QA KABD152001 REPAIR HVAC SYSTEM 20Aug2020.pdf

PDF 74 KB Posted

Attached to
KABD152001 Hawaii Air National Guard - Repair HVAC System, Maui, HI
Solicitation number
W50SLF-20-R-0001
Issued by

About this file

This document contains questions and answers related to solicitation number W50SLF-20-R-0001 for repair of the HVAC system at the Hawaii Air National Guard facility in Maui, Hawaii. The scope of work includes replacing existing air handling units, ductless split systems, a fan coil unit, and interior air distribution network. The contract is a fixed-price construction contract with a 180-day period of performance. The total contract value is estimated between $500,000 to $1 million. The North American Industry Classification System code is 238220 and it is set aside for total women-owned small businesses with a size standard of $16.5 million average annual revenue. The pre-proposal conference was on August 10, 2020 and questions were due by August 7, 2020. The solicitation closing date is September 3, 2020. The source selection will consider technical, past performance, and price factors.

View the file

Other files

File Type Posted
DDC photo2.jpeg JPEG file
DDC photo3.jpeg JPEG file
DDC photo1.jpeg JPEG file
BLDG 501 CHILLER DRAWINGS.pdf PDF
DDC photo5.jpg JPG image
DDC photo7.jpg JPG image
QA KABD152001 REPAIR HVAC SYSTEM (31-Aug-2020).pdf PDF
DDC photo4.jpeg JPEG file
0021-0012 Maui Chiller Sub 12.pdf PDF
DDC photo6.jpg JPG image
1. MFR - Pre-Proposal Conference Site Visit.pdf PDF
6. Q&A KABD152001 Repair HVAC System Maui.pdf PDF
01. Solicitation Amendment W50SLF20R0001 0003.pdf PDF
3. Pre-Proposal Meeting PPT Repair HVAC System Maui.pptx PPTX presentation
5. Maui_HVAC_Pics.xlsx XLSX spreadsheet
EXHIBIT D_Letter of Commitment.docx DOCX document
4. Split_AC_Layout.pdf PDF
01.1. Solicitation W50SLF20R0001 0003 (Conformed Document).pdf PDF
2. Sign-in Sheet.pdf PDF
2. SOW KABD152001 - REPAIR HVAC SYSTEM MAUI.pdf PDF
1.1. Solicitation Amendment 0001.pdf PDF
3. Appendix F - Specifications.pdf PDF
6. EXHIBIT B_HVAC Maui.doc DOC document
5. EXHIBIT A_HVAC Maui.doc DOC document
4. Appendix H- Reference Drawings.pdf PDF
7. EXHIBIT_C_Reference_Questionnaire_HVAC Maui.docx DOCX document
1.2. Solicitation Amendment 0002.pdf PDF
1.0. Solicitation W50SLF20R0001 0002.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers Related To:

KABD152001 REPAIR HVAC SYSTEM, MAUI

Solicitation W50SLF-20-R-0001 Dated 11-Aug-2020

Q1: We were able to look at a few of the Air Handling Units that are to be replaced. Please confirm if replacement will also include the isolation valves. Furthermore, please confirm that the chilled water piping, to include valves and appurtenances will be insulated.

A1: Per Statement of Work page 4, Principle Elements of Work – Mechanical, item 1 states to demolish all existing mechanical equipment, ductwork, piping, valves, appurtenances, and controls. Similarly, item 2 states to provide the demolished items and replace with new, resulting in a complete functioning system in compliance with all applicable codes. In regards to the AHUs, this would include the isolation values for both the return and supply lines.

Concerning the chilled water piping, to have a complete functioning system, all chilled water piping and appurtenances would include insulating as necessary to prevent condensation. This would include any re-insulating necessary due to the demolish phase and the tie-in phase.

Q2: It was noticed that the exterior pipe/duct for the split AC units were different. The exterior pipe/duct for the 12K BTU unit for the Server room had its black insulation exposed, the 36K BTU unit for room 123 was encapsulated in a metal pipe, and the 2 each 36K BTU units for the Keawe Cove room were encapsulated in a PVC type of jacket/channel. Please advise on the jacket/channel type of new split units.

A2: The exterior pipe/duct for all new split AC units will following the existing type, or similar, used for the Keawe Cove room existing split AC units. Refer to the pictures taking during the site visit.

Q3: Page 6 of the Statement of Work provides requirements for DESIGN SUBMISSION.

Please confirm if this is a requirement for this project.

A3: As addressed during the Pre-Proposal Conference, the Design Submission section will be required should the new installation equipment, location, associated piping/routing, and current code requirements differs from what is existing. This will include situations where the existing location may need to be structurally reinforced to receive the new installation (i.e., soffit structure in the Keawe Cove room, boring new holes for piping/routing, etc). If the new equipment, location, and associated piping/routing are in-kind with the existing and there are no conflicts with current code requirements, the Design Submission section is not required.

Q4: It was mentioned that Pre-Construction Meeting requirements will be discussed after project award. Just so we are aware of these requirements, please advise on these.

A4: After project award/NTP and prior to the start of onsite construction, a Pre-Construction Meeting will be held with the Contractor, Contracting, Civil Engineer Squadron, and other key stakeholders from the Government. The purpose of the Pre-Construction Meeting will be for the Contractor to present how they intend to complete the project in accordance with the contract documents. At least 2 weeks prior to the Pre-Con, the Contractor is to submit to the Gov’t the following items as these will be agenda items of discussion: 1) Quality Control Plan to include Submittal Register and Testing/Commissioning Register, 2) Environmental Protection Plan, 3) Safety Plan, 4) Gantt-type Baseline Construction Schedule with sufficient detail to track progress to include Administrative items, Submittals, Onsite Work Activities, and Closeout Activities, and 5) Schedule of Values for Progress Payment with sufficient detail to track completed items for invoice purposes. Approval or further revisions to these submittals will be made at the conclusion of this Pre-Con. For scheduling requirements in the Technical proposal, assume Pre-Construction Meeting to be held no later than 4 weeks after NTP (Notice To Proceed).

Dated 20-Aug-2020

Q5: Can you advise if contracting will accept CPARS for the project experience in lieu of the Project Past Performance Questionnaire? We suspect that CPARS is acceptable as it is more formal than the PPQ and is government furnished.

A5: Yes - CPARS is acceptable.

Reference solicitation, sub-section 2.5.3.11. Past Performance References – REQUIRED – A “Final” Performance Evaluation (Construction) (also referred to as CCASS Evaluation) issued for a project may be included in lieu of sending out reference package for the project.

According to Acquisition Central, the CPARS, Architect-Engineer Contract Administration Support System (ACASS) and Contractor Appraisal Support System (CCASS) are being merged into a single application under the CPARS name in order to standardize the contractor performance evaluation process across the entire Federal Government.

Q6: Please confirm all work is assumed to be non-hazardous.

A6: Other than the work/materials associated with the existing A/C refrigerant and AHUs per industry standards, all other work are non-hazardous. The paint in the building has been tested earlier this year for asbestos with results negative.

Q7: Please confirm where each of the exhibits is to be included

Exh A - Vol 2, Part 2 - Past/Present Info Exh B – Vol 1, Part 1 –Experience and Capability?

Exh C – Vol 2, Part 2 - Past/Present Info Exh D – Vol 1, Part 1 – Experience and Capability?

A7: Exhibit A, Part 1 Information (Provide no more than three (3)) - Vol 2, Part 2 – Offeror’s Past/Present Performance Information

Exhibit A, Part 2 Information (Provide one time) - Vol 2, Part 2 – Offeror’s Past/Present Performance Information

Exhibit B (required if key person is sub-contractor) – Vol 2, Part 2 – Offeror’s Past/Present

Exhibit C – Reference solicitation sub-section 2.5.3.11. Offerors shall prepare and submit to prior client(s) and inform clients the completed Performance Questionnaire should be returned to the Contracting Officer via email at: manuel.llanes.mil@mail.mil and copy to cezar.y.deveas.mil@mail.mil to arrive not later than the closing date for receipt of proposals. Offeror must not review the Past Performance Questionnaire prior to submission. They are to be submitted by the client/evaluator directly to the Contracting Officer. Offeror's should follow-up and encourage references to get the questionnaires to the Contracting Officer in a timely manner.

Exhibit D (required if key person is sub-contractor) – Vol 2, Part 2 – Offeror’s Past/Present

Q8: For JV or teaming arrangements, are max 3 PPE/PPQ (Exh A/Exh C) allowed for each company (total 6 for the team)? Or are max 3 PPE/PPQ (Exh A/Exh C) allowed for the team?

Is it a requirement that each company must submit at least 1?

A8: Max 3 PPE/PPQ (Exh A/Exh C) allowed for the team. There is no such requirement that each company must submit at least 1.

Q9: The Form DD2626 is a standardized final performance evaluation form used by some contracting agencies. Can Form DD2626 be included (similar to the CCASS evaluation) in lieu of the Exhibit C reference package?

From past requests, some agencies will refuse to complete any evaluation and will simply defer to only CCASS evals. However, CCASS evals are generally only required to be completed for projects over $750,000. So if there is a project of smaller scale, there will not be a CCASS on file to reference and the agency will decline to provide an evaluation.

From past requests, DD2626 have been accepted similar to the CCASS since it is a standardized government evaluation form.

A9: DD Form 2626 can be submitted in lieu of CCASS Evaluation (CPARS) or Exhibit C Reference Questionnaire Forms.