This amendment to solicitation W52P1J-17-R-0173 provides answers to industry questions regarding the manufacturing and delivery of 155mm M825A1 and M116A1 Artillery Smoke Canister Projectile Bodies. The U.S. Army Contracting Command - Rock Island intends to award a single-award, firm-fixed-price IDIQ contract with a small business set-aside for annual production quantities of 1,000 M116A1 projectiles per month and 2,500 M825A1 projectiles per month. The contract will have a maximum value of $99,039,742 over five one-year ordering periods from FY2019 through FY2023. Offerors must demonstrate capability to produce the projectile bodies in accordance with government-owned technical data packages for the M825A1 and M116A1.
W52P1J-17-R-0173 Amendment 0006
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of
2. Amendment/Modification No.
3. Effective Date
4. Requisition/Purchase Req No.
5. Project No. (If applicable)
6. Issued By Code 7. Administered By (If other than Item 6) Code
8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)
9A. Amendment Of Solicitation No.
9B. Dated (See Item 11)
10A. Modification Of Contract/Order No.
10B. Dated (See Item 13) Code Facility Code
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting And Appropriation Data (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS
It Modifies The Contract/Order No. As Described In Item 14.
A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In
The Contract/Order No. In Item 10A.
B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set
Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).
C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:
D. Other (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.
14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. Name And Title Of Signer (Type or print)
16A. Name And Title Of Contracting Officer (Type or print)
15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed
By (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITIONS UNUSABLE
30-105-02 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
SEE SCHEDULE
X
Firm Fixed Price
0006 2019MAR26
W52P1J
ARMY CONTRACTING COMMAND - RI
ROCK ISLAND, IL 61299-8000
BLDGS 60 & 62
MATTHEW KOPEL
EMAIL: MATTHEW.J.KOPEL.CIV@MAIL.MIL
W52P1J-17-R-0173
2019JAN03
X
X
/SIGNED/
2 signed
SEE SECOND PAGE FOR DESCRIPTION
1 3
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION A - SUPPLEMENTAL INFORMATION
Buyer Name: MATTHEW KOPEL
Buyer Office Symbol/Telephone Number: CCRC-AC/(309)782-7888
Type of Contract 1: Firm Fixed Price
Kind of Contract: Supply Contracts and Priced Orders
*** End of Narrative A0000 ***
The purpose of Amendment 0006 to Solicitation W52P1J-17-R-0173 is as follows:
1. To answer the following industry questions for Request for Proposal:
Question a): Reference Solicitation W52P1J-17-R-0173, Modification 3, & Modification 4.____________
Is the maximum limit of pages 115 pages or 100 pages? In Modification 3, Answer #5 states that the maximum limit is 115 pages.
However, in Modification 4, Para. L.3.1.a & L.5 Volume 1, it is listed that the maximum number of pages is 100.
Would the Government be able to clarify this information?
Answer a): Refer to Amendment 0005 for answer.__________
Question b): Will the U.S. Government please provide a conformed copy of the entire solicitation (with amendments)?_____________
Answer b): For the convenience of having the solicitation and amendments 0001 to 0005 in one document, the U.S. Government will__________ provide this as supporting documentation within Federal Business Opportunities (FEDBIZOPPS).
2. To Answer the following industry questions for Solicitation W52P1J-17-R-0173 M116A1 155mm Artillery Smoke Projectile Metal Parts:
Question a): Paragraph 4.3.1.1 Heat treatment inspection lot____________
"For continuous heat treat process a heat treat lot shall consist of eight (8) hours of continuous production".
This will result in an excessive amount of mechanical properties testing which will increase the unit cost while adding no value.
Will the USG consider revising this to state the furnace can be run continuously until the entire mill heat of steel has be processed or there is a break in the furnace operation?
Answer a): The following sentence is deleted in its entirety: "For continuous heat treat process a heat treat lot shall consist of__________ eight (8) hours of continuous production".
Question b): Reference Dwg No. 10534906 Rev. C (Body) & MIL-DTL-32595(AR). What are the requirements for the Plane Strain Fracture____________
Toughness on the M116A1 Body (Dwg No. 10534906)? In MIL-DTL-32595(AR), Para. 3.3.2, it is stated The minimum fracture toughness
(Kic) in the body side wall shall be determined by government technical agency.
Would the Government be able to provide this information?
Answer b): The minimum requirement for the body plane-strain fracture toughness shall be 100 KSI-in^.5__________
Question c): Reference Dwg No. 10534906 Rev. C (Body). Geometry on Dwg No. 10534906 Rev. C (Body) in ID nose area is not defined at____________ all. Also, behind the step in the ID of the ogive the geometry shows two tapers, but only two datums (one on each taper) and one taper (basic).
Would the Government be able to clarify this information?
Answer c): The Geometry in regards to the ID of the nose area can be seen in Detail C of sheet 2. A second taper dimension was__________ removed from the previous revision of the drawing because it was only a reference dimension. That area is defined by the other
2 3
W52P1J-17-R-0173
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
remaining dimensions.
Question d): Reference Dwg No. 7548993 Rev. T (Blank, Rotating Band) & MIL-DTL-32595(AR). Dwg No. 7548993 Rev. T (Blank, Rotating____________
Band) calls out Tensile Strength of 40,000 psi Max., whereas MIL-DTL-32595(AR) Para. 4.3.2.1 calls out 40,000 PSI min Yield @ 12% elongation.
Can it be assumed tensile strength typically refers to ultimate tensile strength?
Would the Government be able to clarify this information?
Answer d): The information in Para. 4.3.2.1 is changed FROM: 40,000 PSI min, TO: 40,000 PSI max in order to reflect the drawing__________ requirements. The min for this item is 30,000 PSI as seen in Para 3.3.1.
Question e): Reference Dwg. No. 10534907 Rev. C (Plug, Base). Dwg. No. 10534907 Rev. C (Plug, Base) Spanner holes are listed as____________
03/18 x 5/16 Deep.
Is there a typographical error for the diameter of these holes?
Answer e): The diameter of the holes are changed to 3/8 x 5/16 Deep.__________
Question f): Would the Government review its below Answer to the below Question e on page 7 of Amendment 0005?____________
Question e): Paragraph 3.3.2 Plane strain fracture toughness test. The minimum fracture toughness (K1c) in the body side wall shall be determined by government technical agency.
Will the USG please provide this information? The selection of a steel alloy to meet this requirement will be based on this and will affect the unit price.
Answer e): For this procurement the Flexible Rotating Band is required.
Answer f): Answer e in Amenmdment 0005 was in error. The correct answer is:__________
"The minimum requirement for the body plane-strain fracture toughness shall be 100 KSI-in^.5"
3. To Answer the following industry questions for Solicitation W52P1J-17-R-0173 M825A1 155mm Artillery Smoke Projectile Metal Parts:
Question a): Reference Dwg No. 9352632 Rev. G (Body), Dwg No. 13075008 (Ultrasonic Inspection Standard, Longitudinal Defects,____________
Body, 155MM, M825A1), Dwg No.13075009 (Ultrasonic Inspection Standard, Circumferential Defects, Body, 155MM, M825A1), & MIL-DTL-
64008A.
Is the Ultrasonic Test to be performed on Dwg No. 9352632 Rev. G (Body) before or after the rotating band is welded? The Ultrasonic
Test Standards, Dwg No. 13075008 & Dwg No.13075009, do not show the band on the body. Would the Government be able to clarify this information?
Answer a): The Ultrasonic Test is required to be performed after the Rotating Band is welded.__________
Question b): Reference Dwg No. 10542916 Rev. W (Ogive) & MIL-DTL-64008A. After Hydrostatic Pressure Testing is performed on Dwg____________
No. 10542916 Rev. W (Ogive), should the part be stamped with an "H" to signify completion of the Hydrostatic Pressure Test?
Answer b): After passing Hydrostatic Testing the ogive shall be stamped with an "H".__________