This document provides an amendment to a solicitation and answers questions from industry regarding technical requirements for 155mm M116A1 and M825A1 artillery smoke projectile bodies. The amendment increases page limits for technical proposals from 100 to 115 pages in response to a request from offerors to adequately address requirements for two different projectile types. It also answers questions about ultrasonic testing and machining of threads on projectile bodies and components. The questions and answers clarify technical specifications on drawings for notches, threads and finishing on projectile bodies, plugs and ogives. The U.S. Army Contracting Command - Rock Island intends to issue solicitation W52P1J-17-R-0173 for the manufacturing and delivery of the 155mm M825A1 and M116A1 smoke projectile bodies in accordance with government technical data. The small business set-aside contract will have a single award, firm-fixed price, indefinite delivery/indefinite quantity structure over five one-year ordering periods, with estimated monthly production rates and a maximum contract value provided.

Amendment 0003

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of

2. Amendment/Modification No.

3. Effective Date

4. Requisition/Purchase Req No.

5. Project No. (If applicable)

6. Issued By Code 7. Administered By (If other than Item 6) Code

8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)

9A. Amendment Of Solicitation No.

9B. Dated (See Item 11)

10A. Modification Of Contract/Order No.

10B. Dated (See Item 13) Code Facility Code

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting And Appropriation Data (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS

It Modifies The Contract/Order No. As Described In Item 14.

A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In

The Contract/Order No. In Item 10A.

B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set

Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).

C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:

D. Other (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.

14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. Name And Title Of Signer (Type or print)

16A. Name And Title Of Contracting Officer (Type or print)

15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed

By (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITIONS UNUSABLE

30-105-02 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

SEE SCHEDULE

X

Firm Fixed Price

0003 2019MAR04

W52P1J

ARMY CONTRACTING COMMAND - RI

ROCK ISLAND, IL 61299-8000

BLDGS 60 & 62

MATTHEW KOPEL

EMAIL: MATTHEW.J.KOPEL.CIV@MAIL.MIL

W52P1J-17-R-0173

2019JAN03

X

X

/SIGNED/

2 signed

SEE SECOND PAGE FOR DESCRIPTION

1 3

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION A - SUPPLEMENTAL INFORMATION

Buyer Name: MATTHEW KOPEL

Buyer Office Symbol/Telephone Number: CCRC-AC/(309)782-7888

Type of Contract 1: Firm Fixed Price

Kind of Contract: Supply Contracts and Priced Orders

*** End of Narrative A0000 ***

The purpose of Amendment 0003 to Solicitation W52P1J-17-R-0173 is as follows:

1. Answer the following questions provided by industry for the 155mm M116A1 Projectile Body Reference Drawings 13074830 & 13074831:

Question a): Please confirm that the projectile body may be ultrasonically tested with machined features such as threads. ____________

Answer a): The Projectile Body shall not be ultrasonic tested with threads. __________

Question b): If threads are permitted please clarify that notch depth #2 of drawing 13074830 would be measured from the root of the ____________ threads.

Answer b): N/A __________

Question c): If threads are permitted Request that notch #1 and #2 on drawing number 13074830 be increased in length and depth. ____________

The current size of the notch would be difficult to detect with a machine feature such as a thread. We are requesting that the length of the notch be 0.819 and depth 0.205.

Answer c: N/A _________

Question d): If threads are permitted Request that notch #2 on drawing number 13074831 be removed since it would make it very ____________ difficult to distinguish the notch signal with a machined thread.

Answer d: N/A _________

Question e): If threads are permitted Request that notch #1 on drawing number 13074831 be increased in length and depth. The ____________ current size of the notch would be difficult to detect with a machine feature such as a thread. We are requesting that the length of the notch be 0.819 and depth 0.205.

Answer e): N/A __________

2. Answer the following questions provided by industry for the 155mm M116A1 Base Plug Reference Drawings 10534907, rev C (Plug, Base):

Question a): Require clarification on which surfaces of Base Plug receive Finish 20.2. Both Note 5 symbols on drawing make ____________ reference to Diameter 4.925

Answer a): Only the front and rear faces of the base plug (Drawing 10534907) need to receive Finish 20.2. The remaining surface __________ only needs to be prepared with Finish NO 5.1.1

3. Answer the following questions provided by industry for the 155mm M825A1 Projectile Body Reference Drawings 13075008 & 13075009:

Question a): Please confirm that the projectile body may be ultrasonically tested with machined features such as threads. ____________

Answer a): The Projectile Body shall not be ultrasonic tested with threads. __________

2 3

W52P1J-17-R-0173

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

Question b): If threads are permitted please clarify that notch depth #2 of drawing 13075008 would be measured from the root of the ____________ threads.

Answer b): N/A __________

Question c): If threads are permitted request that notch #1 and #2 on drawing number 13075008 be increased in length and depth. ____________

The current size of the notch would be difficult to detect with a machine feature such as a thread. We are requesting that the length of the notch be 0.819 and depth 0.205.

Answer c): N/A __________

Question d): If threads are permitted request that notch #2 on drawing number 13075009 be removed since it would make it very ____________ difficult to distinguish the notch signal with a machined thread.

Answer d): N/A __________

Question e): If threads are permitted request that notch #1 on drawing number 13075009 be increased in length and depth. The ____________ current size of the notch would be difficult to detect with a machine feature such as a thread. We are requesting that the length of the notch be 0.819 and depth 0.205.

Answer e): N/A __________

4. Answer the following questions provided by industry for the 155mm M825A1 Ogive Reference Drawings 13075006 & 13075007:

Question a) Please confirm that the Ogive may be ultrasonically tested with machined features such as threads. ___________

Answer a): The Ogive shall have machined features such as threads before conducting Ultrasonic Testing. Given the need for __________

Hydrostatic Testing, it is important that these machined features are done before hydrostatic testing and ultrasonic testing.

Question b) If threads are permitted Please clarify that notch depth on #2 and #5 of drawings 13075006 would be measured from the ___________ root of the threads.

Answer b): Yes, they can be measured from the root of the threads. __________

Question c) If threads are permitted Request that notch #2 and #5 on drawing number 13075007 be removed since it would make it very ___________ difficult to distinguish the notch signal with a machined thread.

Answer c): Notch #2 and #5 on drawing 13075007 shall be removed. __________

NOTE: Question 4 and its answers regarding the threads will be incorporated in an ECP once contract is awarded.

5. Question a): Request enlarging the maximum page restriction from 100 to a more realistic 200. The issue boils down to having to ____________ submit all the required documentation for two (2) different projectiles. Each projectile has its unique sequence of processes and operations that must be presented separately. Hence, the 100 page max is simply too restrictive for two different technical packages.

Answer 5: 115 pages will be the maximum limit. No additional pages will be granted. _________

*** END OF NARRATIVE A0004 ***