Exhibit D08 - CDRLs 32-36

View the file

Other files

File Type Posted
W911S2-17-R-0002_Amendment_0003,_Ft_Drum_MATOC.pdf PDF
Conformed_Copy,_W911S2-17-R-0002-0009.pdf PDF
Amendment_0009,_W911S2-17-R-0002,_Fort_Drum.pdf PDF
Conformed_Solicitation_W911S2-17-R-0002_through_Amendment_0008.pdf PDF
Attachment_1_-_Seed_Project_PW_SOW_EE-20008-5J,_Seed_Task_Order_Drum_REV02.pdf PDF
Amendment_0008,_W911S2-17-R-0008.pdf PDF
Revised_Appendix_3v1_-_2016-12-20_3_Int_Munns_100_percent_-_CIVIL_31_May_2017_(FCS).pdf PDF
Conformed_W911S2-17-R-0002_thru_Amendment_0007.pdf PDF
Revised_Appendix_3v1_-_2016-12-20_3_Int_Munns_100_percent_-_ELEC_31_May_2017_(fcs).pdf PDF
Amendment_0007_W911S2-17-R-0002.pdf PDF
W911S2-17-R-0002_Conformed.pdf PDF
Amendment_0006_W911S2-17-R-0002.pdf PDF
Conformed_W911S2-17-R-0002_thru_Amendment_0005.pdf PDF
Appendix_3v5_-_2016-12-20__3_Int._Munns_Corner_SWPPP_100_percent.pdf PDF
Amendment_0005_W911S2-17-R-0002.pdf PDF
Attachment_1_-_Seed_Project_PW_SOW_EE-20008-5J,_Seed_Task_Order_Drum_REV01.pdf PDF
Attachment_4_-__W911S2-17-R-0002_MATOC_Site_Visit_Sign_In_Sheet_21_Mar_2017.pdf PDF
Amendment_0004_W911S2-17-R-0002.pdf PDF
Revised_Appendix_3v1_-_2016-12-20_3_Int_Munns_100_percent_-_CIVIL_18_May_2017.pdf PDF
Revised_Appendix_3v1_-_2016-12-20_3_Int_Munns_100_percent_-_ELEC_18_May_2017.pdf PDF
Exhibit_B_-_Price_Proposal_Worksheet,_v1_(Revised_Amd_0004).xlsx XLSX spreadsheet
Conformed_W911S2-17-R-0002_thru_Amendment_0004.pdf PDF
Attachment_3_-_Site_Visit_Roster_W911S2-17-R-0002_06_MAR_17.pdf PDF
Amendment_0002,_17-R-0002,_Ft_Drum_MATOC,_16_Mar_17.pdf PDF
Solicitation_W911S2-17-R-0002_Through_Amendment_0002.pdf PDF
Solicitation_W911S2-17-R-0002_Through_Amendment_0001.pdf PDF
Amendment_0001_W911S2-17-R-0002_Ft_Drum_MATOC.pdf PDF
Exhibit_B-Price_Proposal_Worksheet_v1.xlsx XLSX spreadsheet
Appendix_3v1-2016-12-20_3_Int_Munns_100_percent_-_ELEC.pdf PDF
Appendix_3v3-2016-11-23__3_Int._NARRATIVE_100_percent.pdf PDF
Appendix_3v6-2016-12-20_3_Int._GEO-TECH_-_SIGNED_-_2.PDF PDF
Appendix_3v1-2016-12-20_3_Int_Munns_100_percent_-_CIVIL.pdf PDF
Appendix_3v1-2016-12-20_3_Int_Munns_100_percent_-_COVER.pdf PDF
Exhibit_D11_CDRL_45-48,17-R-0002,Fort_Drum,Construction_MAIDIQ,5Feb17.pdf PDF
Exhibit_E_Application_and_Certificate_for_Payment.pdf PDF
Exhibit_D05_CDRL_20-23,17-R-0002,Fort_Drum,Construction_MAIDIQ,5Feb17.pdf PDF
Appendix_3v2-2016-12-20__3_Int._Munns_Corner_SPECS_100_percent.pdf PDF
Exhibit_C-Fort_Drum's_SOP_for_Electrical_Outages.pdf PDF
Exhibit_D03_CDRL_11-15,17-R-0002,Fort_Drum,Construction_MAIDIQ,8Feb17.pdf PDF
Exhibit_D07_CDRL_28-31,17-R-0002,Fort_Drum,Construction_MAIDIQ,5Feb17.pdf PDF
Attachment_1-Seed_Project_PW_SOW_EE-20008-5J_Seed_Task_Order_Drum.pdf PDF
Exhibit_D04_CDRL_16-19,17-R-0002,Fort_Drum,Construction_MAIDIQ,8Feb17.pdf PDF
Exhibit_G_Biological_Opinion.pdf PDF
W911S2-17-R-0002_Drum_CONMATOC_SOL.pdf PDF
Exhibit_D02_CDRL_5-10,17-R-0002,Fort_Drum,Construction_MAIDIQ,23Feb17.pdf PDF
Exhibit_D01_CDRL_1-4_17-R-0002,Fort_Drum,Construction_MAIDIQ,5Feb17.pdf PDF
Appendix_3v8-PEWS_015-As-Built_Record_Drawings.pdf PDF
Exhibit_D09_CDRL_37-40,17-R-0002,Fort_Drum,Construction_MAIDIQ,5Feb17.pdf PDF
Appendix_3v8-PEWS_002-Clearing_and_Grubbing.pdf PDF
Exhibit_D10_CDRL_41-44,17-R-0002,Fort_Drum,Construction_MAIDIQ,5Feb17.pdf PDF
Show 40 more

Latest 50 of 57 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DD FORM 1423, AUG 96

CONTRACT DATA REQUIREMENTS LIST

PREVIOUS EDITION MAY BE USED.

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15. TOTAL

16. REMARKS

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15. TOTAL

16. REMARKS

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15. TOTAL

16. REMARKS

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15. TOTAL

16. REMARKS

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

Page ____ of ____ Pages

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoD 5010.12-M for detailed instructions.)

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref.

DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13;

Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data shall be governed by the pertinent provisions of the contract.

DD FORM 1423 (BACK), AUG 96

addr1_1: COR
draft1_1:
reg1_1: 1
repro1_1:
addr1_2:
draft1_2:
reg1_2:
repro1_2:
addr1_3:
draft1_3:
reg1_3:
repro1_3:
draft2_1:
addr2_1: KO
addr2_2:
reg2_1: 1
repro2_1:
addr2_3:
draft2_3:
reg2_3:
repro2_3:
addr3_1: EPCRA MGR
addr3_2:
addr3_3:
draft3_1:
reg3_1: 1
repro3_1:
draft3_2:
reg3_2:
repro3_2:
draft3_3:
reg3_3:
repro3_3:
addr4_1: COR
draft4_1:
reg4_1: 1
repro4_1:
addr4_2:
draft4_2:
reg4_2:
repro4_2:
addr4_3:
draft4_3:
reg4_3:
repro4_3:
draft2_2:
repro2_2:
reg2_2:
line_item: 0001
exhibit: D
xtdp: Off
xtm: Off
othercat: X
system: RRC CONTRACT
ctr_no: RFP NO. W911S2-17-R-0002
contr: TBD
data_item1: D032
title1: ID BADGES
sub1: N/A
auth1: N/A
ref1: SECTION H ADDITIONAL CONSTR
req_ofc1: DPW
dd250_1: N/A
appcode1: N/A
dist1: N/A
freq1: ASREQ
asof1: ASREQ
firstsub1: ASREQ
subsub1: N/A
group1:
totalprice1:
rmks1: A listing of issued identification badges shall be furnished to the COR prior to contract performance date and updated quarterly to reflect Contractor and Subcontractor personnel changes.
totaldraft1: 0
totalreq1: 1
totalrepro1: 0
data_item2: D034
title2: SF FORM 1413 (Statement and Acknowledgement)
sub2: N/A
auth2: N/A
ref2: SECTION H ADDITIONAL CONSTR
req_ofc2: MICC - Fort Drum
dd250_2: N/A
appcode2: N/A
dist2: N/A
freq2: 14 DAYS AA
asof2: 14 DAYS AA
firstsub2: 14 DAYS AA
subsub2: 14 DAYS AA
rmks2: Within 14 days after award of any subcontract either between the prime contractor and a subcontractor, or between a subcontractor and another subcontractor, the Contractor shall deliver a completed SF Form 1413 (Statement and Acknowledgment) to the KO.
group2:
totalprice2:
totaldraft2: 0
totalreg2: 1
totalrepro2: 0
data_item3: D035
title3: MATERIAL SAFETY DATA SHEETS (MSDS)
sub3: N/A
auth3: N/A
ref3: SECTION H ADDITIONAL CONSTR
req_ofc3: DPW Environmental Division
dd250_3: N/A
appcode3: N/A
dist3: N/A
freq3: ASREQ
asof3: ASREQ
firstsub3: ASREQ
subsub3: ASREQ
rmks3: Material Safety Data Sheets (MSDS) will be provided to the Emergency Planning and Community Right to Know Act (EPCRA) manager at Fort Drum Public Works Environmental Division upon request.
group3:
totalprice3:
totaldraft3: 0
totalreg3: 1
totalrepro3: 0
data_item4: D036
title4: NEW YORK STATE MINING PERMIT
sub4: N/A
auth4: N/A
ref4: SECTION H ADDITIONAL CONSTR
req_ofc4: DPW
dd250_4: N/A
appcode4: N/A
dist4: N/A
freq4: ASREQ
asof4: ASREQ
firstsub4: ASREQ
subsub4: ASREQ
rmks4: Any off post source of borrow materials must have a valid New York State Mining Permit.
group4:
totalprice4:
totaldraft4: 0
totalreg4: 1
totalrepro4: 0
prep_by:
prep_sign:
prep_date:
app_by:
app_sign:
app_date:
Page: 8
pages: 12
app: Adobe Professional 7.0