Questions 11-16.pdf

PDF 279 KB Posted

Attached to
Building 420 Renovation Federal contract opportunity
Solicitation number
W50S98-21-B-0001
Issued by
Department of the Army Tennessee Army National Guard

About this file

This document contains questions and answers related to a solicitation for the Building 420 Renovation project. The solicitation is for construction services to repair the dining and medical training facility at McGhee Tyson ANG Base in Tennessee. Work will be performed according to the provided plans and specifications. The project magnitude is between $5 million and $10 million. The North American Industry Classification System code is 236220 and the small business size standard is $39.5 million in average annual receipts. This opportunity is set aside for small businesses. A pre-bid conference site visit is encouraged and funds may become available by September 30, 2021, with award going to the responsible bidder providing the most advantageous price.

View the file

Other files for this federal contract opportunity

Other files attached to Building 420 Renovation, newest first.
File Type Posted
W50S9821B0001 Abstract 1419.pdf PDF
Amendment 6 B420 Revised.pdf PDF
Amendment 6 B420.pdf PDF
McGhee Tyson ANG_5.12.20-QF101.pdf PDF
Amendment 5 420 PreBid Questions.xlsx XLSX spreadsheet
B420 Geotechnical Report.pdf PDF
Amendment 5 B420.pdf PDF
Amendment 4 B420.pdf PDF
21B0001P0001 Solicitation Amendment Conformed Copy.pdf PDF
21B0001P0001 Solicitation Amendment.pdf PDF
Questions 17-63.xlsx XLSX spreadsheet
Amendment 3 B420.pdf PDF
Wage Determination TN20210077 1 Jan 2021.pdf PDF
Amendment 2 B420.pdf PDF
Amendment 1 B420.pdf PDF
Old Addition Drawings.pdf PDF
Old Original Facility Drawings.pdf PDF
Question 1-9 Corrected.pdf PDF
Building 420 A4.0.pdf PDF
Question 10.pdf PDF
S1-1.PDF PDF
Building 420 A3.2.pdf PDF
Building 420 A4.1.pdf PDF
Building 420 S1.2.pdf PDF
Pre-Bid Sign in Sheet.pdf PDF
Pre-Bid Slides.pdf PDF
Pre-Bid Minutes W50S98-21-B-0001.pdf PDF
Questions 1-9.pdf PDF
Construction PWS PSXE162007 Repair Dining- Medical Training Facility-Bldg 420.pdf PDF
Repair B420 - Type B-3 - Vol 2 Drawings (Half Size).pdf PDF
Repair B420 - Type B-3 - Vol 3 Specs (Div 01-11) V2.pdf PDF
Repair B420 - Type B-3 - Vol 4 Specs (Div 12-33).pdf PDF
W50S98-21-B-0001 Solicitation.pdf PDF
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question 11 - Could micropiles be used in place of helical piles? Please advise.

Answer 11- The helical piers are designed and specified based on a site-specific geotechnical investigation, use helical piers as specified.

Question 12- The Pre-Bid Minutes emphasize that the “Total price of all items, including options should be listed in block 22 of the SF1442”. Per the SF1442, Block 22 is to be completed by the Government. There is also no indication in Section 00010 that the total price should be included on SF1442. Please confirm if Total Price should be included on SF1442 with

Bid Package.

Answer 12- The Total Price does not have to be listed on the SF1442.

Question 13- C101 directs us to remove and replace the existing handrails on the ramp and refers us to detail B1/C501. There are no ramp rails shown in this detail. Please clarify the requirements.

Answer 13- The handrails shown in the detail B1/C-501 are representative of the style, material, color, as well as the attachment requirements for all locations around the building including ramps.

Question 14- Are the construction drawings for the existing building available?

Answer 14- These drawings are for reference only and may not reflect the true as-built layout.

See attachments “Old Addition Drawings” and “ Old Original Facility Drawings”.

Question 15- Curtainwall spec 084400 para 1.3.5.5 calls out an “opaque” U-factor of no greater than 0.29. Glazing spec 088100 para 2.2 calls out a U-factor of 0.4 or less for the insulated glass units. Drawing A003 thermal shielding table lists fixed glass windows as having a U-factor of

0.40. Is it correct to assume that the entire curtainwall system (glazing + framing) should have a

U-factor of 0.40 or less, and glazing should be selected as required to meet this overall system thermal performance?

Answer 15- Yes, assume U-factor of 0.40 or less, and glazing should be selected as required to meet this overall system thermal performance

Question 16- The IG unit specified in glazing spec 088100 para 2.2 last paragraph lists an IG unit makeup of bronze tint (uncoated) on the exterior lite, and clear(uncoated) on the interior lite, with argon fill. Are low-E coatings on the IG units acceptable to improve the thermal performance of the IG units in order to meet the overall window system U-value requirements?

Answer 16- Yes, low-E coatings are acceptable