About this file

This is a notional pricing workbook template for the III Corps & Fort Hood Material Handling Equipment (MHE) contract. The spreadsheet serves as an exhibit to support Request for Task Order Proposals (RTOPs) submissions and is designed to help contractors develop pricing for individual task orders under the MATOC (Multiple Award Task Order Contract). The workbook provides a framework for contractors to calculate and present labor, equipment, materials, and other direct costs associated with material handling operations at Fort Hood, Texas and surrounding areas within a 100-mile radius.

The pricing template is structured to accommodate the diverse nature of MHE services required under the contract, which include simultaneous upload and download of containerized equipment across multiple battalion locations, wash rack operations, line haul services, Deployment Ready Reaction Field (DRRF) support, and Rail Operations Center (ROC) operations. Contractors are expected to use this notional pricing structure to submit competitive quotes for specific task orders as they are issued by the Government. The workbook format allows for detailed cost breakdowns covering personnel, equipment, supplies, transportation, fuel, supervision, and other necessary items to perform unit equipment movements and support deployment and redeployment operations, including 24-hour continuous operations when required at the task order level.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

Notional Task Order Details Worksheet
1Offerors review each CLIN / Sub-CLIN for details of quantity of each piece of equipment (Red Text).
2The Period of Performance (PoP) for the Notional Task Order is 10x days, as indicated in cells "B4 & B5" and the SLIN Description (Red Text)
3Offerors calculate the price of each CLIN 0001 SLIN based on the quantity and the PoP (Red Text) and insert into cells "E16 - E24" & "E26 (Orange cells)."
4Amount Totals will automatically calculate (cells "F16 - F26" green cells).
5Grand Total will automatically calculate (cell "F27").
CLIN Pricing Worksheet
1Worksheet is Locked
2Amounts/Totals from Notional Task Order Details Worksheet will auto-populate into the CLIN Pricing Worksheet and auto-multiply by the estimated maximum days per CLIN/SLIN (Estimated Quantities Worksheet).
3Amounts from base series CLINs/SLINs will auto-populate into "2000-series, 3000-series, and 4000-series" CLINS/SLINs with an auto-3% escalation rate from year to year.
4Place totals from column E (orange colored cells) into the SF1449 in the "Unit Price" box for the respective CLIN/SLIN
5Place totals from column F (yellow colored cells) into the SF1449 in the "Amount" box for the respective CLIN/SLIN
6Place amount from cell "F122" (red colored cell) directly beneath CLIN 4003 on the SF1449 labeled Total
Estimated Quantity
1Worksheet is Locked
2Worksheet provides estimated maximum quantities.
3Worksheet will auto-calculate "daily rate" for each SLIN

Notional Task Order Details Notional Task Order Details

Period of Performance:BaseOY1OY 2OY3OY4
Start:7-Jul-2026
End:16-Jul-2026
Points of Contact
Contracting OfficerChris Richie, 520-944-0622, christopher.a.richie.civ@army.mil
Contract SpecilaistShannon Campbell, 520-944-0970, shannon.s.campbell.civ@army.mil
Contracting Officer's Representative (COR)Maj Alexander Lovely alexander.j.lovely.mil@army.mil
Location(s):
#1Building 89240, New Railhead Road & Tank Destroyer Blvd Fort Hood Texas
ItemSupplies/ServicesQuanityUnitUnit PriceAmount
Base 0001Material handling Equipment (MHE) with Operators
0001AA180-Ton Heavy Crane Services include crane operator, spotting crew, Spreader bar and all required permits IAW Attachment-1, Performance Work Statement. QTY 1 EA; 10 days.1Job$ - 0
0001AB300-Ton Heavy Crane. Services include crane operator, spotting crew, Spreader bar and all required permits IAW Attachment-1, Performance Work Statement. QTY 1 EA; 2 days.1Job$ - 0
0001ACForklift, 15K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts.. The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements. QTY 5 EA; 10 days.1Job$ - 0
0001ADForklift, 30K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts (Preferred Fork size 7.5 FT long. /8 in wide.
/Spread 7.5 FT). The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements (PWS). QTY 5 EA; 10 days.1Job$ - 0
0001AEForklift, 36K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts (Fork size 7.5 FT long. /8 in wide. /Spread 7.5 FT). The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements (PWS). QTY 5 EA.; 10 days.1Job$ - 0
0001AFLight Tractor & Removeable Gooseneck (RGN) Trailer (60K Lbs.) with Operator. Services include the Tractor, Light RGN Trailer, capable of hauling 60K, operator(s), and all required permits. IAW Attachment-1, Performance Work Statement. QTY 1 EA; 10 days.1Job$ - 0
0001AGHeavy Tractor & Removeable Gooseneck (RGN) Trailer (150K Lbs.) with Operator. Services include the Tractor, Heavy RGN Trailer, capable of hauling 60K, operator(s), and all required permits. IAW Attachment-1, Performance Work Statement. QTY 2 EA; 10 days.1Job$ - 0
0001AHTractor & Flatbed Trailer with Operator. Services include the Tractor, Flatbed Trailer and all required permits. IAW Attachment-1, Performance Work Statement. QTY 7 EA; 10 days.1Job$ - 0
0001AJRough Terrain Cargo Handler (RTCH) or equivalent. Services nclude the RTCH (or equivalent) and all required permits. IAW Attachment-1, Performance Work Statement. QTY 1 EA; 10 days.1Job$ - 0
0002Minumum Guarantee1EA$500.00$ 500.00
0003Service Contract Reporting (SCR)1EA$ - 0
Grand Total$ 500.00
Work Hours:
Start:0800
End:1630
Chemical Solution:
Location #1Virkon-S, 1%

Location #2 Virkon-S, 1%

Location#3

SCA Wage Determination:
FT. Hood (Bell County)2015-5237 rev30
Environmental Sensitivities / Requirements
None
Overall Task Order Price:

CLIN Pricing MHE Pricing Workbook Matrix Sheet of Supplies or Services and Prices/Costs Additional Information/Notes

ItemSupplies/ServiceQuantityUnitUnit PriceAmount
BASE 000101JUL2026 to 30JUN2027
0001AA180-Ton Heavy Crane. Services include crane operator, spotting crew, Spreader bar and all required permits IAW Attachment-1, Performance Work Statement. Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
0001AB300-Ton Heavy Crane. Services include crane operator, spotting crew, Spreader bar and all required permits IAW Attachment-1, Performance Work Statement.
Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
0001ACForklift, 15K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts.. The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements

(PWS). S

Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
0001ADForklift, 30K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts (Preferred Fork size 7.5 FT long. /8 in wide.
/Spread 7.5 FT). The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements (PWS). Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
0001AEForklift, 36K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts (Fork size 7.5 FT long. /8 in wide. /Spread 7.5 FT). The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements (PWS). Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
0001AFLight Tractor & Removeable Gooseneck (RGN) Trailer (60K Lbs.) with Operator. Services include the Tractor, Light RGN Trailer, capable of hauling 60K, operator(s), and all required permits. IAW Attachment-1, Performance Work Statement Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
0001AGHeavy Tractor & Removeable Gooseneck (RGN) Trailer (150K Lbs.) with Operator. Services include the Tractor, Heavy RGN Trailer, capable of hauling 60K, operator(s), and all required permits. IAW Attachment-1, Performance Work Statement.1Job$ - 0$ - 0
0001AHTractor & Flatbed Trailer with Operator. Services include the Tractor, Flatbed Trailer and all required permits. IAW Attachment-1, Performance Work Statement Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
0001AJRough Terrain Cargo Handler
(RTCH) or equivalent. Services include the RTCH (or equivalent) and all required permits. IAW Attachment-1, Performance Work Statement.1Job$ - 0$ - 0
0002Minimum Guarantee
Product Service Code: W036 Pricing Arrangement: Firm Fixed Price1UNITLESS$500$ 500.00
0003Service Contract Reporting (SCR) Product Service Code: W036 Pricing Arrangement: Firm Fixed Price1NSP$ - 0$ - 0
Base Task Order No. 1 Total$ 500.00

Base Period Total $ 500.00

Option Period 1001 01JUL2027 to 30JUN2028

1001AA180-Ton Heavy Crane. Services include crane operator, spotting crew, Spreader bar and all required permits IAW Attachment-1, Performance Work Statement. Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
1001AB300-Ton Heavy Crane. Services include crane operator, spotting crew, Spreader bar and all required permits IAW Attachment-1, Performance Work Statement.
Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
1001ACForklift, 15K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts.. The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements

(PWS). S

Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
1001ADForklift, 30K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts (Preferred Fork size 7.5 FT long. /8 in wide.
/Spread 7.5 FT). The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements (PWS). Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
1001AEForklift, 36K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts (Fork size 7.5 FT long. /8 in wide. /Spread 7.5 FT). The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements (PWS). Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
1001AFLight Tractor & Removeable Gooseneck (RGN) Trailer (60K Lbs.) with Operator. Services include the Tractor, Light RGN Trailer, capable of hauling 60K, operator(s), and all required permits. IAW Attachment-1, Performance Work Statement Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
1001AGHeavy Tractor & Removeable Gooseneck (RGN) Trailer (150K Lbs.) with Operator. Services include the Tractor, Heavy RGN Trailer, capable of hauling 60K, operator(s), and all required permits. IAW Attachment-1, Performance Work Statement.1Job$ - 0$ - 0
1001AHTractor & Flatbed Trailer with Operator. Services include the Tractor, Flatbed Trailer and all required permits. IAW Attachment-1, Performance Work Statement Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
1001AJRough Terrain Cargo Handler (RTCH) or equivalent. Services include the RTCH (or equivalent) and all required permits. IAW Attachment-1, Performance Work Statement.1Job$ - 0$ - 0
SLIN 100401Services include the Tractor, RGN Trailer, capable of hauling 40T, operator(s), and all required permits1$ - 0
1002Minimum Guarantee
Product Service Code: W036 Pricing Arrangement: Firm Fixed Price1UNITLESS$ 500.00$ 500.00
1003Service Contract Reporting (SCR) Product Service Code: W036 Pricing Arrangement: Firm Fixed Price1NSP$ - 0$ - 0
OPT-1 Task Order No. 1 Total$ 500.00
OPT-1 Task Order No. 2 (15NOV2027-19NOV2027)
CLIN 1001Mobilize to AGSAN Site. The Contractor will mobilize to the specified location(s) and establish the site(s) for AGSAN services IAW Attachment-1 PWS, Exhibit A (TE1)
RTOP, and other attachments and exhibits specified at the Task Order-level per Job. Pricing Arrangement: Firm Fixed PriceJobERROR:#REF!
CLIN 1002AGSAN Services. The Contractor will perform AGSAN services at the specified location(s) IAW Attachment-1 PWS, Exhibit A (TE1) RTOP, and other attachments and exhibits specified at the Task Order-level. Total of 2,856 items of rollong stock, tracked vehicles, containers and secondary loads from Exhibit A (TE1) RTOP (Notional), per Job.
Pricing Arrangement: Firm Fixed PriceJobERROR:#REF!
CLIN 1003Other Direct Costs (ODC). This CLIN is used to account for Contractor required equipment and/or any other allowable Other Direct Costs (ODC) necessary at the Task
Order-level per Job. Pricing Arrangement: Firm Fixed PriceJobERROR:#REF!
OPT-1 Task Order No. 2 TotalERROR:#REF!

Option Period 1 Total $ 500.00

Option Period 2001 01JUL2028 to 30JUN2029

2001AA180-Ton Heavy Crane. Services include crane operator, spotting crew, Spreader bar and all required permits IAW Attachment-1, Performance Work Statement. Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
2001AB300-Ton Heavy Crane. Services include crane operator, spotting crew, Spreader bar and all required permits IAW Attachment-1, Performance Work Statement.
Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
2001ACForklift, 15K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts.. The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements

(PWS). S

Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
2001ADForklift, 30K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts (Preferred Fork size 7.5 FT long. /8 in wide.
/Spread 7.5 FT). The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements (PWS). Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
2001AEForklift, 36K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts (Fork size 7.5 FT long. /8 in wide. /Spread 7.5 FT). The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements (PWS). Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
2001AFLight Tractor & Removeable Gooseneck (RGN) Trailer (60K Lbs.) with Operator. Services include the Tractor, Light RGN Trailer, capable of hauling 60K, operator(s), and all required permits. IAW Attachment-1, Performance Work Statement Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
2001AGHeavy Tractor & Removeable Gooseneck (RGN) Trailer (150K Lbs.) with Operator. Services include the Tractor, Heavy RGN Trailer, capable of hauling 60K, operator(s), and all required permits. IAW Attachment-1, Performance Work Statement.1Job$ - 0$ - 0
2001AHTractor & Flatbed Trailer with Operator. Services include the Tractor, Flatbed Trailer and all required permits. IAW Attachment-1, Performance Work Statement Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
2001AJRough Terrain Cargo Handler (RTCH) or equivalent. Services include the RTCH (or equivalent) and all required permits. IAW Attachment-1, Performance Work Statement.1Job$ - 0$ - 0
2002Minimum Guarantee
Product Service Code: W036 Pricing Arrangement: Firm Fixed Price1UNITLESS$ 500.00$ 500.00
2003Service Contract Reporting (SCR) Product Service Code: W036 Pricing Arrangement: Firm Fixed Price1NSP$ - 0$ - 0
OPT-2 Task Order No. 1 Total$ 500.00
OPT-2 Task Order No. 2 (12MAR2029-16MAR2029)
CLIN 2001Mobilize to AGSAN Site. The Contractor will mobilize to the specified location(s) and establish the site(s) for AGSAN services IAW Attachment-1 PWS, Exhibit A (TE1)
RTOP, and other attachments and exhibits specified at the Task Order-level per Job. Pricing Arrangement: Firm Fixed PriceJobERROR:#REF!
CLIN 2002AGSAN Services. The Contractor will perform AGSAN services at the specified location(s) IAW Attachment-1 PWS, Exhibit A (TE1) RTOP, and other attachments and exhibits specified at the Task Order-level. Total of 2,856 items of rollong stock, tracked vehicles, containers and secondary loads from Exhibit A (TE1) RTOP (Notional), per Job.
Pricing Arrangement: Firm Fixed PriceJobERROR:#REF!
CLIN 2003Other Direct Costs (ODC). This CLIN is used to account for Contractor required equipment and/or any other allowable Other Direct Costs (ODC) necessary at the Task
Order-level per Job. Pricing Arrangement: Firm Fixed PriceJobERROR:#REF!
OPT-2 Task Order No. 2 TotalERROR:#REF!

Option Period 2 Total $ 500.00

Option Period 3001 01JUL2029 to 30JUN2030

3001AA180-Ton Heavy Crane. Services include crane operator, spotting crew, Spreader bar and all required permits IAW Attachment-1, Performance Work Statement. Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
3001AB300-Ton Heavy Crane. Services include crane operator, spotting crew, Spreader bar and all required permits IAW Attachment-1, Performance Work Statement.
Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
3001ACForklift, 15K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts.. The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements

(PWS). S

Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
3001ADForklift, 30K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts (Preferred Fork size 7.5 FT long. /8 in wide.
/Spread 7.5 FT). The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements (PWS). Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
3001AEForklift, 36K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts (Fork size 7.5 FT long. /8 in wide. /Spread 7.5 FT). The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements (PWS). Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
3001AFLight Tractor & Removeable Gooseneck (RGN) Trailer (60K Lbs.) with Operator. Services include the Tractor, Light RGN Trailer, capable of hauling 60K, operator(s), and all required permits. IAW Attachment-1, Performance Work Statement Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
3001AGHeavy Tractor & Removeable Gooseneck (RGN) Trailer (150K Lbs.) with Operator. Services include the Tractor, Heavy RGN Trailer, capable of hauling 60K, operator(s), and all required permits. IAW Attachment-1, Performance Work Statement.1Job$ - 0$ - 0
3001AHTractor & Flatbed Trailer with Operator. Services include the Tractor, Flatbed Trailer and all required permits. IAW Attachment-1, Performance Work Statement Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
3001AJRough Terrain Cargo Handler (RTCH) or equivalent. Services include the RTCH (or equivalent) and all required permits. IAW Attachment-1, Performance Work Statement.1Job$ - 0$ - 0
3002Minimum Guarantee
Product Service Code: W036 Pricing Arrangement: Firm Fixed Price1UNITLESS$ 500.00$ 500.00
3003Service Contract Reporting (SCR) Product Service Code: W036 Pricing Arrangement: Firm Fixed Price1NSP$ 500.00$ 500.00
OPT-3 Task Order No. 1 Total$ 500.00
OPT-3 Task Order No. 2 (06MAY2030-10MAY2030)
CLIN 3001Mobilize to AGSAN Site. The Contractor will mobilize to the specified location(s) and establish the site(s) for AGSAN services IAW Attachment-1 PWS, Exhibit A (TE1)
RTOP, and other attachments and exhibits specified at the Task Order-level per Job. Pricing Arrangement: Firm Fixed PriceJobERROR:#REF!
CLIN 3002AGSAN Services. The Contractor will perform AGSAN services at the specified location(s) IAW Attachment-1 PWS, Exhibit A (TE1) RTOP, and other attachments and exhibits specified at the Task Order-level. Total of 2,856 items of rollong stock, tracked vehicles, containers and secondary loads from Exhibit A (TE1) RTOP (Notional), per Job.
Pricing Arrangement: Firm Fixed PriceJobERROR:#REF!
CLIN 3003Other Direct Costs (ODC). This CLIN is used to account for Contractor required equipment and/or any other allowable Other Direct Costs (ODC) necessary at the Task
Order-level per Job. Pricing Arrangement: Firm Fixed PriceJobERROR:#REF!
OPT-3 Task Order No. 2 TotalERROR:#REF!

Option Period 3 Total $ 500.00

Option Period 4001 01JUL2030 to 30JUN2031

4001AA180-Ton Heavy Crane. Services include crane operator, spotting crew, Spreader bar and all required permits IAW Attachment-1, Performance Work Statement. Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
4001AB300-Ton Heavy Crane. Services include crane operator, spotting crew, Spreader bar and all required permits IAW Attachment-1, Performance Work Statement.
Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
4001ACForklift, 15K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts.. The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements

(PWS). S

Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
4001ADForklift, 30K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts (Preferred Fork size 7.5 FT long. /8 in wide.
/Spread 7.5 FT). The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements (PWS). Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
4001AEForklift, 36K Lb. lifting capacity, with Operator. The contractor shall provide outdoor 36k diesel forklifts (Fork size 7.5 FT long. /8 in wide. /Spread 7.5 FT). The forklifts will be delivered by the vendor vicinity to locations as outlined in the subsequent Task Order Performance Work Statements (PWS). Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
4001AFLight Tractor & Removeable Gooseneck (RGN) Trailer (60K Lbs.) with Operator. Services include the Tractor, Light RGN Trailer, capable of hauling 60K, operator(s), and all required permits. IAW Attachment-1, Performance Work Statement Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
4001AGHeavy Tractor & Removeable Gooseneck (RGN) Trailer (150K Lbs.) with Operator. Services include the Tractor, Heavy RGN Trailer, capable of hauling 60K, operator(s), and all required permits. IAW Attachment-1, Performance Work Statement.1Job$ - 0$ - 0
4001AHTractor & Flatbed Trailer with Operator. Services include the Tractor, Flatbed Trailer and all required permits. IAW Attachment-1, Performance Work Statement Pricing Arrangement: Firm Fixed Price1Job$ - 0$ - 0
4001AJRough Terrain Cargo Handler (RTCH) or equivalent. Services include the RTCH (or equivalent) and all required permits. IAW Attachment-1, Performance Work Statement.1Job$ - 0$ - 0
4002Minimum Guarantee
Product Service Code: W036 Pricing Arrangement: Firm Fixed Price1UNITLESS$ 500.00$ 500.00
4003Service Contract Reporting (SCR) Product Service Code: W036 Pricing Arrangement: Firm Fixed Price1NSP$ - 0$ - 0
OPT-4 Task Order No. 1 Total$ 500.00
OPT-4 Task Order No. 2 (07MAR2031-11MAR2031)
CLIN 4001Mobilize to AGSAN Site. The Contractor will mobilize to the specified location(s) and establish the site(s) for AGSAN services IAW Attachment-1 PWS, Exhibit A (TE1)
RTOP, and other attachments and exhibits specified at the Task Order-level per Job. Pricing Arrangement: Firm Fixed PriceJobERROR:#REF!
CLIN 4002AGSAN Services. The Contractor will perform AGSAN services at the specified location(s) IAW Attachment-1 PWS, Exhibit A (TE1) RTOP, and other attachments and exhibits specified at the Task Order-level. Total of 2,856 items of rollong stock, tracked vehicles, containers and secondary loads from Exhibit A (TE1) RTOP (Notional), per Job.
Pricing Arrangement: Firm Fixed PriceJobERROR:#REF!
CLIN 4003Other Direct Costs (ODC). This CLIN is used to account for Contractor required equipment and/or any other allowable Other Direct Costs (ODC) necessary at the Task
Order-level per Job. Pricing Arrangement: Firm Fixed PriceJobERROR:#REF!
OPT-4 Task Order No. 2 TotalERROR:#REF!

Option Period 4 Total $ 500.00

Grand Total $ 2,500.00

Estimated Quantities

Daily RateEstimated Annual Quantities
CLINSLINDescriptionEST Min QTYEST Max QTY (in days)
CLIN0001AA$ - 00001AA180 Crane140
0001AB$ - 0AB300 Crane16
0001AC$ - 0AC15K FL1200
0001AD$ - 0AD30K FL3200
0001AE$ - 0AE36K FL3250
0001AF$ - 0AFLGN TT1100
0001AG$ - 0AGHGN TT3500
0001AH$ - 0AHFB TT1100
0001AJ$ - 0AJRTCH or Equivalent2120
0002Min Guarantee11
0003SCR11