Questions and Answers 2.pdf

PDF 124 KB Posted

Attached to
115 FW F-35 Repair Building 420 Construction Project
Solicitation number
W50S9F-23-B-0001
Issued by

About this file

This document contains questions and answers related to solicitation number W50S9F-23-B-0001 posted on SAM.gov for the 115th Fighter Wing F-35 Repair Building 420 Construction Project. The solicitation is for a single firm fixed-price construction contract to repair and modify an existing building to accommodate changes from housing the F-16 mission to the F-35 mission. Work includes right-sizing maintenance spaces and administrative areas. The contract duration is 180 days from notice to proceed. One option is included for communication equipment and cabling. Questions cover scheduling and submittal software, fencing specifications, sanitary line removal, potential schedule extensions for long lead times, and conveying lead time issues. Responses provide clarification on these topics and note the government will work with the awardee post-award to determine proper notice and mobilization dates.

View the file

Other files

File Type Posted
20230308 Alter B420 Abstract of Offers.pdf PDF
20230308 Alter B420 Attendance Sheet.pdf PDF
Questions and Answers 4.pdf PDF
QA3 Attachment 3 P-4A Walltype.pdf PDF
FSB2021-613-00 - WI-ANG - B420 - Addendum 01 COMBINED SPECIFICATIONS.pdf PDF
QA3 Attachment 1 P-8 Walltype.pdf PDF
B420 Environmental Site Characterization Sampling Analysis Plan.pdf PDF
QA3 Attachment 2 P-17 Walltype.pdf PDF
B.08.W50S9F23B0001 Solicitation Amendment 0002.pdf PDF
Questions and Answers 3.pdf PDF
FSB2021-613-00 - WI-ANG - B420 - Addendum 01 COMBINED DRAWINGS.pdf PDF
2023-02-28 B420 Wisconsin - Addm No 1.pdf PDF
E.01.W50S9F23B0001 Solicitation Amendment 0001.pdf PDF
Questions and Answers 1.pdf PDF
F-35 B420 Site Visit 20230208.pdf PDF
B.07.Pre-Proposal Slides - F-35 Repair B420.pptx PPTX presentation
ATTACHMENT 6 - XGFG182019 F-35 Repair B420 - Single Source Doc - Monaco.pdf PDF
E.01.W50S9F23B0001 Solicitation.pdf PDF
ATTACHMENT 2 - WI-ANG - F-35 B420 CD Drawings Type B-3.pdf PDF
ATTACHMENT 4 - XGFG182019 F-35 Repair B420 - Single Source Doc - Andover.pdf PDF
ATTACHMENT 1 - Volume 4 - WI ANG F-35 B420 Specifications Type B-3.pdf PDF
ATTACHMENT 5 - XGFG182019 F-35 Repair B420 - Single Source Doc - Marshall Best.pdf PDF
ATTACHMENT 3 - SFS Form 12 - Template.xls XLS spreadsheet
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F-35 Repair B420, Solicitation # W50S9F-23-B-0001 Posted to SAM.Gov 22 February 23

Questions & Responses #2

Question Response

1.

Primavera P6 is mentioned as the scheduling software. Will it be possible to use Microsoft Project as an option?

Micorsoft Project is an acceptable option.

2. Can we use Procore as the submittal software management system?

Submittal process will be discussed with the awardee at the pre-construction meeting. The 115th has employed several methods/software for managing the submittal process.

3.

It is required to provide a 6 ft tall chain fence around storage and materials trailers.

Specification for chain fence is not part of the bid documents. Could another type of fence be provided?

Install chainlink fence per requirements. Specifications are for construction, not for temporary facilities.

4.

Drawing C-301, indicates to remove the existing sanitary line. The line “runs” below the next building perimeter fence. It is the intention of the job to remove and reuse the existing materials (some of the material may be damaged in the removal) or cut and replace them with new materials. If any replacement is required, please provide the specifications required for the chain fence.

The intent is for the fence to remain in place during removal.

Access to the airfield side of the fence can be provided as necessary. If the fence as it exists should be damaged during removal it shall be replaced in kind. Airfield security shall be maintained at all times, fencing shall not be left open overnight.

5.

Reference Q&A #1 dated 14FEB23, specifically question and response #3. If the PoP needs to be increased due to material and equipment lead times at the time of contract award, please verify that Liquidated Damages will not be assessed to the contract.

Contractor will not be assessed liquidated damages for any delays that are beyond their control.

6.

Reference Q&A #1 dated 14FEB23, specifically question #3. Please verify that contractors should only price general conditions based on the mandatory PoP of 180 calendar days prescribed for in the solicitation. If the PoP is adjusted by lead times after contract award, the contractor would then be awarded general conditions costs based on the additional days added to the PoP.

As determined by the A-E and approved by 115 CES, the government stands by the 180-day Construction PoP.

The Government understands that due to supply chain issues, long lead times are a concern. The government cannot address any and every lead time concern during the solicitation process and has amended Clause 52.211-10 for clarification, providing flexibility for lead times. “Begin Performance” shall include beginning the submittal/RFI approval process to facilitate ordering of long lead time items.

Once there is a better understanding of lead times the government will work with the awardee to determine a Notice to Proceed date and subsequent mobilization date.

The contractor will be responsible for managing and

F-35 Repair B420, Solicitation # W50S9F-23-B-0001 Posted to SAM.Gov 22 February 23

Questions & Responses #2 sequencing work activity to ensure the facility is completed as expeditiously as possible.

7.

Reference Q&A #1 dated 14FEB23, specifically question and response #3. Please advise how the offeror/contractor is to convey to the Government that a lead time and PoP issue exists at bid time. The current bid documents do not allow for such clarification to be provided.

As determined by the A-E and approved by 115 CES, the government stands by the 180-day Construction PoP.

The Government understands that due to supply chain issues, long lead times are a concern. The government cannot address any and every lead time concern during the solicitation process and has amended Clause 52.211-10 for clarification, providing flexibility for lead times. “Begin Performance” shall include beginning the submittal/RFI approval process to facilitate ordering of long lead time items.

Once there is a better understanding of lead times the government will work with the awardee to determine a Notice to Proceed date and subsequent mobilization date.

The contractor will be responsible for managing and sequencing work activity to ensure the facility is completed as expeditiously as possible.

8.

Solicitation notes 180 days to complete the project. Will consideration be given during post-award for materials and equipment that have long-lead times and cannot be furnished within the stated performance period?

As determined by the A-E and approved by 115 CES, the government stands by the 180-day Construction PoP.

The Government understands that due to supply chain issues, long lead times are a concern. The government cannot address any and every lead time concern during the solicitation process and has amended Clause 52.211-10 for clarification, providing flexibility for lead times. “Begin Performance” shall include beginning the submittal/RFI approval process to facilitate ordering of long lead time items.

Once there is a better understanding of lead times the government will work with the awardee to determine a Notice to Proceed date and subsequent mobilization date.

The contractor will be responsible for managing and sequencing work activity to ensure the facility is completed as expeditiously as possible.