W50S98-22-B-000100002.pdf

PDF 275 KB Posted

Attached to
B113 Solicitation Federal contract opportunity
Solicitation number
W50S98
Issued by
Department of the Army Tennessee Army National Guard

About this file

This solicitation package includes an invitation for bids for repair and renovation work at Building 113 at McGhee Tyson Air National Guard Base in Tennessee. The solicitation seeks a firm fixed price contract to perform work including hangar bay ventilation, breathing air systems, hangar door refurbishment, fire suppression systems, emergency equipment, climate control, grounding points, and electrical work. An option is included for the demolition of Buildings 110 and 111. The pre-bid conference will be held on July 29, 2022 and bids are due by August 23, 2022. The set-aside is for 100% small business and the wage determination is TN20220177 Mod 3. The questions and answers document provides clarification on the scope of work, drawings, and specifications.

View the file

Other files for this federal contract opportunity

Other files attached to B113 Solicitation, newest first.
File Type Posted
OF 1419 Abstract.pdf PDF
OF 1419 Abstract.pdf PDF
Sign in Sheet - 23 Aug 2022 10am.pdf PDF
B 113 As Built Drawings.pdf PDF
05 40 00 Cold-formed Metal Framing 20220805.pdf PDF
Demo Drawings CS503-506.pdf PDF
Demo 110_110 Drawings GC002 003 004 005.pdf PDF
BLDG 111 Asbestos Info.pdf PDF
P-601_REVISED.pdf PDF
REGISTER-upate 07292022.pdf PDF
1190113_TNANG_B113_ELEC-ADDENDUM 1-072622.pdf PDF
W50S98-22-B-000100001.pdf PDF
1190113_TNANG_B113_FIRE-ADDENDUM 1-072622.pdf PDF
28 31 76 - updated.pdf PDF
Pre-Bid Sign in Sheet B113.pdf PDF
Pre-Bid Slides B113.pdf PDF
MTANG Demo 110 and 111 drawings.pdf PDF
Repair Building 113 Spec. Volume 2.pdf PDF
W50S98-22-B-0001 21 July 2022.pdf PDF
Repair Building 113 Spec. Volume 1.pdf PDF
Repair Building 113 Drawings.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PSXE152020

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

REASON FOR AMENDMENT: Update Wage Determination and Questions/Answ ers

1. Wage determination TN20220177 Mod 3 dated July 22, 2022 is hereby incorporated in to this solicitation

2. Questions and Answ ers 1-55 are hereby incorporated in to this solicitation

3. The follow ing attachments are hereby incorporated in to this solicitation: 05 40 00 Cold Formed Metal Framing 20220805, BLDG 111 Asbestos Info, Demo 110_110 Draw ings GC002 003 004 0005, Demo Draw ings CS503-506, P601 Revised, B 113 As Built Draw ings.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 19

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 17-Aug-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W50S9822B0001

X 9B. DATED (SEE ITEM 11)

21-Jul-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

17-Aug-2022

CODE

USPFO TN 134 MISSION SUPPORT CONTRACTING

123 BRISCOE DRIVE

MCGHEE TYSON ANG BASE TN 37777-6227

W50S98 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W50S9822B0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been modified:

QUESTIONS AND ANSWERS

1. Could you please clarify the Date and time in which this IFB is due to be received by the Government?

A: The bid due date has been updated to 10:00 AM EST on 23 August.

2. Under Section 00010 Notes. It talks about a Different date. Does that just apply to the bond?

A: Correct it just applies to the bond. It allows two extra days to provide the original bond.

3. Ok, so if that's the case are we allowed to submit our proposal electronically?

A: No

Section 08 33 23 Coiling Doors1 On A101 there is a note A1 that states door 126C is to be custom color powdercoat.

4. Is this the only Overhead door to be custom powdercoated, or should this be for all doors? The specification indicates, Part 3 paragraph 3.2 doors are to be field painted.

A: All new exterior roll‐up doors to be custom powder coated.

Again on A101, Note A2 indicates that door 133‐E is insulated. The specification 2.3 Overhead Coiling Doors, paragraph 2.3.1 indicates doors to be insulated.

5. The note A2 on A101 makes this confusing. Are all doors insulated per specification or just door 133‐E?

A: Only new exterior doors to be insulated.

6. Electrical power plans, note E13 indicates, states doors to be motorized suitable for Class 1 Division 2 space. What are the exact requirements? the specification does not indicate this type of motor operator.

A: The door specification itself does not change. The motor operator needs to meet the class 1 div 2 requirements.

7. Door 126B‐E is a door that is taken down and reinstalled. This door also has the

E13 note applied. Does this door now have Class 1 Division 2 Motor operator, or is the motor operator to be replaced to meet this requirement? Also this Door requires a 1 hour fire rating. Does the existing door meet this requirement?

A: This existing door meets the fire resistance rating requirements. The motor operator needs to meet the class 1 div 2 requirements.

8. The specification requires slide locks. The motor operator will lock door. I recommend this option be deleted. If not the TANG will have maintenance issues.

A: Pond/Gov't has no issue with them being removed.

9. Sheet I‐101/101A Nose Bay Existing or New epoxy per general note

A: Room 101A/Nose Bay should state EP‐1 on finish schedule, as noted in Remarks will we redone with the Hangar Floor.

10. 102A Mech EP‐1 or Existing epoxy

A: Room 102A should state Existing on the Finish Schedule and as noted on sheet I‐101

11. 103 Mech EP‐1 or Existing epox

A: Room 103 should state Existing on the Finish Schedule and as noted on sheet I‐101. 103A should not be on the finish schedule as room was removed with HEF removal modification.

12. 113 Fuel Cell Supervisor CT‐1 or Epoxy to match existing

A: Room 113 correctly states CT‐1. The note with arrow on sheet I‐101 should be pointing to room 101A/Nose Bay, not room 113.

13. Per drawings page M‐602 there is quantity 6 existing airhandler units (AHUs). It is unclear whether these AHUs are to be integrated into the new building automation system. If they are required to be integrated and user graphics created for them, do the existing AHUs have BACnet communication cards to allow for integration? If not is the controls contractors responsible to provide said BACnet cards?

A: The existing six (6) AHUs are currently controlled by the existing DDC system. The contractor shall relocate the connection points along with the AHUs and reconnect the AHUs to the DDC system.

14. Sheet S151, Key note S15 calls for a delegated design at the new draft curtain and refers us to specification 05 40 00 for more information. I have not found this specification. Please clarify the requirements.

A: Detail A3/S‐302 refers to note S8 on S‐151. It should refer to note S15.

Detail A3 also specifies 1 ½” metal studs. It should specify 2 ½” metal studs. It also specifies 1 5/8” metal stud blocking, It should specify “Size as required.”

See attached Specification Section 05 4000.

15. Sheet A101, Key Note 6 calls for a spill containment barrier. It suggests a manufacturer, but not a model number. I have not found a specification or construction details. Please clarify the requirements

A: There is enough information in the note for bidding and submittal purposes. There is not an associated specification for this item.

16. The drawings for the demo of buildings 110 & 111 appear to be missing some drawings.

A: Drawings CS503, CS504, CS505, and CS506 are provided. Be advised, some details referenced on these sheets may not apply.

17. Sheet CS110 calls for some detail sheets (CS503, CS504, CS505 & CS506) that are not on the

SAM.gov web site.

18. How do the details on Sht. S‐303 apply to this project, since Sht. FD‐101 indicates that the existing Foam Generator is to be removed?

A: Sheet S‐303 is not used and should have been removed from set. Title block says, “not used”.

Sheet S‐151 Keynote S15 calls out detail A3/S‐303, this is a typo. It should reference A3/S‐302

19. Is the flatness of the current epoxy flooring system acceptable for the new floor that will be installed? If not, a higher build system and or leveling will need to be specified to bring it to an acceptable level.

A: We are not aware of any issues with the flatness of the existing floor that may affect the installation of the new system. Refer to specification section 09 67 23.15 – Fuel Resistive Resinous Flooring, 3‐Coat System for additional information.

20. Since this area involves fuel, would a conductive ignition control ESD flooring system not be required?

A: Provide flooring system as specified.

21. The rooms around the hangar appear to be flat and the existing coating well adhered. Is total removal required for existing rooms that have sound, well bonded coating that can be recoated?

A: Prepare areas to receive new coatings as specified.

22. On the overall floor plan for plumbing P11 note says to drop 3 breathing air drops and tie together. With that said it is just labeled as CA on the drawing and the two tables do not mention breathing air material. Just lubricated compressed air. I assume if it is in fact breathing air then it needs to be cleaned and capped copper like medical gas. Can you confirm please?

A: For breathing compressed air piping, provide cleaned and capped copper.

23. It appears that Bldg 110 will be unoccupied during the project. Therefore, can it be used as a Field office?

A: Once under contract, buildings are turned over to the contractor for their use.

24. They are asking for a Champion L29 (40hp) Compressor. That Compressor produces 173cfm @ 125 psi. However, they are asking for 345cfm. Also the Dryer (CRN200) is no longer in production. We do have a CGD200 available. Don't understand why they ask for a 200cfm Dryer while asking 345cfm from their compressor. Have I missed something? Do they want two compressors & dryers?

A: Provide 175 CFM @125 psi air compressor. Provide 200 CFM air dryer as a 175 CFM air dryer is not standard. Refer to updated drawing P-601.

25. Note 13 on Sht. AD001‐0 says to see Asbestos Report and Asbestos Management plan. Where is this Report located?

A: See BLDG 111 Asbestos attachment for Bldg 111 asbestos report. Bldg 113 has no known asbestos containing material. Please note, it is the contractor’s responsibility to evaluate the structure to determine the extent of ACM that needs to be abated as part of their bid.

26. In the "MTANG+Demo+110+and+111+drawings.pdf" drawing set, the Site Plan Notes on drawing GC006 references drawings GC002, GC003, GC004, and GC005 but these drawings are not part of the drawing set. Please provide these drawings.

A: Drawings GC002, GC003, GC004, and GC005 are provided. Be advised, some details referenced on these sheets may not apply.

27. In the "MTANG+Demo+110+and+111+drawings.pdf" drawing set, drawing CD100 shows detail drawings CD101, CD102, CD103, CD104, CD105, CD106 which are not part of the drawing set.

Please provide these drawings.

A: Drawings CD101, CD102, CD103, CD104, CD105, CD106 do not apply the demo of bldg. 110 and 111.

28. Please confirm that the entire demolition shown on CD100 is included in the scope of work for this project. Specifically, the demolition that is around the KC‐135 Apron approximately 0.5 miles southwest of Bldg 111. If this area is within the scope, it appears (from Google Maps) that there is a building directly above underground utilities marked for demolition between the KC‐ 135 apron and Briscoe Rd (shown as Brisco Dr on Google Maps). Please confirm that this is part of the scope of work for this project.

A: This area by the apron is not part of the Bldg 110 and 111 demolition scope.

29. Due to the instability in our current economy with price escalations and procurement issues, please change the contract type to a Fixed‐Price with Economics Price Adjustments pursuant to

FAR 16.203.

A: Contract type cannot be changed.

30. Please allow us an additional week for RFI's (19 August, 2022) and an additional week for the bid due date (30 August, 2022).

A: Declined

31. Hangar Door Specs have language that refers to a cable system. Please advise if cable system or pickup bracket system is preferred.

A: Provide cable system as specified.

32. Hangar Door Specs have language that refers to sensing edge system. Please advise if this should be included.

A: Provide as specified.

33. The hangar door leaves are 4” thick. This isn’t deep enough to install an internal motor and drive unit assembly. What would you suggest? An alternative is an external motor assembly, commonly knows as a rubber tire operator, but these require more space and add 14‐inches to the door thickness. Example here https://hangardoors.aero/motorized‐hangar‐doors

A: Hangar door is being refurbished. Motor assembly and all other components to be reconfigured to accommodate new work.

34. Whats the anticipated start date for the hangar door work?

A: The contractor will propose what time works for the overall schedule to start in order to meet the contracted period of performance.

35. Are electrical components on the hangar door required to be explosion proof if they are 18‐ inches above the finished floor?

A: Hangar door components are not required to be electrically classified provided that they are above 18".

36. Scope of work says to provide draped cord power system but hangar door specs state trolley buss. Please advise which you prefer.

A: Provide a new drape cord power conveyance system.

37. Option 1, sheet CS110 references drawings CS503, CS504, CS506 & CS507. I have not found these drawings in the bid documents. Please direct me to them or make them available.

A: Drawings CS503, CS504, CS505, and CS506 are provided. Be advised, some details referenced on these sheets may not apply.

38. Option 1, sheet AD001, Notes 13 & 14 reference an Asbestos Report and an Asbestos Management Plan. I have not found these items in the bid documents. Please direct me to them or make them available.

containing material. Please note, It is the contractors responsibility to evaluate the structure to determine the extent of ACM that needs to be abated as part of their bid.

39. The structural specification requires fabrication to be done in an AISC Certified fabrication shop. We are requesting that the AISC certification requirement be waived if a Los Angeles City Certification can be substituted instead? Or can this AISC certification be waived if a third party monitoring agency performs inspection of the fabrication plant during the steel fabrication and erection process?

A: It is permissible to waive the AISC Certification for the Fabricator and Erector if the third party/special inspector performs an inspection of the fabricated items at the fabricator’s shop during fabrication and observes the erection process during construction

40. Provide as-builts for the building(s) and surrounding site (utilities).

A: See provided as‐builts.

41. Provide current geotechnical report.

A: The Government did not accomplish a geotechnical analysis for this project.

42. Provide the firm and point of contact for the mechanical controls system.

A: There is not a firm or specific point of contact assigned to the building’s mechanical control system.

General service/maintenance is performed by the government. Problems outside the government’s capabilities are contracted out as needed. Bidding contractors are allowed access to the building to evaluate the system as needed.

43. Verify that the Owner will be responsible for removing ALL equipment, unbolted furniture, personal effects, etc from the affected areas prior to construction.

A: ALL equipment, unbolted furniture, personal effects, etc will be removed by the owner prior to construction.

44. Provide Hazardous Material Report for this project.

containing material. Please note, It is the contractors responsibility to evaluate the structure to determine the extent of ACM that needs to be abated as part of their bid.

45. Confirm standard / permissible work hours during construction.

A: Standard work hours are from 0700 through 1700 Mon – Friday. After hours and weekend work is allowed for specific project needs with proper, prior coordination with the COR.

46. Confirm that the Government will allow proposers a minimum of seven (7) days to respond to the RFP starting from the date that the Government responds to 100% of the RFIs received.

A: Per the solicitation all questions are due no later than 5 working days prior to bids being due. Therefor there will not be 7 days.

47. Sheet M101A, Key Notes M3 & M4 call for tank purge supply and exhaust duct. What material should this duct be made from?

A: Exhaust and supply ducts must be interior 302 Stainless steel with neoprene outer coating.

48. Sht. CS‐110 Shows details on CS‐503, CS‐504, CS‐505 & CS‐506. These sheets are not included in the set that was posted with solicitation.

49. Sheet E‐111, Keynote E11 calls for replacement of existing hanger bay receptacles with class 1, division 2 explosion proof receptacles, reuse existing circuitry, and to mount at 48” AFF. Sheet E‐ 141 classifies this hanger area as class 1, division 2 only up to 18” AFF. Please clarify if the receptacles will need to be explosion proof since they will be mounted at 48” AFF. If explosion proof devices are required, will an explosion proof seal off be required to be installed on the existing raceways feeding the existing devices?

A: Provide class 1, division 2 receptacles as indicated in the construction documents. The existing conduit serving the receptacles does NOT require seal off fittings.

50. Sheet E‐111, Keynote E25 calls for relocating receptacles in communicating spaces to 48” AFF.

Sheet E‐141 classified these communicating spaces as class 1, division 2 up to 18” AFF. Please clarify if these receptacles being relocated to 48” AFF will need to be explosion proof.

A: Receptacles in communicating spaces mounted 48” AFF are NOT required to be class 1, division 2.

51. E42 calls for 120Vac at every door for ACS, but not where the panel will be located IDS ACS, The

IDS panel should be inside the secure area. where is that going to be?

A: This is not a traditional ACS/IDS system. These are mag locks to control access with pushbutton release. There is no new ACS or IDS panel.

52. At 107 you are calling for Access control going in and out of the mens Rest Room, but not the womans?

A: Contract documents are accurate.

53. 135 does not indicate ACS, or IDS but door 130 has free access to flightline?

A: This is not a full renovation. Existing airfield control systems in place are to remain.

54. Where will be the Main entry Keypad to disarm the area?

A: A new ACS/IDS system is not being installed with this project. The project is adding maglocks to certain doors that will always be locked with the mag and have request to enter buttons to de‐energize the lock and allow entry.

55. Who is responsible for conduit?

A: The contractor is responsible for providing conduit

SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS

SECTION 00100 NOTES

SECTION 00100 INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

1. Description of the Project: The renovation of an existing hanger. The project requires a fully functional aircraft maintenance facilities to support repair and maintenance activities associated with fuel cell systems for all assigned aircraft. A hangar bay ventilation system is required to exhaust jet fuel fumes from inside the hangar bay to the building exterior during periods of aircraft open fuel tanks. Proper breathing air systems are required for maintenance personnel when working in confined cells of aircraft. The hangar bay doors shall be refurbished and are required to mechanically and manually slide properly, and provide adequate insulation properties when closed. Fire suppression systems shall have alarm/notification systems, electrical systems and structural features that meet the fire and safety criteria for fuel systems repair facilities. Operational emergency eyewash/shower with privacy enclosures to permit complete disrobing in the aircraft servicing area. Emergency eyewash/showers shall provide water through a thermostatic mixing valve. Changing areas, locker space, scrub sinks and personnel showers for both male and female personnel. Climatic control units shall provide adequate heating/cooling to support environmentally stable air for air purging, sealant cure and general repair. Sufficient grounding points are required throughout the facility. Electrical systems shall meet Class I, Division 1 and Division 2 as required by applicable Technical Orders. Office space, break room, support equipment/tool room and restrooms require climate control and positive pressure ventilation to prevent fumes and vapors from migrating from the aircraft repair area. Rooms shall be provided for tele-communications, utility/mechanical and fire protection systems. There is also an option for the demolition of buildings 110 and 111.

2. Instructions to Bidders:

2.1. You are invited to submit a bid in response to our Invitation for Bids (IFB) entitled) W950S98-22-B-0001

Repair Bldg. 113 for Fuel Cell PSXE152020 at McGhee Tyson ANG Base, TN.

2.2. As a result of this solicitation, the Government intends to award a Firm Fixed Price (FFP) contract resulting from this solicitation to the responsible bidder whose bid, conforming to the invitation for bids, will be most advantageous to the Government, considering only price.

2.3. This solicitation is set-aside 100% for small businesses.

3. Reserved

4. NOTICE OF PRE-BID CONFERENCE AND SITE VISIT:

4.1. A pre-bid conference will be conducted on 29 July 2022, 9:00 AM EST for the purposes of briefing on the bid requirements and answering questions regarding this solicitation. This conference will be held at the 134th Civil Engineering, Building 320 Post Avenue located on McGhee Tyson ANG Base, Louisville, TN. Interested Contractors are highly encouraged to attend the pre-bid conference. The site visit will be held following the conference.

4.2. Due to security conditions, all offerors must register to attend this conference and site visit. Email the following information for all attendees to Andrew Headrick at the following addresses: andrew.headrick@us.af.mil

Firm Name and Telephone Number Visitor’s Name Drivers License Number and State of Issue

4.3. This information must be provided in advance, 3 business days prior to the meeting, in order to ensure access to the military base and conference site and ensure adequate seating for the conference attendees. Even if you have access to the base you must register to ensure adequate seating. The furnishing of the above information is voluntary; however, your failure to furnish all or part of the requested information may result in the Government’s denial of your access to the pre-proposal conference. This information will be provided to the Base Security Forces who will authorize your entrance to the site.

4.4. Visitors must pick up their passes at the Installation’s Main Entry Gate prior to arrival. You will be required to present the following information upon arrival: (1) Vehicle Registration, (2) Valid Drivers License, (3) Proof of Insurance for Vehicle, (4) Safety Inspection and Car Rental agreement if applicable. Any of the above information furnished by you is protected under the Privacy Act and shall not be released unless permitted by law and/or you have consented to such.

4.5. Information provided at this conference or site visit shall not qualify the terms and conditions of the solicitation and specifications. Terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing. If an amendment is issued, normal procedures relating to the acknowledgment and receipt of solicitation amendments shall apply.

4.6. A record of the conference shall be made and furnished to all prospective bidders via posting at SAM.gov. The record will include minutes of the meeting, including questions (on a non-attribution basis) and answers.

5. FORMAL COMMUNICATION, OFFEROR EXPLANATIONS:

5.1. Submit all questions in the format shown below by email to the contracting office at the addresses show below.

Do NOT contact AE or Engineering personnel directly. Doing so will only delay your answer. All questions must come through the Contracting Office.

Subject Line: Reference No. SOLICITATION W950S98-22-B-0001 Email: lisa.fingland@us.af.mil

PRE-BID INQUIRY FORMAT

Date of Bid Inquiry: _______________

From: ______________________________ Company Name: ________________________________

Address:_____________________________________________________________________________

Phone Number: _____________________________ Fax Number:______________________________

Email address: ________________________________________________________________________

Bid Inquiry: (Please clearly state your question) (If sent via an attachment word docs are preferred to facilitate posting of answers to the master Q&A document.)

5.2. Any explanation desired by an offeror regarding the meaning or interpretation of the solicitation, or proposals, drawings, specifications, etc. must be requested in writing and with sufficient time allowed for a reply to reach bidders before the submission of their bid.

5.3. All questions and requests for information (RFI) must be received NOT LATER THAN the fifth working day prior to bid opening. OFFERORS ARE STRONGLY ENCOURAGED TO SUBMIT QUESTIONS EARLY

IN THIS PROCESS.

5.4. Any changes to the drawings, specifications, etc. will be issued in the form of an amendment. However, any answers that clarify or provide an interpretation to the drawings, specifications, etc. will NOT be posted via amendment but rather as a response to the RFI on SAM.gov at SAM.gov.

5.5. Receipt by the offeror must be acknowledged in the space provided on the SF 1442 or by returning a signed copy of the amendment by the time set for receipt of bids.

5.6. For security reasons, all technical and engineering data related to this solicitation will be distributed using the

Contract Opportunities (SAM.gov) system. Plans and specifications are locked on SAM.gov and require Contractors to request explicit access from the Contracting Officer OR export controlled access through DLA.

See complete instructions on SAM.gov. SAM.gov is a web-based dissemination tool designed to safeguard acquisition-related information for all Federal agencies. Interested bidders/offerors must register with SAM.gov before accessing the system.

5.6.1. Amendments, if/when issued will be posted toSAM.gov for electronic downloading. This will normally be the only method of distributing amendments prior to closing; therefore, it is the offerors responsibility to check the website periodically for any amendments to the solicitation. Websites are occasionally inaccessible due to various reasons.

6. BID REPOSITORY AND BID OPENING:

6.1. A bid repository is provided for hand carried bids and is located at 134ARW Contracting, building 123, McGhee Tyson ANG Base, Louisville, TN 37777. Hand carried bids must be deposited in the repository prior to the time established for opening of bids. Bidders are cautioned that they will be required to sign-in and obtain a visitor’s pass to enter the facility and should allow time to accomplish this. See instructions for obtain access to the base in the Site Visit instruction. Follow the same instruction for obtaining entry to hand carry bid. Late receipt of bids due to entry delays may not be deemed excusable and the Contracting Officer may declare the bid “late” in accordance with FAR 14.304.

6.2. The bid opening will occur at the time and date specified in Block 13 of the SF1442 McGhee Tyson ANG

Base, Contracting Office, Building 123 at McGhee Tyson ANG Base, TN 37777. All interested offerors and their major subcontractors are encouraged to attend the bid opening.

7. WAGE DETERMINATION:

7.1. Construction Wage Rates are applicable to this project are General Decision Number TN20220177, Mod 3.

Building, dated 07/22/2022 as shown in Section 00 72 00.

8. BID PREPARATION EXPENSES AND PRE-CONTRACT COSTS: This IFB does not commit the

Government to pay costs incurred in preparation and submission of bids or for other costs incurred prior to award of a formal contract.

9. CLAUSES:

9.1. Clauses and provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were given in full text.

9.2 Removal of sections at time of award: Sections 00100 and 00600 will be removed as a result of an award but will be deemed to be incorporated by reference in that award

10. DISPOSITION OF UNSUCCESSFUL BIDS:

In compliance with FAR Subpart 4.8, the Government will retain one copy of all unsuccessful bids including the bid bond.

11. OFFERORS QUALIFICATIONS:

To establish its responsibility, the apparent low bidder may be requested by the Government prior to award, to submit a statement regarding his previous experience in performing comparable work, his business and technical organization, financial and bonding resources and plant available to be used in performing the work.

This action may be requested to determine if the contractor is responsible.

SECTION 00 72 00 - GENERAL CONDITIONS

WAGE DETERMINATION

"General Decision Number: TN20220177 07/22/2022

Superseded General Decision Number: TN20210177

State: Tennessee

Construction Type: Building BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories)

County: Blount County in Tennessee.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).

|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $15.00 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2022. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $11.25 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2022. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at https://www.dol.gov/agencies/whd/government-contracts.

Modification Number Publication Date 0 03/11/2022 1 04/22/2022 2 05/06/2022 3 07/22/2022

ASBE0086-002 03/01/2022

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR........................$ 33.25 17.22

ELEC0270-002 06/01/2021

Rates Fringes

ELECTRICIAN (Low Voltage Wiring Only).....................$ 32.96 11%+8.10

* ELEC0760-001 06/01/2022

Rates Fringes

ELECTRICIAN (Excludes Low Voltage Wiring)..................$ 27.25 13.98

ENGI0917-004 05/01/2017

Rates Fringes

POWER EQUIPMENT OPERATOR

(Crane)..........................$ 28.26 10.10

IRON0492-001 05/01/2021

Rates Fringes

IRONWORKER, ORNAMENTAL...........$ 30.35 15.36

IRONWORKER, REINFORCING..........$ 30.35 15.36

LABO0818-005 05/01/2021

Rates Fringes

LABORER (Pipelayer)..............$ 21.45 8.06

PLUM0102-001 03/17/2021

Rates Fringes

PIPEFITTER.......................$ 43.21 27.90

SHEE0005-002 05/01/2021

Rates Fringes

SHEET METAL WORKER (SIDING

(METAL/ALUMINUM/VINYL))..........$ 32.29 12.62

SHEE0005-003 05/01/2021

Rates Fringes

SHEET METAL WORKER (HVAC Duct Installation Only)...............$ 32.29 12.62

TEAM0519-001 05/01/2021

Rates Fringes

TRUCK DRIVER (Dump Truck)........$ 24.81 8.10

* UAVG-TN-0001 04/16/2021

Rates Fringes

SHEET METAL WORKER (HVAC Unit Installation Only)...............$ 29.60 12.48

* SUTN2017-030 04/16/2021

Rates Fringes

BRICKLAYER.......................$ 20.00 0.00

CARPENTER........................$ 16.96 0.00

CEMENT MASON/CONCRETE FINISHER...$ 22.67 4.11

IRONWORKER, STRUCTURAL...........$ 18.30 0.00

LABORER DEMOLITION...............$ 16.74 0.00

LABORER GRADE CHECKER............$ 13.01 ** 0.00

LABORER: Common or General......$ 12.69 ** 1.78

LABORER: Mason Tender - Brick...$ 13.54 ** 0.00

LABORER: Mason Tender - Cement/Concrete..................$ 13.00 ** 0.00

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 27.77 9.75

OPERATOR: Bobcat/Skid Steer/Skid Loader................$ 16.84 0.00

OPERATOR: Bulldozer.............$ 28.52 9.75

OPERATOR: Drill.................$ 26.50 4.76

OPERATOR: Forklift..............$ 15.00 0.00

OPERATOR: Paver (Asphalt, Aggregate, and Concrete).........$ 14.70 ** 0.00

OPERATOR: Roller................$ 14.35 ** 0.00

PAINTER (Brush and Roller).......$ 19.31 10.15

PLUMBER..........................$ 21.63 7.16

ROOFER...........................$ 16.29 0.00

SHEET METAL WORKER, Excludes HVAC Duct and Unit Installation.....................$ 24.19 7.52

TILE FINISHER....................$ 14.00 ** 0.00

TILE SETTER......................$ 19.65 0.00

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($15.00) or 13658 ($11.25). Please see the Note at the top of the wage determination for more information.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour National Office because National Office has responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISIO"

(End of Summary of Changes)