This document includes a bid schedule template and details of a federal contract opportunity for road repair projects at Arlington National Cemetery and Soldier's and Airmen's Home National Cemetery. The contract is a single-phase design-bid-build multiple award task order contract with a total capacity of $49 million to be awarded to approximately three small businesses. Task orders will be for work such as construction, issued on a firm-fixed price basis, and range from $150,000 to $15 million. The base period of the basic contract is one year with four one-year options. Offerors must fill in labor rates that will be used for evaluation and inflated by 2.4% annually, as well as unit prices for work items like milling, paving and material hauling also inflated at 2.4% per option year. The solicitation was issued by the Department of the Army Corps of Engineers Engineering District Norfolk.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SCHEDULE (Blank-Offerors)

FOR OFFICIAL USE ONLY

BID SCHEDULE 10/20/20

TABLE 1TABLE 2
LINEITEMUNIT ITEM PRICETOTAL PRICEFULLY BURDENED WAGE RATES TO BE INCLUDED IN THE BASE CONTRACT
0001ASEED PROJECT, Firm Fixed Price- Construction of Humphreys Drive- complete (BASE), including
All work incidental, thereto as shown on the drawings and specifications, excluding items 0002$ - 0
0001BSEED PROJECT, Firm Fixed Price- Construction of Humphreys Drive- (OPTION), additional undercut of subgrade (0.5ft depth) and replacement with geogrid and suitable backfill material for all of new road complete, including

All work incidental, thereto as shown on the drawings and specifications, excluding items 0001

Est. Qty 500 CUBIC YARDS (Unit - CY)- [Unit Item Price Rate= Total Price / 500 CY]$0.00$ - 0
0001SEED PROJECT SUBTOTAL$ - 0
POSITIONAVERAGE OF RATESESTIMATED HOURSRATE TOTALBASE YEAR RATES ($/HR)OPTION YEAR 1 RATES ($/HR)OPTION YEAR 2 RATES ($/HR)OPTION YEAR 3 RATES ($/HR)OPTION YEAR 4 RATES ($/HR)
0002APROJECT MANAGER$0.002000$ - 0$0.00$0.00$0.00$0.00$0.00
0002BSUPERINTENDENT$0.004000$ - 0$0.00$0.00$0.00$0.00$0.00
0002CQUALITY CONTROL MANAGER$0.003000$ - 0$0.00$0.00$0.00$0.00$0.00
0002WAGE RATE SUBTOTAL$ - 0
DESCRIPTIONAVERAGE OF UNIT PRICEUNIT ITEM ESTIMATETOTAL PRICEBASE YEAR
UNIT PRICEOPTION YEAR 1 UNIT PRICEOPTION YEAR 2 UNIT PRICEOPTION YEAR 3 UNIT PRICEOPTION YEAR 4 UNIT PRICE
0003AMILLING 2-3" of SURFACE COURSE - Est. Qty 18,000 SQUARE FEET (Unit-SF)
- Milling, Demolition, and Hauling of Material included with Unit Price$0.0018000$ - 0$0.00$ - 0$ - 0$ - 0$ - 0
0003BPAVING 2-3" of SURFACE COURSE (VDOT SM-9.5A)

& REQUIRED LEVELING COURSE AS NEEDED -

Est. Qty 300 TONS (Unit-TN)$0.00300$ - 0$0.00$ - 0$ - 0$ - 0$ - 0
0003CSPOILS YARD HAULING EXCESS PRESCREENED MATERIAL -
Est. Qty 5,000 CUBIC YARDS (Unit-CY)$0.005000$ - 0$0.00$ - 0$ - 0$ - 0$ - 0
0003UNIT PRICE (MILLING-PAVING-SY HAULING) SUBTOTAL$ - 0
0004GRAND TOTAL FOR PRICE COMPARISON (0001+0002-0003)$ - 0
NOTES:
1) CELLS IN BLUE ARE COSTS/RATES TO BE FILLED IN BY OFFERORS AND WILL BE INCORPORATED INTO THE BASE/SEED CONTRACTS.
2) 0002 WAGE RATE - ESTIMATED HOURS & RATE TOTALS, WILL BE USED ONLY FOR PURPOSES OF THE PRICE COMPARISON.
3) 0002 THE BASE WAGE RATES SHALL BE INFLATED BY 2.4% FOR EACH SUBSEQUENT OPTION YEAR.
4) 0003 THE BASE UNIT PRICE RATES SHALL BE INFLATED BY 2.4% FOR EACH SUBSEQUENT OPTION YEAR.
5) 0004 IS USED FOR PRICE COMPARISON, WHICH IS SEED W/OPTION (0001) PLUS WAGE RATE TOTAL (0002) PLUS UNIT PRICE MILLING- PAVING-SPOILS YARD HAULING TOTAL (0003).