This document includes a bid schedule template and details of a federal contract opportunity for road repair projects at Arlington National Cemetery and Soldier's and Airmen's Home National Cemetery. The contract is a single-phase design-bid-build multiple award task order contract with a total capacity of $49 million to be awarded to approximately three small businesses. Task orders will be for work such as construction, issued on a firm-fixed price basis, and range from $150,000 to $15 million. The base period of the basic contract is one year with four one-year options. Offerors must fill in labor rates that will be used for evaluation and inflated by 2.4% annually, as well as unit prices for work items like milling, paving and material hauling also inflated at 2.4% per option year. The solicitation was issued by the Department of the Army Corps of Engineers Engineering District Norfolk.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 01_30_00.10_51_para_1.10.1_rev.pdf | ||
| ANC_Tree_Preservation_Specifications_-_UPDATE_Nov-2020.pdf | ||
| W9123621R2012 Amendment 0003.pdf | ||
| 31_00_00.00_51_para_2.5_rev.pdf | ||
| W9123621R2012 Amendment 02.pdf | ||
| W9123621R2012 Amendment 0001.pdf | ||
| W9123621R2012 Attachment 3.pdf | ||
| 17121D - SP RTA 2020.09.25.pdf | ||
| 912_MATOC_MillingSpecification_30SEP2020.pdf | ||
| W9123621R2012 Attachment 1.pdf | ||
| W9123621R2012 Solicitation .pdf | ||
| 2020-0127_2020-08-18_ANCHumphreys_ApprLttr.pdf | ||
| W9123621R2012 Attachment 4.pdf | ||
| 17121D - RTA Specs 2020.10.19.pdf | ||
| W9123621R2012 Attachment 5.pdf | ||
| W9123621R2012 Attachment 2.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID SCHEDULE (Blank-Offerors)
FOR OFFICIAL USE ONLY
BID SCHEDULE 10/20/20
| TABLE 1 | TABLE 2 | |||||
| LINE | ITEM | UNIT ITEM PRICE | TOTAL PRICE | FULLY BURDENED WAGE RATES TO BE INCLUDED IN THE BASE CONTRACT | ||
| 0001A | SEED PROJECT, Firm Fixed Price- Construction of Humphreys Drive- complete (BASE), including | |||||
| All work incidental, thereto as shown on the drawings and specifications, excluding items 0002 | $ - 0 | |||||
| 0001B | SEED PROJECT, Firm Fixed Price- Construction of Humphreys Drive- (OPTION), additional undercut of subgrade (0.5ft depth) and replacement with geogrid and suitable backfill material for all of new road complete, including |
All work incidental, thereto as shown on the drawings and specifications, excluding items 0001
| Est. Qty 500 CUBIC YARDS (Unit - CY)- [Unit Item Price Rate= Total Price / 500 CY] | $0.00 | $ - 0 | ||||||||
| 0001 | SEED PROJECT SUBTOTAL | $ - 0 | ||||||||
| POSITION | AVERAGE OF RATES | ESTIMATED HOURS | RATE TOTAL | BASE YEAR RATES ($/HR) | OPTION YEAR 1 RATES ($/HR) | OPTION YEAR 2 RATES ($/HR) | OPTION YEAR 3 RATES ($/HR) | OPTION YEAR 4 RATES ($/HR) | ||
| 0002A | PROJECT MANAGER | $0.00 | 2000 | $ - 0 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |
| 0002B | SUPERINTENDENT | $0.00 | 4000 | $ - 0 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |
| 0002C | QUALITY CONTROL MANAGER | $0.00 | 3000 | $ - 0 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |
| 0002 | WAGE RATE SUBTOTAL | $ - 0 | ||||||||
| DESCRIPTION | AVERAGE OF UNIT PRICE | UNIT ITEM ESTIMATE | TOTAL PRICE | BASE YEAR | ||||||
| UNIT PRICE | OPTION YEAR 1 UNIT PRICE | OPTION YEAR 2 UNIT PRICE | OPTION YEAR 3 UNIT PRICE | OPTION YEAR 4 UNIT PRICE | ||||||
| 0003A | MILLING 2-3" of SURFACE COURSE - Est. Qty 18,000 SQUARE FEET (Unit-SF) | |||||||||
| - Milling, Demolition, and Hauling of Material included with Unit Price | $0.00 | 18000 | $ - 0 | $0.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||
| 0003B | PAVING 2-3" of SURFACE COURSE (VDOT SM-9.5A) |
& REQUIRED LEVELING COURSE AS NEEDED -
| Est. Qty 300 TONS (Unit-TN) | $0.00 | 300 | $ - 0 | $0.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 0003C | SPOILS YARD HAULING EXCESS PRESCREENED MATERIAL - | |||||||
| Est. Qty 5,000 CUBIC YARDS (Unit-CY) | $0.00 | 5000 | $ - 0 | $0.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 0003 | UNIT PRICE (MILLING-PAVING-SY HAULING) SUBTOTAL | $ - 0 |
| 0004 | GRAND TOTAL FOR PRICE COMPARISON (0001+0002-0003) | $ - 0 |
| NOTES: | ||
| 1) CELLS IN BLUE ARE COSTS/RATES TO BE FILLED IN BY OFFERORS AND WILL BE INCORPORATED INTO THE BASE/SEED CONTRACTS. | ||
| 2) 0002 WAGE RATE - ESTIMATED HOURS & RATE TOTALS, WILL BE USED ONLY FOR PURPOSES OF THE PRICE COMPARISON. | ||
| 3) 0002 THE BASE WAGE RATES SHALL BE INFLATED BY 2.4% FOR EACH SUBSEQUENT OPTION YEAR. | ||
| 4) 0003 THE BASE UNIT PRICE RATES SHALL BE INFLATED BY 2.4% FOR EACH SUBSEQUENT OPTION YEAR. | ||
| 5) 0004 IS USED FOR PRICE COMPARISON, WHICH IS SEED W/OPTION (0001) PLUS WAGE RATE TOTAL (0002) PLUS UNIT PRICE MILLING- PAVING-SPOILS YARD HAULING TOTAL (0003). |