This solicitation amendment updates an energy project opportunity for the Department of the Army National Guard. The project involves updating HVAC and DDC systems at multiple facilities base-wide, including replacing RTUs and split systems, modifying ductwork, replacing boilers, and utilizing temporary equipment. Options specified are replacing the hydronic system and split system at Building 318, work at Building 402, and boiler replacement at Building 301. The amendment incorporates Automated Logic Controls requirements, provides drawings and specifications, and details the use of brand name justification. It also updates wage determinations and labor reporting processes.
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
XHZG162001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1) Update the w age determination current as of the date of the amendment.
2). Update the labor hour reporting to the new w w w .sam.gov process
3) Add FAR 52.204-24 and FAR 52.204-25
4) Update 252.236-7001 to reference documents included w ith RFI responses
1. CONTRACT ID CODE PAGE OF PAGES
J 1 9
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 29-Jul-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W50S8U20B0001
X 9B. DATED (SEE ITEM 11)
25-Jun-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Jul-2020
CODE
USPFO OK 138 MISSION SUPPORT CONTRACTING
4200 N 93RD EAST AVE
TULSA OK 74115-1699
W50S8U 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W50S8U20B0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The Issued By organization has changed from
138 CONTRACTING FLIGHT (MSG/MSC)
9100 E 46TH ST NORTH
ATTN: MSGT DAVID HUGUELEY
TULSA OK 74115-1632
to
USPFO OK 138 MISSION SUPPORT CONTRACTING
4200 N 93RD EAST AVE
TULSA OK 74115-1699
CLIN 0002
The CLIN description has changed from CMRA to Labor Hour Reporting.
The CLIN extended description has changed from:
The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Oklahoma National Guard via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web addresses:
http://www.ecmra.mil/ or https://cmra.army.mil/. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. Data shall be reported not later than the first to occur of (1) submission of contractor’s final invoice following conclusion of the period of performance or (2) October 31 of each calendar year. Contractors may direct questions to the help desk at help desk at: http://www.ecmra.mil
To:
The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Oklahoma National Guard via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web addresses:
http://www.sam.gov Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. Data shall be reported not later than the first to occur of (1) submission of contractor’s final invoice following conclusion of the period of performance or (2) October 31 of each calendar year. Contractors may direct questions to the help desk at help desk at:
http://www.sam.gov
CLIN 0004
The CLIN description has changed from Replace RTU, split, modify Ducting B40 to Replace RTU, split, modify Ducting B402.
SECTION 00600 - REPRESENTATIONS & CERTIFICATIONS
The following have been added by reference:
52.204-24 Representation Regarding Certain Telecommunications and
Video Surveillance Services or Equipment.
DEC 2019
SECTION 00700 - CONTRACT CLAUSES
The following have been added by reference:
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
AUG 2019
The following have been modified:
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
Title File Drawing No.
XHZG162001 Type B-3 Specifications-EP XHZG162001 Type B-3 Drawing Set EP XHZG162001 Type B-3 Controls Shop Drawings-EP 138CES - CONTROLS SYSTEM CONTRACTING LANGUAGE and
RESPONSIBILITIES V 2.0
138CES - NIST SP 800-53 R4 and 800-82 R2 Merged Asbestos Management Plan 1.1 Pre-Bid RFI Energy Project 07-20-2020 B0301 Type B Final Design Drawings_Redacted (to incorporate RFI response)
(End of clause)
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
The following have been added by full text:
WAGE RATE REQUIREMENT
"General Decision Number: OK20200053 06/26/2020 Superseded General Decision Number: OK20190053 State: Oklahoma
Construction Type: Building Building Construction -does not include residential construction consisting of single family homes and apartments up to and including 4 stories. (Including building projects on industrial sites and treatment plants)
County: Tulsa County in Oklahoma.
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2020
1 01/31/2020 2 03/06/2020 3 06/26/2020
BROK0005-004 06/01/2019
Rates Fringes
BRICKLAYER.......................$ 24.87 10.70
ELEC0584-006 05/28/2018
Rates Fringes ELECTRICIAN (Excludes Low Voltage Wiring and Installation of Alarms and Sound and Communication Systems).........................$ 30.43 7%+9.70
ELEV0083-003 01/01/2020
Rates Fringes
ELEVATOR MECHANIC................$ 42.02 34.765+a+b PAID HOLIDAYS:
New Year's Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, the Friday after Thanksgiving, and Christmas Day.
Employer contributes 8% of regular hourly rate to vacation pay credit for employee who has worked in business more than 5 years; 6% for less than 5 years' service.
ENGI0627-020 06/01/2019
POWER EQUIPMENT OPERATOR:
Rates Fringes
Group 1.....................$ 31.05 13.75 Group 2.....................$ 29.35 13.75 Group 3.....................$ 28.80 13.75 Group 4.....................$ 28.00 13.75 Group 8.....................$ 23.65 13.75 Group10.....................$ 22.20 13.75
POWER EQUIPMENT OPERATOR
GROUP 1: All Crane Type Equipment 200 ton and larger and including 400 ton capacity cranes. All Tower Cranes.
GROUP 2: All Crane Type Equipment 100 ton capacity and larger cranes, and less than 200 ton capacity.
GROUP 3: All Crane Type Equipment 50 ton capacity and larger cranes, and less than 100 ton capacity. Crane Equipment (as rated by mfg.) 3 cu. yd. and over Guy derrick Whirley Power Driven Hole Digger (with 30' and longer mast).
GROUP 4: CRANES with Boom Incl. Jib less than 100 ft and less than 3 cu. Yd.; Overhead Monorail Crane
GROUP 8: FORK-LIFT
GROUP 10:OILER; SEMI-TRAILER TRUCK DRIVER
IRON0584-025 06/01/2019
IRONWORKER (Ornamental, Rates Fringes
Reinforcing and Structural)......$ 26.00 15.35
PLUM0430-010 07/01/2018
Rates Fringes PLUMBER (Excludes HVAC Pipe and Unit Installation)...........$ 31.50 13.88
PLUM0430-019 07/01/2018
Rates Fringes HVAC MECHANIC (Installation of HVAC Unit Only, Excludes Installation of HVAC Pipe and Duct)............................$ 31.50 13.88
PLUM0430-020 07/01/2018
Rates Fringes PIPEFITTER (Including HVAC Pipe Installation, excluding HVAC Unit Installation)..........$ 31.50 13.88
* ROOF0143-001 06/01/2020
Rates Fringes
ROOFER...........................$ 22.30 8.35
SHEE0270-006 06/01/2017
Rates Fringes SHEET METAL WORKER (HVAC Duct Installation Only). $ 31.89 14.31
SUOK2012-033 07/30/2012
Rates Fringes CARPENTER (Drywall Hanging Only). $ 15.08 1.21 CARPENTER, Excludes Drywall Hanging, and Form Work. $ 14.96 1.55
CAULKER. $ 20.00 1.61
CEMENT MASON/CONCRETE FINISHER...$ 13.72 1.27
DRYWALL FINISHER/TAPER. $ 13.00 0.00
ELECTRICIAN (Alarm Installation). $ 19.48 3.34 ELECTRICIAN (Low Voltage Wiring). $
20.65 3.06 ELECTRICIAN (Sound and Communications Systems Installation). $
21.11
2.47
FORM WORKER. $ 12.69 0.38
LABORER: Common or General. $ 12.44 2.71 LABORER: Mason Tender - Brick...$ 12.43 0.00 LABORER: Mason Tender - Cement/Concrete. $ 13.00 1.91 LABORER: Pipelayer. $ 12.39 0.00
OPERATOR: Asphalt Paver. $
OPERATOR: 16.25 0.00
Backhoe/Excavator/Trackhoe. $ 16.96 4.22 OPERATOR: Bulldozer. $ 21.07 2.48 OPERATOR: Grader/Blade. $ 14.28 1.70 OPERATOR: Loader (Front End). $ 16.18 0.00 PAINTER: Brush, Roller and Spray, Excludes Drywall Finishing/Taping. $
12.22
0.00 SHEET METAL WORKER, Excludes HVAC Duct Installation. $ 22.11 4.93 SPRINKLER FITTER (Fire Sprinklers). $ 21.86 1.19 TRUCK DRIVER: Dump and Flatbed Truck. $ 11.00 0.00 WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local),a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example: PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana.
2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH- 0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
an existing published wage determination a survey underlying a wage determination a Wage and Hour Division letter setting forth a position on a wage determination matter a conformance (additional classification and rate) ruling On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor
200 Constitution Avenue, N.W. Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION"
The following have been deleted:
WAGE RATE REQUIREMENTS
(End of Summary of Changes)