
CALIFORNIA
INSTALLATION/NOAA STATION
SAN FRANCISCO/REDWOOD CITY
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
(06) (05) (05) (04) (01) (00) (00) (00) (01) (02) (05) (05)
c. Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.
Refer to ER 415-1-15.
1.6 PARTNERING
The Government intends to encourage the foundation of a cohesive partnership with the Contractor and its subcontractors. This partnership
01 14 00 - 8 will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. The objectives are effective and efficient contract performance and are intended to achieve completion within budget, on schedule and in accordance with plans and specifications. To implement this partnership initiative, arrange, within 60 calendar days of Notice To Proceed, a one-day partnership development seminar/team building workshop that will cover at a minimum the following elements: Commitment, Trust, Communication, Roles & Responsibilities, Timely Responsiveness, Mutual Goals, Conflict Management, Dispute Resolution and project specific issues.
Arrange for a meeting location to accommodate at least 40 people (i.e.
made up of the Contractor's key on-site personnel, key subcontractors and key Government personnel) and hire a Facilitator to conduct the workshop.
The initial session will be one-day minimum and the follow-on sessions, held at a minimum of once every three months or as agreed to by the partners, will be half-day minimum. The initial partnering session should be held away from the project site at a location acceptable to the Contractor and to the Government; the follow-on sessions can be held at locations agreed to by the partners. Pay all costs associated with the partnering effort including facilitator, meeting room and other incidental items. Before the partnering session, coordinate with the facilitator requirements for incidental items (audio-visual equipment, two easels, flipchart paper, colored markers, note paper, pens/pencils, colored flash cards, etc.) and have these items available at the partnering session.
The contractor will copy documents for distribution to all attendees. The facilitator must be acceptable to both the Contractor and the Government.
The participants shall bear their own costs for meals, lodging and transportation associated with partnering. A Team Charter, along with a Workshop Report, shall be developed and distributed to each participant at the conclusion of the workshop.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
01 14 00 - 9
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 LUMP SUM PAYMENTS ITEMS
1.1.1 Mobilization and Demobilization (0001AA)
1.1.1.1 Payment
1.1.2 Traffic Control (0001AC)
1.1.2.1 Payment
1.1.3 Traffic Control (0001AD)
1.1.3.1 Payment
1.1.4 Cathodic Protection (0001AV)
1.1.4.1 Payment
1.1.5 Monitoring (0001BG)
1.1.5.1 Payment
1.1.6 Pavement Markings (0001BH)
1.1.6.1 Payment
1.1.7 Mobilization and Demobilization (0002AA)
1.1.7.1 Payment
1.1.8 Traffic Control (0002AB)
1.1.8.1 Payment
1.1.9 Demolish Energy Dissipater (0002AI)
1.1.9.1 Payment
1.1.10 Cofferdams And Dewatering (0002AR)
1.1.10.1 Payment
1.1.11 Monitoring (0002BM)
1.1.11.1 Payment
1.1.12 Box Culvert Structure (0002BV)
1.1.12.1 Payment
1.1.13 Irrigation System (0005AF)
1.1.13.1 Payment
1.1.14 Irrigation Water Line Fee (0007AA)
1.1.14.1 Payment
1.1.15 Floodwall 352 Closure Structure (2002AE)
1.1.15.1 Payment
1.1.16 Floodwall 352 Flood Gate (2002AF)
1.1.16.1 Payment
1.1.17 Patch Asphalt (2002AH)
1.1.17.1 Payment
1.1.18 Floodwall 362 Closure Structure (2002AN)
1.1.18.1 Payment
1.1.19 Floodwall 362 Flood Gate (2002AO)
1.1.19.1 Payment
1.1.20 Patch Asphalt (2002AQ)
1.1.20.1 Payment
1.1.21 Conduits (2002AS)
1.1.21.1 Payment
1.1.22 Conductors (2002AT)
01 22 00 - 1
1.1.22.1 Payment
1.1.23 Floodwall Lighting (2002AU)
1.1.23.1 Payment
1.1.24 Closure Structure Lighting (2002AV)
1.1.24.1 Payment
1.1.25 Power Service (2002AW)
1.1.25.1 Payment
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 Demolition Water Line and Valves (0001AE)
1.2.1.1 Payment
1.2.2 Demolition Sanitary Sewer Lines (0001AF)
1.2.2.1 Payment
1.2.3 Demolition Asphalt Paving (0001AG)
1.2.3.1 Payment
1.2.4 Demolition Concrete Curb (0001AH)
1.2.4.1 Payment
1.2.5 Demolition Landscape Wall (0001AI)
1.2.5.1 Payment
1.2.6 Remove and Return Light Poles (0001AJ)
1.2.6.1 Payment
1.2.7 Relocate Light Poles (0001AK)
1.2.7.1 Payment
1.2.8 Salvage Amtrak Signs and Posts (0001AL)
1.2.8.1 Payment
1.2.9 Rough Grading (0001AM)
1.2.9.1 Payment
1.2.10 Sanitary Sewer Pipe CLSM Encasement (0001AN)
1.2.10.1 Payment
1.2.11 Sanitary Sewer Modifications (0001AO)
1.2.11.1 Payment
1.2.12 Water Line Relocation (0001AP)
1.2.12.1 Payment
1.2.13 Water Line Connection To Kayak Building (0001AQ)
1.2.13.1 Payment
1.2.14 Water Line Connection To 1031 Building (0001AR)
1.2.14.1 Payment
1.2.15 New Fire Hydrant And Service (0001AS)
1.2.15.1 Payment
1.2.16 New Irrigation Service Line (0001AT)
1.2.16.1 Payment
1.2.17 Steel Casing Sleeves (0001AU)
1.2.17.1 Payment
1.2.18 15 Inch RCP Storm Drain (0001AW)
1.2.18.1 Payment
1.2.19 18 Inch RCP Storm Drain
1.2.19.1 Payment
1.2.20 Catch Basins (0001AY)
1.2.20.1 Payment
1.2.21 Subgrade Prep Roads/Paved Areas (0001AZ)
1.2.21.1 Payment
1.2.22 Subgrade Prep Sidewalks/Curbs (0001BA)
1.2.22.1 Payment
1.2.23 Base Course (0001BB)
1.2.23.1 Payment
1.2.24 Place Curb and Gutter (0001BC)
1.2.24.1 Payment
1.2.25 Place New Roadway (0001BD)
1.2.25.1 Payment
1.2.26 Place Sidewalk (0001BE)
01 22 00 - 2
1.2.26.1 Payment
1.2.27 Bollards (0001BF)
1.2.27.1 Payment
1.2.28 Demolish Parking Lots and Pathways (0002AC)
1.2.28.1 Payment
1.2.29 Demolish Curb and Sidewalk (0002AD)
1.2.29.1 Payment
1.2.30 Demolish Fencing (0002AE)
1.2.30.1 Payment
1.2.31 Demolish Guard Rails and Barriers (0002AF)
1.2.31.1 Payment
1.2.32 Remove Light Poles (0002AG)
1.2.32.1 Payment
1.2.33 Remove Street Signs (0002AH)
1.2.33.1 Payment
1.2.34 Remove RCP Pipe (0002AJ)
1.2.34.1 Payment
1.2.35 Remove Sewer Lines (0002AK)
1.2.35.1 Payment
1.2.36 Salvage Tree (0002AL)
1.2.36.1 Payment
1.2.37 Clearing and Grubbing (0002AM)
1.2.37.1 Payment
1.2.38 Channel Excavation (0002AN)
1.2.38.1 Payment
1.2.39 Cut To Fill Excavation (0002AO)
1.2.39.1 Payment
1.2.40 Disposal Yard Grading (0002AP)
1.2.40.1 Payment
1.2.41 Subgrade Preparation (0002AQ)
1.2.41.1 Payment
1.2.42 30 Inch RCP With Outfall (0002AS)
1.2.42.1 Payment
1.2.43 48 Inch Manhole (0002AT)
1.2.43.1 Payment
1.2.44 Fine Grading For Landscaped Areas (0002AU)
1.2.44.1 Payment
1.2.45 Bypass Inlet Sheetpile (0002AV)
1.2.45.1 Payment
1.2.46 Bypass Inlet Bank Rock Slope Bedding (0002AW)
1.2.46.1 Payment
1.2.47 Bypass Inlet Bank Rock Slope Protection D50 (0002AX)
1.2.47.1 Payment
1.2.48 Bypass Inlet VRSS Soil Lifts (0002AY)
1.2.48.1 Payment
1.2.49 Bypass Outlet Sheetpile (0002AZ)
1.2.49.1 Payment
1.2.50 Bypass Outlet Bank Rock Slope Bedding (0002BA)
1.2.50.1 Payment
1.2.51 Bypass Outlet Bank Rock Slope Protection D50 (0002BB)
1.2.51.1 Payment
1.2.52 Bypass Outlet Launchable Toe Bedding(0002BC)
1.2.52.1 Payment
1.2.53 Bypass Outlet Launchable Toe Protection (0002BD)
1.2.53.1 Payment
1.2.54 Bypass Outlet Launchable Toe Fill (0002BE)
1.2.54.1 Payment
1.2.55 Napa Creek Bank Protection STA 17+70 to STA 16+00 (0002BF)
1.2.55.1 Payment
01 22 00 - 3
1.2.56 Napa Creek Bank Protection STA16+00 to STA 14+55 (0002BG)
1.2.56.1 Payment
1.2.57 Rootwads (0002BH)
1.2.57.1 Payment
1.2.58 Stepped Energy Dissipater (0002BI)
1.2.58.1 Payment
1.2.59 Slab On Grade Under Wine Train Bridge (0002BJ)
1.2.59.1 Payment
1.2.60 Energy Dissipater Blocks (0002BK)
1.2.60.1 Payment
1.2.61 Concrete Curb at Energy Dissipater (0002BL)
1.2.61.1 Payment
1.2.62 Low Flow Channel Excavation (0002BN)
1.2.62.1 Unit of Measure
1.2.63 Low Flow Channel Rock Lining (0002BO)
1.2.63.1 Payment
1.2.64 Concrete Elliptical Stage (0002BP)
1.2.64.1 Payment
1.2.65 Gravel Maintenance Road (0002BQ)
1.2.65.1 Payment
1.2.66 China Point Pathway (0002BR)
1.2.66.1 Payment
1.2.67 12' Concrete Pathway (0002BS)
1.2.67.1 Payment
1.2.68 Slab on Grade Under Soscol Street Bridge (0002BT)
1.2.68.1 Payment
1.2.69 Slab on Grade Under First Street Bridge (0002BU)
1.2.69.1 Payment
1.2.70 10' Concrete Pathway (BETTERMENT) (0003AB)
1.2.70.1 Payment
1.2.71 10' Concrete Pathway (RECREATION) (0003AC)
1.2.71.1 Payment
1.2.72 12' Concrete Pathway (BETTERMENT) (0004AA)
1.2.72.1 Payment
1.2.73 12' Concrete Pathway (RECREATION) (0004AB)
1.2.73.1 Payment
1.2.74 Soil Preparation (0005AA)
1.2.74.1 Payment
1.2.75 Turf Reinforcement Mat (0005AB)
1.2.75.1 Payment
1.2.76 Plantings - Shrubs (0005AC)
1.2.76.1 Payment
1.2.77 Plantings - Trees (0005AD)
1.2.77.1 Payment
1.2.78 Plug Plantings (0005AE)
1.2.78.1 Payment
1.2.79 Irrigation System (0005AF)
1.2.79.1 Payment
1.2.80 Seeding (0005AG)
1.2.80.1 Payment
1.2.81 Excavate (BETTERMENT) (1001AA)
1.2.81.1 Payment
1.2.82 Concrete (BETTERMENT) (1001AB)
1.2.82.1 Payment
1.2.83 Backfill (BETTERMENT) (1001AC)
1.2.83.1 Payment
1.2.84 Excavation (2002AA)
1.2.84.1 Payment
1.2.85 Cast-In-Place Wall With Pedestals (2002AB)
01 22 00 - 4
1.2.85.1 Payment
1.2.86 Gabion Wall (2002AC)
1.2.86.1 Payment
1.2.87 Architectural Railing (Low) (2002AD)
1.2.87.1 Payment
1.2.88 Backfill (2002AG)
1.2.88.1 Payment
1.2.89 Floodwall 352 Maintenance Road (2002AI)
1.2.89.1 Payment
1.2.90 Excavation (2002AJ)
1.2.90.1 Payment
1.2.91 Cast-In-Place Wall With Pedestals (2002AK)
1.2.91.1 Payment
1.2.92 Architectural Railing (Low) (2002AL)
1.2.92.1 Payment
1.2.93 Architectural Railing (Tall) (2002AM)
1.2.93.1 Payment
1.2.94 Backfill (2002AP)
1.2.94.1 Payment
2.86 Floodwall 362 Maintenance Road (2002AI)
1.2.95 Payment
1.2.96 Solid Waste Removal (3003AA)
1.2.96.1 Payment
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
01 22 00 - 5
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 LUMP SUM PAYMENTS ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the PRICING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 Mobilization and Demobilization (0001AA)
Mobilization and demobilizations will be paid for by lump sum and will not be measured. Mobilization and demobilization is defined as mobilization/demobilization, project management, compliance with general conditions and special provisions, coordination with utilities, environmental protection, field engineering, surveying, staking. This payment item shall be inclusive of all the construction phases.
Payment shall be in full compensation for all labor, materials, incidentals, and costs associated with, but not limited to, the following mobilization items: preparatory work and operations, including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; the establishment of temporary facilities necessary for work on the project; and all other work and operations that must be performed or costs incurred before work begins on the various Contract items on the project site.
Payment shall be in full compensation for all labor, materials, incidentals, and costs associated with, but not limited to, the following demobilization items: work and operations at the conclusion of construction, including, but not limited to, those necessary for the removal of personnel, equipment, supplies, and incidentals from the project site; of the removal of temporary facilities; and of all other work and operations that must be performed or costs incurred to conclude work on the various Contract items for the project.
1.1.1.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the PRICING SCHEDULE.
1.1.2 Traffic Control (0001AC)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings, the requirements in Section
01 22 00 - 6
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS and as directed by the Contracting Officer.
1.1.2.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the PRICING SCHEDULE.
1.1.3 Traffic Control (0001AD)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings, the requirements in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS and as directed by the Contracting Officer.
1.1.3.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the PRICING SCHEDULE.
1.1.4 Cathodic Protection (0001AV)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings, the requirements in Section 33 11 00 WATER DISTRIBUTION as directed by the Contracting Officer.
1.1.4.1 Payment
This bid item will be paid for by the linear foot for accepted work as shown in the PRICING SCHEDULE.
1.1.5 Monitoring (0001BG)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings and as directed by the Contracting Officer.
1.1.5.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the pricing schedule.
1.1.6 Pavement Markings (0001BH)
Payment will be made for costs associated with furnishing, preparation of receiving surfaces, and placement of required road striping and pavement markings to meet the lines and grades as shown on the drawings for pavement markings, which include performing other operations incidental thereto, per the limits shown on the drawings, and as directed by the Contracting Officer.
1.1.6.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the pricing schedule.
1.1.7 Mobilization and Demobilization (0002AA)
Mobilization and demobilizations will be paid for by lump sum and will not
01 22 00 - 7 be measured. Mobilization and demobilization is defined as mobilization/demobilization, project management, compliance with general conditions and special provisions, coordination with utilities, environmental protection, field engineering, surveying, staking. This payment item shall be inclusive of all the construction phases.
Payment shall be in full compensation for all labor, materials, incidentals, and costs associated with, but not limited to, the following mobilization items: preparatory work and operations, including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; the establishment of temporary facilities necessary for work on the project; and all other work and operations that must be performed or costs incurred before work begins on the various Contract items on the project site.
Payment shall be in full compensation for all labor, materials, incidentals, and costs associated with, but not limited to, the following demobilization items: work and operations at the conclusion of construction, including, but not limited to, those necessary for the removal of personnel, equipment, supplies, and incidentals from the project site; of the removal of temporary facilities; and of all other work and operations that must be performed or costs incurred to conclude work on the various Contract items for the project.
1.1.7.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the pricing schedule.
1.1.8 Traffic Control (0002AB)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings, the requirements in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS and as directed by the Contracting Officer.
1.1.8.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the pricing schedule.
1.1.9 Demolish Energy Dissipater (0002AI)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings, the requirements in Section 02 41 00 DEMOLITION, Section 02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL, and Section 02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS and as directed by the Contracting Officer.
1.1.9.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the pricing schedule.
1.1.10 Cofferdams And Dewatering (0002AR)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings, the requirements in Section 01 57 20 ENVIRONMENTAL PROTECTION, Section 01 57 23 TEMPORARY
01 22 00 - 8
STORM WATER POLLUTION CONTROLS and as directed by the Contracting Officer.
1.1.10.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the pricing schedule.
1.1.11 Monitoring (0002BM)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings and as directed by the Contracting Officer.
1.1.11.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the pricing schedule.
1.1.12 Box Culvert Structure (0002BV)
Payment will be made for costs associated with the site preparation, grading, excavation, furnishing of materials, forming, placement and finishing of architectural flatwork concrete, including cast-in-place concrete, reinforcing bar, and all other required appurtenances in accordance with the drawings and Section 03 30 00 CAST-IN-PLACE CONCRETE, Section 32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS and as directed by the Contracting Officer.
1.1.12.1 Payment
This bid item will be paid for by the lump sum for accepted work as shown in the pricing schedule.
1.1.13 Irrigation System (0005AF)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings, the requirements in Section 32 84 24 IRRIGATION SPRINKLER SYSTEMS and as directed by the Contracting Officer.
1.1.13.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the pricing schedule.
1.1.14 Irrigation Water Line Fee (0007AA)
Payment will be made for costs associated with Irrigation Water Line Fee and as directed by the Contracting Officer.
1.1.14.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the pricing schedule.
1.1.15 Floodwall 352 Closure Structure (2002AE)
Payment will be made for costs associated with the excavation, base course, compaction, backfill and furnishing of materials, forming and
01 22 00 - 9 placement of the Structural Concrete, including cast-in-place concrete, reinforcing bar, and all other required appurtenances in accordance with the drawings and Section 03 30 00 CAST-IN-PLACE CONCRETE, and as directed by the Contracting Officer.
1.1.15.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the pricing schedule.
1.1.16 Floodwall 352 Flood Gate (2002AF)
Payment will be made for costs associated with operations necessary to comply with the detials shown on the drawings, the requirements in Section
05 50 13 MISCELLANEOUS METAL FABRICATIONS, 35 20 16.59 HYDRAULIC CLOSURE
GATES, and as directed by the Contracting Officer.
1.1.16.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the pricing schedule.
1.1.17 Patch Asphalt (2002AH)
Payment will be made for costs assocatied with preparation of receiving surfaces, transportation, furnishing, placement, grading and compaction of Hot Mix Asphalt required to meet the lines and grades as shown on the drawings, which include performing other operations incidental thereto, per limits shown on the drawings, in accordance with Section 32 11 24
GRADED CRUSHED AGGREGATE BASE COURSE PERVIOUS AND FLEXIBLE PAVEMENT,
Section 32 12 17 HOT MIX BITUMINOUS as directed by the Contracting Officer.
1.1.17.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the pricing schedule.
1.1.18 Floodwall 362 Closure Structure (2002AN)
Payment will be made for costs associated with the excavation, base course, compaction, backfill and furnishing of materials, forming and placement of the Structural Concrete, including cast-in-place concrete, reinforcing bar, and all other required appurtenances in accordance with the drawings and Section 03 30 00 CAST-IN-PLACE CONCRETE, and as directed by the Contracting Officer.
1.1.18.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the pricing schedule.
1.1.19 Floodwall 362 Flood Gate (2002AO)
Payment will be made for costs associated with operations necessary to comply with the detials shown on the drawings, the requirements in Section
05 50 13 MISCELLANEOUS METAL FABRICATIONS, 35 20 16.59 HYDRAULIC CLOSURE
GATES, and as directed by the Contracting Officer.
01 22 00 - 10
1.1.19.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the pricing schedule.
1.1.20 Patch Asphalt (2002AQ)
Payment will be made for costs assocatied with preparation of receiving surfaces, transportation, furnishing, placement, grading and compaction of Hot Mix Asphalt required to meet the lines and grades as shown on the drawings, which include performing other operations incidental thereto, per limits shown on the drawings, in accordance with Section 32 11 24
GRADED CRUSHED AGGREGATE BASE COURSE PERVIOUS AND FLEXIBLE PAVEMENT,
Section 32 12 17 HOT MIX BITUMINOUS as directed by the Contracting Officer.
1.1.20.1 Payment
This bid item will be paid for by lump sum for accepted work as shown in the pricing schedule.
1.1.21 Conduits (2002AS)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings and as directed by the Contracting Officer.
1.1.21.1 Payment
This bid item will be paid by lump sum for accepted work as shown in the pricing schedule.
1.1.22 Conductors (2002AT)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings and as directed by the Contracting Officer.
1.1.22.1 Payment
This bid item will be paid by lump sum for accepted work as shown in the pricing schedule.
1.1.23 Floodwall Lighting (2002AU)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings and as directed by the Contracting Officer.
1.1.23.1 Payment
This bid item will be paid by lump sum for accepted work as shown in the pricing schedule.
1.1.24 Closure Structure Lighting (2002AV)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings and as directed by the Contracting Officer.
01 22 00 - 11
1.1.24.1 Payment
This bid item will be paid by lump sum for accepted work as shown in the pricing schedule.
1.1.25 Power Service (2002AW)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings and as directed by the Contracting Officer.
1.1.25.1 Payment
This bid item will be paid by lump sum for accepted work as shown in the pricing schedule.
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the PRICING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.2.1 Demolition Water Line and Valves (0001AE)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings, the requirements in Section 02 41 00 DEMOLITION, Section 02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL, and Section 02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS and as directed by the Contracting Officer.
1.2.1.1 Payment
This bid item will be paid for by the linear foot for accepted work as shown in the PRICING SCHEDULE.
1.2.2 Demolition Sanitary Sewer Lines (0001AF)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings, the requirements in Section 02 41 00 DEMOLITION, Section 02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL, and Section 02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS and as directed by the Contracting Officer.
1.2.2.1 Payment
This bid item will be paid for by the linear foot for accepted work as shown in the PRICING SCHEDULE.
1.2.3 Demolition Asphalt Paving (0001AG)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings, the requirements in Section 02 41 00 DEMOLITION, Section 02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL, and Section 02 81 00 TRANSPORTATION AND DISPOSAL OF
01 22 00 - 12
HAZARDOUS MATERIALS and as directed by the Contracting Officer.
1.2.3.1 Payment
This bid item will be paid by the square yard for accepted work as shown in the PRICING SCHEDULE.
1.2.4 Demolition Concrete Curb (0001AH)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings, the requirements in Section 02 41 00 DEMOLITION, Section 02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL, and Section 02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS and as directed by the Contracting Officer.
1.2.4.1 Payment
This bid item will be paid for by the linear foot for accepted work as shown in the pricing schdule.
1.2.5 Demolition Landscape Wall (0001AI)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings, the requirements in Section 02 41 00 DEMOLITION, Section 02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL, and Section 02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS and as directed by the Contracting Officer.
1.2.5.1 Payment
This bid item will be paid by the square foot for accepted work as shown in the PRICING SCHEDULE.
1.2.6 Remove and Return Light Poles (0001AJ)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings, the requirements in Section 02 41 00 DEMOLITION, Section 02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL, and Section 02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS and as directed by the Contracting Officer.
1.2.6.1 Payment
This bid item will be paid for each instance for accepted work as shown in the pricing schedule.
1.2.7 Relocate Light Poles (0001AK)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings, the requirements in Section 02 41 00 DEMOLITION, Section 02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL, and Section 02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS and as directed by the Contracting Officer.
1.2.7.1 Payment
This bid item will be paid for each instance for accepted work as shown in the PRICING SCHEDULE.
01 22 00 - 13
1.2.8 Salvage Amtrak Signs and Posts (0001AL)
Payment will be made for costs associated with operations necessary to comply with the details shown on the drawings, the requirements in Section 02 41 00 DEMOLITION, Section 02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL, and Section 02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS and as directed by the Contracting Officer.
1.2.8.1 Payment
This bid item will be paid for each instance for accepted work as shown in the pricing schedule.
1.2.9 Rough Grading (0001AM)
Paym…