UFGS_10_44_16_Fire_Extinguishers_-_UFGS_10_44_16.pdf
PDF 44 KB Posted
- Attached to
- Fort Benning MATOC
- Solicitation number
- W911SF-18-R-0022
About this file
This solicitation is for an indefinite delivery/indefinite quantity construction contract to support the U.S. Army Garrison Fort Benning, Georgia. The contract will have a minimum guarantee of $5,000 and a maximum order value of $5 million for construction, repair, and related services at Fort Benning and satellite sites over one five-year ordering period. The work includes site preparation, cleanup, reporting, and record keeping. The solicitation will be available on January 28, 2019 with proposals due February 28, 2019. The contract will be set aside for total small business and have a NAICS code of 236220 for commercial and institutional building construction and a size standard of $36.5 million. The point of contact for any questions is Jackie Peacock at 706-545-2409.
View the file
Other files
Show 40 more
Latest 50 of 138 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 10 44 16 Page 1
SECTION 10 44 16
FIRE
EXTINGUISHERS
05/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced . The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E814 (2013a) Standard Test Method for Fire
Tests of Through-Penetration Fire Stops
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA l (2015; ERTA 2015) Fire Code
NFPA 10 (2013) Standard for Portable Fire
Extinguishers
NFPA 101 (2015; ERTA 2015) Life Safety Code
NFPA 241 (2013; Errata 2015) Standard for
Safeguarding Construction, Alteration, and Demolition Operations
NFPA 303 (2016) Fire Protection Standards for
Marinas and Boatyards
NFPA 385 (2012) Standard for Tank Vehicles for
Flammable and Combustible Liquids
NFPA 409 (2016) Standard on Aircraft Hangars
NFPA 418 (2016) Standard for Heliports
NFPA 505 (2013) Fire Safety Standard for Powered
Industrial Trucks Including Type Designations, Areas of Use, Conversions, Maintenance, and Operations
NFPA 99 (2015) Health Care Facilities Code
U .S . NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910.106 Flammable and Combustible Liquids
29 CFR 1910.157 (2003) Portable Fire
SECTION 10 44 16 Page 2
UNDERWRITERS LABORATORIES (UL)
UL 154 (2005; Reprint May 2014) Carbon- Dioxide Fire Extinguishers
UL 2129 (2017) UL Standard for Safety
Halocarbon Clean Agent Fire
UL 299 (2012) Dry Chemical Fire Extinguishers
UL 626 (2005; Reprint Mar 2012) 2-1/2
Gallon Stored-Pressure, Water-Type Fire Extinguishers
UL 8 (2016) UL Standard for Safety Water
Based Agent Fire Extinguishers
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are or information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00, SUBM ITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Manufacturer's Data; G
SD-02 Shop Drawings
Fire Extinguishers; G
Cabinets; G
SD-03 Product Data
Cabinets; G
SD-07 Certificates
Manufacturer's Warranty with Inspection Tag; G
SECTION 10 44 16 Page 3
1.3 DELIVERY, STORAGE, AND HANDLING
Protect materials from weather, soil, and damage during delivery, storage, and construction.
Deliver materials in their original packages, containers, or bundles bearing the brand name and the name and type of the material.
Provide portable fire extinguishers in compliance with NFPA 505 for all ancillary vehicles where Fire Safety Standard for Powered Industrial Trucks, including type designations, special conditions relating to areas of use, conversions, maintenance, or specific operations apply.
1.4 WARRANTY
Guarantee that Fire Extinguishers are free of defects in materials, fabrication, finish, and installation and that they will remain so for a period of not less than 5 years after completion.
PART 2 PRODUCTS
Submit fabrication drawings consisting of fabrication and assembly details performed in the factory and product data for the following items: Fire Extinguishers; Accessories, cabinets, Wall Brackets.
2 .1 SYSTEM DESCRIPTION
2 .1.1 Types
Submit certificates that show fire extinguishers comply with local codes and regulations.
Provide fire extinguishers conforming to NFPA 10. Provide quantity and placement in compliance with the applicable sections of NFPA 1, NFPA 101, and 29 CFR 1910.157.
Provide dry chemical type fire extinguishers compliant with UL 299.
Submit manufacturer's data for each type of Fire Extinguisher required, detailing all related Cabinet, Wall Mounting and Accessories information, complete with manufacturer's warranty with inspection tag.
2 .l.2 Material
Provide corrosion-resistant steel extinguisher shell.
2 .1.3 Size
10 pounds extinguishers.
SECTION 10 44 16 Page 10
2.1.4 Accessories
Forged brass valve
Fusible plug
Safety release
Pressure gage
2.2 EQUIPMENT
2 .2.l Cabinets
2 .2.1.l Material
Provide corrosion-resistant steel cabinets.
2 .2.1.2 Type
Provide semi-recessed cabinet for a 4-inch wall.
2 .2 .1.3 Size
Dimension cabinets to accommodate the specified fire extinguishers.
PART 3 EXECUTION
3.1 INSTALLATION
Fire Extinguishers where indicated on the drawings. Verify exact locations prior to installation.
Provide extinguishers which are fully charged and ready for operation upon installation. Provide extinguishers complete with Manufacturer's Warranty with Inspection Tag attached.
Comply with the manufacturer's recommendations for all installations.
3.2 PROTECTION
3.2.l Repairing
Remove and replace damaged and unacceptable port ions of completed work with new work at no additional cost to the Government.
Submit replacement parts list indicating specified items replacement part, replacement cost, and name, address and contact for replacement parts distributor.
3.2.2 Cleaning
Clean all surfaces of the work, and adjacent surfaces which are soiled as a result of the work. Remove from the site all construction equipment, tools, surplus materials and rubbish resulting from the work .