Questions and Answers 1.pdf

PDF 841 KB Posted

Attached to
F-35 THREE BAY SPECIALIZED HANGAR Federal contract opportunity
Solicitation number
W50S9F-22-B-0001
Issued by
Department of the Army National Guard

About this file

This is a solicitation for an unrestricted invitation for bid to construct a new three-bay specialized hangar at Dane County Regional Airport-Truax Field in Madison, Wisconsin. The project involves demolishing an existing 19,875 square foot building and constructing a new 31,000 square foot three-bay hangar facility to support F-35 operations including fuel cell operations, indoor wash requirements, squadron level surface coating, and weapons load training. The contract will be a firm-fixed-price contract awarded to the responsive and responsible lowest bidder. The solicitation includes a base bid and two options. The bid due date is June 30, 2022. The contract duration is 550 calendar days. The project value is between $25-100 million. The NAICS code is 236220 with a $39.5 million size standard. The solicitation requires adherence to brand name products including an Advantor security system, Andover DDC software, Marshall Best security keys and cores, and Monaco Vulcan fire alarm panels.

View the file

Other files for this federal contract opportunity

Other files attached to F-35 THREE BAY SPECIALIZED HANGAR, newest first.
File Type Posted
02_ITEM 01.2-2_ADD 04_Section 04 20 00.pdf PDF
04_ITEM 01.2-4_ADD 04_Section 07 24 00.pdf PDF
10_ITEM 01.2-10_ADD 04_Section 32 13 14.13.pdf PDF
15_ITEM 01.3-5_ADD 04_02700SF105.pdf PDF
17_ITEM 01.3-7_ADD 04_02700SF503.pdf PDF
23_ITEM 01.3-13_ADD 04_02700A-503.pdf PDF
25_ITEM 01.3-15_ADD 04_02700ES101.pdf PDF
26_ITEM 01.3-16_ADD 04_02700EP102.pdf PDF
27_ITEM 01.3-17_ADD 04_02700EP701.pdf PDF
03_ITEM 01.2-3_ADD 03_Section 05 50 13.pdf PDF
09_ITEM 01.2-9_ADD 03_Section 26 05 26.00 40.pdf PDF
11_ITEM 01.3-1_ADD 03_02700G-002.pdf PDF
13_ITEM 01.3-3_ADD 03_02700C-401.pdf PDF
15_ITEM 01.3-5_ADD 03_02700C-404.pdf PDF
16_ITEM 01.3-6_ADD 03_02700C-601.pdf PDF
18_ITEM 01.3-8_ADD 03_02700SF103.pdf PDF
33_ITEM 01.3-23_ADD 03_02700IG-500.pdf PDF
34_ITEM 01.3-24_ADD 03_02700FX102.pdf PDF
36_ITEM 01.3-26_ADD 03_02700FA102.pdf PDF
MAT MGMT PPLAN_Approval for 3-Bay Hangar.pdf PDF
W50S9F22B0001 Solicitation - Ammend 0001.pdf PDF
01_FSB2020-270-00_WI-ANG_3-Bay_ADD NO. 02_2022.06.08_Narrative.pdf PDF
05_ITEM 01.2-4_ADD 02_Section 03 30 00.pdf PDF
06_ITEM 01.2-5_ADD 02_Section 04 20 00.pdf PDF
09_ITEM 01.2-10_ADD 02_Section 09 06 00.pdf PDF
10_ITEM 01.2-11_ADD 02_Section 11 94 10.pdf PDF
14_ITEM 01.2-15_ADD 02_Section 32 13 14.13.pdf PDF
15_ITEM 01.3-1_ADD 02_02700G-102.pdf PDF
16_ITEM 01.3-2_ADD 02_02700C-101.pdf PDF
19_ITEM 01.3-5_ADD 02_02700C-402.pdf PDF
20_ITEM 01.3-6_ADD 02_02700S-001.pdf PDF
28_ITEM 01.3-14_ADD 02_02700SF210.pdf PDF
29_ITEM 01.3-15_ADD 02_02700SF502.pdf PDF
30_ITEM 01.3-16_ADD 02_02700AD-101.pdf PDF
35_ITEM 01.3-21_ADD 02_02700A-402.pdf PDF
36_ITEM 01.3-22_ADD 02_02700A-500.pdf PDF
37_ITEM 01.3-23_ADD 02_02700A-501.pdf PDF
38_ITEM 01.3-24_ADD 02_02700A-702.pdf PDF
42_ITEM 01.3-28_ADD 02_02700ES101.pdf PDF
43_ITEM 01.3-29_ADD 02_02700EG101.pdf PDF
Bid Opening Directions.pdf PDF
02_ITEM 01.2-1_ADD 02_PROJECT TOC.pdf PDF
08_ITEM 01.2-9_ADD 02_Section 08 87 35.pdf PDF
17_ITEM 01.3-3_ADD 02_02700C-301.pdf PDF
27_ITEM 01.3-13_ADD 02_02700SF106.pdf PDF
F-35 3-Bay Hangar Site Visit Attendance.pdf PDF
Supplemental Site Visit Instructions.pdf PDF
ATTACHMENT 2 - Volume 4 - WI ANG F-35 3-Bay CD Specs ADD 01 (1 of 2).pdf PDF
ATTACHMENT 6 - 20220208 Single Source Determination - Marshall Best - Redacted.pdf PDF
ATTACHMENT 7 - 20220208 Single Source Determination - Monaco - Redacted.pdf PDF
Show all 50

F-35 THREE BAY SPECIALIZED HANGAR has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F-35 3-Bay Hangar, Solicitation # W50S9F-22-B-0001 Posted to SAM.Gov 05 May 22

Questions & Responses #1

Question Response

1.

I have a question regarding the translucent panel wall openings.

1) Will the openings be added to the window schedule on A/601, including the dimensions?

2) The floorplans do not reference the translucent panel openings. Will they be provided on additional floorplans?

Contract documents will be updated to provide dimensions for translucent panel wall openings on building elevations.

Please see Addendum No. 02.

2.

The Code Summary table on Sheet Number G-102 includes a reference to “Draft Curtains.”

We are unable to locate any draft curtains within the contract drawings.

Please confirm our interpretation of the solicitation; specifically, that draft curtains are not required.

Since the area of each aircraft servicing bay is less than 7,500 S.F. and all bays are separated by walls, draft curtains are not required. Contract documents have been updated to remove reference to draft curtains. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02 Architectural Plans, Sheet G-102.

3.

The Access Plan Sheet Number C-101 includes a note that states “Existing structure to be relocated prior to construction.”

Please confirm our interpretation of the solicitation; specifically, that the “existing structure to be relocated prior to construction” will be relocated by the Government.

Correct. This structure is intended to be removed by the Base prior to construction. Contract documents have been updated to provide clarification on this. This has been updated as part of Addendum No. 02, dated 8 June 2022.

Please see Addendum No. 02 Civil Plans, Sheet C-101.

4.

Sheet Number C-402 includes a pavement section for “Asphalt – Landside” and a pavement section for “Asphalt – Airside.” Each asphalt type has its own specification section.

Please clarify which type (pavement section) of asphalt is to be installed at each specific area labeled as “Proposed Bituminous Pavement” on Sheet Number C-401.

Contract documents have been updated to provide clarification. This has been updated as part of Addendum No.

02, dated 8 June 2022. Please see Addendum No. 02 Civil Plans, Sheet C-401.

5.

There are approximately five locations on Sheet Number C-601 where the Contractor will need to open-cut Mitchell St. (as well as patch the existing roadway) in order to construct the new below-grade site utilities.

Please provide details (i.e., composition, thickness, etc.) for the existing asphalt pavement and aggregate base course section that the Contractor is to assume in its bid.

Additionally, there are multiple locations on Sheet Number C-301 and Sheet Number C-601 where existing utilities are required to be removed and new utilities are required to be constructed below the area of bituminous pavement that extends from the new and existing PCC Pavement, just next to the other existing hangar building. If the bid option is not awarded, the Contractor will need to cut and patch this existing bituminous pavement in order to construct the new utilities.

Please provide details (i.e., composition, thickness, etc.) for the existing bituminous pavement and aggregate base course section that the Contractor is to assume in its bid.

Contract documents have been updated to provide existing pavement sections for Mitchell Street and the access taxi path (Bid Option). This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02 Civil Plans, Sheet C-402.

6.

Please confirm that Madison Gas and Electric (MG&E), not the Contractor, will be responsible for removal and restoration of any surfaces (grassed and/or paved) required to perform MG&E’s work.

Confirmed. MG&E is responsible for removal and replacement of any surfaces required to perform task.

7.

The description for Bid Item No. 0003 Option states, “Aircraft Rated Pavement, Add New Aircraft/Tug Road Tug Access.” It is unclear what specific work is to be included in this bid item.

Please clarify which work specifically on Sheet Number C-301 and Sheet Number C-401 is to be included in Bid Item No. 0003 Option.

Contract documents have been updated to provide clarification on Bid Options. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02 Civil Plans, Sheets C-301 and C-401.

8.

Certain work shown on Sheet Number C-301 and Sheet Number C-401 is labeled “OLI.”

Please clarify what “OLI” means.

Contract documents have been updated to provide clarification on Bid Options. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02 Civil Plans, Sheets C-301 and C-401.

9.

Sheet Number C-401 includes notes for the Contractor to provide “2’ Mow Strip.”

Please provide a detail with the requirements for the mow strip.

Contract documents have been updated to provide clarification on mow strip section. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02 Civil Plans, Sheet C-402.

10.

Sheet Number C-401 includes a note for the Contractor to provide a “Proposed Wall.”

Please provide a detail with the requirements for the proposed wall.

The proposed wall section shall be a 10-foot-tall, post and panel wall with three (3) sections of 12 feet each. Contract documents have been updated to provide clarification. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02 Civil Plans, Sheet C-401.

11.

Sheet Number FA101 and Sheet Number FA102 both include a note that states, “AED (Coord. Location).”

Please confirm our interpretation of this note; specifically, that the AED(s) and AED cabinet(s) will be furnished and installed by the Government; not the Contractor.

Contractor to provide AED in Corridor, Room 106. Contract documents have been updated to provide clarification. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02 Architectural Plans, Sheet A-103.

12.

Sheet Number EP601 includes symbols and notes for two “Portable Generators.”

Please confirm our interpretation; specifically, that the portable generator(s) will be furnished and installed by the Government; not the Contractor.

Confirmed. The portable generators are Government Furnished Government Installed (GFGI).

13.

Note 9 on Sheet Number ET101 states, “Cameras, mounts and cabling shall be provided in Bid Option #2. GC is responsible for coordinating with Advantor for cost of bid option.”

This note does not appear to coincide with the descriptions of the three bid items. Please clarify in which bid item these costs are to be included.

Contract documents have been updated to provide clarification on this scope of work. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02 Telecommunication Plans, Sheet ET101.

14.

The Technology Scope Responsibility Matrix on Sheet Number ET101 indicates that the electrical contractor is to furnish and install “TV outlets, mounts, displays and cabling.”

Additionally, Keynote 11 on Sheet Number A-103 states, “86” TV.”

The TV's and TV mounting brackets are to be provided by the Government and have been included in the Furniture, Please confirm that the Government does, in fact, intend for the electrical contractor to be responsible for providing TV mounts and TV displays (“86” TVs”). If so, please provide details and/or specifications for the TV mounts and TV displays that are to be provided.

Fixtures & Equipment Package Final Submission, dated 28 January 2022.

15.

Please clarify if the “Digital Meter [DM]” indicated on the secondary feeder side of the new pad-mounted transformer on Sheet Number EP601 is to be provided by MG&E or the Contractor.

DM is integral to the switchboard and is to be Contractor Furnished Contractor Installed. Contract documents have been updated to provide clarification on this scope of work.

This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02 Electrical Plans, Sheet EP601.

16.

Keynote 4 on Sheet Number ES101 states, “Proposed location of building fire pumps XFMR.”

Keynote 5 on Sheet Number ES101 states, “Proposed routing of conduit from building fire pumps XFMR to fire pump controllers in fire riser room.” However, the “FX” drawings and the Division 21 specification sections do not include a requirement for the Contractor to provide a fire pump.

Please confirm our interpretation of the contract documents; specifically, that the Contractor is not required to provide a fire pump.

Confirmed. A fire pump is not required. Contract documents have been updated to remove reference to fire pumps. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02 Electrical Site Plans, Sheet ES101.

17.

The Code Summary on Sheet Number G-102 references a “Low-Level High Expansion Foam System Preaction Pipe Sprinkler System” for the “Aircraft Servicing Areas.” However, the “FX” drawings and the Division 21 specification sections do not require a high expansion foam system to be provided.

Please confirm our interpretation of the contract documents; specifically, that the Contractor is not required to provide high expansion foam system(s).

Confirmed. Contractor is not required to provide a HEF system. Wet pipe system was added in luei of HEF System in Addendum No. 01, dated 22 April 2022. Contract documents have been updated to remove reference to HEF system. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02 Architectural Plans, Sheet G-102.

18.

Keynote 8 on Sheet Number A-103 states, “Weapons Load Trailer.”

Please confirm our interpretation; specifically, that the weapons load trailer(s) are Government-Furnished, Government-Installed (GFGI).

Confirmed. The Weapons Load Trailer noted is GFGI.

19.

Keynote 21 on Sheet Number MH103 states, “Owner Furnished, Contractor Installed (Relocated) Breathing Air Apparatus.”

Please provide information/details on the existing breathing air apparatus.

Existing Breathing Air Apparatuses are to be removed and salvaged for re-use in new facility. Breathing Air Apperatus is RhineAir, Model NF23-1.

20.

Note 2 within the Paint Booth Make-Up Air Unit Schedule on Sheet Number M-703 states, “The unit shall be purchased from the Owner’s selected paint booth provider.”

Note 3 states, “Unit controls shall be as required to be configured by the Owner-selected paint booth provider to accommodate the required modes of operation.”

Note 4 states, “Unit configuration shall be as required by the Owner-selected paint booth provider.”

Please provide all information and details for the Owner’s selected paint booth. Also, please provide contact information for the Owner’s selected paint booth provider.

Paint Booth will not be delivered as part of this contract

For Reference, Gov't preferred paint booth company:

ICAFe, Inc.

W223N790 Saratoga Dr.

Waukesha, WI 53186 Office: (262) 970-7153

Fax: (262) 970-7160

Reference: Budget Quotation No.: W20-3479-10009-115FW

21.

The “Furniture & Equipment Schedule 1 – Bid Option 1” on Sheet Number A-702 lists “EQ4 – Full Size Refrigerator w/ Ice & Water,” “EQ10 – Freezer,” “EQ11 – Downdraft Multi-Slotted Vent Table,” and “EQ12 – Downdraft Slotted Vent Table.”

General Note A on Sheet Number IF-101 states, “All furniture and equipment are shown for coordination only and are not included in this package.”

Please clarify if the furniture and equipment listed on Sheet Number A-702 (i.e., EQ4, EQ10, EA11, and EA12) are to be furnished and installed by the Government or are to be furnished and installed by the Contractor.

EQ11 and EQ12 will be provided by contractor, remainng Government Furnished items on Furniture, Fixtures & Equipment Package Final Submission, dated 28 January 2022, will not be part of this contract.

22.

Section 07 61 14.00 20 Steel Standing Seam Roofing is included in the specifications;

however, we cannot locate any steel standing seam roofing within the contract drawings.

Please clarify if this specification section is applicable to the project.

Confirmed. There is no standing seam metal roof.

Specification Section 07 61 14.00 20 has been removed from the contract documents. This has been updated as part of Addendum No. 02, dated 8 June 2022.

23.

Subpart 1.6.9c of Section 03 30 00 states, “Contractor Quality Control: All sampling and testing must be performed by an approved, onsite, independent, accredited laboratory.”

Additionally, Subpart 1.4.3.3 of Section 32 13 14.13 states, “All sampling and testing is required to be performed by an approved, ON-SITE, independent, commercial laboratory, or for cementitious materials and admixtures, the manufacturer’s laboratory.”

Please clarify whether the Contractor is required to provide and maintain ONSITE validated testing laboratories, or if the Contractor is allowed to utilize offsite testing laboratories (which is more common for a project of this size and magnitude) during the performance of the contract.

Contractor is allowed to utilize an off-site testing laboratory.

Spec section 03 30 00 Subpart 1.6.9.c will be updated.

Contract documents have been updated to provide clarification. This has been updated as part of Addendum No.

02, dated 8 June 2022. Please see Addendum No. 02, Specification Section 03 30 00, Subpart 1.6.9.c.

24.

Subparts 3.2 and 3.2.1 Availability and Use of Utility Services, Temporary Utilities states, “Provide temporary utilities required for construction.”

Will the Contractor be required to pay for temporary utilities (usage fees) (i.e., water, sewer, electrical, natural gas) during construction, or will the Government provide usage of these temporary utilities (usage fees) at no cost to the Contractor?

Contractor will not be required to pay for temporary utilities, however government expects contractor to be frugale/responsible in spending tax payers money on utilities provided.

25.

Subpart 3.4.2 Storage Area of Section 01 50 00 requires the temporary chain link fence to have “plastic strip inserts” installed in the temporary fencing. Most fencing contractors and suppliers no longer provide plastic strip inserts; however, provide a more-efficient and equally-effective option of wind screen.

Will the Government allow wind screen in lieu of the specified “plastic strip inserts?”

Also, would the Government please consider omitting the requirement for any type of screening in the temporary fencing altogether?

Plastic inserts are not required. However, material uilitzed must ensure appropriate FOD mitigation is maintained.

26.

Subpart 1.7.2b of Section 01 91 00.15 10 requires the Electrical Technical Commissioning Specialist duties to “be performed by an engineering technician certified by the InterNational Electrical Testing Association (NETA) with five years of experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices.”

The requirement for the Electrical Technical Commissioning Specialist to be NETA-certified is very restrictive and will eliminate most qualified commissioning firms from being able to bid the project, since most commissioning firms do not have individuals who are NETA-certified.

It is common for the Government to allow the Electrical Technical Commissioning Specialist to have other commonly-recognized qualifications, other than a NETA certification.

Will the Government allow the commissioning firm to utilize an Electrical Technical Commissioning Specialist with qualifications other than a NETA certification?

Allowing alternative qualifications will result in much more competitive pricing without compromising quality or performance.

All Electrical system Commisioning shall be done by NETA- Certified individuals.

27.

Section 08 87 35 Architectural Window Film is listed in the Project Table of Contents of the specifications; however, the section is missing from the specifications.

Please provide Section 08 87 35 Architectural Window Film.

This is a substantial additional cost that the Contractors need to know whether or not to include in their bid amounts.

Contract documents have been updated to provide requirements for Architectural Window Film. This has been updated as part of Addendum No. 02, dated 8 June 2022.

Please see Addendum No. 02, Specification Section 08 87 35.

Additionally, dimensions have been added to C4/A-402 and B1/A-402 Interior Elevations for additional clarification. See Privacy Film (PRF) referenced on A-601, A-402 and Finish Legend A-602. Privacy Film is Architectural Window Film.

This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02 Architectural Plans, Sheet A-402.

28.

Subpart 2.3 Transition Membrane in Section 07 27 26 references, “Section 07 27 19.01 Self- Adhering Air Barriers.”

Section 07 27 19.01 is not included in the specifications.

Please provide Section 07 27 19.01.

Contract documents have been updated to remove reference to 07 27 19.01 from Specification Section 07 27 26. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02, Specification Section 07 27 26.

29.

Subpart 2.1.1.3 Cathodic Protection of Section 46 25 14 references, “Section 26 42 13 Galvanic (Sacrificial) Anode Cathodic Protection (GACP) System.”

Section 26 42 13 is not included in the specifications.

Please provide Section 26 42 13.

Contract documents have been updated to provide requirements for GACP System noted. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02, Specification Section 26 42 13.

30.

Sheet Numbers C-301 and C-601 indicate certain electrical service demolition and new work activities that the Contractor is required to “Coordinate with Madison Gas and Electric”

(MG&E).

All work will be performed and paid for by MG&E, except for possible associated fees that the contractor will be responsible to pay MG&E. Contractor shall coordinate with

General Note A on Sheet Number ES101 states, “Utility company is responsible for primary side of transformer conduit and conductors, transformer, transformer pad, secondary side of transformer conduit, conductor and final terminations to disconnecting means in main switchboard.”

General Note A on Sheet Number ED101 states, “Utility company is responsible for demo of primary side of transformer conduit and conductors, transformer, transformer pad, secondary side of transformer conduit, conductor and final terminations to disconnecting means in main switchboard.”

Will the work (demolition and new work) indicated to be the responsibility of MG&E be contracted and paid for by the Government directly with MG&E, or will the Contractor be required to contract with and/or pay for the work indicated to be the responsibility of

MG&E?

MG&E. Contract documents have been updated to provide clarification. This has been updated as part of Addendum No.

02, dated 8 June 2022. Please see Addendum No. 02 Electrical Plans.

31.

Section 01 78 00 does not include any requirements for the Contractor to provide Record Drawings (see Subpart 3.2); only to provide As-Built Drawings, the “red-lined hard copies on site and red-lined PDF files” (see Subpart 3.1).

Please confirm our interpretation of the specifications; specifically, that the Contractor is not required to prepare and submit Record Drawings.

If our interpretation is incorrect, please clarify what type of Record Drawings are to be provided; for example, AutoCAD, BIM, etc.

Confirmed. Contractor is not required to provide Record Drawings. Contract documents have been updated to remove reference to Record Drawings in Specification Section 01 78 00. This has been updated as part of Addendum No.

02, dated 8 June 2022. Please see Addendum No. 02, Specification Section 01 78 00.

32.

Subpart 3.5 Government Field Office of Section 01 50 00 specifies requirements for the Contractor to “Provide the Government with an office” at the project site with certain provisions and utility connections.”

Please confirm that the Government will in fact require the Contractor to provide an office for the Government.

Contractor is not required to provide a Field Office for the Government. Contract documents have been updated to remove requirements for Government Field Office in Specification Section 01 50 00. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02, Specification Section 01 50 00.

33.

Please confirm that the Air Barrier Inspector specified in Subpart 1.7 of Section 07 27 10.00 10 must be an independent third-party entity and cannot be employed by the air barrier subcontractor.

Confirmed. Inspector shall be independent third party per 1.7.

34.

Please confirm that Section 09 97 13.27 High Performance Coating for Steel Structures is only applicable to the Fuel Cell 119, Wash Bay 128, and Weapons Training 101 hangar areas of the buildings

Confirmed.

35.

Subpart 1.1 Unit Prices of Section 02 65 00 Underground Storage Tank Removal states, “Assume, for bidding purposes, that soil bituminous pavement, concrete slabs, and water encountered during the removal of the underground tanks are contaminated with JP-5 fuel oil and diesel fuel and gasoline to be handled as specified herein. Payment for removal from temporary stockpile and disposal of contaminated soil and furnishing clean soil will be paid for at the contract unit price per cubic yard.”

The bid pricing schedule does not include any unit priced items as stated in Subpart 1.1.

It is the Government's intent that Lump Sum pricing is included as part of base bid.

Please clarify what quantities, for the work specified in Subpart 1.1, that the Contractors are to include in their bid. Additionally, will the Government be adding unit priced items to the bid pricing schedule to address this requirement?

36.

A review of the “Soils/Foundation Notes” on Sheet Number S-001 reveals that the Government has concerns over the suitability of the existing soils materials below the building footprint and throughout the project site.

Soils/Foundation Note 6 on Sheet Number S-001 states, “Stripping and undercutting shall extend a minimum of 5 feet beyond the building perimeter and the depth shall be as determined by the Geotechnical Engineer.” Additionally, Note 9 states, “After inspection of the subgrade, structural fill material shall be placed in lifts between 6 and 12 inches.

1) Please clarify what depth of stripping and undercutting and replacement with compacted structural fill (below the building footprint and extending 5 feet beyond the building perimeter), if any, the Contractors are to assume and include in their bids. This is a potential substantial cost that the Contractors need to understand what quantity, if any, to include in their bids.

Soils/Foundation Note 7 on Sheet Number S-001 states, “After stripping the site but prior to placing fill the site shall be compacted. Any areas of significant deflection during compaction may be disked, dried, and re-compacted if weather permits, or removed and replaced with engineered fill.” Note 7 continues by requiring the identification of soft or unstable areas (during proof-rolling) and subsequent remediation procedures for “soft areas of subgrade that deflect more than 1 inch or show permanent deformation greater than 1 inch.” Additionally, Note 9 states, “After inspection of the subgrade, structural fill material shall be placed in lifts between 6 and 12 inches.

2) Please clarify what volume (depth and area) of undercutting and replacement with compacted engineered fill (of the site), if any, the Contractors are to assume and include in their bids. This is a potential substantial cost that the Contractors need to understand what quantity, if any, to include in their bids.

Note 10 states, “The Geotechnical Engineer shall provide recommendations for suitable types of engineered fill. Where unsuitable soils are encountered at the base of the foundations, soil correction should consist of additional excavation to remove the unsuitable soils to a depth determined by the Geotechnical Engineer. These over excavations shall be filled with engineered fill as given in Note 9. Alternatively a lean concrete with a minimum compressive strength of 500 psi can be used to fill the over-excavation to the bottom of the foundation.”

3) Please clarify what volume of removal of unsuitable soils and replacement with compacted engineered fill or lean concrete (below the base of foundations), if any, the Contractors are to assume and include in their bids. This is a potential substantial cost that the Contractors need to understand what quantity, if any, to include in their bids.

Undercut amount and soil characteristics to be determined by Contractor from information provided in contract documents and the geotechnical report for the project.

Geotechnical report will be provided for use and review.

Government is considering this pay item as a Lump Sum.

Subpart 1.3d “Criteria for Bidding” of Section 31 00 00 states, “Material character is indicated by the boring logs.”

According to the Site Characterization Report included in Section 02 61 13, Boring Numbers AA-MW-1 and AA_MW-2 indicate that the first approximately five feet (5’) consists of silty sand (SM), a combination of fill and silty sand (SM), clayey sand (SC), and lean clay (CL).

Poorly graded sand (SP) begins at a depth of approximately five feet (5’).

Boring Number AA-MW-3 indicates that the first approximately five feet (5’) consists of silty sand (SM), a combination of fill and clayey sand (SC), silt (ML), and lean clay (CL). Poorly grade sand (SP) begins at a depth of approximately five feet (5’).

Boring Numbers AA-MW-4 and AA-MW-5 indicate that the first approximately five feet (5’) consists of silty sand (SM), a combination of fill and silty sand (SM), and a combination of fill and clayey sand (SC). Poorly grade sand (SP) begins at a depth of approximately five feet (5’).

Subpart 1.5.1 “Satisfactory Materials” of Section 31 00 00 states, “Satisfactory materials comprise any materials classified by ASTM D2487 as GW, GP, GM, GP-GM, GW-GM, GC, GP-

GC, GM-GC, SW, SP.”

Subpart 1.5.2 “Unsatisfactory Materials” of Section 31 00 00 states, “Materials which do not comply with the requirements for satisfactory materials are unsatisfactory.”

According to the boring logs and Subpart 1.5.1, “Satisfactory Materials” are not present until approximately five feet (5’) below existing finish grade and, therefore, according to Subpart 1.5.2, the first five feet below finish grade would be considered “Unsatisfactory Materials.”

Subparts 3.7 and 3.7.1 “Ground Surface Preparation, General Requirements” of Section 31 00 00 states, “Remove and replace unsatisfactory material with satisfactory materials, as directed by the Contracting Officer, in surfaces to receive fill or in excavated areas.”

Subparts 3.13 and 3.13.2 “Subgrade Preparation, Construction” of Section 31 00 00 states, “Remove soft of otherwise unsatisfactory material and replace with satisfactory excavated material or other approved material as directed.”

4) Please clarify whether or not it is the Government’s intent that the Contractor is to consider the first approximately five feet (5’) of the existing soils to be “Unsatisfactory Material” and whether or not the Contractors are to include the costs in their bids to remove (undercut) and dispose of this existing material (“Unsatisfactory Material”) and replace with selected fill (“Satisfactory Material”) throughout the project site. This is a substantial cost that the Contractors need to know whether or not to include in their bid amounts.

37.

Soils/Foundation Note 1 on Sheet Number S-001 states, “Foundation recommendations are based on the geotechnical report prepared by Gestra dated September 10, 2020 . . .”

Subpart 1.6 of Section 31 00 00 states, “Subsurface soil boring logs are available upon request. The subsoil investigation report and samples of materials taken from subsurface investigations may be examined at the contractor’s request.”

Geotechnical report will be provided for use and review.

Please provide a copy of the geotechnical report prepared by Gestra dated September 10, 2022, as well as any other pertinent subsurface soil boring logs and subsoil investigation reports.

38.

Subpart 3.2.4 of Section 31 00 00 states, “The water level encountered during subgrade investigations was approximately 4.5 feet. If ground water is encountered, treatment for PFAS may be required.”

Please clarify if the Contractor is to include costs in its bid for the potential treatment for PFAS (of encountered ground water) that “may be required,” or if the Contractor should assume that a modification will be issued if treatment for PFAS (of encountered ground water) is actually required.

If the Government intends the Contractor to include costs in its bid for the potential treatment for PFAS (of encountered ground water), please clarify what quantity of treatment for PFAS (of encountered ground water) the Contractor is to assume in its bid.

This is a potential substantial cost that the Contractors need to understand what quantity, if any, to include in their bids.

Contractor should not include costs for environmental remediation associated with PFAS-contaminated groundwater as part of the base bid. The Environmental Materials Management Plan (to be provided) states soil will be stock piled/treated on base at the 115 FW. If dewatering is required the permit won't has PFAS in it. Therefore anything deviation from the plan would be part of a contract action in the future.

39.

Subpart 1.3 Description of Work of Section 02 61 13 Excavation and Handling of Contaminated Material states, “The work consists of excavation and temporary storage of approximately 25 cubic yards of contaminated material, including contaminated soil . . .”

Please confirm our interpretation of the contract documents; specifically, that the Contractor is only required to assume and include a total of 25 cubic yards of contaminated material (contaminated soil) removal (excavation and temporary storage), hauling, disposal, and replacement (with suitable backfill material) in its bid for this project, and that, if additional contaminated material is discovered, the Government will issue a modification for additional contaminated soil removal, handling, hauling, disposal, and replacement with select fill.

Provide pricing as Lump Sum included in the base bid.

40.

Subpart 1.5.9 Surface Smoothness of Section 32 12 16.16 of the specifications specifies that “Straightedge Testing” shall be performed on the finished surfaces of the pavements.

However, it appears that a reference to the “profilograph” method was erroneously left in Subpart 1.5.9.2 Testing Method.

According to Unified Facilities Guide Specifications (UFGS), the profilograph method cannot be used for paving lanes less than 0.25 miles in length and states to “use the straightedge method for transverse testing, for longitudinal testing where the length of each pavement lane is less than 0.25 miles, and at the ends of the paving limits for the project.”

Please confirm that only straightedge testing will be required for surface smoothness testing.

Correct. Only straightedge testing will be required. The profilograph has been omitted. Contract documents have been updated to remove reference to profilograph from Specification Section 32 12 16.16. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02, Specification Section 32 12 16.16.

41.

The specifications for this project include Section 07 61 14.00 20 Steel Standing Seam Roofing We are unable to locate any steel standing seam roofing on this project.

Please confirm our interpretation that steel standing seam roofing is not required.

Confirmed. There is no standing seam metal roof.

Specification Section 07 61 14.00 20 has been removed from the contract documents. This has been updated as part of Addendum No. 02, dated 8 June 2022.

42.

Subparts 1.1.2 and 1.1.2.1 Payment, Excavation and Transportation of Section 02 61 13 Excavation and Handling of Contaminated Material states, “Compensation for excavation and onsite transportation of contaminated material will be paid as a unit cost. This unit cost shall include any other items incidental to excavation and handling not defined as having a specific unit cost.”

Additionally, Subparts 1.1.2 and 1.1.2.2 Payment, Backfilling of Section 02 61 13 states, “Compensation for backfill soil, transportation of backfill, backfill soil conditioning, backfilling, compaction, and geotechnical testing will be paid as a single unit cost.”

Further, Subparts 1.1.2 and 1.1.2.3 Payment, Stockpiling of Section 02 61 13 states, “Compensation for construction of stockpile areas will be paid for as a unit cost. This unit cost shall include all aspects of grading, preparation, handling, placement, maintenance, removal, treatment, and disposal of stockpile cover materials and liner materials and all other items incidental to construction of stockpile.”

The bid pricing schedule does not include any unit priced items as stated in Subparts 1.1.2 through 1.1.2.3 of Section 02 61 13. Will the Government be adding unit priced items to the bid pricing schedule to address this requirement?

It is the Government's intent to provide this item as Lump Sum in the base bid.

43.

Item 11 on the Standard Form 1442 and Contract Clause 52.211-10 states that the contract performance duration is only 550 calendar days (approximately 18 months). We are requesting that the Government please consider increasing the duration by 12 months for the reasons discussed below.

The bid due date is currently 15 June 2022 and the Government is requiring an acceptance period of 180 calendar days. This means that the contract will likely be awarded during, or just prior to, the winter season. The winter weather conditions will prohibit, or greatly limit, the Contractor from performing many of the major earthwork activities that must be performed to prepare the project site for construction of the new concrete building foundations. The Contractor will likely not be able to make substantial progress on the major earthwork and concrete foundations activities until Spring of 2023, unless substantial costs are expended utilizing ground thaw provisions and winter-concrete provisions; both of which will only substantially increase the overall price of the project for the Government.

Also, before the earthwork activities can begin, the Contractor has hazardous material abatement work to perform, as well as major demolition of the entire existing Building 414;

both of which will require substantial time to perform.

As the Government is aware, the Contractors are also still faced with long lead-times for certain key building materials, such as structural steel, steel roof deck, insulated metal wall panels, roof deck insulation, etc. Extended durations to fabricate and delivery these items

Contracts period of performance WILL NOT be changed.

directly impacts the Contractor’s ability to construct the building structure and ‘dry in’ the building envelope to allow the interior work to progress.

Additionally, the development of a concrete mix design required by Section 32 13 14.13 “Concrete Paving for Airfields and Other Heavy Duty Pavements” typically requires approximately 12 months in order to complete the proportioning studies and prepare the mix design for the Government 30-day review and approval, which is then followed by key, time-consuming quality control activities before production paving can begin. It will be a challenge to obtain an approved mix design and construct the airfield concrete paving for the new PCC pavement (apron area) and three hangar floor slabs before the onset of the second winter season in late 2023; as it is not possible at all to expedite the concrete mix design process due to the strict prescriptive requirements in Section 32 13 14.13. Also, due to the stringent weather and environmental requirements contained within Section 32 13 14.13, the Contractor will likely have to wait until the Spring season of 2024 to construct the airfield concrete paving for the new PCC Pavement and three hangar floor slabs, or be faced with substantial costs for utilizing ground thaw provisions and winter-concrete provisions;

both of which will only substantially increase the overall price of the project for the Government. It should be noted that there is a substantial amount of work that still must be performed within the hangar bays after the hangar floor slabs are constructed.

The specifications also include time-consuming start-up and testing requirements for this project, which are typical for a Federal Government project of this size and complexity (i.e., fire suppression, plumbing, mechanical, building automation, electrical, fire alarm and mass notification, and security system start-ups; performance verification testing (PVT); testing, adjusting, and balancing (TAB); total building commissioning (both pre-FPT and FPT) of the numerous systems required by Section 01 91 00.15 10; and both the preliminary and final testing requirements for the fire suppression systems and fire alarm and mass notification system). Also taking into consideration the items discussed above, it will be a challenge to complete all of the work and the start-up and testing requirements within the only 550 calendar day duration due to the prescriptive sequencing and scheduling requirements for these tests contained throughout the specifications.

As mentioned above, we are requesting that the Government please consider increasing the duration by 12 months for these reasons. If the contract duration is maintained at only 550 calendar days, it will require extensive expediting fees and a considerable amount of overtime to complete the contract within the 550 calendar days. This will simply result in increased costs to the Government.

44.

Will the Government please provide the bidders with copies of all available as-built drawings for existing Building 414?

As-built drawings can be provided to successful bidder.

45.

Is the Contractor required to install the “Fuel Resistive Resinous Flooring, 5-Coat System” on the vertical concrete wall faces and bottom face of the trench drains (see D1/SB502, B1/SB502, and A3/SB502) located in the Weapons Training 101, Fuel Cell 119, and Wash Bay 128?

The Fuel Resistive Resinous Flooring, 5-Coat System does need to be installed on the vertical concrete wall faces and bottom face of the trench drains in Weapons Training 101, Fuel Cell 119, and Wash Bay 128.

46.

Subpart 3.5 “Government Field Office” of Section 01 50 00 “Temporary Construction Facilities and Controls” does not list telecommunications (telephone, internet, cable TV, etc.) as temporary utilities that the Contractor is required to provide for the Government Field Office.

Please clarify if the Contractor will also be required to provide telecommunications (telephone, internet, cable TV, etc.) of any specific type for the Government Field Office, or if the Government will leave this requirement omitted from the list of required temporary utilities.

Contractor is not required to provide a Field Office for the Government. Contract documents have been updated to remove requirements for Government Field Office in Specification Section 01 50 00. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02, Specification Section 01 50 00.

47.

Subpart 3.5 “Government Field Office” of Section 01 50 00 “Temporary Construction Facilities and Controls” does not specify that the Contractor will be required to provide janitorial services for the Government Field Office.

Please clarify if the Contractor will also be required to provide janitorial services for the Government Field Office, or if the Government will leave this requirement omitted from the specification. If the services are required, please clarify how often the services will be required.

Contractor is not required to provide a Field Office for the Government. Contract documents have been updated to remove requirements for Government Field Office in Specification Section 01 50 00. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02, Specification Section 01 50 00.

48.

Part 1 “General” of Section 06 73 01 “Fiberglass Reinforced Plastic (FRP) Grating” states, “This Section includes, but is not limited to, new fiberglass reinforced plastic (FRP) grating for elevated platforms and walkways.”

Please clarify where specifically the FRP Grating is required to be provided. The “Typ Mechanical Platform Guardrail Section” A1 on Sheet Number SF504 indicates that “1/4” Checkered Steel Plate” is to be provided; not FRP Grating.

FRP grating is not required on the project. Specification Section 06 73 01 has been removed from the contract documents. This has been updated as part of Addendum No.

02, dated 8 June 2022.

49.

Sheet Number C-301 shows two parallel light gray dotted lines routed from the Existing Building 414, continuing towards the plan Northwest, and then continuing towards the plan North. Sheet Number C-401 reflects the same two parallel lines. During the pre-bid site visit, there was evidence of saw cutting and sealant (of some unknown type) within the existing concrete and asphalt pavements following this approximate route. Since the existing concrete and asphalt pavements are indicated to be demolished, it is assumed that whatever this item is will also be demolished with the pavement.

Will the Government please clarify what these two parallel lines represent?

Please confirm our interpretation of the contract drawings; specifically, that the Contractor will have no responsibility to replace whatever these two lines represent.

Correct. These are existing fiber optic lines with backer rod and sealant. This will be removed at any location where pavement is indicated to be removed. Replacement is not required.

50.

Slab Plan Note 1 on Sheet Numbers SB105 and SB106 states, “11” Concrete Pavement (Flex Strength = 650 PSI at 90 Days) Reinf w/ #4 at 8” OC EW . . .” This note applies to the Weapons Training 101, Fuel Cell 119, and Wash Bay 128.

Will the Government please confirm that Section 03 30 00 Cast-In-Place Concrete (not Section 32 13 14.13 Concrete Paving for Airfields and Other Heavy Duty Pavements) is the specification section applicable to the concrete pavement work in the Weapons Training 101, Fuel Cell 119, and Wash Bay 128?

Confirmed. Specification Section 03 30 00 contains the applicable requirements for 11-inch-thick, concrete slabs within Weapons Training, Room 101; Fuel Cell, Room 119;

and Wash Bay, Room 128.

51.

Please confirm our interpretation of the specifications; specifically, that the Contractor is only required to assume the quantities of “Non-friable Category I and Category II ACM” and “RACM” listed on Pages 2 and 3 of 5 of the Ayres letter dated 29 July 2020, which is included as the “02 61 13 _02 Final Asbestos Report (072920)” in Volume 1 of the specifications, are required to be abated and that any additional asbestos abatement will be considered a change to the contract.

Asbestos removal will be Lump Sum as part of the Base Bid based upon the study.

52.

Sheets A-201 & A-202 Building Elevations refer to “color #1” and “color #2” for the vertical and horizonal insulated metal wall panels and well as split-faced “colored” CMU. However, no color schedule or reference to any of the exterior finishes can be located. Please provide the exterior finish schedule.

Contract documents have been updated to provide exterior finish/color information. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02, Specification Section 09 06 00.

53.

Subpart 3.6 Test Section of Section 32 12 15.13 Asphalt Paving for Airfields states, “Prior to full production, place a test section for each JMF used. Construct a test section 250 to 500 feet long and two paver passes wide with a longitudinal cold joint.”

There appears to be a minimal amount of airfield asphalt pavement on this project for which Section 32 12 15.13 is applicable. There is no area of new airfield asphalt paving that is 250 to 500 feet long. Additionally, two paver passes wide would complete a substantial majority, if not all, of the new airfield asphalt paving required for the entire project.

Will the Government please consider waving the requirement for the “Test Section” associated with the asphalt paving for airfields?

Contract documents have been updated to remove requirements for test section from Specification Section 32 12

15.13. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02, Specification Section 32 12 15.13.

54.

Section 32 13 14.13 Concrete Paving for Airfields and Other Heavy Duty Pavements of the specifications includes requirements for a project-specific mix design, with the Contractor performing deleterious testing and alkali-silica reactivity (ASR) testing of aggregates, proportioning studies, trial mixture studies, and uniformity testing for its proposed mix design. These tests amount to costs in excess of $50,000 and, for a relatively small quantity of airfield pavement (PCC Pavement) and hangar floor slab pavement, it would be much more cost-effective if the Government were to provide bidders with an option to use a previously-approved mix design(s) that has been successfully utilized on other projects at Truax Field ANGB. It is understood that the Government requires a quality product for the concrete paving and we believe this would be a more cost-effective way to achieve that end result.

Additionally, Subpart 1.4.4 “Preconstruction Testing of Materials” of Section 32 13 14.13 states, “All sampling and testing is required to be performed” and “Materials are not allowed to be used until notice of acceptance has been given. Additional payment or extension of time due to failure of any material to meet project requirements, or for any additional sampling or testing required is not allowed.” Subpart 1.4.4.1 “Aggregates” of Section 32 13 14.13 states, “Perform all aggregate tests no earlier than 120 days prior to contract award.” Based on experience on past projects and the required testing sequence for aggregate testing (ASR / deleterious testing), proportioning study, trial mixes (with 90-day breaks), uniformity testing, and Government-approvals for each, the total time to perform pre-construction testing is approximately 12 months. Due to the extremely short contract duration (550 calendar days), it will be extremely difficult to perform all preconstruction testing of materials, proportioning studies, trial mixture studies, and uniformity testing and leave adequate time for construction of the airfield pavement and the subsequent construction activities.

A mix design will be provided upon award by the Base to be utilized for the PCC apron paving.

Will the Government please provide the mix design company and mix design number of an acceptable previously-approved mix design(s) that will be acceptable for the Contractor to utilize for the project? Note, due to the limited size of paved areas, it is anticipated most, if not all, of the concrete paving will be performed by fixed forms; therefore, please provide previously-approved mix design(s) for slip-form and fixed form paving methods.

55.

Please confirm that the CQC System Manager specified by Subpart 1.4.1a of Section 32 13

14.13 Concrete Paving for Airfields and Other Heavy Duty Pavements of the specifications can be the same individual as the CQC System Manager specified by Subpart 3.4.2 of Section 01 45 00.00 10 of the specifications.

Correct. This may be the same individual.

56.

Please confirm that the Airfield Asphalt Pavement QC Manager specified by Subpart 1.5a of Section 32 12 15.13 Asphalt Paving for Airfields of the specifications can be the same individual as the CQC System Manager specified by Subpart 3.4.2 of Section 01 45 00.00 10 of the specifications.

Correct. This may be the same individual.

57.

Subpart 1.4.6.1 “Pilot Lane (Test Section)” and Subpart 1.4.6.2 “Fill-In Lane (Test Section)” of Section 32 13 14.13 Concrete Paving for Airfields and Other Heavy Duty Pavements of the specifications require the Contractor to construct a pilot lane test section of at least 200 feet long and a fill-in lane test section 400 feet long as part of the production paving area. Due to the relatively small size of the project, this is not possible.

Contract documents have been updated to remove requirements for test section from Specification Section 32 13

14.13. This has been updated as part of Addendum No. 02, dated 8 June 2022. Please see Addendum No. 02, Specification Section 32 13 14.13.

58.

As it relates to the pilot lane test section, there are no lanes that are 200 feet long. Also, a 200-foot-long pilot lane test section would be approximately thirty percent (30%) of the entire area of PCC pavement required for the project.

As it relates to the fill-in lane test section, the project does not even contain 400 feet of production fill-in lanes that can utilize two adjacent existing lanes as forms. Also, 400 feet of fill-in lane test section would be another approximately sixty percent (60%) of the entire area of PCC pavement required for the project.

Collectively, the specified pilot and fill-in lane test sections would be greater than ninety percent (90%) of the entire area of PCC pavement required for the project.

Will the Government please revise the specifications to remove the requirements for the test sections (pilot lane and fill-in lane) given the small amount of concrete paving on the project? If the Government determines test section(s) are required, please provide reduced requirements consistent with the size of the paving scope and confirm that test section(s) may be part of the completed work if they meet specified requirements.

Contract documents have been updated to remove requirements for test section (pilot lane and fill-in lane) from…