This document provides details for an unrestricted invitation for bid for the construction of an F-35 three bay specialized hangar. Key requirements include the complete demolition of an existing building and construction of a new three bay hangar facility totaling 31,000 square feet to support fuel cell operations, indoor wash capabilities, squadron level surface coating operations, and weapons load training. The facility must meet various technical specifications including pre-conditioned aircraft air, 270 VDC aircraft power, and fire suppression. The contract value is estimated between $25-100 million. Interested parties must register in the System for Award Management and the pre-bid conference will be held on-site at Truax Field in Madison, Wisconsin. The bid opening will follow standard FAR procedures and award will be made to the responsive and responsible lowest bidder. The North American Industry Classification Code is 236220 and the period of performance is 550 calendar days from notice to proceed.
View the file
Other files for this federal contract opportunity
Show all 50
F-35 THREE BAY SPECIALIZED HANGAR has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For the best experience, open this PDF portfolio in
Acrobat X or Adobe Reader X, or later.
Get Adobe Reader Now!
http://www.adobe.com/go/reader
From: Ales, Stephen M -DNR To: DUNLAP, MICHAEL J Lt Col US Air Force ANG 115 CES/CC; HINMAN, MICHAEL T GS-12 USAF ANG 115
CES/Architect Subject: [Non-DoD Source] FW: MMP Approval for 3-Bay Hangar Date: Tuesday, November 2, 2021 9:41:10 AM Attachments: image001.png image002.png image003.png image004.png image007.png
Mike and Mike:
Here is the email I sent yesterday afternoon for the 3-Bay Hangar. I don’t know why this and the B401 didn’t go through. I will send that one next. I’ll call or text to confirm this went through.
Steve
From: Ales, Stephen M -DNR <stephenm.ales@wisconsin.gov> Sent: Monday, November 1, 2021 2:01 PM To: Dunlap, Mike J - DMA <michael.dunlap@us.af.mil> Cc: HINMAN, MICHAEL T GS-12 USAF ANG 115 CES/Architect <michael.hinman.4@us.af.mil>; Ross, Issac A - DNR <Issac.Ross@wisconsin.gov>; Ales, Stephen M -DNR <stephenm.ales@wisconsin.gov> Subject: MMP Approval for 3-Bay Hangar
Mike:
On October 14, 2021 The Wisconsin Air National Guard (WANG) submitted a materials management plan (MMP) for the F-35 3-Bay Hangar. This hangar will be a new structure to be located in the area currently occupied by building B414. Five (5) borings were completed around current B414 and these borings were converted to groundwater monitoring wells.
PFAS compounds were found in all soil borings at sample depths of 0 – 1 foot, 2 – 3 feet, and 3 – 4 feet. Ten (10) different PFAS compounds were found in soil. No VOCs were found in the soil samples.
PFAS and VOC compounds were found in groundwater. PFOS, PFHxS and PFOA were generally the PFAS compounds of the highest concentrations in groundwater. Several VOCs exceeded Enforcement Standards found in NR 140. These include benzene, 1,2,4-TMB, naphthalene and vinyl chloride.
The information submitted with this MMP did not contain a map or figure showing the planned location for the 3-Bay Hangar. Since both soil and groundwater samples from this location contain PFAS compounds WANG must treat all soil and groundwater removed from this location as PFAS containing soil and handle it in accordance with the Materials Management Plan approved for this site on July 21, 2021. The soil may be temporarily stored at this location, or may be moved to the mailto:stephenm.ales@wisconsin.gov mailto:michael.dunlap@us.af.mil mailto:michael.hinman.4@us.af.mil mailto:michael.hinman.4@us.af.mil location to the west of building 1209. Upon completion of the project the PFAS containing soil must be below an impervious surface.
The monitoring wells indicate the water table to be between 3 – 5 feet below ground surface. If it is necessary to lower the water table to complete construction activities the WANG must contact the DNR prior to starting construction to determine a proper method for containing and treating the water. Also, precautions should be taken to protect the monitoring wells during demolition and construction activities. Alternatively, the wells should be filled and sealed prior to demolition taking place.
Let me know if you have any questions.
Steve
We are committed to service excellence.
Visit our survey at http://dnr.wi.gov/customersurvey to evaluate how I did.
Stephen M. Ales, P.G.
Hydrogeologist Program Coordinator – Remediation and Redevelopment Bureau, Division of Environmental Management Wisconsin Department of Natural Resources Phone: 608-400-9187 Stephenm.Ales@wisconsin.gov dnr.wi.gov http://dnr.wi.gov/customersurvey mailto:Stephenm.Ales@wisconsin.gov http://dnr.wi.gov/ http://facebook.com/WIDNR https://twitter.com/WDNR http://www.youtube.com/user/WIDNRTV https://public.govdelivery.com/accounts/WIDNR/subscriber/new
File details come from the government source that posted it. Updated .