6. Q&A KABD152001 Repair HVAC System Maui.pdf

PDF 107 KB Posted

Attached to
KABD152001 Hawaii Air National Guard - Repair HVAC System, Maui, HI
Solicitation number
W50SLF-20-R-0001
Issued by

About this file

This document provides details for a federal contract solicitation to repair the HVAC system at a National Guard facility in Maui, Hawaii. The scope of work includes replacing existing air handling units, ductless split systems, a fan coil unit and interior air distribution network. The contractor must demolish and remove all existing mechanical and electrical equipment, ductwork, piping, valves, conduit, wiring, appurtenances and controls, and provide and install new replacement components to create a fully functioning system. The magnitude of the project is estimated between $500,000 and $1,000,000, and work must be completed within 180 calendar days of the notice to proceed. A pre-proposal conference will be held on August 10, 2020, with questions due by August 7, 2020. Proposals are due by September 3, 2020 and will be evaluated based on technical, past performance and price factors. This is a total women-owned small business set-aside with an annual revenue size standard of $16.5 million.

View the file

Other files

File Type Posted
DDC photo2.jpeg JPEG file
DDC photo3.jpeg JPEG file
DDC photo1.jpeg JPEG file
BLDG 501 CHILLER DRAWINGS.pdf PDF
DDC photo5.jpg JPG image
DDC photo7.jpg JPG image
QA KABD152001 REPAIR HVAC SYSTEM (31-Aug-2020).pdf PDF
DDC photo4.jpeg JPEG file
0021-0012 Maui Chiller Sub 12.pdf PDF
DDC photo6.jpg JPG image
QA KABD152001 REPAIR HVAC SYSTEM 20Aug2020.pdf PDF
1. MFR - Pre-Proposal Conference Site Visit.pdf PDF
01. Solicitation Amendment W50SLF20R0001 0003.pdf PDF
3. Pre-Proposal Meeting PPT Repair HVAC System Maui.pptx PPTX presentation
5. Maui_HVAC_Pics.xlsx XLSX spreadsheet
EXHIBIT D_Letter of Commitment.docx DOCX document
4. Split_AC_Layout.pdf PDF
01.1. Solicitation W50SLF20R0001 0003 (Conformed Document).pdf PDF
2. Sign-in Sheet.pdf PDF
2. SOW KABD152001 - REPAIR HVAC SYSTEM MAUI.pdf PDF
1.1. Solicitation Amendment 0001.pdf PDF
3. Appendix F - Specifications.pdf PDF
6. EXHIBIT B_HVAC Maui.doc DOC document
5. EXHIBIT A_HVAC Maui.doc DOC document
4. Appendix H- Reference Drawings.pdf PDF
7. EXHIBIT_C_Reference_Questionnaire_HVAC Maui.docx DOCX document
1.2. Solicitation Amendment 0002.pdf PDF
1.0. Solicitation W50SLF20R0001 0002.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

KABD152001 REPAIR HVAC SYSTEM, MAUI

Solicitation W50SLF‐20‐R‐0001

Questions and Answers

8/11/2020

Q1: We were able to look at a few of the Air Handling Units that are to be replaced. Please confirm if replacement will also include the isolation valves. Furthermore, please confirm that the chilled water piping, to include valves and appurtenances will be insulated.

A1: Per Statement of Work page 4, Principle Elements of Work – Mechanical, item 1 states to demolish all existing mechanical equipment, ductwork, piping, valves, appurtenances, and controls. Similarly, item 2 states to provide the demolished items and replace with new, resulting in a complete functioning system in compliance with all applicable codes. In regards to the AHUs, this would include the isolation values for both the return and supply lines. Concerning the chilled water piping, to have a complete functioning system, all chilled water piping and appurtenances would include insulating as necessary to prevent condensation. This would include any re‐insulating necessary due to the demolish phase and the tie‐in phase.

Q2: It was noticed that the exterior pipe/duct for the split AC units were different. The exterior pipe/duct for the 12K BTU unit for the Server room had its black insulation exposed, the 36K BTU unit for room 123 was encapsulated in a metal pipe, and the 2 each 36K BTU units for the Keawe Cove room were encapsulated in a PVC type of jacket/channel. Please advise on the jacket/channel type of new split units.

A2: The exterior pipe/duct for all new split AC units will following the existing type, or similar, used for the Keawe Cove room existing split AC units. Refer to the pictures taking during the site visit.

Q3: Page 6 of the Statement of Work provides requirements for DESIGN SUBMISSION. Please confirm if this is a requirement for this project.

A3: As addressed during the Pre‐Proposal Conference, the Design Submission section will be required should the new installation equipment, location, associated piping/routing, and current code requirements differs from what is existing. This will include situations where the existing location may need to be structurally reinforced to receive the new installation (i.e., soffit structure in the Keawe Cove room, boring new holes for piping/routing, etc). If the new equipment, location, and associated piping/routing are in‐kind with the existing and there are no conflicts with current code requirements, the Design Submission section is not required.

Q4: It was mentioned that Pre‐Construction Meeting requirements will be discussed after project award.

Just so we are aware of these requirements, please advise on these.

A5: After project award/NTP and prior to the start of onsite construction, a Pre‐Construction Meeting will be held with the Contractor, Contracting, Civil Engineer Squadron, and other key stakeholders from the Government. The purpose of the Pre‐Construction Meeting will be for the Contractor to present how they intend to complete the project in accordance with the contract documents. At least 2 weeks prior to the Pre‐Con, the Contractor is to submit to the Gov’t the following items as these will be agenda items of discussion: 1) Quality Control Plan to include Submittal Register and Testing/Commissioning

Register, 2) Environmental Protection Plan, 3) Safety Plan, 4) Gantt‐type Baseline Construction Schedule with sufficient detail to track progress to include Administrative items, Submittals, Onsite Work

Activities, and Closeout Activities, and 5) Schedule of Values for Progress Payment with sufficient detail to track completed items for invoice purposes. Approval or further revisions to these submittals will be made at the conclusion of this Pre‐Con. For scheduling requirements in the Technical proposal, assume

Pre‐Construction Meeting to be held no later than 4 weeks after NTP (Notice To Proceed).

File details come from the government source that posted it. Updated .