This document contains responses to questions received regarding a solicitation for a construction MATOC recompete opportunity with the Department of the Army. Key details include that the solicitation is for construction services at the Darby Military Community and seeks a multiple award task order contract vehicle. The response date was extended to January 12th, 2024 to accommodate holidays. Clarification was provided that Italian documents do not require translation. Proof of registration is not required but will be validated. A standard bid sheet will be provided in an amendment for pricing the seed project. Cost savings methods should be described in the narrative to support the proposed price and avoid appearing that requirements were not fully understood.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912PF24R0003
DMC Construction MATOC
RFI Responses
No. Date Received RFI Question RFI Response Date Posted Action Results in Amendment
Legal Review
1 28‐Nov‐23
Can a USA‐based company with SOA certification participate in this solicitation? The company does not have:
1) L.5.2 Documento Unico di Regolarita’ Contributiva (DURC)
2) L.5.3 Certificate of Chamber of Commerce
3) L.5.4 Anti‐Mafia / White List
Can we submit USA‐equivalent documents? Documents outlined in Section L must be provided as requested. No substitutions. 8‐Dec‐23 NO 7‐Dec‐23
2 29‐Nov‐23
Reference to page: 41 of Solicitation: L.3 Proposal Submission
It is not clear if offerors must submit their proposal whether through PIEE/standard email transmission or other government utilization of DoD SAFE. Please clarify.
L.3.1 states Proposals shall be submitted via E‐Mail using the subject line W58D2M‐24‐R‐0003 “MATOC”.
Directions for multiple emails are provided. 8‐Dec‐23 NO 7‐Dec‐23
3 30‐Nov‐23
This RFI is intended to request an extension to the proposal submission due date as of
04JAN2024.
As you are aware the period of the proposal due date falls under Christmas Holidays and Company closures (from Monday 25DEC2023 through 5JAN2024).
This leads to the unavailability to obtain timely offers from subcontractors and to develop a clear and strong technical proposal.
Please postpone the proposal delivery due date to at least Friday 19JAN2024.
At this time the government does not intend to alter any due dates.
New proposal due date is 12 January 2024, this will be reflected in an amendment. 15‐Dec‐23 YES 14‐Dec‐23
4 30‐Nov‐23
Volume I ‐ Factor I – Capability ‐ Sub‐Factor One: Organizational Structure for subject solicitation.
Reference page: 42 of Solicitation:
L.4.1.1 Sub‐Factor One: Organizational Structure Should we include Resumes and Certificates of the appointed team? If yes, are resumes and Certificates excluded from page count? L.4.1.1 Does not request or require Certificates or Resumes. No page count change is required 8‐Dec‐23 NO 7‐Dec‐23
5 30‐Nov‐23
Is there an Attachment/Standard Form/Project Info Sheet to fill out the requested project information for each completed project submitted as experience?
Should we include CPARS Evaluations as well? If yes, are CPARS evaluations excluded from the page limit?
No standard form or info sheet is provided with the solicitation to support the experience Factor. CPARS should not be included. Section M.3.3.1 affords the government to the right to utilize past performance data, such as CPARS. 8‐Dec‐23 NO 7‐Dec‐23
6 7‐Dec‐23
1)VOL III – Price & Contract Documents Para. L.2.1. & L.5.1.1.
Para L.2.1. specifies a 25 page limit for this Volume which also includes Contract Documents (SF1442, DURC, CCIAA, Anit‐Mafia, Section A through K, etc) Para L.5.1.1. Last sentence states….. All documents subject to submission under L.5.1.1. are excluded for the from the page limitations…. meaning all Contract Docs.
a)Please clarify if Contract docs are included or not within Page Limita ons. Bear in mind that contract docs are quite consistent and may vary by issuance of Amend.s, CCIAA page numbers, etc. so I would suggest no page limitations for Volume III;
b)Seed project is within Vol III? If so… does it have page limita ons?
A number error occurred in the format, an amendment will correct this oversight ‐ all documents submitted in Sections L.5, are excluded from the page limitations. b) it is the intent that all documents regarding the seed projects are submitted in Vol III, the page limit remains 25 pages. 8‐Dec‐23 YES 7‐Dec‐23
7 7‐Dec‐23 DURC, CCIAA, White List are obviously certificates issued in Italian.. do you need a brief translation or they may be submitted in Italian?´ Translation not required for these documents. 8‐Dec‐23 YES 7‐Dec‐23
8 7‐Dec‐23 3)L.5.1.2. Unique En ty ID, NCAGE, SAM… do you need a proof of these registra ons?
Prior to any bid/proposal opening or review, the government will validate SAM registration, so proof is not required within the proposal. 8‐Dec‐23 NO 7‐Dec‐23
9 7‐Dec‐23
4)L.4.4. Price breakdown shall address at least the following items:
a)Since we have a Low Price Technically Acceptable evalua on and to have an overall fair comparison between Offerors it would perhaps be reasonable to have the same line items vs.
at least following items
The Governments intent is to allow the vendors the flexibility to price the seed project based on each vendors unique proposed solution. The Government does not want to limit the vendors ability to provide unique solutions by providing specific line items.
Bid sheet will be provided as an attachment. 15‐Dec‐23 YES 14‐Dec‐23
10 11‐Dec‐23
Reference to Volume III Factor III – Price Section L.4.4.1 “Price breakdown shall address at least the following items…”. Will the Government provide a Standard Form for the Price Breakdown or the Contractor shall use its own form? Attachment 03 requests to indicate only LUMP SUM. Bid sheet will be provided as an attachment. 15‐Dec‐23 YES 14‐Dec‐23
11 11‐Dec‐23
Reference to Volume III Factor III – Price Section L.4.4.2.1 “The government may perform a realism analysis on the pricing proposed for the seed project in conjunction with the proposed narrative, schedule and/or Gantt chart proposed. Undeclared cost saving methods pose a risk to the contractor of being excluded from the competition for the appearance of the two parts of the proposal not being developed jointly”. Please clarify if it is mandatory to propose and include eventual cost saving methods within our proposal.
No, as this is a Lowest price technically acceptable (LPTA) award, contractor should submit their best offor for the "Seed Project", a detailed bid sheet will be provided within Amendment 0002. Any cost savings as a result of differing methods from the items identified in the bid sheet should be identified to ensure the government is aware of the alternative methods/savings to avoid interpretation that the company did not fully understand the seed project requirement. 15‐Dec‐23 YES 14‐Dec‐23
RFI Responses
12 11‐Dec‐23
Reference to Volume III Factor III – Price Section L.4.4.2.1 “The government may perform a realism analysis on the pricing proposed for the seed project in conjunction with the proposed narrative, schedule and/or Gantt chart proposed. Undeclared cost saving methods pose a risk to the contractor of being excluded from the competition for the appearance of the two parts of the proposal not being developed jointly”. Please clarify if the Government expects a Schedule Narrative or a technical proposal / approach?
No technical prposal/approach is required/requested. Only a narrative and schedule/Gantt chart to support the provided price for the seed project. 15‐Dec‐23 NO 14‐Dec‐23
13 11‐Dec‐23
Volume III Factor III – Price Section L.4.4.2.1 NARRATIVE, SCHEDULE. “The government may perform a realism analysis on the pricing proposed for the seed project in conjunction with the proposed narrative, schedule and/or Gantt chart proposed. Undeclared cost saving methods pose a risk to the contractor of being excluded from the competition for the appearance of the two parts of the proposal not being developed jointly”. Please clarify if a schedule narrative is intended to be submitted or a technical approach identifying and proposing cost savings methods / unique solutions to save money.
See previous question, the proposed detailed bid schedule to be provided in Amendment 0002 will help clarify. In the narrative, include any unique solutions or cost savings to ensure the government does not incorrectly interpret the price as a misunderstanding of the requirement. 15‐Dec‐23 YES 14‐Dec‐23
14 11‐Dec‐23
Reference to Volume III Factor III – Price Section L.4.4.2.1 “The government may perform a realism analysis on the pricing proposed for the seed project in conjunction with the proposed narrative, schedule and/or Gantt chart proposed. Undeclared cost saving methods pose a risk to the contractor of being excluded from the competition for the appearance of the two parts of the proposal not being developed jointly”. Please clarify the limits within the contractor to can change the provided Design package in order to provide cost saving methods.
Offeror is expected to review the Government's requirement and provide an acceptable solution IAW with the Solicitation. 15‐Dec‐23 NO 14‐Dec‐23
15 11‐Dec‐23
Reference to Volume III Factor III – Price Section L.4.4.2.1. “The government may perform a realism analysis on the pricing proposed for the seed project in conjunction with the proposed narrative, schedule and/or Gantt chart proposed. Undeclared cost saving methods pose a risk to the contractor of being excluded from the competition for the appearance of the two parts of the proposal not being developed jointly”. The Solicitation clearly states that undeclared cost saving methods is a risk to the contractor of being excluded from the competition. Please clarify how the proposed cost saving methods are evaluated.
Any cost savings would be anticipated in the total price for the seed project and referenced as part of the narrative, as such if a total price apppears low when pricing is evaluated, an analysis may be performed by the government to ensure the proposed narrative and schedule support the price proposed for the requirement and does not ommit any requirements of the seed project. 15‐Dec‐23 NO 14‐Dec‐23
16 11‐Dec‐23
Reference to Volume III Factor III – Price Section L.4.4.2.1. “The government may perform a realism analysis on the pricing proposed for the seed project in conjunction with the proposed narrative, schedule and/or Gantt chart proposed. Undeclared cost saving methods pose a risk to the contractor of being excluded from the competition for the appearance of the two parts of the proposal not being developed jointly”. The Solicitation clearly states that undeclared cost saving methods is a risk to the contractor of being excluded from the competition. Please clarify how the proposed cost savings shall be provided. In detail, shall the Contractor split in line items such as Price as per design provided plus the proposed saving in a separate line item or one Price including the cost saving? In the second case how will the Government recognize/realize the amount of the proposed savings?
This has been answered in previous questions ‐ Narrative/Schedule would be the method to communicate any proposed savings. 15‐Dec‐23 NO 14‐Dec‐23
17 11‐Dec‐23
Reference to Volume III Factor III – Price Section L.4.4.2.1. “The government may perform a realism analysis on the pricing proposed for the seed project in conjunction with the proposed narrative, schedule and/or Gantt chart proposed. Undeclared cost saving methods pose a risk to the contractor of being excluded from the competition for the appearance of the two parts of the proposal not being developed jointly”. Will Factor III – Price be rated more favorable if all Offerors’ cost saving methods are explicitly declared / proposed within the narrative? Is there a minimum number of methods that will be rated as acceptable?
Price will not be rated as acceptable or unacceptable. Any cost savings would be anticipated in the total price for the seed project and referenced as part of the narrative, as such if a total price apppears low when pricing is evaluated, an analysis may be performed by the government to ensure the proposed narrative and schedule support the price proposed for the requirement and does not ommit any requirements of the seed project. 15‐Dec‐23 NO 14‐Dec‐23
18 11‐Dec‐23
Reference to Volume I Capability – L.4.1.1 Sub‐Factor One: Organizational Structure “Offerors shall provide organizational chart(s) that clearly identifies the management, design, and construction teams, and key personnel to be utilized in executing task orders under the contract. Arrange the chart by organizational levels and location, depicting lines of authority.
The chart should show the interrelationship between all levels of leadership within the offeror’s…”.
By reading the Solicitation it seems that only a Organizational Chart is required and not the related Narrative describing the Chart. Since in Sec. L.2.1 for Capability are allowed 10 pages the question is if those pages are referred to the Narrative that shall be considered as required even if not mentioned or to the other documentation requested in Sub‐Factor Two. Please clarify. Narrative shall be included in Volume III along with schedule and price breakdown. 15‐Dec‐23 NO 14‐Dec‐23
RFI Responses
19 11‐Dec‐23
Reference page: 42 of Solicitation:
L.4.1.1 Sub‐Factor One: Organizational Structure Please clarify that eventual Letters of Commitment for Teaming Subcontractor Agreements are excluded from page count. Thank you.
Subcontractor relationships are not evaluated, no Letters of Commitment have been requested in Section L of the solicitation. Subcontactor's will be evaluated at the task order level but as a submission after award of a task order. 15‐Dec‐23 NO 14‐Dec‐23
20 12‐Dec‐23
VOLUME I FACTOR ONE – Subfactor Two: SOA Provide proof of SOA qualification as a company with the levels as stated herein.
Proof of qualification shall be via applicable SOA certificate submission, as follows:
OG 1: “Civil and Industrial Buildings Construction” Classification IV or higher (up to euro 2,582,000.00 or higher)
OR
OG 11: ‘’Technological Plants Utility Systems” Classification III or higher (up to euro 1,033,000.00 or higher)
Please clarify if both categories must be fulfilled, in other words if ‘’or’’ must be intended as ‘’and’’.
Or please clarify if there is a primary category and secondary category.
This is intended as "or", either category will suffice. Both are treated equally, no primary or secondary category. 15‐Dec‐23 NO 14‐Dec‐23
21 12‐Dec‐23 Will the removal of asbestos be considered on the seed project?
Although the presence of asbestos was discussed during the site visit, there will be no requirement for the Offeror to propose on removal of any asbestos. If asbestos is required to be removed from the seed project, then the Government will assess outside of this solicitation how to conduct its removal. 15‐Dec‐23 NO 14‐Dec‐23