W50S98-22-B-000100001.pdf

PDF 260 KB Posted

Attached to
B113 Solicitation Federal contract opportunity
Solicitation number
W50S98
Issued by
Department of the Army Tennessee Army National Guard

About this file

This is an amendment to a solicitation for building repairs. The solicitation is for repair work to Building 113 at McGhee Tyson Air National Guard Base in Tennessee. The amendment changes the bid due date to August 23, 2022 at 10:00 AM EST and incorporates addendum 1, revised specifications and drawings. Bids must include pricing on the provided line item sheet and be submitted prior to the amended due date. The Department of the Army Tennessee Army National Guard is the issuing agency. An option to demolish Buildings 110 and 111 using separate past drawings is also included.

The amendment provides responses to contractor questions to clarify requirements such as door and floor material specifications. It modifies the finish schedule and directs contractors to existing control systems. Joint venture proposals must include a signed agreement and documentation of board approval from each partner.

View the file

Other files for this federal contract opportunity

Other files attached to B113 Solicitation, newest first.
File Type Posted
OF 1419 Abstract.pdf PDF
OF 1419 Abstract.pdf PDF
Sign in Sheet - 23 Aug 2022 10am.pdf PDF
B 113 As Built Drawings.pdf PDF
Demo 110_110 Drawings GC002 003 004 005.pdf PDF
BLDG 111 Asbestos Info.pdf PDF
05 40 00 Cold-formed Metal Framing 20220805.pdf PDF
Demo Drawings CS503-506.pdf PDF
W50S98-22-B-000100002.pdf PDF
P-601_REVISED.pdf PDF
REGISTER-upate 07292022.pdf PDF
1190113_TNANG_B113_ELEC-ADDENDUM 1-072622.pdf PDF
1190113_TNANG_B113_FIRE-ADDENDUM 1-072622.pdf PDF
28 31 76 - updated.pdf PDF
Pre-Bid Sign in Sheet B113.pdf PDF
Pre-Bid Slides B113.pdf PDF
MTANG Demo 110 and 111 drawings.pdf PDF
Repair Building 113 Spec. Volume 2.pdf PDF
W50S98-22-B-0001 21 July 2022.pdf PDF
Repair Building 113 Spec. Volume 1.pdf PDF
Repair Building 113 Drawings.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PSXE152020

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

REASON FOR AMENDMENT: Add Addendum 1, Change Bid Due Date, Add Questions and Answ ers

1. Addendum 1 is hereby incorporated in to this solicitation. Revised Spec section 28 31 76, revised submittal register, and revised draw ings E-001, E-002, E-111, E-604, FA-001,FA-101,FA-501 are hereby incorporated in to this solicitatoin.

2. The proposal due date and time are hereby changed to 23 August 2022 at 10:00 AM EST. This change also changes the due date of the original bid bond to 25 August 2022 at 10:00 AM EST per section 00010 Notes.

3. Question and Answ ers 1-13 are hereby incorporated into this solicitation

1. CONTRACT ID CODE PAGE OF PAGES

J 1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 03-Aug-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W50S9822B0001

X 9B. DATED (SEE ITEM 11)

21-Jul-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

03-Aug-2022

CODE

USPFO TN 134 MISSION SUPPORT CONTRACTING

123 BRISCOE DRIVE

MCGHEE TYSON ANG BASE TN 37777-6227

W50S98 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W50S9822B0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

ADDENDUM NO. 1

ADDENDUM NO. 1

JAugust 1, 2022

TO DRAWINGS FOR

AREPAIR BLDG 113 FOR FUEL CELL

MCGHEE TYSON AIR NATIONAL GUARD BASE

PPSXE152020

ITEM DESCRIPTION

1.

2.

3.

4.

4.

See update Spec “SECTION 28 31 76”

See attached revised drawings E-001, E-002, E-111, E-604

See attached revised drawings FA-001, FA-101, FA-501

See update Submittal Register

QUESTIONS AND ANSWERS

1. Could you please clarify the Date and time in which this IFB is due to be received by the Government?

A: The bid due date has been updated to 10:00 AM EST on 23 August.

2. Under Section 00010 Notes. It talks about a Different date. Does that just apply to the bond?

A: Correct it just applies to the bond. It allows two extra days to provide the original bond.

3. Ok, so if that's the case are we allowed to submit our proposal electronically?

A: No

Section 08 33 23 Coiling Doors1 On A101 there is a note A1 that states door 126C is to be custom color powdercoat.

4. Is this the only Overhead door to be custom powdercoated, or should this be for all doors? The specification indicates, Part 3 paragraph 3.2 doors are to be field painted.

A: All new exterior roll‐up doors to be custom powder coated.

Again on A101, Note A2 indicates that door 133‐E is insulated. The specification 2.3 Overhead Coiling Doors, paragraph 2.3.1 indicates doors to be insulated.

5. The note A2 on A101 makes this confusing. Are all doors insulated per specification or just door 133‐E?

A: Only new exterior doors to be insulated.

6. Electrical power plans, note E13 indicates, states doors to be motorized suitable for Class 1 Division 2 space. What are the exact requirements? the specification does not indicate this type of motor operator.

A: The door specification itself does not change. The motor operator needs to meet the class 1 div 2 requirements.

7. Door 126B‐E is a door that is taken down and reinstalled. This door also has the

E13 note applied. Does this door now have Class 1 Division 2 Motor operator, or is the motor operator to be replaced to meet this requirement? Also this Door requires a 1 hour fire rating. Does the existing door meet this requirement?

A: This existing door meets the fire resistance rating requirements. The motor operator needs to meet the class 1 div 2 requirements.

8. The specification requires slide locks. The motor operator will lock door. I recommend this option be deleted. If not the TANG will have maintenance issues.

A: Pond/Gov't has no issue with them being removed.

9. Sheet I‐101/101A Nose Bay Existing or New epoxy per general note

A: Room 101A/Nose Bay should state EP‐1 on finish schedule, as noted in Remarks will we redone with the Hangar Floor.

10. 102A Mech EP‐1 or Existing epoxy

A: Room 102A should state Existing on the Finish Schedule and as noted on sheet I‐101

11. 103 Mech EP‐1 or Existing epox

A: Room 103 should state Existing on the Finish Schedule and as noted on sheet I‐101. 103A should not be on the finish schedule as room was removed with HEF removal modification.

12. 113 Fuel Cell Supervisor CT‐1 or Epoxy to match existing

A: Room 113 correctly states CT‐1. The note with arrow on sheet I‐101 should be pointing to room 101A/Nose Bay, not room 113.

13. Per drawings page M‐602 there is quantity 6 existing airhandler units (AHUs). It is unclear whether these AHUs are to be integrated into the new building automation system. If they are required to be integrated and user graphics created for them, do the existing AHUs have BACnet communication cards to allow for integration? If not is the controls contractors responsible to provide said BACnet cards?

A: The existing six (6) AHUs are currently controlled by the existing DDC system. The contractor shall relocate the connection points along with the AHUs and reconnect the AHUs to the DDC system.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 22-Aug-2022 12:00 AM to 23-Aug-2022 10:00 AM.

The following have been modified:

SECTION 00010

SECTION 00010 Solicitation Contract Form

TABLE OF CONTENTS

SOLICITATION, OFFER, AND AWARD SF 1442 and SF 1442 BACK

SECTION 00010 - BID SCHEDULE, NOTES

SECTION 00 01 00 - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

SECTION 00 10 00 - SOLCITATION

SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS

SECTION 00 45 00 - REPRESENTATIONS & CERTIFICATIONS

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

SECTION 00 72 00 - GENERAL CONDITIONS

SECTION 01 00 00 - GENERAL REQUIREMENTS

ATTACHMENT 1 – PLANS AND SPECIFICATIONS Project #PSXE152020 Dated 15 March 2022 ATTACHMENT 2- Wage Determination – See Section 07200 of solicitation

SECTION 00010 NOTES

NOTES

1. All information relating to this IFB, including pertinent changes/amendments and information will be posted on web site: SAM.gov.

2. Facsimile transmission of bid is not authorized. Electronic submission of bids will NOT be accepted.

3. All information relating to this IFB, including pertinent changes/amendments and information will be posted on web site: SAM.gov. For security reasons, all potential offerors, plan rooms and printing companies are required to be registered in the GSA System for Award Management (SAM) database. Firms can register via the SAM internet site at sam.gov. Interested bidders are required to submit their representations and certifications at the same site.

4. Reserved

5. A complete bid package must contain the following:

(a) Offer, Standard Form (SF) 1442 front and back signed

(b) Section 00010 Line Items- all items must be priced

(c) A copy of the bond and POA may be submitted with the proposal, with the original signed copy with Seal to be submitted no later than 25 August 2022, 10:00 AM EST. The bid bond must be on a SF24 form. Rejection of a bid bond shall be in accordance with FAR 28.101-4 Noncompliance with bid guarantee requirements. .

(d) Section 00600, Representations and Certifications, completed and return only additional certifications found in this section In addition, the offeror must have entered current and complete data within the past year in Online Representations and Certifications at www.sam.gov.

(e) When completing the “Offeror” portion of the SF 1442 (Blocks 14 – 20), an official having the authority to contractually bind the company must sign the SF 1442 in accordance with FAR 4.102.

One copy of the SF1442 is required to have an original signature.

(f) All amendments to the solicitation must be acknowledged.

(g) Mark the front of the envelope with the following: “BID No. W50S98-22-B-0001”, and the Name and

Address of Bidder. See Block 13A of SF 1442 for required number of copies.

6. Joint Venture Requirements - Parties wishing to propose as a joint venture must submit, with the Pro Forma documents, an executed copy of the joint venture agreement. The joint venture agreement shall be executed in accordance with FAR 4.102(d). Each joint venture partner shall submit evidence satisfactory to the Contracting Officer that its Board of Directors has approved its participation in the joint venture or by an instrument of similarly binding character in the case of an unincorporated entity. Offerors are reminded that to obtain an award the awardee, to include a joint venture, must be registered in the System for Award Management (SAM) database.

Applicable to set-aside solicitations: Joint Ventures must meet applicable size standards (See FAR Subpart 19.1).

Submit with the proposal any size determination for the Joint Venture entity received from the Small Business Administration. A Joint Venture where-in one party is not a small business may be referred to the Small Business Administration ( IAW FAR 19.302 (b)) to determine eligibility. All questions regarding Joint Ventures must be directed to the Small Business Administration (SBA) and not the Contracting Officer.

End of Section 00010

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following have been modified:

252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall--

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

DRAWINGS: PSXE152020, Repair Building 113, 109 Sheets; dated 15 March 2022

PSXE152020, Demo Building 113, 8 Sheets; dated 19 August 2019

Updated Drawings- 1190113_TNANG_B113_ELEC-ADDENDUM#1-072622 and

1190113_TNANG_B113_FIRE-ADDENDUM #1-072622

SPECIFICATIONS: PSXE152020, Repair Building 113, Volume 1 totaling 568 pages including inside and outside cover; dated 15 March 2022

PSXE152020, Repair Building 113, Volume 2 totaling 616 pages including inside and outside cover; dated 15 March 2022

Updated Spec section 28 31 76, dated 29 July 2022, totalling 32 pages Updated submittal register: Register-update 07292022

Option 1- Drawings: MTANG Demo 110_111 drawings, totaling 8 pages, dated 19 August 2019

(End of clause)

(End of Summary of Changes)

File details come from the government source that posted it. Updated .