Attachment 2G - Addendum 002 -Deconstruct-Reconstruct facility in ASA. Bldg. 2022.pdf
PDF 324 KB Posted
- Solicitation number
- W58D2M24R0003
About this file
This document outlines a Multiple Award Task Order Contract (MATOC) solicitation. The U.S. Army Contracting Command seeks to award up to four IDIQ contracts to satisfy construction and design-build projects for the Darby Military Community over a five year ordering period. The guaranteed minimum is $500 and the total maximum amount is $15 million. The seed project NAICS code is 236220. A pre-proposal conference will be held on December 6, 2023 to coordinate site visits. Responses are due by the dates specified in the solicitation for the MATOC recompete to provide construction services for the U.S. Army Materiel Command at the Darby Military Community.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
19 December 2023
ADDENDUM 002
PROJECT AA1-00150-2P Deconstruct and Reconstruct facility in ASA. Bldg. 2022
Design drawings and technical specification are modified as follows:
1. With reference to the electrical cable ducts shown in sheet CS103, the correct details to be considered are detail 1 and 2 of sheet C-502 instead of details 3 and 4.
2. With reference to the communication cable ducts shown in sheet CS103, the correct details to be considered are detail 3 and 4 of sheet C-502 instead of details 6.
3. New work item 5 shown in sheet CS103 is replaced by: “Install new FO cable single mode 12 strands in new cable duct”.
4. With reference to technical specification paragraph 3b-04, the following sentence is added:
“diameter and depth of the pilot hole shall be selected according to the machine used for the horizontal drilling, the number and the diameter of pipes to be installed”.
5. With reference to drawing T-102, new work item 1 is deleted.
6. With reference to drawing T-102, new work item 2, the following sentence is added:
"Perform the splice of the new 12 strands fiber optic cable to the existing 72 strands fiber optic cable inside manhole AMH-89".
7. With reference to technical specification paragraph 2a-02, the following sentence is added:
“Class of execution of the new steel structure as per UNI EN 1090 shall be EXC2 as reported in the table below”.
8. With reference to technical specification paragraph 2a-03, the following sentence is added:
“Structural Works Director will be in charge of defining the acceptance tests of materials and welds in accordance with the technical standards for construction Ministerial Decree January 17, 2018, optionally referring to the laboratory tests specified by UNI EN 1090”.
9. With reference to technical specification preface “Naturalistic Restrains”, the following sentence is added: “Since the project award exact date is unknown, assume Notice to
Proceed for the construction start be issued after July 15th (after the fauna reproduction period)”.
10. With reference to technical specification, paragraphs 4a-05 and 4c-06 are deleted. Refer to paragraph 2a-04 for the structural static test requirements.
11. With reference to technical specification, paragraph 7f-02 does not apply to the steel elements of the new construction. All the steel elements shall be hot galvanized without additional treatments (no black steel surfaces to be treated are present in the design).