UFGS_01_78_00_Closeout_Submittals_-_UFGS_01_78_00_E.pdf
PDF 160 KB Posted
- Attached to
- Fort Benning MATOC
- Solicitation number
- W911SF-18-R-0022
About this file
This document provides details for a federal indefinite delivery/indefinite quantity contract opportunity with the U.S. Army Mission and Installation Command at Fort Benning, Georgia. The contract has a one year base period and four one-year options with a minimum guarantee of $5,000 and a maximum task order value of $5 million to provide construction and facilities maintenance services at Fort Benning and related sites. Eligible firms must be small businesses with a NAICS code of 236220. The solicitation number is W911SF-18-R-0022 and will be available on January 28, 2019 with proposals due February 28, 2019. Services include repair, construction, planning, administration and cleanup for orders under the contract. The point of contact is listed for any questions.
View the file
Other files
Show 40 more
Latest 50 of 138 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 78 00 Page 10
SECTION 01 78 00
CLOSEOUT SUBMITTALS
08/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E1971 (2005; R 2011) Standard Guide for
Stewardship for the Cleaning of Commercial and Institutional Buildings
GREEN SEAL (GS)
GS-37 (2012) Cleaning Products for
Industrial and Institutional Use
U .S . ARMY CORPS OF ENGINEERS (USACE)
ERDC/ITL TR-12-1 (2015) A/E/C Graphics Standard, Release 2 .0
ERDC/ITL TR-12-6 (2015) A/E/C CAD Standard - Release
6.0 U .S . DEPARTMENT OF DEFENSE (DOD)
FC 1-300-09N (2014; with Change 2) Navy and Marine Corps Design Procedures
UFC 1-300-08 (2009, with Change 2) Criteria for
Transfer and Acceptance of DoD Real Property
1.2 DEFINITIONS
1.2.1 As-Built Drawings
As-built drawings are developed and maintained by the Contractor and depict actual conditions, including deviations from the Contract Documents. These deviations and additions may result from coordination required by, but not limited to: contract modifications; official responses to Contractor submitted Requests for Information; direction from the Contracting Officer;
designs which are the responsibility of the Contractor, and differing site conditions. Maintain the as-builts throughout construction as red-lined hard copies on site . As-built drawings are further defined in NFAS 5252 .236-9310. These files serve as the basis for the creation of the record drawings.
1.2.2 Record Drawings
The record drawings are the final compilation of actual conditions
SECTION 01 78 00 Page 11 reflected in the as-built drawings.
1.3 SOURCE DRAWING FILES
Request the full set of electronic drawings, in the source format, for Record Drawing preparation, after award and at least 30 days prior to required use .
1.3.l Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction drawings and data for the referenced project . Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government . The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files . The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files .
These electronic CAD drawing files are not construction documents .
Differences may exist between the CAD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CAD files, nor does it make representation to the compatibility of these files with the Contractor hardware or software . In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished Source drawing files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project. If the Contractor uses, duplicates or modifies these electronic source drawing files for use in producing construction data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).
l .4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only . When used, a designation following the "G " designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00, SUBM ITTAL PROCEDURES:
SD-03 Product Data
Warranty Management Plan Warranty Tags Final Cleaning Spare Parts Data
SD-08 Manufacturer's Instructions
Posted Instructions
SECTION 01 78 00 Page 12
SD-10 Operation and Maintenance Data
Operation and Maintenance Manuals; G [, l l
SD-11 Closeout Submittals
As-Built Drawings; G Record Drawings; G As-Built Record of Equipment and Materials Final Approved Shop Drawings Construction Contract Specifications Checklist for DD FORM 1354; G
1.5 QUALITY CONTROL
Additions and corrections to the contract drawings must be equal in quality and detail to that of the originals. Line colors, line weights, lettering, layering conventions, and symbols must [conform to ERDC/ITL TR-12-6][be the same as the original line colors, line weights, lettering, layering conventions, and symbols]
1.6 WARRANTY MANAGEMENT
1.6 . 1 Warranty Management Plan
Develop a warranty management plan which contains information relevant to the clause Warranty of Construction in FAR. At least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan . Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesmen, or of engineering background, not necessarily familiar with this contract.
The term "status" as indicated below must include due date and whether item has been submitted or was accomplished. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly pay estimate .
Assemble approved information in a binder and turn over to the Government upon acceptance of the work . The construction warranty period will begin on the date of project acceptance and continue for the full product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contractor, Contracting Officer and the Customer Representative . Include within the warranty management plan , but not limited to, the following :
a. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the organizations of the Contractors, subcontractors, manufacturers or suppliers involved .
b . Furnish with each warranty the name, address, and telephone number of each of the guarantor's representatives nearest to the project location
c. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers, and for all commissioned systems such as fire
SECTION 01 78 00 Page 13 protection and alarm systems, sprinkler systems, lightning protection systems, etc .
d. A list for each warranted equipment, item, feature of construction or system indicating :
(1) Name of item .
(2) Model and serial numbers. (3) Location where installed .
(4) Name and phone numbers of manufacturers or suppliers .
(5) Names, addresses and telephone numbers of sources of spare parts . (6) Warranties and terms of warranty . Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates .
(7) Cross-reference to warranty certificates as applicable .
(8) Starting point and duration of warranty period.
(9) Summary of maintenance procedures required to continue the warranty in force .
(10) Cross-reference to specific pertinent Operation and Maintenance manuals.
(11) Organization, names and phone numbers of persons to call for warranty service .
(12) Typical response time and repair time expected for various warranted equipment .
e . The plans for attendance at the 4 and 9 month post-construction warranty inspections conducted by the Government .
f. Procedure and status of tagging of all equipment covered by extended warranties .
g . Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
1.6.2 Performance Bond
The Performance Bond must remain effective throughout the construction period.
a. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work per formed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while per forming the work, including, but not limited to administrative expenses .
b . In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the Contractor's expense, the Contracting Officer will have the right to recoup expenses from the bonding company.
c. Following oral or written notification of required construction warranty repair work, respond in a timely manner . Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
1.6.3 Pre-Warranty Conference
SECTION 01 78 00 Page 14
Prior to contract completion, and at a time designated by the Contracting Officer, meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section.
Communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/reviewed at this meeting . In connection with these requirements and at the time of the Contractor's quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor . This point of contact will be located within the local service area of the warranted construction, be continuously available, and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in connection with other port ions of this provision.
1.6 . 4 Contractor's Response to Construction Warranty Service Requirements
Following oral or written notification by the Contracting Officer, respond to construction warranty service requirements in accordance with the "Construction Warranty Service Priority List" and the three categories of priorities listed below . Submit a report on any warranty item that has been repaired during the warranty period . Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed . If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established .
a. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
b . Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
c. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
d. The "Construction Warranty Service Priority List" is as follows:
Code 1-Life Safety Systems
(1) Fire suppression systems .
(2) Fire alarm system(s) in place in the building .
Code (1) (2) (3)
1- Air Conditioning Systems Recreational support .
Air conditioning leak in part of building, if Air conditioning system not cooling properly.
causing damage .
SECTION 01 78 00 Page 15
Code 1-Doors
(1) Overhead doors not operational, causing a security, fire, or safety problem .
(2) Interior, exterior personnel doors or hardware, not functioning properly, causing a security, fire, or safety problem.
Code 3-Doors
(1) Overhead doors not operational.
(2) Interior/exterior personnel doors or hardware not functioning properly .
Code 1-Electrical
(1) Power failure (entire area or any building opera ional after 1600 hours).
(2) Security lights
(3) Smoke detectors
Code 2-Electrical
(1) Power failure (no power to a room or part of building).
(2) Receptacle and lights (in a room or part of building) .
Code 3-Electrical Street lights.
Code 1-Gas
(1) Leaks and breaks .
(2) No gas to family housing unit or cantonment area.
Code 1-Heat
(1) Area power failure affecting heat .
(2) Heater in unit not working .
Code 2-Kitchen Equipment
(1) Dishwasher not operating properly.
(2) All other equipment hampering preparation of a meal.
Code 1-Plumbing
(1) Hot water heater failure .
(2) Leaking water supply pipes .
(2) (3)
2-Plumbing Flush valves not operating properly.
Fixture drain, supply line to commode, or any water pipe leaking .
Commode leaking at base .
Code 3 -Plumbing Leaky faucets .
(2) (3)
3-Interior Floors damaged.
Paint chipping or peeling.
Casework .
SECTION 01 78 00 Page 16
Code 1-Roof Leaks Temporary repairs will be made where major damage to property is occurring .
Code 2-Roof Leaks Where major damage to property is not occurring, check for location of leak during rain and complete repairs on a Code 2 basis.
Code 2-Water (Exterior) No water to facility .
Code 2-Water (Hot)
No hot water in portion of building listed.
Code 3-All other work not listed above .
l.6 .5 Warranty Tags
At the time of installation, tag each warranted item with a durable, oil and water resistant tag approved by the Contracting Officer . Attach each tag with a copper wire and spray with a silicone waterproof coating . Also, submit [two][ ][four] record copies of the warranty tags showing the layout and design . The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy . Show the following information on the tag.
Type of product/material
Model number
Serial number
Contract number
Warranty period from/to
Inspector's signature
Construction Contractor
Address
Telephone number
Warranty contact
Address
Telephone number
SECTION 01 78 00 Page 17
Warranty response time priority code
WARNING - PROJECT PERSONNEL TO PERFORM ONLY OPERATIONAL MAINTENANCE DURING THE
WARRANTY PERIOD .
PART 2 PRODUCTS
2 .1 GOVERNMENT FURNISHED MATERIALS
The Government will provide an optical disc (CD or DVD) at the preconstruction conference that contains the following :
a. One set of "as-designed" electronic CAD files in the specified software and format revised to reflect all amendments and the final contract PDF drawings. The CAD files are provided to enable preparation of as-built or as-constructed drawings. If discrepancies exist between the CAD files and the contract PDF drawings, correct the CAD files to show the contract PDF drawings.
b. A submittal register data file in comma separated value (CSV) format for import into the Resident Management System (RMS).
2 .2 SYSTEM DESCRIPTION
Prepare the CAD drawing files in Microstation i8V format compatible with a Windows 13.
SECTION 01 78 00 Page 18
2 .2.1 Additional Drawings
If additional drawings are required, prepare them using the specified electronic file format applying the same graphic standards specified for original drawings. The title block and drawing border to be used for any new final record drawings must be identical to that used on the contract
2 .2.1.1 Sheet Numbers and File Names
If a sheet needs to be added between two sequential sheets, append a Supplemental Drawing Designator in accordance with ERDC/ITL TR-12-6 Adding a drawing sheet, and ERDC/ITL TR-12-1 Adding or deleting drawing sheets and index sheet procedures.
2 .3 CERTIFICATION OF EPA DESIGNATED ITEMS
Submit the Certification of EPA Designated Items as required by FAR 52 .223-9, "Certification and Estimate of Percentage of Recovered Material Content for EPA Designated Items". Include on the certification form the following information: project name, project number, Contractor name, license number, Contractor address, and certification. The certification will read as follows and be signed and dated by the Contractor.
PART 3 EXECUTION
3.1 AS-BUILT DRAWINGS
Provide and maintain two black line print copies of the PDF contract drawings for As-Built Drawings. Provide and maintain As-Built Drawings in accordance with NFAS 5252 .236-9310. Submit As-Built Drawings 30 days prior to Beneficial Occupancy Date(BOD) .
3 .l. l Markup Guidelines
Make comments and markup the drawings complete without reference to letters, memos, or materials that are not part of the As-Built drawing .
Show what was changed, how it was changed, where items(s) were relocated and change related details. These working as-built markup prints must be neat, legible and accurate as follows :
a. Use base colors of red, green, and blue . Color code for changes as follows :
(1) Special (Blue) - Items requiring special information, coordination, or special detailing or detailing notes.
(2) Deletions (Red) - Over-strike deleted graphic items (lines), lettering in notes and leaders .
(3) Additions (Green) - Added items, lettering in notes and leaders .
b . Provide a legend if colors other than the "base" colors of red, green, and blue are used.
c. Add and denote any additional equipment or material facilities, service lines, incorporated under As-Built Revisions if not already shown in legend .
SECTION 01 78 00 Page 19
d. Use frequent written explanations on markup drawings to describe changes. Do not totally rely on graphic means to convey the revision e . Use legible lettering and precise and clear digital values when marking prints . Clarify ambiguities concerning the nature and application of change involved.
f. Wherever a revision is made, also make changes to related section views, details, legend, profiles, plans and elevation views, schedules, notes and call out designations, and mark accordingly to avoid conflicting data on all other sheets .
g . For deletions, cross out all features, data and captions that relate to that revision.
h . For changes on small-scale drawings and in restricted areas, provide large-scale inserts, with leaders to the applicable location .
i. Indicate one of the following when attaching a print or sketch to a markup print :
1) Add an entire drawing to contract drawings
2) Change the contract drawing to show
3) Provided for reference only to further detail the initial design.
j. Incorporate all shop and fabrication drawings into the markup
3.1.2 As-Built Drawings Content
Revise As-Built Drawings in accordance with ERDC/ITL TR-12-1 and ERDC/ITL TR-12-6. Provide six sets of paper copies from PDF drawings to show the as-built conditions by red-line process during the execution of the project .
Keep these working as-built markup drawings current on a weekly basis and at least one set available on the jobsite at all times . Changes from the contract drawings which are made during construction or additional information which might be uncovered in the course of construction must be accurately and neatly recorded as they occur by means of details and notes . Submit the working as-built markup drawings for approval prior to submission of each monthly pay estimate . For failure to maintain the working and final record drawings as specified herein, the Contracting Officer will withhold 10] percent of the monthly progress payment until approval of updated drawings. Show on the as-built drawings, but not limited to, the following information :
a. The actual location, kinds and sizes of all sub-surface utility lines .
In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered over or obscured, show by offset dimensions to two permanently fixed surface features the end of each run including each change in direction on the record drawings. Locate valves, splice boxes and similar appurtenances by dimensioning along the utility run from a reference point . Also record the average depth below the surface of each run .
SECTION 01 78 00 Page 20 b . The location and dimensions of any changes within the building structure
c. Layout and schemat ic drawings of electrical circuits and piping . d.
Correct grade, elevations, cross section, or alignment of roads, earthwork, structures or utilities if any changes were made from contract plans.
e . Changes in details of design or additional information obtained from working drawings specified to be prepared and/or furnished by the Contractor; including but not limited to shop drawings, fabrication, erection, installation plans and placing details, pipe sizes, insulation mater ial, dimensions of equipment foundations, etc.
f. The topography, invert elevations and grades of drainage installed or affected as part of the project construction.
g . Changes or Revisions which result from the final inspection.
h . Where contract drawings or specifications present options, show only the option selected for construction on the working as-built markup drawings
i. If borrow material for this project is from sources on Government property, or if Government property is used as a spoil area, furnish a contour map of the final borrow pit/spoil area elevations .
j. Systems designed or enhanced by the Contractor, such as HVAC controls, fire alarm, fire sprinkler, and irrigation systems .
k . Changes in location of equipment and architectural features .
j. Modifications (include within change order price the cost to change working as-built markup drawings to reflect modifications) and compliance with FC l-300-09N procedures .
1. Actual location of anchors, construction and control joints, etc ., in concrete .
m . Unusual or uncharted obstructions that are encountered in the contract work area during construction .
n . Location, extent, thickness, and size of stone protection particularly where it will be normally submerged by water.
3.2 RECORD DRAWING FILES
If additional drawings are required, prepare them using the specified electronic file format applying the same graphic standards specified for original drawings. The title block and drawing border to be used for any new final record drawings must be identical to that used on the contract drawings. Accomplish additions and corrections to the contract drawings using CAD files . Provide all program files and hardware necessary to prepare final PDF record drawings. The Contracting Officer will review final PDF record drawings for accuracy and return them to the Contractor for required corrections, changes, additions, and deletions .
3.2.1 Rename the CAD Drawing files
SECTION 01 78 00 Page 21
Rename the CAD Drawing files using the contract number as the Project Code field,(e .g ., W91238-15-C-10A-102.DWGDGN) as instructed in the Pre-Construction conference . Use only those renamed files for the Marked-up changes . Make all changes on the layer/level as the original item .
a. For AutoCAD files (DWG), enter all as-built delta changes and notations on the AS-BUILT layer .MicroStation files (DGN), enter all as-built delta changes and notations on:
- Level #63
- Level/Layer Name contains: ANNO-REVS
- Level/Layer Description : Revisions
c. When final revisions have been completed, show the wording "RECORD
DRAWING AS-BUILTS" followed by the name of the Contractor in letters at least 5 mm 3/16 inch high on the cover sheet drawing . Date RECORD DRAWING AS-BUILTS" drawing revisions in the revision block .
d. The Government reserves the right to reject any drawing files it deems incompatible with the customer's CAD system . Paper prints, drawing files and storage media submitted will become the property of the Government upon final approval. Failure to submit final record PDF drawing files, CAD files and marked prints as specified will be cause for withholding any payment due under this contract . Approval and acceptance of final record drawings must be accomplished before final payment is made . Draft final as-built drawings shall be submitted on later than 20 calendar days after all work is completed (To include field and modification changes). Draft drawings shall be reviewed and are subject to changes and/or rejection. Final as-built drawings shall be submitted 30 calendar days after the draft final drawings have been returned to the contractor.
3.3 RECORD DRAWINGS
Prepare final record drawings after the completion of each definable phase of work as listed in the Contractor Quality Control Plan (Foundations, Utilities, Structural Steel, etc ., as appropriate for the project) . Transfer the changes from the approved working as-built markup drawings to the original electronic CAD drawing files. Modify the as-built CAD drawing files to correctly show the features of the project as-built by bringing the working CAD drawing set into agreement with approved working as-built markup drawings, and adding such additional drawings as may be necessary. Refer to ERDC/ITL TR-12-1 Chapter 11 Drawing Revisions Jointly review the working as-built markup drawings with printouts from working as-built CAD drawing PDF files for accuracy and completeness .
Monthly review of working as-built CAD drawing PDF file printouts must cover all sheets revised since the previous review . These PDF drawing files are part of the permanent records of this project . Any drawings damaged or lost must be satisfactorily replaced at no expense to the Government .
a. Drawing revisions (include within change order price the cost to
SECTION 01 78 00 Page 22 change working and final record drawings to reflect revisions) and compliance with the following procedures .
(1) Follow directions in the revision for posting descriptive changes.
(2) The revision delta size must be 8 mm 5/16 inch unless the area where the delta is to be placed is crowded . Use a smaller size delta for crowded areas.
(3) Place a revision delta at the location of each deletion .
(4) For new details or sections which are added to a drawing, place a revision delta by the detail or section title .
(5) For minor changes, place a revision delta by the area changed on the drawing (each location).
(6) For major changes to a drawing, place a revision delta by the title of the affected plan, section, or detail at each location.
(7) For changes to schedules or drawings, place a revision delta either by the schedule heading or by the change in the schedule.
3.3.l Final Record Drawing Package
Submit the final record PDF and CAD drawings package for the entire project within 30 days of substantial completion of all phases of work.
Submit one set of ANSI D size PDF and CAD files on optical disc, read-only memory (ROM), two sets of ANSI D size prints and one set of the approved working record drawings. The package must be complete in all details and identical in form and function to the contract drawing files supplied by the Government.
3.4 FINAL APPROVED SHOP DRAWINGS
Submit final approved project shop drawings 30 of the completed facility.
days after transfer
3.5 CONSTRUCTION CONTRACT SPECIFICATIONS
Submit final PDF file record construction contract specifications, including revisions thereto, 30 days after transfer of the completed facility .
3.6 AS-BUILT RECORD OF EQUIPMENT AND MATERIALS
Furnish s i x copies of preliminary record of equipment and materials used on the project 15 days prior to final inspection. This preliminary submittal will be reviewed and returned 2 days after final inspection with Government comments. Submit six sets
SECTION 01 78 00 Page 23 of final record of equipment and materials 10 inspection . Key the designations to the related contract drawings. List the following data:
days after final area depicted on the
SECTION 01 78 00 Page 24
RECORD OF DESIGNATED EQUIPMENT AND MATERIALS DATA
Description Specification Section
Manufacturer and Catalog, Model, and Serial Number
Composition and Size
Where Used
3.7 OPERATION AND MA INTENANCE MANUALS
Provide project operation and maintenance manuals as specified in Section 01 78 23 OPERATION AND MA INTENANCE MANUALS DATA . Provide four electronic copies of the Operation and Maintenance Manual files and 6 hard copy of the Operation and Maintenance Manuals . Submit to the Contracting Officer for approval within 30 calendar days of the Beneficial Occupancy Date (BOD). Update and resubmit files for final approval at BOD.
3.8 CLEANUP
Provide final cleaning in accordance with ASTM E1971 and submit four copies of the listing of completed final clean‐up items. Leave premises "broom clean ." Comply with GS‐ 37 for general purpose cleaning and bathroom cleaning . Use only nonhazardous cleaning materials, including natural cleaning materials, in the final cleanup . Clean interior and exterior glass surfaces exposed to view; remove temporary labels, stains and foreign substances; polish transparent and glossy surfaces; vacuum carpeted and soft surfaces . Clean equipment and fixtures to a sanitary condition. [Clean][Replace] filters of operat ing equipment and comply with the Indoor Air Quality (IAQ) Management Plan . Clean debris from roofs, gutters, downspouts and drainage systems. Sweep paved areas and rake clean landscaped areas . Remove waste and surplus materials, rubbish and construction facilities from the site .
3 . 9 REAL PROPERTY RECORD
Near the completion of Project, but a minimum of 60 days prior to final acceptance of the work, complete and submit an accounting of all installed property with Interim DD FORM 1354. Include any additional assets, improvements, and alterations from the Draft DD FORM 1354. Contact the Contracting Officer for any project specific information necessary to complete the DD FORM 1354. Refer to UFC 1-300-08 for instruction on completing the DD FORM 1354. For information purposes, a blank fillable PDF DD FORM 1354 may be obtained at the following :
http ://www .dtic.mil/whs/directives/forms/eforms/dd1354.pdf Submit the completed Checklist for DD FORM 1354 of Installed Building Equipment items. Attach this list to the updated DD FORM 1354.