This document summarizes an invitation for bid for construction services. The 115th Fighter Wing of the Wisconsin Air National Guard is seeking a contractor to repair and upgrade Building 420 at Dane County Regional Airport - Truax Field in Madison, Wisconsin to support the base's upcoming transition from F-16 to F-35 aircraft. The project includes modifying existing maintenance and administrative spaces as well as adding warm storage capability for aircraft maintenance equipment. Brand name products from Andover, Marshall Best Security, and Monaco Vulcan will be required. The solicitation includes a base CLIN for the project work and an optional CLIN for communication equipment and cabling. The pre-bid conference will be held on-site with immediate site visit. Bids are due by January 20, 2023 and award will be made to the responsive and responsible lowest bidder. The NAICS code is 236220 and contract performance period is 180 days from notice to proceed.

View the file

Other files

File Type Posted
20230308 Alter B420 Abstract of Offers.pdf PDF
20230308 Alter B420 Attendance Sheet.pdf PDF
Questions and Answers 4.pdf PDF
QA3 Attachment 3 P-4A Walltype.pdf PDF
FSB2021-613-00 - WI-ANG - B420 - Addendum 01 COMBINED SPECIFICATIONS.pdf PDF
QA3 Attachment 1 P-8 Walltype.pdf PDF
B420 Environmental Site Characterization Sampling Analysis Plan.pdf PDF
QA3 Attachment 2 P-17 Walltype.pdf PDF
B.08.W50S9F23B0001 Solicitation Amendment 0002.pdf PDF
Questions and Answers 3.pdf PDF
FSB2021-613-00 - WI-ANG - B420 - Addendum 01 COMBINED DRAWINGS.pdf PDF
2023-02-28 B420 Wisconsin - Addm No 1.pdf PDF
Questions and Answers 2.pdf PDF
E.01.W50S9F23B0001 Solicitation Amendment 0001.pdf PDF
Questions and Answers 1.pdf PDF
F-35 B420 Site Visit 20230208.pdf PDF
B.07.Pre-Proposal Slides - F-35 Repair B420.pptx PPTX presentation
ATTACHMENT 6 - XGFG182019 F-35 Repair B420 - Single Source Doc - Monaco.pdf PDF
E.01.W50S9F23B0001 Solicitation.pdf PDF
ATTACHMENT 2 - WI-ANG - F-35 B420 CD Drawings Type B-3.pdf PDF
ATTACHMENT 1 - Volume 4 - WI ANG F-35 B420 Specifications Type B-3.pdf PDF
ATTACHMENT 5 - XGFG182019 F-35 Repair B420 - Single Source Doc - Marshall Best.pdf PDF
ATTACHMENT 3 - SFS Form 12 - Template.xls XLS spreadsheet
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SIMPLIFIED ACQUISITION PROCEDURES (SAP)

SINGLE SOURCE DETERMINATION FOR ACQUISITIONS NOT EXCEEDING THE SIMPLIFIED ACQUISITION THRESHOLD AS DEFINED IN

FAR 2.101

SOLICITATIONS MAY BE LIMITED TO ONE SOURCE ONLY IF THE CONTRACTING OFFICER (within its warrant authority) DETERMINES THAT ONLY ONE SOURCE IS AVAILABLE IAW FAR 13.106-1(b). THIS DETERMINATION SHALL BE SUPPORTED WITH FULL JUSTIFICATION FOR SINGLE SOURCE FROM THE CUSTOMER. THE CUSTOMER SHALL PROVIDE THE FOLLOWING INFORMATION:

QUOTE/SOLICITATION NUMBER:

ESTIMATED AMOUNT (Not exceeding $150,000):

PROVIDE A STATEMENT OF ACTIONS, IF ANY, THE GOVERNMENT MAY TAKE TO REMOVE OR OVERCOME ANY BARRIERS TO

COMPETITION BEFORE FUTURE ACQUISITIONS ARE REQUIRED:

The Government will continue to seek out vendors proposing cost-effective solutions that meet the Government's needs. Additionally, we will continue to conduct market research to find equipment/systems that are not proprietary in nature.

I certify that the statements above are complete and correct to the best of my knowledge. TELEPHONE NUMBER DATE

TELEPHONE NUMBER DATE

TELEPHONE NUMBER DATE

DESCRIPTION OF SUPPLIES OR SERVICES REQUIRED AND THE INTENDED USE:

UNIQUE CHARACTERISTICS THAT LIMIT AVAILABILITY TO ONLY ONE SOURCE, WITH THE REASON NO OTHER SUPPLIES OR

SERVICES CAN BE USED:

EXPLAIN WHY AN ADEQUATE PURCHASE DESCRIPTION OR OTHER INFORMATION SUITABLE TO SOLICIT BY FULL AND OPEN

COMPETITION HAS NOT BEEN DEVELOPED OR IS NOT AVAILABLE:

REASON THAT SUGGESTED SOURCE IS THE ONLY SOURCE WHICH CAN PROVIDE THE SUPPLIES OR SERVICES AND DETAILED

DESCRIPTION OF MARKET RESEARCH PERFORMED:

TELEPHONE NUMBER:
0:
0:
0:
0: 608-245-4563
1: 20 Dec 2022
1:
0: 608-245-4757
1: 20 Dec 2022
2:
0: 608-245-4788
1: 20 Dec 2022
2022-12-20T07:40:52-0600
SACKETT.AMELIA.ANN HARTKE.1181250123
2022-12-20T15:10:11-0600
HOMNER.SCOTT.E.1257506394
2022-12-20T15:32:40-0600
MATTILA.DAVE.WESLEY.JR.1100939327
Text2: 86366
Text5: Many other ANG installations have Andover equipment and systems in use for the same purposes. As stated above, to install another manufacturer's equipment/systems would require substantial duplication of cost to the Government not expected to be recovered through competition resulting in unacceptable delays in fulfilling the agency's requirements. It is customary industry practice for manufacturers to limit proprietary information to technicians who have been properly trained and certified on how to install, maintain, repair, and integrate their equipment and systems.
Text6: Andover systems and items are already in place at the installation and in this instance, no other manufacturer's systems or items will communicate and work with the current system. The cost to convert a new system is not reasonable compared to the cost to maintain parts of the current system.
Text1: W50S9F-23-R-0006
Text3: The 115FW currently employs Andover Automated Controls equipment and systems for our base-wide HVAC, power, and door security systems. The overall system incorporates a central reporting station that is located within the Civil Engineering Squadron with transceivers located in every building on base and communicates back to the central reporting station. Andover equipment/systems are proprietary in nature and no other manufacturer's equivalent products can communicate and support the current Andover system currently employed at this installation. To install another manufacturer's equipment/systems would require substantial duplication of cost to the Government not expected to be recovered through completion resulting in unacceptable delays in fulfilling the agency's requirements. This estimated cost for converting the entire installation to a new automated control system would be well over $6M for the 27 facilities currently implementing this system.
Text4: Andover Automated Controls is a state of the art building automation system that adds efficiency to the Heating, Ventilation, and Air Conditioning (HVAC) and is used to monitor and control facility HVAC equipment. It is also used to monitor and control facility door security base wide.

File details come from the government source that posted it. Updated .