ID Task Name Duration Start Finish Predecessors
1 EMD PHASE 462 days? Wed 7/27/16 Thu 5/3/18 2 Contract Award - DO1 EMD 1 day Wed 7/27/16 Wed 7/27/16
3 RAMPP (CDRL A010) 31 days Fri 8/19/16 Mon 10/3/16
7 Risk Management Plan (CDRAL A081) 0 days Wed 8/24/16 Wed 8/24/16 13SF-5 edays
8 Meeting Agenda (CDRL A001) 4 days Mon 8/22/16 Sat 8/27/16
13 Start of Work 1 day Mon 8/29/16 Mon 8/29/16 2FS+30 edays
33 Meeting Minutes (CDRL A002) 6 days Wed 8/31/16 Thu 9/8/16
37 Developmental Drawings (CDRL A009) 11 days Mon 11/14/16 Tue 11/29/16
41 Technical Review Criteria (A007) 15 days Tue 11/8/16 Tue 11/29/16
45 Hazardous Materials Management Plan -HMMP (CDRL A016) 44 days Mon 11/14/16 Fri 1/13/17
49 CPCP (CDRL A021) 32 days Sun 10/30/16 Wed 12/14/16
53 Human Factors Engineering Analysis - initial - (CDRL A027) 21 days Sun 10/30/16 Tue 11/29/16
57 System Safety Program Plan (SSP) (CDRL A084) 22 days Mon 11/14/16 Wed 12/14/16
58 System Safety Program Plan deliverable 0 days Mon 11/14/16 Mon 11/14/16 76SF-15 edays
59 Government Review SSP 15 edays Mon 11/14/16 Tue 11/29/16 58
60 Updated SSP delivery 15 edays Tue 11/29/16 Wed 12/14/16 59
61 FMECA (CDRL A034) 33 days Mon 11/14/16 Thu 12/29/16
64 Software Development Plan - SDP - (CDRL A026) 1 day? Fri 11/11/16 Mon 11/14/16 76SF-15 edays
65 Interface Requirements Specification - Initial (CDRL A019) 0 days Mon 11/14/16 Mon 11/14/16 76SF-15 edays
66 Initial CyberSecurity Strategy (CDRL A067) 0 days Mon 11/14/16 Mon 11/14/16 76SF-15 edays
67 Initial Software Requirements Specifications (SRS) (CDRL A088) 0 days Mon 11/14/16 Mon 11/14/16 76SF-15 edays
68 Initial Software Test Plan (STP) (CDRL A089) 0 days Mon 11/14/16 Mon 11/14/16 76SF-15 edays
69 UID Candidate List (CDRL A058) 0 days Mon 11/14/16 Mon 11/14/16 76SF-15 edays
70 Risk Management Plan (CDRAL A081) 0 days Mon 11/14/16 Mon 11/14/16 76SF-15 edays
71 Meeting Agenda (CDRL A001) 3 days Tue 11/22/16 Sun 11/27/16
76 PDR/PSR 1 - EMD 1 day Tue 11/29/16 Tue 11/29/16 13FS+91 edays
77 IPMR (IMS CDRL A0003) 1 day Tue 11/29/16 Tue 11/29/16
78 System Requirements Compliance Matrix (CDRL A006) 1 day Tue 11/29/16 Tue 11/29/16
79 Meeting Minutes (CDRL A002) 6 days Thu 12/1/16 Fri 12/9/16
83 Technical Review Criteria Exit Criteria (A007) 18 days Tue 11/29/16 Sat 12/24/16
87 Developmental Drawings (CDRL A009) 11 days Mon 2/13/17 Tue 2/28/17
91 Technical Review Criteria (A007) 15 days Tue 2/7/17 Tue 2/28/17
95 Hazardous Materials Management Plan -HMMP (CDRL A016) 44 days Mon 2/13/17 Fri 4/14/17
99 Initial SUPPORT EQUIPMENT TOOLS & TEST EQUIPMENT
(STTE) (CDRL A029)
44 days Mon 2/13/17 Fri 4/14/17
103 Interface Design Description (CDRL A018) 0 days Mon 2/13/17 Mon 2/13/17 142SF-15 edays
104 Interface Requirements Specification - Final (CDRL A019) 0 days Mon 2/13/17 Mon 2/13/17 142SF-15 edays
105 System Test Support Package (STSP) (CDRL A024) 1 day? Tue 1/31/17 Tue 1/31/17 142FF-30 edays
106 CSAI (CDRL A011) 0 days Sun 1/29/17 Sun 1/29/17 142SF-30 edays
107 R&M Case Report (RCR) - (CDRL A020) 8 days Mon 2/13/17 Thu 2/23/17
110 Human Factors Engineering Analysis - Final - (CDRL A027) 21 days Sun 1/29/17 Tue 2/28/17
114 Maintenance Task Analysis (CDRL A037) 0 days Mon 2/13/17 Mon 2/13/17 142SF-15 edays
115 Updated FMECA (CDRL A034) 0 days Mon 2/13/17 Mon 2/13/17 142SF-15 edays
116 Level of Repair Analysis -LORA - (CDRL A035) 55 days Mon 2/13/17 Sat 4/29/17
120 Fault Tree Analysis (FTA) (CDRL A079) 55 days Mon 2/13/17 Sat 4/29/17
124 Reliability Centered Maintenance (RCM) (CDRL A080) 55 days Mon 2/13/17 Sat 4/29/17
125 RCM Delivery 0 days Mon 2/13/17 Mon 2/13/17 142SF-15 edays
126 Government Revie RCM 45 edays Mon 2/13/17 Thu 3/30/17 125
127 Updated RCM 30 edays Thu 3/30/17 Sat 4/29/17 126
7/27
8/24
11/14
11/14
11/14
11/14
11/14
11/14
11/14
11/29
11/29
2/13
2/13
1/29
2/13
2/13
2/13
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Half 1, 2013 Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
Project: E2FDS Date: Tue 2/16/16
128 Final CyberSecurity Strategy (CDRL A067) 0 days Mon 2/13/17 Mon 2/13/17 142SF-15 edays
129 Software Test Description (CDRL A074) 0 days Mon 2/13/17 Mon 2/13/17 142SF-15 edays
130 Initial Software Design Description (CDRL A086) 0 days Mon 2/13/17 Mon 2/13/17 142SF-15 edays
131 System Subsystem Design Description (SSDD) (CDRL A087) 0 days Mon 2/13/17 Mon 2/13/17 142SF-15 edays
132 Software Requirements Specifications (SRS) (CDRL A088) 0 days Mon 2/13/17 Mon 2/13/17 142SF-15 edays
133 Software Test Plan (STP) (CDRL A089) 0 days Mon 2/13/17 Mon 2/13/17 142SF-15 edays
134 RAMPP (CDRL A010) 0 days Mon 2/13/17 Mon 2/13/17 142SF-15 edays
135 IBOM (initial) CDRL A070 0 days Mon 2/13/17 Mon 2/13/17 142SF-15 edays
136 Risk Management Plan (CDRAL A081) 0 days Mon 2/13/17 Mon 2/13/17 142SF-15 edays
137 Meeting Agenda (CDRL A001) 3 days Thu 2/23/17 Tue 2/28/17
142 CDR/PSR 2 - EMD 3 days Tue 2/28/17 Thu 3/2/17 76FS+90 edays
145 Meeting Minutes (CDRL A002) 5 days Sat 3/4/17 Sat 3/11/17
149 Technical Review Criteria Exit Criteria (A007) 17 days Thu 3/2/17 Mon 3/27/17
153 Sample Developmental TDP (CDRL A008) 20 days Thu 3/16/17 Thu 4/13/17
157 R&M Case Report (RCR) Update - (CDRL A020) 8 days Sun 3/12/17 Wed 3/22/17
160 Diagnostic Testability Analysis (CDRL A028) 54 days Mon 5/1/17 Sat 7/15/17
164 Fabricate EMD PRS 180 edays Tue 3/7/17 Sun 9/3/17 142FS+5 edays,218SF
165 Contractor Demonstration Plan (CDRL A022) 23 days? Fri 4/7/17 Tue 5/9/17
169 Contractor Demonstration 15 edays Thu 6/8/17 Fri 6/23/17 201SF-30 edays
170 Contractor Demonstration Report (CDRL A060) 0 days Sat 7/8/17 Sat 7/8/17 169FS+15 edays
171 Technical Review Criteria (A007) 15 days Mon 7/3/17 Sun 7/23/17
175 Configuration Audit Plan (CDRL A012) 15 days Fri 6/23/17 Fri 7/14/17
179 Safety Assessment Report - SAR (CDRL A017) 22 days Wed 5/24/17 Fri 6/23/17
183 System Test Support Package (STSP) - UPDATED (CDRL A024)
0 days Tue 4/25/17 Tue 4/25/17 201FF-90 edays
184 Initial CyberSecurity Artifact Package (CDRL A066) 0 days Mon 5/22/17 Mon 5/22/17 186SF-45 edays
185 Initial System Security Design and Risk Assessment (CDRL A068)
0 days Wed 6/21/17 Wed 6/21/17 186SF-15 edays
186 Initial Baseline CyberSecurty Scan 2 days Thu 7/6/17 Sat 7/8/17 201SF-15 edays
187 Updated CyberSecurity Artifact Package (CDRL A066) 0 days Wed 9/6/17 Wed 9/6/17 186FS+60 edays
188 Updated System Security Design and Risk Assessment (CDRL A068)
0 days Wed 9/6/17 Wed 9/6/17 186FS+60 edays
189 Draft Long Lead Time Items (CDRL A038) 0 days Sat 7/8/17 Sat 7/8/17 201SF-15 edays
190 Maintenance Task Analysis (CDRL A037) 0 days Sat 7/8/17 Sat 7/8/17 201SF-15 edays
191 Software Test Report (CDRL A072) 0 days Sat 7/8/17 Sat 7/8/17 201SF-15 edays
192 Final Software Test Description (CDRL A074) 0 days Sat 7/8/17 Sat 7/8/17 201SF-15 edays
193 Software Design Description (CDRL A086) 0 days Sat 7/8/17 Sat 7/8/17 201SF-15 edays
194 RAMPP (CDRL A010) 0 days Sat 7/8/17 Sat 7/8/17 201SF-15 edays
195 Risk Management Plan (CDRAL A081) 0 days Sat 7/8/17 Sat 7/8/17 201SF-15 edays
196 Meeting Agenda (CDRL A001) 4 days Mon 7/17/17 Fri 7/21/17
201 TRR / PSR 3/ FCA - EMD 1 day Sun 7/23/17 Mon 7/24/17 218FS-30 edays
202 CyberSecurity Vulnerability scanning report (CDLR A069) 0 days Sun 7/23/17 Sun 7/23/17
203 IPMR (IMS CDRL A0003) 1 day Mon 7/24/17 Mon 7/24/17
204 Meeting Minutes (CDRL A002) 5 days Sun 7/23/17 Sat 7/29/17
208 Technical Review Criteria Exit Criteria (A007) 19 days Mon 7/24/17 Fri 8/18/17
212 Configuration Audit Summary Report (CDRL A013) 15 days Tue 8/8/17 Tue 8/29/17
216 Contractor Provide List for VDLS access 0 days Fri 6/30/17 Fri 6/30/17 225SF-60 edays
217 Contractor Commericial TMs 1 day Mon 8/14/17 Mon 8/14/17 225SF-15 edays
218 Delivery of EMD PRS 1 day Tue 8/22/17 Tue 8/22/17 2FS+390 edays
219 EDT Familiarization Training Guide (CDRL A071) 11 days Sun 7/30/17 Mon 8/14/17
223 Familiarization Training EDT 5 days Mon 8/21/17 Sat 8/26/17 225SF-3 edays
224 Training Course Completion Report (CDRL A077) 0 days Tue 9/5/17 Tue 9/5/17 223FS+10 edays
225 EDT (FAT) 180 edays Tue 8/29/17 Sun 2/25/18 218FS+7 edays
2/13
2/13
2/13
2/13
2/13
2/13
2/13
2/13
2/13
3/2
7/8
4/25
5/22
6/21
9/6
9/6
7/8
7/8
7/8
7/8
7/8
7/8
7/8
7/24
7/23
7/24
6/30
8/14
8/22
9/5
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Half 1, 2013 Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
228 Finalized UID Candidate List (CDRL A058) 0 days Tue 3/27/18 Tue 3/27/18 225FS+30 edays
229 RAMPP (CDRL A010) 0 days Sun 10/8/17 Sun 10/8/17 236SF-15 edays
230 Risk Management Plan (CDRAL A081) 0 days Sun 10/8/17 Sun 10/8/17 236SF-15 edays
231 Meeting Agenda (CDRL A001) 4 days Mon 10/16/17 Sat 10/21/17
236 PSR 4 1 day Mon 10/23/17 Mon 10/23/17 201FS+90 edays
237 IPMR (IMS CDRL A0003) 1 day Mon 10/23/17 Mon 10/23/17
238 Meeting Minutes (CDRL A002) 6 days Wed 10/25/17 Thu 11/2/17
242 PDEP Operator Manual - Overarching E2FDS System Manual to include Hose, ERS, and Hose Equipment - (CDRL A044)
1 day Fri 1/19/18 Fri 1/19/18 2FS+540 edays
243 PDEP Field Maintenance Manual - Overarching E2FDS System Manual to include Hose, ERS, and Hose Equipment -
(CDRL A045)
1 day Fri 1/19/18 Fri 1/19/18 2FS+540 edays
244 RAMPP (CDRL A010) 0 days Sun 1/7/18 Sun 1/7/18 251SF-15 edays
245 Risk Management Plan (CDRAL A081) 0 days Sun 1/7/18 Sun 1/7/18 251SF-15 edays
246 Meeting Agenda (CDRL A001) 4 days Mon 1/15/18 Sat 1/20/18
251 PSR 5 1 day Mon 1/22/18 Mon 1/22/18 236FS+90 edays
252 IPMR (IMS CDRL A0003) 1 day Mon 1/22/18 Mon 1/22/18
253 Meeting Minutes (CDRL A002) 6 days Wed 1/24/18 Thu 2/1/18
257 RAMPP (CDRL A010) 0 days Sun 4/8/18 Sun 4/8/18 264SF-15 edays
258 Risk Management Plan (CDRAL A081) 0 days Sun 4/8/18 Sun 4/8/18 264SF-15 edays
259 Meeting Agenda (CDRL A001) 4 days Mon 4/16/18 Sat 4/21/18
264 PSR 6 1 day Mon 4/23/18 Mon 4/23/18 251FS+90 edays
265 IPMR (IMS CDRL A0003) 1 day Mon 4/23/18 Mon 4/23/18
266 Meeting Minutes (CDRL A002) 6 days Wed 4/25/18 Thu 5/3/18
270 P&D PHASE 1181 days? Fri 4/6/18 Mon 10/17/22 271 Fair Opportunity Decision - DO2 P&D 20 days Fri 4/6/18 Sun 5/6/18
272 Fair Opportunity Evaluation Board 30 edays Fri 4/6/18 Sun 5/6/18 225FS+40 edays
273 Award DO2 to one vendor 0 days Sun 5/6/18 Sun 5/6/18 272
274 RAMPP (CDRL A010) 0 days Tue 5/22/18 Tue 5/22/18 281SF-15 edays
275 Risk Management Plan (CDRAL A081) 0 days Tue 5/22/18 Tue 5/22/18 281SF-15 edays
276 Meeting Agenda (CDRL A001) 2 days Wed 5/30/18 Mon 6/4/18
281 Follow-on SOWM / PSR 7 / LUT Readiness Review 1 day Wed 6/6/18 Wed 6/6/18 271FS+30 edays
283 Meeting Minutes (CDRL A002) 5 days Fri 6/8/18 Sat 6/16/18
287 Meeting Agenda (CDRL A001) 56 days Fri 8/3/18 Mon 10/22/18
292 Technical Manual Quality Assurance (TMQA) (CDRL A055) 0 days Tue 6/5/18 Tue 6/5/18 271FS+30 edays
293 Equipment Publications Development Status report (CDRL A054) 0 days Thu 7/5/18 Thu 7/5/18 271FS+60 edays
294 Validation Plan (CDRL A052) 42 days Wed 6/6/18 Sun 8/5/18
298 EDFP (CDRL A078) 21 days Sat 7/21/18 Mon 8/20/18
301 Initial Provisioining Conference 60 days Sun 8/5/18 Fri 10/26/18 281FS+60 edays
325 Meeting Minutes (CDRL A002) 5 days Sun 10/28/18 Sat 11/3/18
329 LMI (CDRL A063) 0 days Sun 11/25/18 Sun 11/25/18 301FS+30 edays
330 SPI (CDRL A064) 0 days Sun 11/25/18 Sun 11/25/18 301FS+30 edays
331 SPI Validation Report (CDRL A065) 0 days Sun 11/25/18 Sun 11/25/18 301FS+30 edays
332 Contractor Technical Manual Validation 90 edays Fri 7/6/18 Thu 10/4/18 281FS+30 edays,342SF-30 edays,350SF-30 edays,358SF-30 edays,366SF-30 edays,374SF-30 edays
333 NMWR Data Summary (CDRL A033) 43 days Sat 11/3/18 Wed 1/2/19
337 Logistics/Publications Configuration Lock 1 day Tue 9/18/18 Tue 9/18/18 342SF-45 edays,366SF-45 edays,358SF-45 edays,350SF-45 edays,374SF-45 edays
338 Validation Report Overarching Operator Manual (CDRL A053) 42 days Fri 11/2/18 Tue 1/1/19
342 DEP Overarching Operator Manual (CDRL A046) 65 days Fri 11/2/18 Sun 2/3/19
346 Validation Report Overarching Field Maintenance Manual
(CDRL A053)
42 days Fri 11/2/18 Tue 1/1/19
350 DEP Overarching Field Maintenance Manual (CDRL A047) 65 days Fri 11/2/18 Sun 2/3/19
3/27
10/8
10/8
10/23
10/23
1/19
1/19
1/7
1/7
1/22
1/22
4/8
4/8
4/23
4/23
5/6
5/6
5/22
5/22
6/5
7/5
10/26
9/18
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Half 1, 2013 Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
354 Validation Report Overarching RPSTL Manual (CDRL A053) 42 days Fri 11/2/18 Tue 1/1/19
358 DEP RPSTL (CDRL A048) 65 days Fri 11/2/18 Sun 2/3/19
362 Validation Report Automated Pumps Operator Manual (CDRL A053)
42 days Fri 11/2/18 Tue 1/1/19
366 DEP Automated Pump Station Operator Manual (CDRL A049) 65 days Fri 11/2/18 Sun 2/3/19 271FS+180 edays
370 Validation Report Automated Pumps RPSTL Manual (CDRL A053)
42 days Fri 11/2/18 Tue 1/1/19
374 DEP Automated Pump Station RPSTL (CDRL A051) 65 days Fri 11/2/18 Sun 2/3/19 271FS+180 edays
378 Validation Report Automated Pumps IETM (CDRL A053) 42 days Thu 1/31/19 Mon 4/1/19
382 IETM DEP Pump Field Maint. (CDRL A050) 86 days Thu 1/31/19 Fri 5/31/19
386 LUT Familiarization Training Guide (CDRL A071) 11 days Wed 6/6/18 Thu 6/21/18
390 Familiarization Training LUT 5 days Wed 6/27/18 Tue 7/3/18 392SF-3 edays
391 Training Course Completion Report (CDRL A077) 0 days Fri 7/13/18 Fri 7/13/18 390FS+10 edays
392 LUT 90 edays Fri 7/6/18 Thu 10/4/18 281FS+30 edays
393 Final - Software Development Plan (CDRL A026) 1 day Fri 10/19/18 Sun 10/21/18 429SF-15 edays
394 Second IBOM (CDRL A070) 1 day Fri 10/19/18 Sun 10/21/18 429SF-15 edays
395 Developmental Drawings (CDRL A009) 10 days Sun 10/21/18 Mon 11/5/18
399 Technical Review Criteria (A007) 15 days Mon 10/15/18 Mon 11/5/18
403 Configuration Audit Plan - PCA (CDRL A014) 15 days Sat 10/6/18 Sat 10/27/18
407 Hazardous Materials Management Plan -HMMP (CDRL A016) 43 days Sun 10/21/18 Thu 12/20/18
411 Safety Assessment Report - SAR (CDRL A017) 22 days Thu 9/6/18 Sat 10/6/18
415 AI&T - Inspection and Test Plan (CDRL A023) 0 days Thu 9/6/18 Thu 9/6/18 429SF-60 edays
416 Software Documentation (CDRL A062) 0 days Sun 10/21/18 Sun 10/21/18 429SF-15 edays
417 Baseline CyberSecurity Scan 2 days Tue 11/6/18 Wed 11/7/18 429
418 Follow-on CyberSecurity Vulnerability scanning report (CDLR A069)
0 days Thu 11/22/18 Thu 11/22/18 417FS+15 edays
419 Final Software Test Report (CDRL A072) 0 days Sun 10/21/18 Sun 10/21/18 429SF-15 edays
420 Program Protection Implementation Plan (PPIP) (CDRL A082) 0 days Sun 10/21/18 Sun 10/21/18 429SF-15 edays
421 RAMPP (CDRL A010) 0 days Sun 10/21/18 Sun 10/21/18 429SF-15 edays
422 Risk Management Plan (CDRAL A081) 0 days Sun 10/21/18 Sun 10/21/18 429SF-15 edays
423 Production Change Package (CDRL A004) 1 day? Thu 10/25/18 Fri 10/26/18 429SF-10 edays
424 Meeting Agenda (CDRL A001) 4 days Mon 10/29/18 Sat 11/3/18
429 PRR P&D / PSR 8 / PCA 1 day Mon 11/5/18 Mon 11/5/18 392FS+30 edays
432 Meeting Minutes (CDRL A002) 6 days Wed 11/7/18 Thu 11/15/18
436 Technical Review Criteria Exit Criteria (A007) 19 days Mon 11/5/18 Fri 11/30/18
440 Configuration Audit Summary Reprot - PCA (CDRL A015) 15 days Tue 11/20/18 Tue 12/11/18
444 ***Sample Production TDP (CDRL A085) - if executed placeholder
20 days Wed 12/5/18 Wed 1/2/19
448 RAMPP (CDRL A010) 0 days Sun 1/20/19 Sun 1/20/19 456SF-15 edays
449 Updated Program Protection Implementation Plan (PPIP) (CDRL A082)
0 days Sun 1/20/19 Sun 1/20/19 456SF-15 edays
450 Risk Management Plan (CDRAL A081) 0 days Sun 1/20/19 Sun 1/20/19 456SF-15 edays
451 Meeting Agenda (CDRL A001) 4 days Mon 1/28/19 Sat 2/2/19
456 PSR 9 1 day Mon 2/4/19 Mon 2/4/19 429FS+90 edays
458 Meeting Minutes (CDRL A002) 6 days Wed 2/6/19 Thu 2/14/19
462 RAMPP (CDRL A010) 0 days Sun 1/20/19 Sun 1/20/19 456SF-15 edays
463 Updated Program Protection Implementation Plan (PPIP) (CDRL A082)
0 days Sun 4/21/19 Sun 4/21/19 470SF-15 edays
464 Risk Management Plan (CDRAL A081) 0 days Sun 4/21/19 Sun 4/21/19 470SF-15 edays
465 Meeting Agenda (CDRL A001) 4 days Mon 4/29/19 Sat 5/4/19
470 PSR 10 1 day Mon 5/6/19 Mon 5/6/19 456FS+90 edays
472 Meeting Minutes (CDRL A002) 6 days Wed 5/8/19 Thu 5/16/19
7/13
10/21
10/21
9/6
10/21
10/21
10/21
10/21
10/21
10/26
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Half 1, 2013 Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
476 Provisioning and Pre-Procurement Screening (CDRL A042) 0 days Sun 2/17/19 Sun 2/17/19 492SF-15 edays
477 Provisioning Parts List (PPL) (CDRL A043) 0 days Sun 2/17/19 Sun 2/17/19 492SF-15 edays
478 EDFP (CDRL A078) 21 days Sun 2/17/19 Tue 3/19/19
481 Technical Review Criteria (A007) 15 days Mon 2/11/19 Mon 3/4/19
482 Technical Review Criteria Initial Delivery 1 day Mon 2/11/19 Tue 2/12/19 492SF-20 edays
483 Government Comments 5 edays Tue 2/12/19 Sun 2/17/19 482
484 Contractor Updated Technical Review Criteria 15 edays Sun 2/17/19 Mon 3/4/19 483
485 RAMPP (CDRL A010) 0 days Sun 2/17/19 Sun 2/17/19 492SF-15 edays
486 Risk Management Plan (CDRAL A081) 0 days Sun 2/17/19 Sun 2/17/19 492SF-15 edays
487 Meeting Agenda (CDRL A001) 4 days Mon 2/25/19 Sat 3/2/19
492 Test Readiness Review (TRR) P&D / PSR 11 1 day Mon 3/4/19 Mon 3/4/19 503FS-30 edays
493 IPMR (IMS CDRL A0003) 1 day Mon 3/4/19 Mon 3/4/19
494 Meeting Minutes (CDRL A002) 6 days Wed 3/6/19 Thu 3/14/19
498 Technical Review Criteria Exit Criteria (A007) 19 days Mon 3/4/19 Fri 3/29/19
499 Exit Criteria Documentation 10 edays Mon 3/4/19 Thu 3/14/19 492
500 Government Comments to Exit Criteria 10 edays Thu 3/14/19 Sun 3/24/19 499
501 Contractor Updates - Updated Delivery 5 edays Sun 3/24/19 Fri 3/29/19 500
502 Fabricate Production PRS 144 edays Sat 11/10/18 Wed 4/3/19 429FS+5 edays,503SF
503 Delivery of P&D PRS 1 day Tue 4/2/19 Tue 4/2/19 271FS+330 edays
504 Technical Review Criteria (A007) 15 days Fri 4/12/19 Fri 5/3/19
505 Technical Review Criteria Initial Delivery 1 day Fri 4/12/19 Sat 4/13/19 514SF-20 edays
506 Government Comments 5 edays Sat 4/13/19 Thu 4/18/19 505
507 Contractor Updated Technical Review Criteria 15 edays Thu 4/18/19 Fri 5/3/19 506
508 Risk Management Plan (CDRAL A081) 0 days Thu 4/18/19 Thu 4/18/19 514SF-15 edays
509 Meeting Agenda (CDRL A001) 2 days Fri 4/26/19 Wed 5/1/19
514 Pre Test Readiness huddle - P&D / PSR12 1 day Fri 5/3/19 Fri 5/3/19 503FS+30 edays
516 Meeting Minutes (CDRL A002) 5 days Sun 5/5/19 Sat 5/11/19
520 Technical Review Criteria Exit Criteria (A007) 17 days Fri 5/3/19 Tue 5/28/19
521 Exit Criteria Documentation 10 edays Fri 5/3/19 Mon 5/13/19 514
522 Government Comments to Exit Criteria 10 edays Mon 5/13/19 Thu 5/23/19 521
523 Contractor Updates - Updated Delivery 5 edays Thu 5/23/19 Tue 5/28/19 522
524 RAMPP (CDRL A010) 0 days Thu 7/18/19 Thu 7/18/19 532SF-15 edays
525 Updated Program Protection Implementation Plan (PPIP) (CDRL A082)
0 days Thu 7/18/19 Thu 7/18/19 532SF-15 edays
526 Risk Management Plan (CDRAL A081) 0 days Thu 7/18/19 Thu 7/18/19 532SF-15 edays
527 Meeting Agenda (CDRL A001) 2 days Fri 7/26/19 Wed 7/31/19
532 PSR 13 1 day Fri 8/2/19 Fri 8/2/19 514FS+90 edays
534 Meeting Minutes (CDRL A002) 5 days Sun 8/4/19 Sat 8/10/19
538 Exhibit IUID (CDRL A083) 0 days Thu 4/18/19 Thu 4/18/19 545SF-30 edays
539 PQT Familiarization Training Guide (CDRL A071) 11 days Thu 4/18/19 Fri 5/3/19
543 Familiarization Training PQT 5 days Thu 5/9/19 Wed 5/15/19 545SF-3 edays
544 Training Course Completion Report (CDRL A077) 0 days Sat 5/25/19 Sat 5/25/19 543FS+10 edays
545 PQT (FAT) 180 edays Sat 5/18/19 Thu 11/14/19 514FS+15 edays
546 RAMPP (CDRL A010) 0 days Sun 11/17/19 Sun 11/17/19 554SF-15 edays
547 Updated Program Protection Implementation Plan (PPIP) (CDRL A082)
0 days Sun 11/17/19 Sun 11/17/19 554SF-15 edays
548 Risk Management Plan (CDRAL A081) 0 days Sun 11/17/19 Sun 11/17/19 554SF-15 edays
549 Meeting Agenda (CDRL A001) 4 days Mon 11/25/19 Sat 11/30/19
554 PSR 14 1 day Mon 12/2/19 Mon 12/2/19 574SS-30 edays
556 Updated EDIL (CDRL A040) 0 days Mon 12/9/19 Mon 12/9/19 574SF-21 edays
557 Updated COEI (CDRL 041) 0 days Mon 12/9/19 Mon 12/9/19 574SF-21 edays
558 Updated BII (CDRL A039) 0 days Mon 12/9/19 Mon 12/9/19 574SF-21 edays
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Half 1, 2013 Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
559 Meeting Minutes (CDRL A002) 6 days Wed 12/4/19 Thu 12/12/19
563 Final IBOM (CDRL A070) 1 day Tue 1/14/20 Tue 1/14/20 545FS+60 edays
564 ERR Package - Production level TDP (CDRL A056) 64 days Wed 2/12/20 Tue 5/12/20
568 LD Familiarization Training Guide (CDRL A071) 10 days Sat 11/30/19 Sun 12/15/19
569 Familiarization Training Guide Delivery 0 days Sat 11/30/19 Sat 11/30/19 574SF-30 edays
570 Government Review Familiarization Training Guide 5 edays Sat 11/30/19 Thu 12/5/19 569
571 Updated Familiarization Training Guide 10 edays Thu 12/5/19 Sun 12/15/19 570
572 Familiarization Training LD 5 days Fri 12/20/19 Fri 12/27/19 574SF-3 edays
573 Training Course Completion Report (CDRL A077) 0 days Mon 1/6/20 Mon 1/6/20 572FS+10 edays
574 Logistics Demonstration (LD) 75 days Mon 12/30/19 Fri 4/10/20
575 LD Phase One 10 days Mon 12/30/19 Fri 1/10/20 545FS+45 edays
576 LD Phase Two 10 days Mon 1/20/20 Fri 1/31/20 575FS+7 edays
577 LD Phase Three 40 days Mon 2/17/20 Fri 4/10/20 576FS+14 edays
578 Updated Program Protection Implementation Plan (PPIP) (CDRL A082)
0 days Sun 4/12/20 Sun 4/12/20 585SF-15 edays
579 Risk Management Plan (CDRAL A081) 0 days Sun 4/12/20 Sun 4/12/20 585SF-15 edays
580 Meeting Agenda (CDRL A001) 4 days Mon 4/20/20 Sat 4/25/20
585 PSR 15 1 day Mon 4/27/20 Mon 4/27/20 593SS-30 edays
586 IPMR (IMS CDRL A0003) 1 day Mon 4/27/20 Mon 4/27/20
587 Meeting Minutes (CDRL A002) 6 days Wed 4/29/20 Thu 5/7/20
591 Operator and Maintainer Training IOTE 15 days Mon 5/4/20 Fri 5/22/20 593SF-3 edays
592 Training Course Completion Report (CDRL A077) 0 days Mon 6/1/20 Mon 6/1/20 591FS+10 edays
593 IOTE 90 edays Mon 5/25/20 Sun 8/23/20 574FS+45 edays
594 Developmental Drawings (CDRL A009) 11 days Tue 9/8/20 Wed 9/23/20
598 Technical Review Criteria (A007) 15 days Wed 9/2/20 Wed 9/23/20
602 Updated Program Protection Implementation Plan (PPIP) (CDRL A082)
0 days Tue 9/8/20 Tue 9/8/20 609SF-15 edays
603 Risk Management Plan (CDRAL A081) 0 days Tue 9/8/20 Tue 9/8/20 609SF-15 edays
604 Meeting Agenda (CDRL A001) 2 days Wed 9/16/20 Mon 9/21/20
609 Follow-on PRR P&D / PSR 16 1 day Wed 9/23/20 Wed 9/23/20 593FS+30 edays
610 IPMR (IMS CDRL A0003) 1 day Wed 9/23/20 Wed 9/23/20
611 Meeting Minutes (CDRL A002) 5 days Fri 9/25/20 Sat 10/3/20
615 Technical Review Criteria Exit Criteria (A007) 17 days Wed 9/23/20 Sun 10/18/20
619 Delivery of TADSS 1 day Mon 11/23/20 Mon 11/23/20 593FS+90 edays
620 PRODUCTION (60 miles) 278 days Tue 9/22/20 Sun 10/17/21
621 Refurbish P&D PRS 91 days Thu 10/22/20 Fri 2/26/21
622 Government Provide EMD and P&D PRS as GFP to Contractor 0 days Thu 10/22/20 Thu 10/22/20 593FS+60 edays
623 Contractor provide proposal on reburshment 30 edays Thu 10/22/20 Sat 11/21/20 622
624 Government Accepts proposal 0 days Sat 11/28/20 Sat 11/28/20 623FS+7 edays
625 EMD and P&D Refurbishment 90 edays Sat 11/28/20 Fri 2/26/21 624
626 PCA 0 days Tue 9/22/20 Tue 9/22/20 627SF-30 edays
627 E2FDS Production (50 miles) 256 days Thu 10/22/20 Sun 10/17/21
630 Updated Support Tools List (CDRL A030) 0 days Mon 3/8/21 Mon 3/8/21 663SF-21 edays
631 RAMPP (CDRL A010) 0 days Tue 12/8/20 Tue 12/8/20 639SF-15 edays
632 Updated Program Protection Implementation Plan (PPIP) (CDRL A082)
0 days Tue 12/8/20 Tue 12/8/20 639SF-15 edays
633 Risk Management Plan (CDRAL A081) 0 days Tue 12/8/20 Tue 12/8/20 639SF-15 edays
634 Meeting Agenda (CDRL A001) 2 days Wed 12/16/20 Mon 12/21/20
639 PSR 17 1 day Wed 12/23/20 Wed 12/23/20 609FS+90 edays
640 IPMR (IMS CDRL A0003) 1 day Wed 12/23/20 Wed 12/23/20
641 Meeting Minutes (CDRL A002) 5 days Fri 12/25/20 Sat 1/2/21
645 RAMPP (CDRL A010) 0 days Sun 2/14/21 Sun 2/14/21 653SF-15 edays
646 Updated Program Protection Implementation Plan (PPIP) (CDRL A082)
0 days Sun 2/14/21 Sun 2/14/21 653SF-15 edays
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Half 1, 2013 Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
647 Risk Management Plan (CDRAL A081) 0 days Tue 12/8/20 Tue 12/8/20 639SF-15 edays
648 Meeting Agenda (CDRL A001) 4 days Mon 2/22/21 Sat 2/27/21
653 PSR 18 1 day Mon 3/1/21 Mon 3/1/21 663SS-30 edays
654 IPMR (IMS CDRL A0003) 1 day Mon 3/1/21 Mon 3/1/21
655 Updated EDIL (CDRL A040) 0 days Mon 3/8/21 Mon 3/8/21 663SF-21 edays
656 Updated COEI (CDRL 041) 0 days Mon 3/8/21 Mon 3/8/21 663SF-21 edays
657 Updated BII (CDRL A039) 0 days Mon 3/8/21 Mon 3/8/21 663SF-21 edays
658 Updated MAC (CDRL A036) 0 days Mon 3/8/21 Mon 3/8/21 663SF-21 edays
659 Meeting Minutes (CDRL A002) 6 days Wed 3/3/21 Thu 3/11/21
663 TM Verficatoin 180 days Mon 3/29/21 Fri 12/3/21
667 Final SUPPORT EQUIPMENT TOOLS & TEST EQUIPMENT
(STTE) (CDRL A029)
44 days Sun 1/2/22 Thu 3/3/22
671 Training Course Completion Report (CDRL A077) 0 days Mon 12/13/21 Mon 12/13/21 663FS+10 edays
672 RAMPP (CDRL A010) 0 days Tue 11/2/21 Tue 11/2/21 680SF-15 edays
673 Updated Program Protection Implementation Plan (PPIP) (CDRL A082)
0 days Tue 11/2/21 Tue 11/2/21 680SF-15 edays
674 Risk Management Plan (CDRAL A081) 0 days Tue 11/2/21 Tue 11/2/21 680SF-15 edays
675 Meeting Agenda (CDRL A001) 2 days Wed 11/10/21 Mon 11/15/21
680 PSR 19 1 day Wed 11/17/21 Wed 11/17/21 627FS+30 edays
681 IPMR (IMS CDRL A0003) 1 day Wed 11/17/21 Wed 11/17/21
682 Meeting Minutes (CDRL A002) 5 days Fri 11/19/21 Sat 11/27/21
686 *** Production TDP (CDRL A085) - if executed placeholder 129 days Sat 11/27/21 Thu 5/26/22
687 Execute Option Place Holder 0 days Sat 11/27/21 Sat 11/27/21 680FS+10 edays
688 Delivery of Production TDP 120 edays Sat 11/27/21 Sun 3/27/22 687
689 Government Review Production TDP 30 edays Sun 3/27/22 Tue 4/26/22 688
690 Updated Production TDP 30 edays Tue 4/26/22 Thu 5/26/22 689
691 Final Support Tools List (CDRL A030) 0 days Sun 1/2/22 Sun 1/2/22 693
692 FDEP Overarching Operator Manual (CDRL A046) 65 days Sun 1/2/22 Sun 4/3/22
696 FDEP Overarching Field Maintenance Manual (CDRL A047) 65 days Sun 1/2/22 Sun 4/3/22
700 FDEP RPSTL (CDRL A048) 65 days Sun 1/2/22 Sun 4/3/22
704 FDEP Automated Pump Station Operator Manual (CDRL A049) 65 days Sun 1/2/22 Sun 4/3/22
708 FDEP Automated Pump Station RPSTL (CDRL A051) 65 days Sun 1/2/22 Sun 4/3/22 663FS+30 edays
712 IETM FDEP Pump Field Maint. & RPSTL (CDRL A050) 86 days Tue 2/1/22 Wed 6/1/22
716 FRC Overarching Operator Manual (CDRL A046) 0 days Mon 4/18/22 Mon 4/18/22 692FS+15 edays
717 FRC Overarching Field Maintenance Manual (CDRL A047) 0 days Mon 4/18/22 Mon 4/18/22 696FS+15 edays
718 FRC Overarching RPSTL (CDRL A048) 0 days Mon 4/18/22 Mon 4/18/22 700FS+15 edays
719 FRC Automated Pump Station Operator Manual (CDRL A049) 0 days Mon 4/18/22 Mon 4/18/22 704FS+15 edays
720 FRC Automated Pump Station RPSTL (CDRL A051) 0 days Mon 4/18/22 Mon 4/18/22 708FS+15 edays
721 FRC IETM Automated Pump Station (CDRL A050) 1 day Mon 7/4/22 Mon 7/4/22 712FS+30 edays
722 Final STTE (CDRL A029) 1 day Mon 1/3/22 Mon 1/3/22 663FS+30 edays
723 Training Courseware (CDRL A076) 20 days Sat 6/25/22 Mon 7/25/22
724 Training Courseware Deliveralbe 0 days Sat 6/25/22 Sat 6/25/22 744SF-40 edays
725 Government Review Training Courseware 15 edays Sat 6/25/22 Sun 7/10/22 724
726 Updated Training Courseware 15 edays Sun 7/10/22 Mon 7/25/22 725
727 Initial Training Outline (CDRL A075) 20 days Sat 6/25/22 Mon 7/25/22
728 Training Outline Deliveralbe 0 days Sat 6/25/22 Sat 6/25/22 744SF-40 edays
729 Government Review Training Outline 15 edays Sat 6/25/22 Sun 7/10/22 728
730 Updated Training Outline 15 edays Sun 7/10/22 Mon 7/25/22 729
731 Updated Program Protection Implementation Plan (PPIP) (CDRL A082)
0 days Mon 7/4/22 Mon 7/4/22 738SF-15 edays
732 Risk Management Plan (CDRAL A081) 0 days Mon 7/4/22 Mon 7/4/22 738FS-15 edays
733 Meeting Agenda (CDRL A001) 3 days Tue 7/12/22 Sun 7/17/22
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Half 1, 2013 Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
738 PSR 20 1 day Tue 7/19/22 Tue 7/19/22 744FS-30 edays
740 Meeting Minutes (CDRL A002) 6 days Thu 7/21/22 Fri 7/29/22
744 I&KPT 10 days Thu 8/4/22 Wed 8/17/22 721FS+30 edays
745 Operator Training 5 days Thu 8/4/22 Wed 8/10/22
746 Maintainer Training 5 days Thu 8/11/22 Wed 8/17/22 745
747 Final Training Outline (CDRL A075) 22 days Wed 8/17/22 Fri 9/16/22
750 Final Training Courseware (CDRL A076) 22 days Wed 8/17/22 Fri 9/16/22
753 Final Production TDP (CDRL A085) 0 edays Fri 9/2/22 Fri 9/2/22 758SF-45 edays
754 Final FMECA (CDRL A034) 0 days Mon 9/26/22 Mon 9/26/22 758SF-21 edays
755 Final Maintenance Task Analysis (CDRL A037) 1 day Fri 9/23/22 Mon 9/26/22 758SF-21 edays
756 Final Long Lead Time Items Outline (CDRL A038) 0 days Mon 9/26/22 Mon 9/26/22 758SF-21 edays
757 Final Lora Outline (CDRL A035) 1 day Fri 9/23/22 Mon 9/26/22 758SF-21 edays
758 End of Contract 1 day Mon 10/17/... Mon 10/17/22 744FS+60 edays
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Half 1, 2013 Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
7/27
8/24
11/14
11/14
11/14
11/14
11/14
11/14
11/14
11/29
11/29
2/13
2/13
1/29
2/13
2/13
2/13
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017 Half 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
2/13
2/13
2/13
2/13
2/13
2/13
2/13
2/13
2/13
3/2
7/8
4/25
5/22
6/21
9/6
9/6
7/8
7/8
7/8
7/8
7/8
7/8
7/8
7/24
7/23
7/24
6/30
8/14
8/22
9/5
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017 Half 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
3/27
10/8
10/8
10/23
10/23
1/19
1/19
1/7
1/7
1/22
1/22
4/8
4/8
4/23
4/23
5/6
5/6
5/22
5/22
6/5
7/5
10/26
11/25
11/25
11/25
9/18
2/3
2/3
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017 Half 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
2/3
2/3
2/3
5/31
7/13
10/21
10/21
9/6
10/21
11/22
10/21
10/21
10/21
10/21
10/26
11/5
1/20
1/20
1/20
2/4
1/20
4/21
4/21
5/6
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017 Half 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
2/17
2/17
2/12
2/17
2/17
3/4
3/4
4/2
4/13
4/18
5/3
7/18
7/18
7/18
8/2
4/18
5/25
11/17
11/17
11/17
12/2
12/9
12/9
12/9
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017 Half 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
1/14
11/30
1/6
4/12
4/12
4/27
4/27
6/1
9/8
9/8
9/23
9/23
11/23
10/22
11/28
9/22
3/8
12/8
12/8
12/8
12/23
12/23
2/14
2/14
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017 Half 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
12/8
3/1
3/1
3/8
3/8
3/8
3/8
12/13
11/2
11/2
11/2
11/17
11/17
11/27
1/2
4/3
4/3
4/3
4/3
4/3
6/1
4/18
4/18
4/18
4/18
4/18
7/4
1/3
7/25
6/25
7/25
6/25
7/4
7/4
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017 Half 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
9/16
9/16
9/2
9/26
9/26
9/26
9/26
10/17
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017 Half 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
File details come from the government source that posted it. Updated .