This document provides an overarching Quality Assurance Plan (QAP) for the Modernizing Instrumentation Solutions for Test and Evaluation (MISTE) Indefinite Delivery/Indefinite Quantity contract to provide test capabilities to the Army Major Range Test Facility Base and Department of Defense test and evaluation customers. The QAP outlines performance standards and acceptable quality levels for key contract requirements including quality control plans, data and product deliverables, schedule adherence, cost and schedule performance, program management effectiveness, subcontractor management, and criteria for rating contractor performance. It establishes surveillance methods for monitoring contractor performance, documenting acceptable and unacceptable performance, conducting reviews, and resolving any issues. The QAP will be used by the Contracting Officer's Representative to evaluate contractor performance on individual delivery orders under the IDIQ contract.
MISTE Base Quality Assurance Plan Draft RFP
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Quality Assurance Plan (QAP) for
Modernizing Instrumentation Solutions for Test and Evaluation
(MISTE)
Indefinite Delivery / Indefinite Quantity Contract
# W900KK-R-19-0006
DEPARTMENT OF THE ARMY
PROGRAM EXECUTIVE OFFICE FOR SIMULATION, TRAINING, AND
INSTRUMENTATION
(PEO STRI)
Approved By: _________________________________ Date: _______________ Ron Miller, PM ITTS IMO
MISTE Quality Assurance Plan (QAP) V.1 December 14, 2018 ii
Table of Contents
1. Introduction
2. Purpose
3. Scope
4. Performance Measurement and Monitoring Approach
5. Methods of Performance Monitoring
6. Communications and Customer Feedback
7. Customer Satisfaction
8. Formal Project Reviews
7. QASP Criteria Performance Metrics
8. Rating Definitions
9. Documenting Performance
10. Reviews and Resolution Appendix A – Acronym List Appendix B – Performance Report Appendix C – Contract Discrepancy Report (CDR)
1. Introduction The Modernizing Instrumentation Solutions for Test & Evaluation (MISTE) contract provides an Indefinite Delivery/Indefinite Quantity (ID/IQ) vehicle to Program Executive Office for Simulation Training and Instrumentation, Program Manager Instrumentation, Target, Threat Simulators, and SOF Training Systems (PM ITTS) Instrumentation Management Office (IMO) for delivering test capabilities to the Army Major Range Test Facility Base (MRTFB) and Department of Defense (DOD) test & evaluation (T&E) customers. Individual Delivery Order (DO) work efforts may take the form of a Statement of Work (SOW), or Performance Work Statement (PWS), or Statement of Objectives (SOO). DO’s may be negotiated as Firm Fixed Price (FFP) or Cost-Plus Fixed Fee
(CPFF).
This overarching Quality Assurance Plan (QAP) was developed in accordance with Federal Acquisition Regulations (FAR) 46.4 “Government Contract Quality Assurance”, which states in 46.401(a) “Government quality assurance shall be performed at such times (including any stage of manufacture or performance of services) and places (including subcontractors’ plants) as may be necessary to determine that the supplies or services conform to contract requirements…Quality assurance surveillance plans should be prepared in conjunction with the preparation of the statement of work.”
2. Purpose This QAP describes a systematic method that will be used to evaluate the contractor’s performance under individual delivery orders. This QAP provides examples of how quality assurance will be monitored and measured by the DO Contracting Officer’s Representative (COR) and/or other assigned support staff. Examples include:
• What will be monitored, and the performance standards associated with that activity, including remediation/disposition actions
• How monitoring will take place
• Who will conduct the monitoring
• How monitoring efforts and results will be documented
• How will performance be rated
• How often will surveillance/measurements take place
The QAP sets forth the procedures and guidelines the Government will use in ensuring that contract performance standards are achieved through effective and ongoing monitoring of metrics and Acceptable Quality Levels (AQL). The performance standards associated with the majority of DOs can be found in Table 1 of Section 9 as the baseline for performance monitoring. Individual DOs will include the actual Quality Assurance Surveillance Plan (QASP) to be used in association with that DO. Adjustments or supplementation (additions, deletions, changes) to the monitoring criteria, metrics, or performance standards reflected in the QAP may be made based on the unique performance requirements of each individual DO.
The QAP performance standards (metrics) established herein are applicable to achieving the functional and operational standards, thresholds, and contract performance objectives of the DO SOW (or PWS / SOO as applicable) as well as the contractor’s effective project management of the effort. This QAP is designed specifically to effectively monitor the contractor’s ongoing performance to deliver a successful end-product that meets cost, schedule, and quality requirements. This QAP shall not be construed as a substitute for, or relieve the contractor of, the Government’s rights under FAR clauses 52.246-2 Inspection of Supplies—Fixed-Price or 52.246-3 Inspection of Supplies – Cost Reimbursement.
3. Scope The contractor is responsible for the quality control of all work performed in accordance with the performance standards set forth in the DO QASP. The contractor measures that quality through their own approved Quality Control Plan (QCP), while the Government’s role is ensuring proper Quality Assurance by measuring the performance standards of the QASP. The contractor’s QCP will be provided and accepted by the Government at the time of award and will be incorporated as a binding contractual requirement. As such, this QAP does not detail how the contractor will accomplish quality control in accordance with the performance standards provided herein. Rather it provides the performance standards and the Government’s approach to measurement and monitoring of those performance standards.
4. Performance Measurement and Monitoring Approach The Government’s performance measurement and monitoring (i.e. surveillance) approach defined herein provides the Government’s intentions and plans to review and analyze information generated thorough contractor performance assessments throughout the term of each specific DO according to DO QASP. The following Government personnel shall oversee and coordinate surveillance activities:
a. Contracting Officer (KO) - The KO shall ensure the performance of all necessary Government actions for effective contracting, compliance with the contract terms, and safeguard of the interests of the United States in the contractual relationship.
The KO shall also ensure that the contractor receives impartial, fair, and equitable treatment under this contract. The KO is ultimately responsible for the final determination of the adequacy of the contractor’s performance.
Assigned KO: Dan Veentra
Organization or Agency: U.S. Army Contracting Command - Orlando
Telephone: 407-380-3968
Email: dan.veentra.civ@mail.mil
b. Contract Specialist (CS) - The CS acts as an acquisition consultant and serves as liaison between the requesting program office, the contractor, and the supporting contracting office.
Assigned CS: Joseph Candelaria
Organization or Agency: U.S. Army Contracting Command - Orlando
Telephone: 407-208-3220
Email: joseph.candalaria5.civ@mail.mil
c. Contracting Officer’s Representative (COR) - The COR is responsible for technical administration of the contract and shall assure proper Government surveillance of the contractor’s performance. The COR shall keep a quality assurance file. At the conclusion of the contract, or when requested by the KO, the COR shall provide documentation to the KO. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf. The contractor shall refer any changes they deem may affect contract price, terms, or conditions to the KO for action.
Assigned COR: TBD by individual delivery Order
Organization or Agency: TBD by individual delivery Order Telephone: TBD
Email: TBD
d. Government Product Manager (PM) – The Government PM is the customer of individual DOs under this contract. As such, the PM plays an important role in the customer feedback mechanism necessary for measurement of customer satisfaction for each specific DO. The focus of each DO is to fulfill requirements from a specific PM or PMs. Therefore, feedback from PMs through the mechanisms described in Sections 6-8 will provide the validation that requirements have been properly fulfilled.
Assigned PM: TBD, based on DO
Organization or Agency: TBD, based on DO
Telephone: TBD
Email: TBD
e. The contractor has assigned the following contractor personnel to measure the contractor’s quality control against the performance standards of this QAP in accordance with the contractor’s QCP. In addition, they will serve as the contractor’s Program Manager and Task Manager for this contract.
Program Manager: TBD
Telephone: TBD
Email: TBD
Task Manager: TBD
Telephone: TBD
Email: TBD
Other Contractor Personnel: TBD
Title: TBD
Telephone: TBD
Email: TBD
The Government’s acceptance of the contractor’s performance and deliverables will be based on analysis of factual data provided by the contactor and validated by the Government in accordance with the DO QASP. Based on this analysis, project performance information is documented, communicated, and used for contractor corrective actions, as applicable, and can be used as support for other contractual remedies that may be imposed by the Contracting Officer (KO) if performance is not maintained at acceptable levels in accordance with the performance standards of the DO
QASP.
Because the DO QASP defines the criteria and performance standards (i.e. metrics and AQLs) the contractor must continuously achieve for acceptable performance, it serves as the official basis for formal evaluation and rating of the contractor’s performance.
Accordingly, the QASP serves as the formal basis upon which the Contractor’s Performance Assessment Reporting System (CPARS) evaluation ratings are assigned in accordance with FAR 42.15.
5. Methods of Performance Monitoring The primary methods of DO performance surveillance include, but are not limited to:
a. Monitoring of contractor’s cost and schedule performance.
b. 100% review and inspection of all data and product deliverables including products physically installed at Government installations.
c. Periodic inspections of contractor facilities.
d. Direct observations of contractor work activities and deliverables.
e. Data validation.
f. Additional surveillance methods may be employed as determined necessary based on contractor performance. This could include assignment of an on-site Government quality assurance inspector/monitor and/or third party audits.
6. Communications and Customer Feedback The primary objective of ensuring a high level of effective communications is to ensure superior customer awareness at all times allowing for efficient customer feedback and leading to improved customer satisfaction. The timeliness and effectiveness of the contractor’s communications will be tracked, evaluated, and reported. Contractor’s communications will take the following forms:
a. Face-to-face meetings – as required
b. Reports – as required
c. Email – daily, as required
d. Briefings – every 30 days or earlier, if required
e. Teleconference – weekly or otherwise as scheduled
7. Customer Satisfaction Customer satisfaction is the most significant indicator of success and effectiveness of all products provided by the contractor. It will be evidence of proper contractor project management and quality control to ensure quality products are delivered on time and within cost. Customer feedback (level of satisfaction) will be primarily communicated in the form of email, verbally, and surveys using the communication methods in Section 6.
Customer satisfaction evaluation results will use the same definitions used for CPARS found in FAR 42.15, Table 42-1 “Evaluation Rating Definitions” and will be reflected under the “Management or Business Relations” factor in the annual assessment.
8. Formal Project Reviews Project reviews assist the Government customer in making ongoing business decisions regarding the project by evaluating its overall health at any given moment in time by:
a. Evaluating the effectiveness of project management
b. Comparing actual deliverables against the original requirements
c. Identifying lessons learned
d. Assessing performance (e.g. comparing the planned schedule, cost, and compliance requirements against the actuals)
e. Capturing stakeholders’ opinion of how the project was delivered
f. Disseminating project status results and findings for the record
7. DO QASP Criteria Performance Metrics The contractor is responsible for achieving the AQLs for all of the major processes identified below as included and identified under individual DO’s. The Government will perform surveillance of the contractor’s compliance with the standards through the various surveillance methods identified in Sections 5-8 of this QAP. The Government will document quality assurance findings on the formats provided in Appendix B – Performance Report and Appendix C – Contract Discrepancy Report (CDR) herein. Table 1 below provides the standards, acceptable quality levels, method of surveillance, and remediation/disposition (incentives and disincentives) that will be imposed based on the contractor’s performance based on specific DO requirements adhering to the following criteria:
Table 1: Acceptable Quality Levels (AQL) NOTE: DO metrics and criteria may include additions, deletions, and revision to the baseline metrics shown below
Product/Service Requirement – SOO Reference
Performance Standard
Acceptable Quality Level
(AQL)
Method of
Surveillance Remediation/Disposition
1. Contractor Quality Control Plan (QCP) SOW 3.4
Full (100%) implementation and management of approved QCP accepted at time of contract award.
Compliance with approved QCP >98% of the time.
Periodic Inspection (minimum 4 times annually).
[I] When consistently met or exceeded annually, annual CPARS subfactor rating of Very Good or Exceptional.
[D] Standard not met 2 or more times annually, contractor considered contractually non-compliant. CAP required and annual CPARS subfactor rating no higher than Marginal. Other contractual remedies considered by Contracting Officer.
2. Data and Product Deliverables
SOW 3.8
and FAR clauses 52.246-2 Inspection of Supplies—Fixed- Price or 52.246-3 Inspection of Supplies – Cost Reimbursement
100% of deliverables are submitted timely and accepted by the Government upon initial submission.
>95% are accepted upon initial submission and are considered timely.
100% acceptable upon first resubmission.
100% review and inspection of all data and products.
[I] Contract compliance considered favorably for customer satisfaction and consideration of Option Exercise.
[D] Standard not met 3 or more times annually, Fixed Fee under CPFF reduced by 2% and Profit reduced by 3% under FFP. Potentially negative CPARS rating under Technical/Quality of Product or Service factor.
Product/Service Requirement – SOO Reference
Performance Standard
Acceptable Quality Level
(AQL)
Method of
Surveillance Remediation/Disposition
3.Contractor maintains adherence to
IMP/IMS SOW
3.4.2
Manage and track schedule status and accomplish all
IMP/IMS
milestones on schedule
100% schedule adherence demonstrated on all DO’s
IMP/IMS
tracking through monthly reports and status reviews.
[I] Contractor compliant with DO requirement and demonstrated good schedule control viewed favorably toward Government consideration of Option Exercise.
[D] Loss of schedule control and/or high variation is risk indicator requiring a CAP if schedule risk is imminent.
Consistently poor performance results in annotated CPARS narrative for Schedule/Timeliness and may result in rating of no higher than marginal if schedule product delivery date not met.
4. Integrated Performance Management System Cost and Schedule Performance tracked against EVM reporting
SOW 3.4.3
Strict adherence to negotiated contract cost and performance schedules.
> 95% cost control demonstrated on CPFF DO’s.
100% schedule adherence demonstrated on all DO’s.
Monthly Trend Analysis of EVMS data and other cost and schedule reporting requirements when EVM is applied.
[I] Consistently positive SPI (> 1) and CPI (> 1) indicators viewed favorably toward Government consideration of Option Exercise. When consistently met or exceeded, annual CPARS Cost Control and/or Schedule/ Timeliness factor rating of Very Good or Exceptional for CPFF DO’s.
[D] Consistent or significant negative SPI (<
1) and CPI (<1) indicators viewed unfavorably toward Government consideration of Option exercise. CAP required and annual CPARS Cost Control and/or Schedule/ Timeliness factor rating no higher than Marginal.
SOO Reference
Performance Standard
Acceptable Quality Level
(AQL)
Method of
Surveillance Remediation/Disposition
5. Customer Satisfaction
No customer complaints with high levels of satisfaction reported.
Contractor has established positive working relationship with Government customer that is maintained.
Areas of concern/ dissatisfaction are resolved to the Government’s satisfaction within 15 business days and maintained.
Results of ongoing dialog and satisfaction survey results.
[I] Consistently high levels of satisfaction viewed favorably toward Government consideration of Option exercise. When consistently high levels are maintained annually, CPARS Management or Business Relations factor rating of Very Good or Exceptional.
[D] Negative satisfaction levels viewed unfavorably toward Government consideration of Option exercise. CAP required.
Annual CPARS Management or Business Relations factor rating could be rated no higher than Marginal if CAP unsuccessful.
6. Program Management Reports and Reviews SOW
3.4 and 3.4.1
100% accuracy presented in contract performance and risk management status.
>98% accuracy in reporting that demonstrates program outcomes are being properly managed and controlled.
Effectiveness of Program Management Function is validated through survey methods, performance monitoring and communication and feedback.
[I] Standard consistently met is viewed favorably toward Government consideration of Option Exercise. When consistently high levels are maintained annually, annual CPARS Management or Business Relations factor rating of Very Good or Exceptional.
[D] Negative satisfaction levels viewed unfavorably toward Government consideration of Option exercise. CAP required.
Annual CPARS Management or Business Relations factor rating could be rated no higher than Marginal if CAP unsuccessful.
SOO Reference
Performance Standard
Acceptable Quality Level
(AQL)
Method of
Surveillance Remediation/Disposition
7. Subcontractor Management
SOW 3.4.7
100% compliant with Small Business Participation percentages evaluated for contract award.
Subcontractor performance effectively monitored and controlled
>95% compliance on each delivery order
Monthly reporting and monitoring
[I] Contractor considered compliant for SBA reporting purposes.
Favorable CPARS ratings under Small Business Subcontracting factor under annual ratings when standard consistently met.
[D] Contractor considered non-compliant and consideration of Liquidated Damages equal to the percentage non-compliance in the form of Fee/Profit reduction may be imposed in addition to negative CPARS if standard not consistently met.
8. Rating Definitions
Table 2: FAR 42-1 Evaluation Ratings Definitions
Overall Performance Rating Standard
Exceptional
Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
Very Good
Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
Satisfactory Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
Marginal
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being evaluated reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.
Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
9. Documenting Performance
a. Acceptable Performance The Government shall document positive (i.e. acceptable) performance. Any report may become a part of the supporting documentation for payments or other actions.
Additionally, surveillance results will be used to prepare or support Performance Assessment Reports in CPARS.
b. Unacceptable Performance When unacceptable performance occurs, the COR shall inform the contractor. This will normally be in writing unless circumstances necessitate verbal communication. In any case the COR shall document verbal communications via the COR monthly report in the COR tracking tool.
When the COR determines formal written communication is required, the COR shall prepare a Contract Discrepancy Report (CDR) and present it to the contractor’s task manager or on-site representative. A CDR template is attached to this QASP (See Appendix C – Contract Discrepancy Report (CDR)).
The contractor shall acknowledge receipt of the CDR in writing. The CDR will specify if the contractor is required to prepare a corrective action plan to document how the contractor shall correct the unacceptable performance and avoid a recurrence. The CDR will also state how long after receipt the contractor has to present his corrective action plan to the COR. The Government shall review the contractor’s corrective action plan to determine acceptability.
Any CDRs may become a part of the supporting documentation for contract payment deductions, fixed fee deductions, award fee nonpayment, or other actions deemed necessary by the KO.
10. Reviews and Resolution The COR must initially coordinate and communicate with the contractor to resolve immediate performance issues or concerns while informing the Government’s PM and KO. The Government’s PM, COR, and contractor should jointly formulate and document long-term courses of action with the concurrence of the KO. Decisions regarding changes to metrics, thresholds, or service levels should be clearly documented and must be approved by the KO and incorporated into the contract via a modification.
If the contractor disputes a surveillance determination or has concerns over the Government’s performance management of the contract in general, they must first attempt to resolve through the Government’s PM. If, in the contractor’s opinion, resolution is not possible or there is clearly an impasse that is adversely affecting the contractual relationship and/or performance, the contractor must report their concerns to the KO within three business days from the date they determine resolution through the Government’s PM is not possible. The KO will be responsible to determining or negotiating the resolution approach and timeframe.
Appendix A – Acronym List
AQL – Acceptable Quality Level
CAP – Corrective Action Plan
CDR – Contractor Discrepancy Report
COR – Contracting Officer’s Representative
CPARS – Contractor Performance Assessment Reporting System
CPFF – Cost Plus Fixed Fee
DO – Delivery Order
EVMS – Earned Value Management System
FAR – Federal Acquisition Regulations
FFP – Firm Fixed Price
KO – Contracting Officer
PWS – Performance Work Statement
PM – Project Manager
QASP – Quality Assurance Surveillance Plan
QCP – Quality Control Plan
SOO – Statement of Objectives
SOW – Statement of Work
Appendix B – Performance Report
1) CONTRACT NUMBER: W900KK-XX-D-XXXX
2) Prepared by: (Name of COR) [Insert Name]
3) Date and time of observation:
4) Description of Observation:
Examples of items to include in a report are:
− Method of surveillance:
− How frequently you conducted surveillance:
− Surveillance Results:
− Number of Observations:
Prepared by: [Enter COR’s name]
Signature of Contracting Officer’s Representative Date
Appendix C – Contract Discrepancy Report (CDR)
1) CONTRACT NUMBER: W900KK-XX-D-XXXX
2) TO: (Contractor Task Manger or on-site representative) [Insert Name]
3) FROM: Prepared by: [Enter COR’s name]
4) Date and time of observation:
5) Description of discrepancy or problem: [Describe in detail. Identify any attachments, engineering reports or contractor-provided specification sheets]
6) Corrective action plan:
[COR’s and Government team’s assessment if a written corrective action plan< is / is not> required]
[If a written corrective action plan is required include the following. > The written Corrective Action Plan will be provided to the undersigned not later than <# of days after receipt of COR notification]
Prepared by: [Enter COR’s name]
Signature of Contracting Officer’s Representative Date
Received by:
Signature of Contractor Task Manger or Date on-site representative
The COR may initiate a CDR at any time contractor performance is determined to be impacting cost, schedule, or performance standards.
| 1. Introduction |
| 2. Purpose |
| 3. Scope |
| 4. Performance Measurement and Monitoring Approach |
| 5. Methods of Performance Monitoring |
| 6. Communications and Customer Feedback |
| 7. Customer Satisfaction |
| 8. Formal Project Reviews |
| 7. DO QASP Criteria Performance Metrics |
| 8. Rating Definitions |
| 9. Documenting Performance |
| 10. Reviews and Resolution |
| Appendix A – Acronym List |
| Appendix B – Performance Report |
| Appendix C – Contract Discrepancy Report (CDR) |