Revised_Appendix_3v1_-_2016-12-20_3_Int_Munns_100_percent_-_ELEC_31_May_2017_(fcs).pdf
PDF 6 MB Posted
- Attached to
- Fort Drum MATOC (Construction)
- Solicitation number
- W911S2-17-R-0002
About this file
Revised Appendix 3 v 1 - 2016-12-20 3 Int Munns 100 percent ELEC 31 May 2017
View the file
Other files
Show 40 more
Latest 50 of 57 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ksharpless New Stamp ksharpless New Stamp frederick.c.ston3786 Text Box frederick.c.ston3786 Text Box
RFI# 29, 34, 36, 59, 71,77
frederick.c.ston3786 Text Box frederick.c.ston3786
RFi #33, 35
Rectangle frederick.c.ston3786
RFI # 35, 36, 38, 59, 71
Rectangle frederick.c.ston3786
RFI # 29, 36, 59, 71
RFI # 35, 36, 38, 59, 71
Note:
1. Light pole base to be 36" above grade for parking lots
2. Light pole base to be 1'-6" above grade for roadways
RFI#37
frederick.c.ston3786 Text Box Typical Bollard Detail
RFI 65