This document contains questions and answers related to solicitation number W50S9C-21-B-0002 from the US Army National Guard for repair and upgrade of the electrical distribution system at the Vermont Air National Guard Base. Key work includes demolition, trenching, transformer and switch work, and high and medium voltage electrical upgrades. Bids are due by June 25, 2021. The contract will be a firm-fixed-price contract awarded for 365 days. Services required include provision of all plant, labor, materials and equipment to perform the electrical distribution upgrades. The utility company involvement is limited to removal of existing infrastructure.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W50S9C-21-B-0002
REPAIR BASE ELECTRICAL DISTRIBUTION
QUESTIONS and ANSWERS
As of 6/15/21
1. Question: Are bids to be hand-delivered or can we send our bid package via FedEx?
Answer: Interested bidders may submit complete bid packages via FedEx, UPS, USPS, Courier, etc. Address per Block 7 of the solicitation. Please plan accordingly to ensure delivery prior to due date and time.
2. Question: Is the contractor required to test existing cables?
Answer: Yes. May be tested as one cable between elbow junctions.
3. Question: Where is the location of TCB 9?
Answer: TCB-9 does not exist. See Revised E6.1 issued by amendment.
4. Is aluminum or copper URD required? The plans and specifications conflict.
Answer: Cable to be #1/0 aluminum URD, 100% insulation XLPE. Single phase runs of cable to be full neutral. Three phase runs of cable to be either 1/3 neutral or full neutral.
Design intent is to match Green Mountain Power (GMP) standard cable type.
5. Is the contractor required to pay any Green Mountain Power (GMP) fees associated with this project?
Answer: The extent of GMP work is expected to be the removal of the wood structure GMP substation, the removal of the temporary overhead line along Falcon Drive, and miscellaneous pole work to tie the new S-VTANG switch to the new 12,470V service. There are no GMP fees expected for this project for the work above. If the contractor uses GMP as a subcontractor to perform any work outside of the scope noted above, the contractor shall pay any GMP fees.
6. Please clarify extent of work involve with “remove cable back to GMP Substation”.
Answer: GMP Substation shall refer to the wood structure located adjacent to switches S1 and S6. Contractors shall remove all cables back to the riser pole switches.
7. What duct bank requires concrete encasement? What is considered “Low Voltage” and what must be concrete encased for “Low Voltage” duct bank, if different?
Answer: All duct banks for circuits above 600V shall be considered high voltage and shall be encased in concrete. Low voltage circuit conduits (under 600V) that are not part of a ductbank that included high voltage cables only requires concrete encasement when run under roads (paved or not paved) and parking lots.
8. When work is in a parking lot, can the entire parking lot be closed during construction or must work are be isolated/fenced?
Answer: No. The entire parking lot cannot be closed during construction. The COR will work with the contractor to provide the largest area of access as possible while allowing base operations to continue.
9. Can NCO Drive be closed during construction activities in the roadway?
Answer: No. Only one lane on NCO drive can be closed at a time. Contractor to provide flaggers to route traffic during lane closures. At night, contractor to place signs to use caution and yield to oncoming traffic.
10. Do any of the transformers being removed have PCBs?
Answer: The contractor shall bid the project as if there are no PCBs in the transformers.
11. Could you provide a specification on the 6 single phase submersible transformers AST2/2A/2B & BPT2/2A/2Bs?
Answer: Specification 261200 – Medium Voltage Transformers is replaced in its entirety with Specification 261200 Medium Voltage Transformers – REV1 06/1-21. It now includes submersible transformers.
12. Please clarify the 15kv cable required. The prints call for 3-1/c 1/0 alum. URD 15kv cable with a full neutral per conductor with xlp insulation. The specs approved Okonite as a cable manufacture. Okonite does not make xlp cable, is epr insulation acceptable? Also is the full neutral for each conductor correct, or do you want 1/3 neutral per conductor?
Answer: The intent is to match, within reason, GMP standards. Provide 175mil (100%) insulation, full neutral for all URD cables. Okonite cable may be used in lieu of Hendrix since it works with the same elbow connectors.
13. Could you provide specifications for the Fault indicators?
Answer: Design intent is to use the test point of elbows to provide test point reset type faulted circuit indicators with low pass filter and variable trip setting that reset when power restored. Eaton STAR FCI STHIA or equal. Verify all indicator flags are viewable without moving equipment. Just prior to completion of project, use testing tool to verify all indicators are reset and batteries are operational. Provide testing/reset tool to Owner when complete. Answer is Deleted in its’ entirety. See 18 for corrected response.
14. Could you provide specifications for the Sectional Cabinets?
Answer: Detail 3 on E6.1 indicates 66" LONG THREE PHASE TC CABINET (EATON SEC36A23FOOOOMOG, OR EQUAL). Detail 5 on E6.1 indicates 30" LONG SINGLE PHASE MTC CABINET (EATON SEC13023FOOOOMOG, OR EQUAL) on
FIBERGLASS GROUND SLEEVE (EATON GS303022, OR EQUAL).
15. Could you provide a list of all the existing transformers that will need to have the fusses changed and the required fuse sizes?
Answer: All the existing transformers are shown on E3.1 and E3.2. All of them will require new fusing except 2500kVA transformer T-12 which is presently fed via a GMP 12,470V circuit. E5.1 shows all fuses and sizes required based on voltage and kVA rating.
This information shall be used by the contractor to determine actual number of transformers, and fuses based on the kVA rating of the transformer.
16. Is ABB an approved manufacture for the pad mounted transformers?
Answer: Yes.
17. Is Power Partners an approved manufacture for the submersible transformer units?
Answer: Yes.
18. The Fault indicators that you called out in Amendment 001 “Eaton STAR FCI STHIA” have an auxiliary contact. The contract does not call for anything to be connect to the auxiliary contact. Please confirm this is the Fault indicator the Guard wants.
Answer: Design intent is to use the test point of elbows to provide test point reset type faulted circuit indicators with low pass filter and high trip setting that reset when power restored. Eaton STAR FCI STHI with no auxiliary contact or equal. The trip function is to be the high setting type (HI), not the variable trip (VT) type. Verify all indicator flags are viewable without moving equipment. Just prior to completion of project, use testing tool to verify all indicators are reset and batteries are operational. Provide testing/reset tool to Owner when complete.
19. On E5.1 “Transformers Replacements and Conversions” #2 it refers to some buildings being provided generators by VTANG, Can you clarify which buildings affected will be provided generators by VTANG and which ones need to be provided by the contractor?
Answer: Building 328 will require the contractor to supply generator power during the duration of power outages. All the rest of the buildings will either lose power or have Gov supplied generator power during all outages.
20. In UH #16 and UH #17, Is the opening of vaults large enough for removal of existing transformers and installing of new Submersible transformers, or does the top of the vault need to be removed?
Answer: Based on standard submersible transformer dimensions, the transformer vaults UH- 16 and UH-17 access covers are large enough to remove and install a 25kva, single phase submersible transformer. The ladder may need to be temporarily removed.
21. Please confirm if taxes should be carried in proposals?
Answer: No taxes on this project.
22. Please confirm if any state, local, and/or Federal permits will be required on this project?
Answer: A federal Construction General Permit (CGP) will be required.
23. Please confirm if there are any known hazardous materials?
Answer: No known hazardous materials.
24. The Electrical Feed Schedule on Drawing E3.2 indicates AL (Aluminum) cables. Spec Section 26 05 13 indicates copper conductors. Which is correct? If AL is correct, please provide the spec section for aluminum cables.
Answer: An updated version of Specification 260513 is being provided. The new 15kV cable shall be aluminum. An updated version of Specification 260519 is also being provided. All new conductors rated 600V or less shall be copper.
25. Please confirm who is responsible for the utility company charges? Could the utility companies contact be provided?
Answer: The extent of GMP work is expected to be the removal of the wood structure GMP substation, the removal of the temporary overhead line along Falcon Drive, and miscellaneous pole work to tie the new S-VTANG switch to the new 12,470V service. There are no GMP fees expected for this project for the work above. If the contractor uses GMP as a subcontractor to perform any work outside of the scope noted above, the contractor shall pay any GMP fees. The GMP contact is Cory Sullivan Cory.Sullivan@greenmountainpower.com Office: 802.655.8715
26. Drawing ES1.4 shows a new Termination Cabinet TCB11 in the run from TCB10 to TCB8.
This is not shown on the One-Line Diagram, Drawing E3.2. Can a revised One-Line Diagram be established indicating this Termination Cabinet and the appropriate terminations and vault indicators or is this cabinet to be deleted? If the cabinet is deleted, what is to be installed as the pull between TCB8 and TCB10?
Answer: TCB-11 is a new termination cabinet to be installed where shown on E1.1. Drawing E3.2 has been updated.
27. E3.2 Electrical Feed Schedule tag 5 indicated existing conduit, existing cables. TCB-8 shows existing conduit and existing cable to T-23. Please Verify this is true.
Answer: Tag to change to 2. New cables run from TCB-8 to T-23. New E3.2 drawing attached.
28. On E3.2 in loops A and B it calls to replace 3 below grade single phase transformers with 3 new 25KVA 3 phase transformers. Please verify this is accurate
Answer: Intent is to replace (3) 25kVA submersible single-phase transformers wired in a 3-phase arrangement with new in same configuration.
29. Will a Coordination Study be preformed to determine accurate fuse sizing? If so is the contractor responsible for preforming the coordination study?
Answer: Coordination study will be performed by LN Consulting when all work is complete.
Fuse sizes shall be per the fuse chart on E5.1, except where fuse size recommended to vary per transformer manufacturer’s recommendations. There is no other coordination required..
30. Drawing E3.2 Primary Voltage One-Line Proposed does not show TCB-11. TCB-11 is shown on Drawings E6.3 and ES1.4. Is TCB-11 required?
Answer: TCB-11 has been added in Addendum 0002.
31. Drawing E6.3 - The Duct Bank ID for S-VTANG to S1 in the schedule does not match the ID on the Electrical Ductbank Riser Diagram.
mailto:Cory.Sullivan@greenmountainpower.com
Answer: E6.3 indicated ductbank size. E3.2 indicates circuit size via conduit. In this instance, E6.3 indicates a (4) 4” ductbank from S-VTANG to S1. Electrical Feed Schedule Tag 2 indicates that 3/c #1/0 cable will be run via one of those 4” conduits.
32. Drawing E6.3 - The Duct Bank ID for S-VTANG to S6 in the schedule does not match the ID on the Electrical Ductbank Riser Diagram.
Answer: See response to question 31.
33. Drawing E6.3 - The Duct Bank ID for Existing TCA-3 to T3 in the schedule does not match the ID on the Electrical Ductbank Riser Diagram.
34. Drawing E6.3 - The Duct Bank ID for S3 to Existing UH 8 in the schedule does not match the ID on the Electrical Ductbank Riser Diagram.
35. Drawing E6.3 - The Duct Bank ID for UH 8 to TCA-9 in the schedule does not match the ID on the Electrical Ductbank Riser Diagram.
REMINDER – ALL QUESTIONS MUST BE SUBMITTED BY TUESDAY 15 JUNE 20 –
FIVE WORKING DAYS PRIOR TO BID OPENING DATE.