E2FDS_Contractor_Solicitation_Questions29FEB2016_-_Set2_FINAL.pdf

PDF 223 KB Posted

Attached to
Early Entry Fluid Distribution System (E2FDS)
Solicitation number
W56HZV15R0221
Issued by

View the file

Other files

File Type Posted
Instructions_for_Interested_Subcontractors.pdf PDF
List_of_Interested_Potential_Subcontractors.pdf PDF
E2FDS_Contractor_Solicitation_Questions_-_Set4.pdf PDF
E2FDS_Attachment_0031_Price_Evaluation_Sheet.xlsx XLSX spreadsheet
E2FDS_W56HZV-15-R-0221_0004.pdf PDF
E2FDS_Attachment_0032_Ordering_Period_2_PES.xlsx XLSX spreadsheet
E2FDS_Attachment_0002_Technical_Verification_Requirements.docx DOCX document
E2FDS_Attachment_0025_Integrated_Master_Schedule.pdf PDF
A073_Certification_Report.doc DOC document
E2FDS_W56HZV-15-R-0221_0002.pdf PDF
E2FDS_Attachment_0030_Cross-Reference_Matrix_for_Experience.docx DOCX document
W56HZV15R0221-0003.pdf PDF
E2FDS_Attachment_0001-_ATPD_2417.pdf PDF
E2FDS_Attachment_0031_Price_Evaluation_Sheet.xlsx XLSX spreadsheet
E2FDS_Attachment_0032_Ordering_Period_2_PES.xlsx XLSX spreadsheet
E2FDS_Attachment_0025_Integrated_Master_Schedule.pdf PDF
W56HZV-15-R-0221_Amendment_0001.pdf PDF
ATPD-2306_-_Suspension_Kit _Collapsible_Hoseline.pdf PDF
Drawing_13228E3612_001.pdf PDF
E2FDS_Contractor_Solicitation_Questions_-_Set1.pdf PDF
E2FDS_CDRLs.zip ZIP file
Exhibit_A_-_E2FDS_Contract_Data_Requirements_List.pdf PDF
E2FDS_Solicitation_W56ZHV-15-R-0221.pdf PDF
E2FDS_Attachments.zip ZIP file
Instructions_Q A.pdf PDF
E2FDS_Q A_v2.pdf PDF
Attendees-E2FDS_Industry_Day_UPDATED.pdf PDF
E2FDS-Industry-Day-16Jun2015.pdf PDF
13219E0462.pdf PDF
11674728.pdf PDF
E2FDS-Market-Survey1-Initial.pdf PDF
E2FDS-Market_Survey2_-_FollowOn.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

E2FDS Contractor Solicitation Questions W56HZV-15-R-0221 Set 2 C o n Contractor Question Government Answer Question Status

1West

Does the Government have a CDRL and DID for CLIN 2016, Training Aides, Devices, Simulations and Simulators (TADDS)? Are there specific critical tasks and learning objectives relative to collective training the simulators must address?

There is no CDRL associated with CLIN 2016. That CLIN is created for a hardware deliverable, not a data deliverable. Answered

2WestWill the Government clarify that CDRL A085 is to be priced separately under CLIN 2021?

Yes, CLIN 2021 is to be separately priced. The correction will be added to a future solicitation amendment.

Attachments 0031 and

0032 updated via

Amendment 0001

3West

Since this is in the EMD phase, it appears that CDRL A046 should not be a required deliverable during the EMD phase as CDRL A044 is the Operator Manual in the EMD phase and A046 is the Operator Manual in the P&D phase. Will the Government please clarify?

CDRL A046 (OPERATOR TM OVERARCHING) is not a deliverable during the

EMD phase. Answered

4West

Attachment 0025, ID 136 - Technical Manuals CDRL A044, A045, A046, A047: The deliverables on this task include CDRL A044 and A045. Since this is in the P&D phase it appears that CDRLs A044 and A045 (an EMD requirement) should not be included.

Shouldn't CDRLs A046 and A047 be the DEP TM deliveries in the P&D phase that essentially replace the EMD PDEP manuals of CDRLs A044 and A045? Please clarify.

CDRLs A044 and A045 are associated with EMD TM deliverables. CDRLs

A046 and A047 are associated with P&D TM deliverables. Attachment 0025

(Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule.

Attachment 0025 updated via

Amendment 0001

5West

Page 69 of the Solicitation shows CLIN 2005, DEP delivery is 270 DADO. CDRL A051 states the DEP is delivered at 180 days. Attachment 0025 indicates pubs initial validation plan would be held 30 days after Fair opportunity decision in the timeline. Will the

Government please clarify the due date of CLIN 2005 DEP?

CDRL A051 already reflects the correct delivery timing of 180 DADO. The

CLIN 2005 delivery timing narrative will be changed from 270 to 180 DADO in a future amendment.

Within Attachment 0025, the delivery timing listed for CDRL A051 is correct.

Though Attachment 0025 has been updated to show a corrected name change for CDRL A051. Attachment 0025 has been updated in Amendment

0001.

Attachment 0025 updated via

Amendment 0001.

CLIN 2005 narrative will be corrected in a future amendment

6West

CDRL A071 states, "The contractor shall deliver a Familiarization Training Guide (FTG) for each test event." Paragraph C.6.13.19.2.4 states, "The contractor shall provide familiarization training…at LUT, PQT, and LD." Attachment 0025 includes an entry for

FTGs for the Engineering Development Test (EDT), but it does not specify FTGs for the

Logistics Demonstration. Request the Government clarify which events will require FTGs.

Are they required for the EDT, LUT, PQT, TM Verification, and LD?

Familiarization training is provided for all test events. EMD testing is defined under C.5.15 Training. P&D testing is defined under C.6.13.19.2.4

Contractor Familiarization Training & C.6.13.19.3 IOT&E System Operator and Maintainer Training. Answered o n Contractor Question Government Answer Question Status

7West

CDRL A077 states the Training Course Completion Report is due for all training events at

Logistics Demonstration, TM Verification, Limited User Test, and Initial Operator Test and

Evaluation. This list does not include the Production Quality Test (PQT). Does the

Government expect a Training Course Completion Report following the training that would precede the PQT?

CDRL A077 lists all events for which Training Course Completion Reports are required. Answered

8West

CDRL A077 includes the TM Verification as an event that requires a Training Course

Completion Report. Does the Government intend the contractor to deliver the full

Operator (40 hours) and Maintainer (80 hours) Training in support of the TM Verification event? Familiarization Training is for Test events. TM Verification is not a test event. Answered

9West

Solicitation paragraph C.6.1.4.1, requires the delivery of two Collective Virtual Training

Simulators. Is there guidance as to the requirements of the training simulator including a user manual and training on the training simulator? If so, what is the period of time for performance of this training?

C.6.1.4.1 will be revised in a future amendment as follows:

"The contractor shall deliver one TADSS package 90 days after completion of IOT&E as identified in the specified DO. The TADSS package consists of two collective Virtual Training Simulators, one ERS, two containment loads of hose, one Automated Pump Station, Support Equipment (for one mile), and one C2M. The contractor shall provide adequate training, no more than three days so that the Government can operate and train the simulator."

This will be added to section C.6.1.4.1 in a future solicitation amendment:

"The Collective Virtual Training Simulator will simulate E2FDS operations as well as introduce conditions and faults that would require actions from leaders and operators. It will be in the form of a software module integrated in the centralize control station, stand-alone laptop based software, integrated Human/Machine Interface (HMI) panels with software integrated in pump stations or any combination of these approaches. No special facilities are required for the Collective Virtual Training Simulator. "

Definition to be added to future solicitation amendment

10West

Reference solicitation paragraph C.6.1.4.1. Are there any unique installation requirements, such as power consideration or other environmental considerations, that apply to the two locations where the simulators will be used? No. See answer above concerning Collective Virtual Training Simulator. Answered

11West

Reference solicitation paragraph C.6.1.4.1. Are there any sustainment or warranty considerations in the requirements of the training simulators? No. Answered

12West

Reference solicitation paragraph C.6.1.4.1. What are the delivery requirements for the two Virtual Training Simulators?

IAW C.6.1.4.1, a virtual simulator will be delivered with each 5 mile training set (PRS) after refurbishment when fielded. Answered n Contractor Question Government Answer Question Status

13West

Are the hardware deliverables under EMD PRS CLIN 1000 and P&D PRS CLIN 2006 the same? Yes, both hardware deliverables are the same. Answered

14WestWhat CLIN should be used in pricing additional pump assemblies?

No spare pumps are being procured. The Government will have sufficient spares with the extra test pumps. This clarification will be added to the

ATPD (Attachment 0001), which will be updated in a future solicitation amendment.

Attachment 0001 updated via

Amendment 0001

15West

We are asking for a minimum 30-day extension to the due date of the proposal to incorporate answered responses to the above questions into our proposal We are only granting a 15 day extension. Answered

16West

Please provide guidance on ATPD 3.3.1.6 Pressure Reduction with Multiple Facility connections

ATPD revised to require a quantity of one (1) pressure reduction with multiple facility connections for EACH 5-mile set. A revision will be added to a future solicitation amendment.

Attachment 0001 updated via

Amendment 0001

17DRS

Reference Att.0025. Should we delete CDRL A046 from Item 106? CDRL A046 is for the production version of CDRL A044 and is due 180 days after the Fair Opportunity Decision.

Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule

Attachment 0025 updated via

Amendment 0001

18DRS

Reference Att.0025. What is purpose of Item #58 "Update 1 - Software Development

Plan (CDRL A026)? CDRL A026 requires delivery of the SDP 15 days prior to PDR and this is covered by Item #38.

Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule

Attachment 0025 updated via

Amendment 0001

19DRS

Reference Att.0025. Item #116 is for the Initial Validation Plan (CDRL A051). Should this be CDRL A052? CDRL A051 is for the Operator and Field RPSTL.

Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule

Attachment 0025 updated via

Amendment 0001

20DRS

Reference Att.0025. Item #133 is for the TMQA (CDRL A054). Should this be CDRL

A055? CDRL A054 is for the Equipment Pub Developmental Status Report.

Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule

Attachment 0025 updated via

Amendment 0001 n Contractor Question Government Answer Question Status

21DRS

Reference Att.0025. Item #134 is for the Publications Status Reports (CDRL A053).

Should this be CDRL A054? CDRL A053 is for the Validation Report.

Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule

Attachment 0025 updated via

Amendment 0001

22DRS

Reference Att.0025. Should we delete CDRLs A044 and A045 from Item #136 and #191?

CDRLs A044 and A045 were delivered as part of the EMD phase (Item #106). CDRLs

A046 provides the production version of A044 and A047 provides the production version of A045.

Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule

Attachment 0025 updated via

Amendment 0001

23DRS

Reference Att.0025. Item #136 and #192 includes DEP and FDEP TM Delivery (CDRL

A050). Should this be CDRL A049? CDRL A050 is for an IETM.

Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule

Attachment 0025 updated via

Amendment 0001

24DRS

Reference Att.0025. Item #138 is for IETM Delivery of the Pump Field Maintenance

Manual (CDRL A049). Should this be CDRL A050? CDRL A049 is for a page based

Operator TM.

Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule

Attachment 0025 updated via

Amendment 0001

25DRS

Reference Att.0025. What is required for item #140? Description lists "Technical Report

(CDRL A009). CDRL A009 is for Developmental Drawings. Should this be a LUT Technical

Report and should there be a CDRL reference?

Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule

Attachment 0025 updated via

Amendment 0001

26DRS

Reference Att.0025. Items #148 and #190 contain PCA (Physical Configuration Audits).

What is the purpose of the PCA in #190?

Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule

Attachment 0025 updated via

Amendment 0001

27DRS

Reference Att.0025. Item #200 is for 5 days of I&KPT Maintainer Training. Should this be for 10 days, as specified in SOW, paragraph C.6.13.19.4.1?

Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule

Attachment 0025 updated via

Amendment 0001 n Contractor Question Government Answer Question Status

28DRS

CLIN 2021 Technical Data Package (TDP) Option references Statement of Work paragraph

C.6.4.1. Paragraph C.6.4.1 states that 'the contractor shall prepare and deliver the

Production Baseline TDP in contractor format IAW CDRL A085 and Attachment 0016

Production TPD 20JUL2015.' However, Attachment 0016 states 'Production Government

Format Technical Data Package (TDP)' in its title and CDRL A085 states that 'the contractor shall prepare the Production Level Government Format Technical Data

Package (TDP) in English per Attachment 0016.' Therefore, the statement of work, Attachment 0016 and CDRL A085 appear to be in conflict. Please advise of the desired format for CLIN 2021 Technical Data Package (TDP) Option. This is the same scenario for

Statement of Work paragraph C.5.4 EMD Technical Data Package (TDP) Requirements.

C.5.4 states 'The contractor shall prepare and deliver a sample TDP in contractor format IAW

CDRL A008 and Attachment 0003 Sample Developmental TDP 20JUL15.' However, both

CDRL A008 and Attachment 0003 state Sample Developmental Government Format

Technical Data Package (TDP). Please advise.

Solicitation sections C.5.4 and C.6.4.1 both incorrectly call for "Contractor" format drawings. Both locations should call for "Government" format drawings. Though all associated CDRLs and Attachments are correct. A revision will be added to a future solicitation amendment.

Solicitation Scope update made via

Amendment 0001

29DRS

Sentence in paragraph C.6.1.3.1 reads, "In addition to bringing a unit up to the current baseline, refurbish efforts shall include, but are not limited to the following actions." The next sentence discusses disposal of parts. Was that the specified "following actions" in the previous sentence?

The following sentence will be deleted from Solicitation Section C.6.1.3.1.

"In addition to bringing a unit up to the current baseline, refurbish efforts shall include, but are not limited to the following actions." A revision will be added to a future solicitation amendment.

Solicitation Scope update made via

Amendment 0001

30DRS

Paragraph C.6.1.3.2 states that refurbishment effort shall be completed in 90 days.

ID#179 of IMS states 60 days. Assume C.6.1.3.2 is correct?

Section C.6.1.3.2 is correct. Attachment 0025 has been updated in

Amendment 0001. The revision will be added to a future solicitation amendment.

Attachment 0025 updated via

Amendment 0001

31DRS

Paragraph C.3.1.3 states, "The contractor shall develop and deliver a detailed IPMR for the E2FDS IAW CDRL A003 and Attachment 0025 Integrated Master Schedule. The IPMR defines the contractor's organizational roles, staffing (prime and subcontractor), and the program in terms of cost, schedule, and performance." Since the E2FDS is a Firm Fixed

Price Contract, why is cost reporting requested? Please clarify cost data requested.

CDRL A003 Block 16 states: "Section 2: IMPR (Format 2 Organizational

Structure) defines cost and schedule performance data by the contractor's organizational structure (e.g., Functional or Integrated Product Team (IPT)).

Since the E2FDS is a Firm Fixed Priced contract organizational structure will not include cost breakdown."

We are only asking for formats 1, 2, 4, 5, 6. Answered

32DRS

Reference C.3.5.1. Since the E2FDS is a Firm Fixed Price Contract, why is cost status to be reported at PSRs?

Costs are not being reported or tracked as this is a FFP contract. Reference to "Cost" is to be removed from section C.3.5.1. A revision will be added to a future solicitation amendment.

Solicitation Scope update made via

Amendment 0001

33DRS

Reference paragraph C.3.1.2. Should the 'two days' stated in this paragraph be 'two working days'?

Section C.1.3 states all contract references to days shall be recognized as calendar days. Answered n Contractor Question Government Answer Question Status

34DRS

Reference para C.3.2.1.1. What are the government approved systems available to contractors?

DCO (Defense Collaborative Services https://www.dcs.apps.mil) or if that changes before/during contract period then whatever the Government replacement is at that time. Answered

35DRS

CDRL A085 is the Government Format TDP, which is an option under CLIN 2021. Yet CLIN

3000 states to include A001 thru A0043 and A052 thru A089. Should A008 and A085 be listed as exclusions here under CLIN 3000?

CLIN 3000 has been updated to exclude CDRL A085 from the "Not

Separately Priced" CDRLs. A revision will be added to a future solicitation amendment.

Addressed in

Solicitation Amendment

36INTERNAL

What change was made to the FBO website on 08 Feb 2016?. There were no new documents listed.

On 08 Feb 2016, the draft SOW and early version ATPD (both posted in