Text version
E2FDS Contractor Solicitation Questions W56HZV-15-R-0221 Set 2 C o n Contractor Question Government Answer Question Status
1West
Does the Government have a CDRL and DID for CLIN 2016, Training Aides, Devices, Simulations and Simulators (TADDS)? Are there specific critical tasks and learning objectives relative to collective training the simulators must address?
There is no CDRL associated with CLIN 2016. That CLIN is created for a hardware deliverable, not a data deliverable. Answered
2WestWill the Government clarify that CDRL A085 is to be priced separately under CLIN 2021?
Yes, CLIN 2021 is to be separately priced. The correction will be added to a future solicitation amendment.
Attachments 0031 and
0032 updated via
Amendment 0001
3West
Since this is in the EMD phase, it appears that CDRL A046 should not be a required deliverable during the EMD phase as CDRL A044 is the Operator Manual in the EMD phase and A046 is the Operator Manual in the P&D phase. Will the Government please clarify?
CDRL A046 (OPERATOR TM OVERARCHING) is not a deliverable during the
EMD phase. Answered
4West
Attachment 0025, ID 136 - Technical Manuals CDRL A044, A045, A046, A047: The deliverables on this task include CDRL A044 and A045. Since this is in the P&D phase it appears that CDRLs A044 and A045 (an EMD requirement) should not be included.
Shouldn't CDRLs A046 and A047 be the DEP TM deliveries in the P&D phase that essentially replace the EMD PDEP manuals of CDRLs A044 and A045? Please clarify.
CDRLs A044 and A045 are associated with EMD TM deliverables. CDRLs
A046 and A047 are associated with P&D TM deliverables. Attachment 0025
(Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule.
Attachment 0025 updated via
Amendment 0001
5West
Page 69 of the Solicitation shows CLIN 2005, DEP delivery is 270 DADO. CDRL A051 states the DEP is delivered at 180 days. Attachment 0025 indicates pubs initial validation plan would be held 30 days after Fair opportunity decision in the timeline. Will the
Government please clarify the due date of CLIN 2005 DEP?
CDRL A051 already reflects the correct delivery timing of 180 DADO. The
CLIN 2005 delivery timing narrative will be changed from 270 to 180 DADO in a future amendment.
Within Attachment 0025, the delivery timing listed for CDRL A051 is correct.
Though Attachment 0025 has been updated to show a corrected name change for CDRL A051. Attachment 0025 has been updated in Amendment
0001.
Attachment 0025 updated via
Amendment 0001.
CLIN 2005 narrative will be corrected in a future amendment
6West
CDRL A071 states, "The contractor shall deliver a Familiarization Training Guide (FTG) for each test event." Paragraph C.6.13.19.2.4 states, "The contractor shall provide familiarization training…at LUT, PQT, and LD." Attachment 0025 includes an entry for
FTGs for the Engineering Development Test (EDT), but it does not specify FTGs for the
Logistics Demonstration. Request the Government clarify which events will require FTGs.
Are they required for the EDT, LUT, PQT, TM Verification, and LD?
Familiarization training is provided for all test events. EMD testing is defined under C.5.15 Training. P&D testing is defined under C.6.13.19.2.4
Contractor Familiarization Training & C.6.13.19.3 IOT&E System Operator and Maintainer Training. Answered o n Contractor Question Government Answer Question Status
7West
CDRL A077 states the Training Course Completion Report is due for all training events at
Logistics Demonstration, TM Verification, Limited User Test, and Initial Operator Test and
Evaluation. This list does not include the Production Quality Test (PQT). Does the
Government expect a Training Course Completion Report following the training that would precede the PQT?
CDRL A077 lists all events for which Training Course Completion Reports are required. Answered
8West
CDRL A077 includes the TM Verification as an event that requires a Training Course
Completion Report. Does the Government intend the contractor to deliver the full
Operator (40 hours) and Maintainer (80 hours) Training in support of the TM Verification event? Familiarization Training is for Test events. TM Verification is not a test event. Answered
9West
Solicitation paragraph C.6.1.4.1, requires the delivery of two Collective Virtual Training
Simulators. Is there guidance as to the requirements of the training simulator including a user manual and training on the training simulator? If so, what is the period of time for performance of this training?
C.6.1.4.1 will be revised in a future amendment as follows:
"The contractor shall deliver one TADSS package 90 days after completion of IOT&E as identified in the specified DO. The TADSS package consists of two collective Virtual Training Simulators, one ERS, two containment loads of hose, one Automated Pump Station, Support Equipment (for one mile), and one C2M. The contractor shall provide adequate training, no more than three days so that the Government can operate and train the simulator."
This will be added to section C.6.1.4.1 in a future solicitation amendment:
"The Collective Virtual Training Simulator will simulate E2FDS operations as well as introduce conditions and faults that would require actions from leaders and operators. It will be in the form of a software module integrated in the centralize control station, stand-alone laptop based software, integrated Human/Machine Interface (HMI) panels with software integrated in pump stations or any combination of these approaches. No special facilities are required for the Collective Virtual Training Simulator. "
Definition to be added to future solicitation amendment
10West
Reference solicitation paragraph C.6.1.4.1. Are there any unique installation requirements, such as power consideration or other environmental considerations, that apply to the two locations where the simulators will be used? No. See answer above concerning Collective Virtual Training Simulator. Answered
11West
Reference solicitation paragraph C.6.1.4.1. Are there any sustainment or warranty considerations in the requirements of the training simulators? No. Answered
12West
Reference solicitation paragraph C.6.1.4.1. What are the delivery requirements for the two Virtual Training Simulators?
IAW C.6.1.4.1, a virtual simulator will be delivered with each 5 mile training set (PRS) after refurbishment when fielded. Answered n Contractor Question Government Answer Question Status
13West
Are the hardware deliverables under EMD PRS CLIN 1000 and P&D PRS CLIN 2006 the same? Yes, both hardware deliverables are the same. Answered
14WestWhat CLIN should be used in pricing additional pump assemblies?
No spare pumps are being procured. The Government will have sufficient spares with the extra test pumps. This clarification will be added to the
ATPD (Attachment 0001), which will be updated in a future solicitation amendment.
Attachment 0001 updated via
Amendment 0001
15West
We are asking for a minimum 30-day extension to the due date of the proposal to incorporate answered responses to the above questions into our proposal We are only granting a 15 day extension. Answered
16West
Please provide guidance on ATPD 3.3.1.6 Pressure Reduction with Multiple Facility connections
ATPD revised to require a quantity of one (1) pressure reduction with multiple facility connections for EACH 5-mile set. A revision will be added to a future solicitation amendment.
Attachment 0001 updated via
Amendment 0001
17DRS
Reference Att.0025. Should we delete CDRL A046 from Item 106? CDRL A046 is for the production version of CDRL A044 and is due 180 days after the Fair Opportunity Decision.
Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule
Attachment 0025 updated via
Amendment 0001
18DRS
Reference Att.0025. What is purpose of Item #58 "Update 1 - Software Development
Plan (CDRL A026)? CDRL A026 requires delivery of the SDP 15 days prior to PDR and this is covered by Item #38.
Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule
Attachment 0025 updated via
Amendment 0001
19DRS
Reference Att.0025. Item #116 is for the Initial Validation Plan (CDRL A051). Should this be CDRL A052? CDRL A051 is for the Operator and Field RPSTL.
Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule
Attachment 0025 updated via
Amendment 0001
20DRS
Reference Att.0025. Item #133 is for the TMQA (CDRL A054). Should this be CDRL
A055? CDRL A054 is for the Equipment Pub Developmental Status Report.
Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule
Attachment 0025 updated via
Amendment 0001 n Contractor Question Government Answer Question Status
21DRS
Reference Att.0025. Item #134 is for the Publications Status Reports (CDRL A053).
Should this be CDRL A054? CDRL A053 is for the Validation Report.
Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule
Attachment 0025 updated via
Amendment 0001
22DRS
Reference Att.0025. Should we delete CDRLs A044 and A045 from Item #136 and #191?
CDRLs A044 and A045 were delivered as part of the EMD phase (Item #106). CDRLs
A046 provides the production version of A044 and A047 provides the production version of A045.
Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule
Attachment 0025 updated via
Amendment 0001
23DRS
Reference Att.0025. Item #136 and #192 includes DEP and FDEP TM Delivery (CDRL
A050). Should this be CDRL A049? CDRL A050 is for an IETM.
Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule
Attachment 0025 updated via
Amendment 0001
24DRS
Reference Att.0025. Item #138 is for IETM Delivery of the Pump Field Maintenance
Manual (CDRL A049). Should this be CDRL A050? CDRL A049 is for a page based
Operator TM.
Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule
Attachment 0025 updated via
Amendment 0001
25DRS
Reference Att.0025. What is required for item #140? Description lists "Technical Report
(CDRL A009). CDRL A009 is for Developmental Drawings. Should this be a LUT Technical
Report and should there be a CDRL reference?
Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule
Attachment 0025 updated via
Amendment 0001
26DRS
Reference Att.0025. Items #148 and #190 contain PCA (Physical Configuration Audits).
What is the purpose of the PCA in #190?
Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule
Attachment 0025 updated via
Amendment 0001
27DRS
Reference Att.0025. Item #200 is for 5 days of I&KPT Maintainer Training. Should this be for 10 days, as specified in SOW, paragraph C.6.13.19.4.1?
Attachment 0025 (Integrated Master Schedule) has been updated and will be made available through a future solicitation amendment. CDRLs will always take precedence over any attachment or program schedule
Attachment 0025 updated via
Amendment 0001 n Contractor Question Government Answer Question Status
28DRS
CLIN 2021 Technical Data Package (TDP) Option references Statement of Work paragraph
C.6.4.1. Paragraph C.6.4.1 states that 'the contractor shall prepare and deliver the
Production Baseline TDP in contractor format IAW CDRL A085 and Attachment 0016
Production TPD 20JUL2015.' However, Attachment 0016 states 'Production Government
Format Technical Data Package (TDP)' in its title and CDRL A085 states that 'the contractor shall prepare the Production Level Government Format Technical Data
Package (TDP) in English per Attachment 0016.' Therefore, the statement of work, Attachment 0016 and CDRL A085 appear to be in conflict. Please advise of the desired format for CLIN 2021 Technical Data Package (TDP) Option. This is the same scenario for
Statement of Work paragraph C.5.4 EMD Technical Data Package (TDP) Requirements.
C.5.4 states 'The contractor shall prepare and deliver a sample TDP in contractor format IAW
CDRL A008 and Attachment 0003 Sample Developmental TDP 20JUL15.' However, both
CDRL A008 and Attachment 0003 state Sample Developmental Government Format
Technical Data Package (TDP). Please advise.
Solicitation sections C.5.4 and C.6.4.1 both incorrectly call for "Contractor" format drawings. Both locations should call for "Government" format drawings. Though all associated CDRLs and Attachments are correct. A revision will be added to a future solicitation amendment.
Solicitation Scope update made via
Amendment 0001
29DRS
Sentence in paragraph C.6.1.3.1 reads, "In addition to bringing a unit up to the current baseline, refurbish efforts shall include, but are not limited to the following actions." The next sentence discusses disposal of parts. Was that the specified "following actions" in the previous sentence?
The following sentence will be deleted from Solicitation Section C.6.1.3.1.
"In addition to bringing a unit up to the current baseline, refurbish efforts shall include, but are not limited to the following actions." A revision will be added to a future solicitation amendment.
Solicitation Scope update made via
Amendment 0001
30DRS
Paragraph C.6.1.3.2 states that refurbishment effort shall be completed in 90 days.
ID#179 of IMS states 60 days. Assume C.6.1.3.2 is correct?
Section C.6.1.3.2 is correct. Attachment 0025 has been updated in
Amendment 0001. The revision will be added to a future solicitation amendment.
Attachment 0025 updated via
Amendment 0001
31DRS
Paragraph C.3.1.3 states, "The contractor shall develop and deliver a detailed IPMR for the E2FDS IAW CDRL A003 and Attachment 0025 Integrated Master Schedule. The IPMR defines the contractor's organizational roles, staffing (prime and subcontractor), and the program in terms of cost, schedule, and performance." Since the E2FDS is a Firm Fixed
Price Contract, why is cost reporting requested? Please clarify cost data requested.
CDRL A003 Block 16 states: "Section 2: IMPR (Format 2 Organizational
Structure) defines cost and schedule performance data by the contractor's organizational structure (e.g., Functional or Integrated Product Team (IPT)).
Since the E2FDS is a Firm Fixed Priced contract organizational structure will not include cost breakdown."
We are only asking for formats 1, 2, 4, 5, 6. Answered
32DRS
Reference C.3.5.1. Since the E2FDS is a Firm Fixed Price Contract, why is cost status to be reported at PSRs?
Costs are not being reported or tracked as this is a FFP contract. Reference to "Cost" is to be removed from section C.3.5.1. A revision will be added to a future solicitation amendment.
Solicitation Scope update made via
Amendment 0001
33DRS
Reference paragraph C.3.1.2. Should the 'two days' stated in this paragraph be 'two working days'?
Section C.1.3 states all contract references to days shall be recognized as calendar days. Answered n Contractor Question Government Answer Question Status
34DRS
Reference para C.3.2.1.1. What are the government approved systems available to contractors?
DCO (Defense Collaborative Services https://www.dcs.apps.mil) or if that changes before/during contract period then whatever the Government replacement is at that time. Answered
35DRS
CDRL A085 is the Government Format TDP, which is an option under CLIN 2021. Yet CLIN
3000 states to include A001 thru A0043 and A052 thru A089. Should A008 and A085 be listed as exclusions here under CLIN 3000?
CLIN 3000 has been updated to exclude CDRL A085 from the "Not
Separately Priced" CDRLs. A revision will be added to a future solicitation amendment.
Addressed in
Solicitation Amendment
36INTERNAL
What change was made to the FBO website on 08 Feb 2016?. There were no new documents listed.
On 08 Feb 2016, the draft SOW and early version ATPD (both posted in
November 2015) were removed from the website. Answered