W52P1J17R0173-0007.pdf
PDF 14 KB Posted
- Attached to
- M116 & M825 Smoke Projectiles
- Solicitation number
- W52P1J-17-R-0173
About this file
This document provides details for a federal solicitation seeking manufacturing of 155mm M825A1 and M116A1 smoke projectile bodies. The Army Contracting Command - Rock Island intends to issue solicitation W52P1J-17-R-0173 for a small business set-aside firm-fixed price indefinite delivery indefinite quantity contract with a single award and five one-year ordering periods. The M825A1 is a 58-pound hot rolled steel projectile body approximately 30 inches long, while the M116A1 is a 60-pound hot forged carbon steel projectile body measuring 24 inches. Monthly production rates are 1,000 units for the M116A1 and 2,500 units for the M825A1, with an estimated maximum contract value of $99,039,742. Offerors must manufacture and deliver the projectile bodies in accordance with a government-provided technical data package. The anticipated award is in the fourth quarter of fiscal year 2019.
W52P1J-17-R-0173 Amendment 0007
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of
2. Amendment/Modification No.
3. Effective Date
4. Requisition/Purchase Req No.
5. Project No. (If applicable)
6. Issued By Code 7. Administered By (If other than Item 6) Code
8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)
9A. Amendment Of Solicitation No.
9B. Dated (See Item 11)
10A. Modification Of Contract/Order No.
10B. Dated (See Item 13) Code Facility Code
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting And Appropriation Data (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS
It Modifies The Contract/Order No. As Described In Item 14.
A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In
The Contract/Order No. In Item 10A.
B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set
Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).
C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:
D. Other (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.
14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. Name And Title Of Signer (Type or print)
16A. Name And Title Of Contracting Officer (Type or print)
15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed
By (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITIONS UNUSABLE
30-105-02 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
SEE SCHEDULE
X
Firm Fixed Price
0007 2019MAR29
W52P1J
ARMY CONTRACTING COMMAND - RI
ROCK ISLAND, IL 61299-8000
BLDGS 60 & 62
MATTHEW KOPEL
EMAIL: MATTHEW.J.KOPEL.CIV@MAIL.MIL
W52P1J-17-R-0173
2019JAN03
X
X
/SIGNED/
2 signed
SEE SECOND PAGE FOR DESCRIPTION
1 3
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION A - SUPPLEMENTAL INFORMATION
Buyer Name: MATTHEW KOPEL
Buyer Office Symbol/Telephone Number: CCRC-AC/(309)782-7888
Type of Contract 1: Firm Fixed Price
Kind of Contract: Supply Contracts and Priced Orders
*** End of Narrative A0000 ***
\*The purpose of Amendment 0007 to Solicitation W52P1J-17-R-0173 is as follows:
1. The closing of this solicitation remains at 1600 Central Time, 18 April 2019. No questions on this solicitation will be accepted after 1600 Central Time, 4 April 2019.
2. As this solicitation is utilizing a Subjective Best Value Tradeoff Source Selection Process, significant strengths and strengths may be incorporated into the contract and become part of the requirement. Significant strengths and strengths incorporated into the contract are those aspects of an offerors proposal that has merit or exceeds specified performance or capability requirements in a way that will be advantageous to the U.S. Government during contract performance. If discussions are conducted, offerors will have the opportunity to remove identified significant strengths and strengths in their Final Proposal Revisions if they do not want to be held to them contractually.
3. To Answer the following industry questions for Solicitation W52P1J-17-R-0173:
Question a): Sections L.5.1.1.d and L.5.1.2d - Identification and Description of the Inspection Equipment Utilized require for____________ each prime contractor and major subcontractors to identify all corresponding Critical, Major, and Minor Characteristics, per item specification, within their respective inspection points in the proposed manufacturing processes.
As reflected in the TDP, these characteristics are quite extensive and completed lists may be as long as 10 pages for each projectile. Will the Government please consider permitting contractors to provide these extensive, data rich documents as separate attachments to the response, excluded from the current page count restrictions?
Answer a): From L.5.1.1.d.i "...Identification of all corresponding Critical, Major, and Minor Characteristics, per item__________ specification, within their Respective inspection points in the proposed manufacturing processes for both the prime contractor and major subcontractors/suppliers.
To L.5.1.1.d.i "...Identification of all corresponding Critical, and Major Characteristics, per item specification, within their respective inspection points in the proposed manufacturing processes for both the prime contractor and major subcontractors/suppliers.
4. To Answer the following industry questions for Solicitation W52P1J-17-R-0173 for ECP R18A2021:
Question a): Drawing 13074830 Rev. - Ultrasonic Inspection Standard, Longitudinal and Radial Cracks, 155MM, M116A1____________
In Zone D6 Notch #9 and in Zone C6 Notch #10 cannot be detected as shown in the bottom of the band seat and on the ID wall under the band seat location.
Will the USG please consider relocating these notches at the same longitudinal location prior to machining of the band seat?
Answer a): No, the notches need to be machined and checked after the band seat is machined.__________
Question b): Drawing 13074831 Rev. - Ultrasonic Inspection Standard, Circumferential and Piping Defects, Body, 155MM, M116A1____________
In Zone C3 Notch #2 at the root of the ID fuze thread and Zone C7 Notch #12 at the root of the ID base thread cannot be detected due to ultrasonic noise generated by the thread forms.
Will the USG please consider eliminating these notches?
Answer b): No, the notches need to machined and checked before thread features are machined into both locations.__________
2 3
W52P1J-17-R-0173
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
Question c): Answer k: The minimum requirement for the body plane-strain fracture toughness shall be 100 KSI checkmark in.____________
At what temperature is this plane-strain fracture toughness test to be performed?
Answer c): All plane-strain fracture toughness testing shall be performed at -65 degrees F (4.4.2.3.1 M116A1 MIL-DTL,__________
.4.5.1/4.4.5.2 M825A1 MIL-DTL).
Question d): Answer l: The minimum requirement for the base plane-strain fracture toughness shall be 100 KSI checkmark in.____________
At what temperature is this plane-strain fracture toughness test to be performed?
Answer d): All plane-strain fracture toughness testing shall be performed at -65 degrees F (4.4.2.3.1 M116A1 MIL-DTL,__________
4.4.5.1/4.4.5.2 M825A1 MIL-DTL).
*** END OF NARRATIVE A0008 ***
3 3
W52P1J-17-R-0173
SECTION A
File details come from the government source that posted it. Updated .