Attachment_0005_-__Integrated_Mast_Plan_(IMP).pptx
PPTX presentation 1 MB Posted
- Attached to
- Common Robotic System (Individual) CRS(I)
- Solicitation number
- W56HZV-16-R-CRSI
About this file
Draft Attachment 0005
View the file
Other files
Show 40 more
Latest 50 of 58 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 0005 - CRS (I) Integrated Master Plan (IMP)
| CRS(I) | OY1 | OY2 | OY3 | OY4 | OY5 | OY6 | OY7 | |||||||||||||||||||||||||
| QTRS | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 |
| Major Events |
| Contracting |
| Systems Engineering |
| Deliveries |
| Test & Evaluation |
| Logistics Events |
Updated: 10 Dec 16
PDR
SRR
LRIP
CDR
MS C/TC/LP
PCA
SVR/FCA
Base/TO1 Award
TRR
OTRR
LUT
OER
IOC
CTR
PPQT
TO3 Award
TO1 Ends
TO2 Award
Draft Test Report
Run-Off Post CDR Assessment
Final Test Report
NET
LCSP Update
SSR
CFA
Run-Off TRR
EUA
TO2 Ends TO3 Ends
TO4 Award
SOWM1
SOWM2
PQT
TM VER
LOG Demo
TM VAL
I&KPT #2
I&KPT #1
PTM 1
PTM 2
FRC
PC2
PC1
LGR
LGR
2 Run-Off Assets 15 LRIP PQT / LUT Assets 3 LRIP LOG Assets
2 LOG/2 SW/1 FAC
PRR
FRP
FMR/TC STD
Timing of events in the IMP (Attachment 0005) are projections only. The contract delivery schedule (Section F) takes precedence in the event of a conflict.
15 PPQT/ EUA Assets
PMR4
PMR3
PMR5
PMR4
PMR2
PMR1
PMR3
PMR1
PMR3
PMR2
PMR1
PMR2
FUE
Distribution Statement A – Approved for Public Release; distribution unlimited
Integrated Master Plan Legend
(EMD1)
(EMD 2)
(LRIP)
image10.emf
Microsoft_Excel_Worksheet1.xlsx IMP Legend
CRS(I) Timeline Legend Deliverable Timing
Target Contractor Award
SOWM1 (2 day event) with IMS Review included NLT 20 days after CA
SRR (2 day event) NLT 21 days after CA
LGR (1 day event) NLT 21 days after CA
PDR (1 day event) 3 months after CA
PMR 1 (1 day event immediately following PDR) 3 months after CA
CFA (1 day event immediately following PMR) 3 months after CA
SSR (1 day event) 6 months after CA
PMR 2 (1 day event immediately following SSR) 6 months after CA
CDR (2 day event) 9 months after CA
PMR 3 (1 day event immediately following CDR) 9 months after CA
2 Run-Off Test Assets Delivery 12 months after TO1 Award
Run-Off TRR (1 day event) 13 months after CA
Run-Off Test (60 day event) 13 months after CA
Target Task Order 2 Award 3 months after TO1 completion
SOWM 2 (2 day event - IMS, IBR) NLT 15 days after TO2 Award
Post CDR Assessment (1 day event) Next day after SOWM2
LGR (1 day event) Immediately following SOWM2
I&KPT1 1 week after TO2 Award
EMD 2 PMR #1 (1 day event) 2.5 months after SOWM2
1st Provisioning Conference (PC1) (1 day event) 3 months after TO2 Award
TM Validation 30 days after Prov Conf 1
Pre-TRR (1 day event) NLT 10 days prior to TRR
15 PPQT/EUA Test Asset Deliveries 5 months after TO2 Award
2 LOG Asset Deliveries 5 months after TO2 Award
1 SW Asset Delivery 5 months after TO2 Award
1 SW Asset Delivery 5 months after TO2 Award
TRR (1 day event) 5 months after SOWM2
EMD 2 PMR #2 (1 day event) 5 months after SOWM2
PPQT (9 month event) 5 months after TO2 Award
Early User Assessment (14 day event) roughly 30 days after PPQT start
EMD 2 PMR #3 (1 day event) 8 months after SOWM2
EMD 2 PMR #4 (1 day event) 11 months after SOWM2
EMD 2 PMR #5 (1 day event) 16 months after SOWM2
PTM1 15 months after TO2 Award
Target Task Order 3 Award
SVR/FCA (2 day event) 15 days after TO3 Award
LRIP PMR 1 (1 day event) 3 months after TO3 Award
Provision Conference #2 (PC2) 3 months after TO3 Award
LRIP PMR 2 (1 day event) 6 months after TO3 Award
Pre OTRR (1 day event) 5 business days prior to OTRR
15 LRIP PQT/LUT Test Asset Deliveries 5 months after TO2 Award
2 LRIP LOG Asset Deliveries 5 months after TO2 Award
OTRR (1 day event) 6 months after TO3 Award
PQT (9 month event) 6 months after TO3 Award
LOG Demo (60 day event) 1 month after TO3 Award
PTM2 1 month after Log Demo
TM Verification (90 day event) 2 months after Log Demo
FRC 4 months after TM Verification
NET Training (14 day event) 6 moths after FRC
LUT (30 day event) Immediately following PQT
LRIP PMR 3 (1 day event) 9 months after TO3 Award
LRIP PMR 4 (1 day event) 12 months after TO3 Award
PRR (1 day event) 3 months after TO3 Award
PCA (4 day event) 12 months after TO3 Award
Task Order 4 Award 24 months after T03 Award
I&KPT2 1 month before FRC image11.emf
Microsoft_Excel_Worksheet2.xlsx IMP Legend
CRS(I) Timeline Legend Deliverable Timing
Target Contractor Award
SOWM1 (2 day event) NLT 15 days after CA
SRR (2 day event) NLT 16 days after CA
LGR (1 day event) NLT 16 days after CA
PDR (1 day event) 3 months after CA
PMR 1 (1 day event immediately following PDR) 3 months after CA
CFA (1 day event immediately following PMR) 3 months after CA
SSR (1 day event) 6 months after CA
PMR 2 (1 day event immediately following SSR) 6 months after CA
CDR (2 day event) 9 months after CA
PMR 3 (1 day event immediately following CDR) 9 months after CA
2 Run-Off Test Assets Delivery 12 months after TO1 Award
Run-Off TRR (1 day event) 13 months after CA
Run-Off Test (60 day event) 13 months after CA
Target Task Order 2 Award 3 months after TO1 completion
SOWM 2 (2 day event - IMS, IBR) NLT 15 calendar days after TO2 Award
Post CDR Assessment (1 day event) Next day after SOWM2
LGR (includes Provisioning Gudiance Discussion) (1 day event) Immediately following SOWM2
I&KPT1 10 days after SOWM2
EMD 2 PMR #1 (1 day event) 2.5 months after TO2
1st Provisioning Conference (PC1) (1 day event) 6 months after TO2 Award
TM Validation Upon completion of PPQT
Pre-TRR (1 day event) NLT 10 days prior to TRR
15 PPQT/EUA Test Asset Deliveries 140 calendar days after TO2 Award
2 LOG Asset Deliveries 5 months after TO2 Award
1 SW Asset Delivery 5 months after TO2 Award
1 SW Asset Delivery 5 months after TO2 Award
TRR (1 day event) 5 months after TO2 Award
EMD 2 PMR #2 (1 day event) 5 months after TO2 Award
PPQT (9 month event) 5 months after TO2 Award
Early User Assessment (14 day event) 30 days after PPQT start
EMD 2 PMR #3 (1 day event) 8 months after SOWM2
EMD 2 PMR #4 (1 day event) 11 months after SOWM2
EMD 2 PMR #5 (1 day event) 16 months after SOWM2
Target Task Order 3 Award
SVR/FCA (2 day event) 15 days after TO3 Award
LRIP PMR 1 (1 day event) 3 months after TO3 Award
Provision Conference #2 (PC2) 3 months after TO3 Award
LRIP PMR 2 (1 day event) 6 months after TO3 Award
Pre OTRR (1 day event) 5 business days prior to OTRR
15 LRIP PQT/LUT Test Asset Deliveries 5 months after TO2 Award
2 LRIP LOG Asset Deliveries 5 months after TO2 Award
OTRR (1 day event) 6 months after TO3 Award
PQT (9 month event) 6 months after TO3 Award
LOG Demo (60 day event) 1 month after TO3 Award
PTM2 1 month after Log Demo
TM Verification (90 day event) 2 months after Log Demo
FRC 4 months after TM Verification
NET Training (14 day event) 6 moths after FRC
LUT (30 day event) Immediately following PQT
LRIP PMR 3 (1 day event) 9 months after TO3 Award
LRIP PMR 4 (1 day event) 12 months after TO3 Award
PRR (1 day event) 3 months after TO3 Award
PCA (4 day event) 12 months after TO3 Award
Task Order 4 Award 24 months after T03 Award
I&KPT2 1 month before FRC image12.emf
Microsoft_Excel_Worksheet3.xlsx IMP Legend
CRS(I) Timeline Legend Deliverable Timing
Target Contractor Award
SOWM1 (2 day event) NLT 15 days after CA
SRR (2 day event) NLT 16 days after CA
LGR (1 day event) NLT 16 days after CA
PDR (1 day event) 3 months after CA
PMR 1 (1 day event immediately following PDR) 3 months after CA
CFA (1 day event immediately following PMR) 3 months after CA
SSR (1 day event) 6 months after CA
PMR 2 (1 day event immediately following SSR) 6 months after CA
CDR (2 day event) 9 months after CA
PMR 3 (1 day event immediately following CDR) 9 months after CA
2 Run-Off Test Assets Delivery 12 months after TO1 Award
Run-Off TRR (1 day event) 13 months after CA
Run-Off Test (60 day event) 13 months after CA
Target Task Order 2 Award 3 months after TO1 completion
SOWM 2 (2 day event - IMS, IBR) NLT 15 days after TO2 Award
Post CDR Assessment (1 day event) Next day after SOWM2
LGR (1 day event) Immediately following SOWM2
I&KPT1 1 week after TO2 Award
EMD 2 PMR #1 (1 day event) 2.5 months after SOWM2
1st Provisioning Conference (PC1) (1 day event) 3 months after TO2 Award
TM Validation 30 days after Prov Conf 1
Pre-TRR (1 day event) NLT 10 days prior to TRR
15 PPQT/EUA Test Asset Deliveries 5 months after TO2 Award
2 LOG Asset Deliveries 5 months after TO2 Award
1 SW Asset Delivery 5 months after TO2 Award
1 SW Asset Delivery 5 months after TO2 Award
TRR (1 day event) 5 months after SOWM2
EMD 2 PMR #2 (1 day event) 5 months after SOWM2
PPQT (9 month event) 5 months after TO2 Award
Early User Assessment (14 day event) roughly 30 days after PPQT start
EMD 2 PMR #3 (1 day event) 8 months after SOWM2
EMD 2 PMR #4 (1 day event) 11 months after SOWM2
EMD 2 PMR #5 (1 day event) 16 months after SOWM2
PTM1 15 months after TO2 Award
Target Task Order 3 Award
SVR/FCA (2 day event) 15 days after TO3 Award
LRIP PMR 1 (1 day event) 3 months after TO3 Award
Provision Conference #2 (PC2) 3 months after TO3 Award
LRIP PMR 2 (1 day event) 6 months after TO3 Award
Pre OTRR (1 day event) 5 business days prior to OTRR
15 LRIP PQT/LUT Test Asset Deliveries 5 months after TO3 Award
3 LRIP LOG Asset Deliveries 5 months after TO3 Award
OTRR (1 day event) 5 months after TO3 Award
PQT (9 month event) 6 months after TO3 Award
LOG Demo (60 day event) 6 month after TO3 Award
PTM2 1 month after Log Demo
TM Verification (90 day event) 3 months after PTM2
FRC 2 months after LUT
NET Training (14 day event) 1 month after FMR
LUT (30 day event) Immediately following PQT
LRIP PMR 3 (1 day event) 9 months after TO3 Award
LRIP PMR 4 (1 day event) 12 months after TO3 Award
PRR (1 day event) 3 months after TO3 Award
PCA (4 day event) 12 months after TO3 Award
I&KPT2 2 months before LUT
FMR 4 months after OER
FUE 1 month after FMR image1.png image2.png image3.jpeg image4.png image5.png