Attachment_0050_-_Technical_Review_Criteria.pdf

PDF 193 KB Posted

Attached to
Common Robotic System (Individual) CRS(I)
Solicitation number
W56HZV-16-R-CRSI
Issued by

About this file

Draft Attachment 0050

View the file

Other files

File Type Posted
Synopsis_-_CRS(I).pdf PDF
FCL_Orientation_Handbook_18FEB15.pdf PDF
FCL_Sponsorship_Letter_MAY16.pdf PDF
FBO_Notice_FCL.docx DOCX document
Attachment_0047_-_Copyright_Release_Letter.docx DOCX document
Attachment_0028_CRS(I)_GFP_List.pdf PDF
Attachment_0009_-_Equipment_Publications_Defects_List.doc DOC document
Attachment_0019_-__MIL_Grade_Connector_Waiver_Form.xlsx XLSX spreadsheet
Attachment_0039_-_RAS-G_IOP_V2_-_JAUS_Profiling_Rules.pdf PDF
Attachment_0079_-__Example_Critical_Stockage_List_Worksheet.docx DOCX document
Attachment_0052_-_ATEC_Policy_Bulletin_13-12_Software_Safety_Verification_Policy_and_Guid.pdf PDF
Attachment_0012_-_DD1494_PreparationGuide.pdf PDF
Attachment_0042_-__RAS-G_IOP_Control_Profile.pdf PDF
Attachment_0011_-_TM_Matrix_MIL-STD_40051-2C_Appendix_A.pdf PDF
Attachment_0004_-_VDLS_Account_Access.docx DOCX document
Attachment_0013_-_DD1494_Frequency_Alocation_Form.doc DOC document
Attachment_0027_-_TRR_Checklist.docx DOCX document
Attachment_0040_-__RAS-G_IOP_V2_Overarching_Profile_Custom_Services,_Messages,_Transports.pdf PDF
Attachment_0005_-__Integrated_Mast_Plan_(IMP).pptx PPTX presentation
Attachment_0049_-_SSv_Severity_Scale.pdf PDF
Attachment_0002_Non_Disclosure_Agreement_(NDA).docx DOCX document
Attachment_0032-_CRS(I)_Work_Breakdown_Structure_(WBS).xlsx XLSX spreadsheet
Attachment_0046_-_Human_Engineering_Systems_Analysis_(HESA)_Instructions.docx DOCX document
Attachment_0003_-__Statement_Of_Work_Applicable_Documents.docx DOCX document
Attachment_0024_-_GEIA_STD_0007_ATTRIBUTE_SELECTION_WORKSHEET.xlsx XLSX spreadsheet
Attachment_0036_-_RAS-G_IOP_V2_-_Overarching_Profile.pdf PDF
Attachment_0044_-_Summary_of_Changes_-_IOP_V1_to_V2.xlsx XLSX spreadsheet
Attachment_0075_-_Running_Sheet.xls XLS spreadsheet
Attachment_0038_-_RAS-G_IOP_V2_-_Payloads_Profile.pdf PDF
Attachment_0081_-_Transaction_Format.doc DOC document
Attachment_0015_Required_Supplementation_from_MIL-PRF-32216A.pdf PDF
Attachment_0077_-_Example_Data_for_Battery_Modeling.pdf PDF
Attachment_0016_-__Publications_Style_Guide.pdf PDF
Attachment_0051_-_Joint_Software_Systems_Safety_Engineering_Handbook.pdf PDF
Attachment_0072_-_Supplier_RFI_Form.xlsx XLSX spreadsheet
Attachment_0043_-_RAS-G_IOP_V2_Applique_Profile.pdf PDF
Attachment_0023_Risk_Mgt_Scoring_Criteria_and_Reporting_Template.xlsx XLSX spreadsheet
Attachment_0080_-_Logistics_Product_Data.doc DOC document
Attachment_0078_-_Request_for_Use_of_Prohibited_Materials.doc DOC document
Attachment_0014__-Publications_General_Requirements.doc DOC document
Attachment_0041_-__RAS-G_IOP_V2-JAUS_Instantiation_Helper.pdf PDF
Attachment_0037-_RAS-G_IOP_V2_Comms_Profile.pdf PDF
Attachment_0010_-_Start_of_Work_Meeting_1_(SOWM1)_Agenda.xlsx XLSX spreadsheet
Attachment_0035_-_UGV_Interoperability_Profile_(IOP)_Capabilities_Plan_V2.pdf PDF
Attachment_0007_Run-Off_TRR_Checklist.docx DOCX document
SECTION_D_DRAFT.docx DOCX document
SECTION_C_DRAFT.docx DOCX document
SECTION_E_DRAFT.docx DOCX document
CRS_(I)_Special_Notice.pdf PDF
Special_Notice_5_Aug_16.docx DOCX document
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CRS(I)

TECHINICAL REVIEW CRITERIA

25 Jul 2016

UNCLASSIFIED - Distribution Statement A – Approved for Public Release; distribution unlimited

SRR Details Area SRR Review Details

Chairperson CRS(I)Program Officer (or designee)

PMO Participants PdM UGV Members of CRS(I) IPT(Contracting, Cost Analysis, Scheduler, LSE, Engineering, Software, Test, Logistics)

Contracting Officer

Anticipated

Stakeholder Participant

Organizations

PM Force Projection, PdM UGV, MSCoE, CASCOM, TARDEC, ATEC Maneuver Center of Excellence, Manuever Support Center of Excellence, TACOM ILSC, Sustainment Center of Excellence/EOD

Anticipated Peer and

Program-Independent

SME Participant Orgs.

TARDEC

Purpose of the review Ensures the contractor understands the CRS(I) Performance Specification and the proposed approach is compliant with these requirements.

Entrance Criteria SRR Agenda Per the DAG Section 4.2.10

Exit Criteria Per the DAG Section 4.2.10

Products/Artifacts

(from the review)

Contractor documentation per contract delivered and accepted.

Government Documents per the DAG Section 4.2.10.

PDR Details Area PDR Review Details

Chairperson CRS(I) Program Officer (or designee)

PMO Participants PdM UGV Members of CRS(I) IPT(Contracting, Cost Analysis, Scheduler, LSE, Engineering, Software, Test, Logistics)

Contracting Officer

Anticipated

Stakeholder

Participant

Organizations

PM Force Projection, PdM UGV, MSCoE, CASCOM, TARDEC, ATEC Maneuver Center of Excellence, Manuever Support Center of Excellence, TACOM ILSC, Sustainment Center of Excellence/EOD

Anticipated Peer and

Program-Independent

SME Participant Orgs.

TARDEC

Purpose of the review

The Preliminary Design Review (PDR) ensures the preliminary design and basic system architecture are complete, and that there is technical confidence the capability need can be satisfied within cost and schedule goals. The PDR provides the acquisition community, end user, and other stakeholders with an opportunity to understand the trade studies conducted during the preliminary design, and thus confirm that design decisions are consistent with the user’s performance and schedule needs. The PDR also establishes the system’s allocated baseline.

Entrance Criteria PDR Agenda Action items from the SRR have been closed

Per the DAG Section 4.2.12

Exit Criteria Per the DAG Section 4.2.12

Products/Artifacts

(from the review)

Contractor documentation per contract delivered and accepted.

Government Documents per the DAG Section 4.2.12.

CDR Details Area CDR Review Details

Chairperson CRS(I) Program Officer (or designee)

PMO Participants PdM UGV Members of CRS(I) IPT(Contracting, Cost Analysis, Scheduler, LSE, Engineering, Software, Test, Logistics) Contracting Officer

Anticipated

Stakeholder Participant

Organizations

Anticipated Peer and

Program-Independent

SME Participant Orgs.

TARDEC

Purpose of the review

The Critical Design Review (CDR) confirms the system design is stable and is expected to meet system performance requirements, confirms the system is on track to achieve affordability and should cost goals as evidenced by the detailed design documentation, and establishes the system’s initial product baseline.

Entrance Criteria CDR Agenda Action items from the PDR have been closed

Per the DAG Section 4.2.13

Exit Criteria Per the DAG Section 4.2.13

Products/Artifacts

(from the review)

Contractor documentation per contract delivered and accepted.

Government Documents per the DAG Section 4.2.13.

M Force Projection, PdM UGV, MSCoE, CASCOM, TARDEC, ATEC Maneuver Center of Excellence, Manuever Support Center of Excellence, TACOM ILSC, Sustainment Center of Excellence/EOD

SVR/FCA Details Area SVR/FCA Review Details

Chairperson CRS(I) Program Officer (or designee) PMO Participants PdM UGV

Members of CRS(I) IPT(Contracting, Cost Analysis, Scheduler, LSE, Engineering, Software, Test, Logistics) Contracting Officer

Anticipated

Stakeholder

Participant

Organizations

Anticipated Peer and

Program-Independent

SME Participant Orgs.

TARDEC

Purpose of the review

The System Verification Review (SVR) is the technical assessment point at which the actual system performance is verified to meet the requirements in the system performance specification and is documented in the system functional baseline. The Functional Configuration Audit

(FCA) is the technical audit during which the actual performance of a system element is verified and documented to meet the requirements in the system element performance specification in the allocated baseline.

Entrance Criteria

SVR/FCA Agenda Action items from the CDR have been closed

Per the DAG Section 4.2.14

Exit Criteria Per the DAG Section 4.2.14

Products/Artifacts

(from the review)

Contractor documentation per contract delivered and accepted.

Government Documents per the DAG Section 4.2.14.

PM Force Projection, PdM UGV, MSCoE, CASCOM, TARDEC, ATEC

PRR Details Area PRR Review Details

Chairperson CRS(I) Program Officer (or designee) PMO Participants PdM UGV

Members of CRS(I) IPT(Contracting, Cost Analysis, Scheduler, LSE, Engineering, Software, Test, Logistics) Contracting Officer

Anticipated

Stakeholder

Participant

Organizations

Anticipated Peer and

Program-Independent

SME Participant Orgs.

TARDEC

Purpose of the review

The Production Readiness Review (PRR) for the system determines whether the system design is ready for production, and whether the developer has accomplished adequate production planning for entering

Low-Rate Initial Production (LRIP) and Full-Rate Production (FRP).

Production readiness increases over time with incremental assessments accomplished at various points in the life cycle of a program.

Entrance Criteria

PRR Agenda Action items from the SVR/FCA have been closed

Per the DAG Section 4.2.15

Exit Criteria Per the DAG Section 4.2.15

Products/Artifacts

(from the review)

Contractor documentation per contract delivered and accepted.

Government Documents per the DAG Section 4.2.15.

PM Force Projection, PdM UGV, MSCoE, CASCOM, TARDEC, ATEC

TRR Details Area TRR Review Details

Chairperson CRS(I) Program Officer (or designee)

PMO Participants PdM UGV Members of CRS(I) IPT(Contracting, Cost Analysis, Scheduler, LSE, Engineering, Software, Test, Logistics) Contracting Officer

Anticipated

Stakeholder Participant

Organizations

Anticipated Peer and

Program-Independent

SME Participant Orgs.

TARDEC

Purpose of the review

The Test Readiness Review (TRR) is a technical review designed to ensure that the subsystem or system under review is ready to proceed into formal test. The TRR assesses test objectives, test methods and procedures, scope of tests, and safety and confirms that required test resources have been properly identified and coordinated to support planned tests. The TRR verifies the traceability of planned tests to program requirements and user needs. It determines the completeness of test procedures and their compliance with test plans and descriptions. The TRR also assesses the system under review for development maturity, cost/ schedule effectiveness, and risk to determine readiness to proceed to formal testing.

Entrance Criteria

Program manager's and T&E WIPT's determination that preliminary, functional, and pre-qualification test evaluation results form a satisfactory basis to initiate formal, system-level testing.

System has stabilized in configuration Compliance with Pre-TRR checklist

Exit Criteria

Necessary stakeholders were involved.

All planned tests verify a requirement that is directly traceable back to a system specification or other program requirement.

The system under test (i.e. configuration) is sufficiently mature, defined, and representative to accomplish planned test objectives and or support defined program objectives.

All planned preliminary, informal, functional, unit level, subsystem, system, and qualification tests were conducted, and are the results are satisfactory.

All expected results are known and their affect on the program is also known.

All planned tests resources (people, test article or articles, facilities, data systems, support equipment, logistics, etc.) are identified.

All risks associated with the tests are known and mitigation plans are complete.

Hazards and ESOH risks associated with the specific testing are identified.

The necessary “Safety Releases” from the Program Manager (PM) are provided to developmental and operational testers prior to any test using personnel.

A fall-back plan (should a technical issue or potential showstopper arise during testing) is available.

PM Force Projection, PdM UGV, MSCoE, CASCOM, TARDEC, ATEC Maneuver Center of Excellence, Manuever Support Center of Excellence, TACOM ILSC, Sustainment Center of Excellence/EOD

Products/Artifacts

(from the review)

Completed and approved test plans for the system under test.

Completed identification and coordination of required test resources.

Previous component, subsystem, and system test results form a satisfactory basis for proceeding into planned tests.

Identified risk level acceptable to the program leadership.

PCA Details Area PCA Review Details

Chairperson CRS(I) Program Officer (or designee) PMO Participants PdM UGV

Members of CRS(I) IPT(Contracting, Cost Analysis, Scheduler, LSE, Engineering, Software, Test, Logistics) Contracting Officer

Anticipated

Stakeholder

Participant

Organizations

Anticipated Peer and

Program-Independent

SME Participant Orgs.

TARDEC

Purpose of the review

The Physical Configuration Audit (PCA) is a formal examination to verify the “to be fielded” configuration of a validated system against its design and manufacturing documentation. The objective of the PCA is to resolve any discrepancies between the production-representative item that has successfully passed Operational Test and Evaluation (OT&E) and the associated documentation currently under configuration control.

Entrance Criteria

PCA Agenda Action items from the PRR have been closed

Per the DAG Section 4.2.16

Exit Criteria Per the DAG Section 4.2.16

Products/Artifacts

(from the review)

Contractor documentation per contract delivered and accepted.

Government Documents per the DAG Section 4.2.16.

PM Force Projection, PdM UGV, MSCoE, CASCOM, TARDEC, ATEC